BASIC TERMINOLOGY IN CONSTRUCTING PERT/CPM 1. Project Network Diagram:- It is a Pictorial representation of the sequence in which the project work can be done 2.Activity:- Chunk Of Work. 3.Slack/Float Activity :- it is that type of Activity which can be started earlier or finished later without affecting the time duration of the Project CHAPTER 6-1

Transcript of Chapt 6 slides

Page 1: Chapt 6 slides

BASIC TERMINOLOGY IN CONSTRUCTING PERT/CPM

1. Project Network Diagram:- It is a Pictorial representation of the sequence in which the project work can be done2.Activity:- Chunk Of Work.3.Slack/Float Activity:- it is that type of Activity which can be started earlier or finished later without affecting the time duration of the Project

CHAPTER 6-1

Page 2: Chapt 6 slides

BASIC TERMINOLOGY IN CONSTRUCTING PERT/CPM

4. Slack/ Float of an Activity:- It is the time duration for which an activity can be slacked/Floated.5.EST:- Earliest Start time of an activity.6.LST:- Latest Start time of an activity.7.EFT:-Earliest Finish time of an activity.8.LFT:- Latest Finish Time of an activity.9.Critical Path:- It is the largest path or sequence of Activities (in terms of Activity Time Duration), through the Network Diagram.

CHAPTER 6-2

Page 3: Chapt 6 slides

SAMPLE NETWORK DIAGRAMCHAPTER 6-3

1

2

4

3

5 DAYS9 DAYS

8 DAYS 11 DAYS

A

B

C

D

Question: Calculate Critical Path From Above Network Diagram

Page 4: Chapt 6 slides

CONSTRAINTS WHICH EFFECT SEQUENCING OF PROJECT ACTIVITIES

There are Four type of constraints which effect the sequence of Project Activities:-1. Technical constraints.2. Management constraints.3. Inter Project constraints.4. Date Constraints.

CHAPTER 6-4

Page 5: Chapt 6 slides

ACTIVITIES DEPENDENCIES

A dependency is a relationship that exist between activities. To say that Activity B depends on Activity A. It means Activity A produces a deliverable which is needed in order to do the work associated with Activity B. there are Four type of Activity Dependencies.

CHAPTER 6-5

Continued…

Page 6: Chapt 6 slides

ACTIVITIES DEPENDENCIES

1. Finish to Start (FS):- When A finishes B start.

2. Start to Start(SS):- Activity A & B Start Together

CHAPTER 6-6

Continued…

A B

A

B

Page 7: Chapt 6 slides

ACTIVITIES DEPENDENCIES

3. Start to Finish (SF):- Activity B can only finish when Activity A has Started.

4. Finish to Finish (FF):- Activity A and Activity B finish at the same time.

CHAPTER 6-7

BA

A

B

Page 8: Chapt 6 slides

ACTION PLAN

Activity Precedence Time DurationA - 5 DaysB - 4 DaysC A 6 DaysD B 2 DaysE B 5 DaysF C, D 8 DaysAssignment:- Draw a PERT/CPM from above Action Plan. Calculate critical Path? Please submit this Assignment to the Teacher in next Class.

CHAPTER 6-8

Continued…

Page 9: Chapt 6 slides

PERT/CPM OF ACTION PLAN GIVEN AS ASSIGNMENT

CHAPTER 6-9

1

2

3

4

5 DAYS6 DAYS

2 DAYS

4 DAYS

A

B

C

D

Critical Path = A + C + F= 5 Days + 6 Days + 8 Days= 19 Days

5

E

F

5 DAYS

8 DAYS