CERN SPL Fundamental Power Coupler Progress report

41
CERN SPL Fundamental Power Coupler Progress report SPL meeting CERN, 6 - 7 December 2012 Eric Montesinos, CERN BE-RF-PM

description

CERN SPL Fundamental Power Coupler Progress report. SPL meeting CERN, 6 - 7 December 2012 Eric Montesinos , CERN BE-RF-PM. Contents. Introduction CERN RF Fundamental Power Coupler team SPL coupler project SPL FPC initial design proposals March 2010 Coupler review - PowerPoint PPT Presentation

Transcript of CERN SPL Fundamental Power Coupler Progress report

Page 1: CERN SPL Fundamental Power Coupler Progress report

CERN SPLFundamental Power CouplerProgress report

SPL meetingCERN, 6 - 7 December 2012Eric Montesinos, CERN BE-RF-PM

Page 2: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

2

Contents• Introduction

▫ CERN RF Fundamental Power Coupler team

• SPL coupler project▫ SPL FPC initial design

proposals▫ March 2010 Coupler review▫ June 2010 SPL Coupler

project▫ Construction▫ Assembly in DESY clean room▫ Double walled Tubes (DT)▫ LLRF tests▫ High Power tests at CEA : TW▫ High Power tests at CEA : SW

• Next steps

• Key R&D results :▫ Mono bloc waveguide▫ Test box▫ Double walled Tube as

support for cavity▫ High Average power air

cooled couplers

5-6 December 2012

Page 3: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

3

CERN RF Fundamental Power Coupler teamCERN Machine Design Prototype Series

SPS 200 2001 LHC 400 2006

Linac 4 Under Way

SPL cylindrical Under test

SPL planar Under test

HIE-Isolde Under test

Crab Cavities

To come

SPS 800 To come

LIU- SPS 200

To come

5-6 December 2012

SPS 200 MHz coupler

LHC 400 MHz coupler

Linac 4352 MHz coupler SPL 704 MHz

couplers

HIE Isolde 100 MHz couplers

Page 4: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

4

CERN RF Fundamental Power Coupler team

5-6 December 2012

Machine Design Prototype Tests

ESRF 300 kW CW

ANL-APS 100 kW CW

SOLEIL Under way

ESRF 352 MHz coupler Argonne APS 352 MHz coupler

SOLEIL 352 MHz coupler design

Page 5: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

5

SPL FPC initial design proposals

5-6 December 2012

RF Characteristicsf0 704.4 MHz

Power levels

1000 kW pulsed0.4 + 1.2 + 0.4 = 2.0 ms50 Hz (20 ms)100 kW average

Cavity design gradient 19-25 MV/m

Qext of input coupler 1.2 x 106

Input line Ø100 / 43.5 mm = 50 Ω(from the cavity design)

Waveguides WR 1150

2009 2010 2011 2012 2013

CEA HIPPI(baseline)

CylindricalWindow

Disk WGWindow

DiskCoaxial window

Page 6: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

6

SPL FPC initial design proposals

5-6 December 2012

2009 2010 2011 2012 2013

30 kCHF8.25 MCHF

15 kCHF4.125 MCHF

15 kCHF4.125 MCHF

14 kCHF3.85 MCHF

Baseline: CEA Saclay coupler

To be upgraded for SPL cryomodule compatibility

Kept open the possibility to use another design, to be fixed in March 2010

Comparison basis: RF power capability Low heat load Tuning capability (fixed coupling,

adjustable coupling) Conditioning time Contamination during beam part

assembly Easy installation Integration with the cryomodule Easy operation Cost

Window-Ceramic-Antenna275 Series 4-8 MCHF

Page 7: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

7

March 2010 Coupler review• Review committee members :

▫ Ali Nassiri (Chair)▫ Wolf Dietrich Moeller▫ Mark Champion▫ Sergey Kazakov▫ Mircea Stirbet

• Presenters :▫ Amos Dexter & Rama Calaga

(Multipacting simulations)▫ Miguel Jimenez (Vacuum)▫ Sergio Calatroni (DT Coating)▫ Ofelia Capatina & Vittorio

Parma (Cryomodule integration)

▫ Eric Montesinos (FPC)

5-6 December 2012

2009 2010 2011 2012 2013

Technical ChoicesSingle window couplerFixed couplerWith a Double Walled TubeMounted in clean room with its double walled tube horizontally in only one operationVertically below the cavity and will be a support for the cavity (first time worldwide)

With a HV DC biasing capacitorAir cooled

Page 8: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

8

Two designs have been validated

5-6 December 2012

Cylindricalceramic window

Coaxial diskceramic window

Page 9: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

9

5-6 December 2012

Same Double Walled Tube(Outer line of a coaxial

transmission Line)With same interface flange

to cryomodule

Same Waveguide with integrated matching step (instead of a doorknob)And same DC capacitor

Page 10: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

10

Cylindrical window• Advantages

▫ LHC window with high power capability due to its solid copper collars

▫ Simple to cool down with air▫ Absolutely free of mechanical

stress onto the antenna▫ “plug and play” waveguide

and DC capacitor, no stress to the ceramic

• Drawbacks▫ Ceramic is part of the

matching system, imposing the waveguide position

5-6 December 2012

Page 11: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

11

Coaxial Disk window• Advantages

▫ Very simple and well mastered brazing of ceramic onto a titanium flange

▫ Simple to cool down with air

▫ “plug and play” waveguide and DC capacitor, no stress to the ceramic

• Drawback▫ Ceramic is part of the

matching system, fixing the waveguide position

5-6 December 2012

Page 12: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

12

SPL coupler project (June 2010)• Four vacuum lines:

▫ 4 cylindrical window couplers

▫ 4 disk window couplers▫ 8 Double walled Tubes▫ 4 test boxes

• DESY clean process assembly▫ (Jlab also proposed to help)

• CERN LLRF measurements

• CEA RF power tests▫ (BNL also proposed to help)

5-6 December 2012

2009 2010 2011 2012 2013

Page 13: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

13

Couplers construction• All parts have been

produced by May 2011 (10 months)

• All components have been individually vacuum leak free tested before being sent to DESY for assembly

5-6 December 2012

2009 2010 2011 2012 2013

Page 14: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

14

Couplers construction• All parts have been

produced by May 2011 (10 months)

• All components have been individually vacuum leak free tested before being sent to DESY for assembly

• Specific transport boxes with springs as per tetrodes have been designed to avoid any shocks

5-6 December 2012

2009 2010 2011 2012 2013

Page 15: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

15

Assembly in DESY clean room• In June 2011, the four

cavities were assembled in DESY clean room

• Use of a specially designed helicoflex seal

5-6 December 2012

2009 2010 2011 2012 2013

Page 16: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

16

Assembly in DESY clean room• In June 2011, the four

cavities were assembled in DESY clean room

• Use of a specially designed helicoflex seal

• Thanks to DESY colleagues who have performed a very good job and to a very good preparation job of the jointing surfaces all four cavities were leak free

5-6 December 2012

2009 2010 2011 2012 2013

Page 17: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

17

Double walled Tube (DT)• Copper sputtering removed with

simple water Ultra Sonic cleaning process

• Mistake in the machining process :▫ An additional machining step not

included in the lists has erased all the care put into the preparation of DT

• Decision to continue the first two vacuum lines with NOT copper sputtered DT :▫ Lead into a very important delay

onto the schedule▫ Will limit average power during

tests

5-6 December 2012

2009 2010 2011 2012 2013

Page 18: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

18

LLRF measurements at CERN (summer 2011)

5-6 December 2012

• S11 with 2 x N/WG adaptors + 2 couplers + 2 DT + test box :▫ Cylindrical windows = -26.5 dB▫ Coaxial planar disk = -18 dB

• Pfwd/Prev (S11) at CEA premises with 2 couplers + 2 DT + test box :▫ Cylindrical window = -17 dB▫ Coaxial planar disk = -40 dB

• Even with only -16 dB, 1 MW will reverse 25 kW, acceptable with CEA premises, thanks to their circulator

2009 2010 2011 2012 2013

Page 19: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

19

RF power tests at CEA cylindrical window• First test were to check RF,

so No bake out to take no risk with the test box helicoflex gasket

• Static vacuum ~ 2 x 10-7 mbar

• Pulse mode process

• After 3 weeks, 50 kW 20 s - 20 Hz

• We Stopped the test

5-6 December 2012

2009 2010 2011 2012 2013

Page 20: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

20

RF power tests at CEA disk windows• In the meantime, second test box

with two disk window couplers has been baked out at CERN

• No helicoflex leak▫ Very slow heating up and

heating down ramps 10 C / hour▫ Maximum temperature during

48 hours was only 150 C▫ Nitrogen onto copper rings to

avoid any oxidization

• Very good static vacuum after the process ~ 1 x 10-10 mbar (vs 5 x 10-7 mbar before starting the bake out)

• Pulse mode process

• After two weeks :▫ 1000 kW 2 ms - 20 Hz

• Ultimate goal of 1000 kW 2 ms - 50 Hz was not possible due to losses in uncoated DT limitation

5-6 December 2012

2009 2010 2011 2012 2013

Page 21: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

21

RF power tests at CEA cylindrical window• We also baked out the first

test box with two cylindrical windows at CERN

• No helicoflex leak

• Very good static vacuum after the process ~ 1 x 10-10 mbar (vs 2 x 10-7 mbar before starting the bake out)

• Pulse mode process

• After 1 week:▫ 1000 kW 2 ms - 20 Hz

• Ultimate goal of 2 ms - 50 Hz was not possible due to losses in uncoated DT limitation

5-6 December 2012

2009 2010 2011 2012 2013

Page 22: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

22

TW tests ok (May 2012)

•Both coupler versions have reached TW maximum values of 1 MW 2 ms - 20 Hz

•Limitation of average power to 20 Hz instead of 50 Hz due to uncoated TD

•Successful TW tests

5-6 December 2012

2009 2010 2011 2012 2013

Page 23: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

23

SW tests with cylindrical window• A variable short

circuit has been designed and constructed at CERN for SW test

• Steps of 20 mm to have enough accuracy performing tests within all phases

5-6 December 2012

2009 2010 2011 2012 2013

Page 24: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

24

SW tests with cylindrical window• We started SW tests in pulse

mode

• With 500 µs – 8Hz :▫ Up to 500 kW, no trouble▫ Arcing when reached 575 kW

• It seemed to be air side as there was no vacuum activity

• There was no arc detector to stop the test, a photomultiplier modulated RF, and it was possible to hear arcing in the WG system

5-6 December 2012

2009 2010 2011 2012 2013

Page 25: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

25

SW tests with cylindrical window• Air side arcing were

confirmed when dismounting WG

• Input coupler presented some impressive arcing traces

• Output coupler was without any trouble

5-6 December 2012

2009 2010 2011 2012 2013

Page 26: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

26

SW tests with cylindrical window• Analyzing black deposit, we

only identified :▫ Gold coming from upper

gold platted copper collar▫ Copper coming from lower

copper collar

• There were without any doubt electrical arcing (>1’000) between two copper brazed collars

• The only positive point is that ceramic remained vacuum leak free

5-6 December 2012

2009 2010 2011 2012 2013

0 2 4 6 8 10Energy (keV)

0

10

20

30

cps

C

OCu

Au

Cu

Cu

Au

0 2 4 6 8 10Energy (keV)

0

10

20

30

cps

O

Cu

Al

Cu

Cu

Page 27: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

27

Improvement of cylindrical window• A trick given by Michel

Langlois (ex-Thales tube designer) is to improve air flow in the critical area in order to avoid ionization of the air around the ceramic itself

• improve air cooling around ceramic with a short circuit as air inlet

• Inserting PEEK screen all around ceramic

5-6 December 2012

Air inlet throughWG short circuit

PEEK Screen all around ceramic

Page 28: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

28

SW tests with coaxial disk windows• We then decided to start

SW tests with coaxial disk windows

• Up to date, we performed:▫ 1000 kW 1.5 ms – 4 Hz

• Some RF leaks were observed

• CEA was finally not sure if these RF leaks were coming form couplers

5-6 December 2012

2009 2010 2011 2012 2013

Page 29: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

29

SW tests with coaxial disk windows• Last week, while

preparing test box with copper coated DT, we observed some arcing traces on the outer line in front of the inner contact

• These traces were not present after TW test

• There were no arc detector fault during the whole SW test (interlock active)

5-6 December 2012

2009 2010 2011 2012 2013

Arcing traces on inner line

Arcing traces on outer line

Page 30: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

30

SW tests with coaxial disk windows

• Still waiting items to find an explanation

• Possible candidates :

▫ Not enough springs ensuring specific 1MW RF contact :

1. Inner ceramic is brazed with a stainless steel nut

2. Air cane is built with a specific bolt

3. Air cane is screwed compressing springs which when relaxed ensure 1 MW RF contact

▫ Contact surfaces were not flat enough

5-6 December 2012

1.

2.3.

2009 2010 2011 2012 2013

Page 31: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

31

SW tests conclusion• Cylindrical window couplers have performed

575 kW 500 µs - 8 Hz full reflection all phases -> very strong arcing, interlock not operative

• Coaxial disk window couplers have performed1000 kW 1.5 ms - 4 Hz full reflection all phases, no interlock (operative), but few arcing traces (to be understood and explained)

• SW tests are not conclusive, work still have to be done

5-6 December 2012

2009 2010 2011 2012 2013

Page 32: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

32

Coated DT• 6 DT with new copper sputtering have been processed :

▫ Test with 150 Bars water have been performed▫ TD qualified▫ 2 have been provided to cryomodule team

• Unfortunately DESY clean room was not anymore available

• CEA proposed to assemble couplers and copper sputtered DT onto test boxes in ‘L’orme les Meurisiers’ premises :▫ One Test box with two copper plated DT and two coaxial disk

window has been assembled last week

5-6 December 2012

2009 2010 2011 2012 2013

Page 33: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

33

Next steps

• Second test box will be assembled beginning 2013

• Cylindrical or Disk windows ? Decision after cylindrical arcing analysis

• Beginning 2013, final tests at CEA with :▫ 1000 kW TW 2 ms – 50 Hz▫ 1000 kW SW limited to 200 µs – 50 Hz

5-6 December 2012

2009 2010 2011 2012 2013

Page 34: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

34

Next steps• EB welding of cryostat

flanges will be done afterward

• Study of clean room tooling for assembly onto SPL cavity has started

• Assembly of couplers onto cavities in CERN clean room goal remains mid-2013

• RF power tests on cavity asap

5-6 December 2012

2009 2010 2011 2012 2013

Page 35: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

35

Next steps• Provide a CERN clean assembly premises for

couplers

• Continue all remaining couplers power tests with CERN amplifiers when available

• Longer term basis :▫ After qualification of SPL cavities, make a test with

‘dirty’ couplers (ISO 7 instead of ISO 4 for example, tbd), to quantify coupler cleanliness impact onto cavity field

5-6 December 2012

2009 2010 2011 2012 2013

Page 36: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

36

Key R&D resultsMono bloc waveguides

• ‘Plug and Play’ waveguide with matching step and DC capacitor included :

1. Connect the waveguide to the body line2. Insert the contacts ring3. Final assembly of air cooling system

• No doorknob, reduced height, with no mechanical stress to the ceramic

5-6 December 2012

1. 2.

3.

Page 37: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

37

Key R&D resultsTest box

• All in one, only two covers conditioning test box

• Pros :▫ Easier (not easy) copper

sputtering▫ Self supporting shape▫ Easily cleanable for SRF needs,

can be used for several sets of coupler (if large series : SPL, ESS, …)

• Cons :▫ Helicoflex faces to be very well

prepared▫ Self-supporting structure : heavy

weight

5-6 December 2012

Page 38: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

38

• Successfully made available 3D printing for RF tests with a special silver paint

5-6 December 2012

S21 = 0.01 dBS11 = -40 dB

S21 = 0.03 dBS11 = -25 dB

@ 400 MHz

Machined 3D printed

Delay [days] Cost [CHF]

Machined 3D Machined 3D

15 5 9000 3800

Key R&D results3D printing & RF

Page 39: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

39

Key R&D results High average power air cooled couplers

• Cylindrical window : ▫ TW : 1000 kW 2 ms - 20

Hz▫ SW : 550 kW 500 µs - 8

Hz

• Coaxial disk window : ▫ TW : 1000 kW 2 ms - 20

Hz▫ SW : 1000 kW 1.5 ms - 4

Hz

5-6 December 2012

Page 40: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

40

Acknowledgements• SPL coupler review committee :

▫ Ali Nassiri, Wolf Dietrich Moeller, Mark Champion, Sergey Kazakov, Mircea Stirbet, Amos Dexter, Rama Calaga, Miguel Jimenez, Sergio Calatroni, Ofelia Capatina, Vittorio Parma

• DESY :▫ Wolf-dietrich Moeller, Axel Matthaisen,

Birte Van der Horst, and local team

• CEA :▫ Stephane Chel, Guillaume Devanz, Michel

Desmond, and local team

• ESRF :▫ Jorn Jacob, Vincent Serriere, Loys, Jean-

Maurice Mercier, Didier Boillot

• APS :▫ Ali Nassiri, Doug Horan, Gian Trenko, Dave

Brubenker, and local team

• CERN :

▫ Mechanical & Material Engineering group : Francesco Bertinelli, Ramon Folch, Serge

Mathot, Agostino Vacca, Thierry Tardy, Thierry Calamand, Thierry Renaglia, Ofelia Capatina, Marc Polini, Laurent Deparis, Philippe Frichot, Jean-Marie Geisser, Jean-Marc Malzacker, Pierre Moyret, Alain Stadler

▫ Vacuum, Surface & Coating group : Miguel Jimenez, Sergio Calatroni,

Wilhelmus Vollenberg, Marina Malabaila, Nicolas Zelko

▫ Magnets, Superconductors & Cryostats : Vittorio Parma, Arnaud Van de Craene,

▫ RF group : Sebastien Calvo, Antoine Boucherie, all

FSU-BE03 members

5-6 December 2012

Page 41: CERN SPL Fundamental Power Coupler Progress report

SPL meeting, CERN

41

Thank you very much for your attention

5-6 December 2012