CERN SPL Fundamental Power Coupler Progress report
description
Transcript of CERN SPL Fundamental Power Coupler Progress report
CERN SPLFundamental Power CouplerProgress report
SPL meetingCERN, 6 - 7 December 2012Eric Montesinos, CERN BE-RF-PM
SPL meeting, CERN
2
Contents• Introduction
▫ CERN RF Fundamental Power Coupler team
• SPL coupler project▫ SPL FPC initial design
proposals▫ March 2010 Coupler review▫ June 2010 SPL Coupler
project▫ Construction▫ Assembly in DESY clean room▫ Double walled Tubes (DT)▫ LLRF tests▫ High Power tests at CEA : TW▫ High Power tests at CEA : SW
• Next steps
• Key R&D results :▫ Mono bloc waveguide▫ Test box▫ Double walled Tube as
support for cavity▫ High Average power air
cooled couplers
5-6 December 2012
SPL meeting, CERN
3
CERN RF Fundamental Power Coupler teamCERN Machine Design Prototype Series
SPS 200 2001 LHC 400 2006
Linac 4 Under Way
SPL cylindrical Under test
SPL planar Under test
HIE-Isolde Under test
Crab Cavities
To come
SPS 800 To come
LIU- SPS 200
To come
5-6 December 2012
SPS 200 MHz coupler
LHC 400 MHz coupler
Linac 4352 MHz coupler SPL 704 MHz
couplers
HIE Isolde 100 MHz couplers
SPL meeting, CERN
4
CERN RF Fundamental Power Coupler team
5-6 December 2012
Machine Design Prototype Tests
ESRF 300 kW CW
ANL-APS 100 kW CW
SOLEIL Under way
ESRF 352 MHz coupler Argonne APS 352 MHz coupler
SOLEIL 352 MHz coupler design
SPL meeting, CERN
5
SPL FPC initial design proposals
5-6 December 2012
RF Characteristicsf0 704.4 MHz
Power levels
1000 kW pulsed0.4 + 1.2 + 0.4 = 2.0 ms50 Hz (20 ms)100 kW average
Cavity design gradient 19-25 MV/m
Qext of input coupler 1.2 x 106
Input line Ø100 / 43.5 mm = 50 Ω(from the cavity design)
Waveguides WR 1150
2009 2010 2011 2012 2013
CEA HIPPI(baseline)
CylindricalWindow
Disk WGWindow
DiskCoaxial window
SPL meeting, CERN
6
SPL FPC initial design proposals
5-6 December 2012
2009 2010 2011 2012 2013
30 kCHF8.25 MCHF
15 kCHF4.125 MCHF
15 kCHF4.125 MCHF
14 kCHF3.85 MCHF
Baseline: CEA Saclay coupler
To be upgraded for SPL cryomodule compatibility
Kept open the possibility to use another design, to be fixed in March 2010
Comparison basis: RF power capability Low heat load Tuning capability (fixed coupling,
adjustable coupling) Conditioning time Contamination during beam part
assembly Easy installation Integration with the cryomodule Easy operation Cost
Window-Ceramic-Antenna275 Series 4-8 MCHF
SPL meeting, CERN
7
March 2010 Coupler review• Review committee members :
▫ Ali Nassiri (Chair)▫ Wolf Dietrich Moeller▫ Mark Champion▫ Sergey Kazakov▫ Mircea Stirbet
• Presenters :▫ Amos Dexter & Rama Calaga
(Multipacting simulations)▫ Miguel Jimenez (Vacuum)▫ Sergio Calatroni (DT Coating)▫ Ofelia Capatina & Vittorio
Parma (Cryomodule integration)
▫ Eric Montesinos (FPC)
5-6 December 2012
2009 2010 2011 2012 2013
Technical ChoicesSingle window couplerFixed couplerWith a Double Walled TubeMounted in clean room with its double walled tube horizontally in only one operationVertically below the cavity and will be a support for the cavity (first time worldwide)
With a HV DC biasing capacitorAir cooled
SPL meeting, CERN
8
Two designs have been validated
5-6 December 2012
Cylindricalceramic window
Coaxial diskceramic window
SPL meeting, CERN
9
5-6 December 2012
Same Double Walled Tube(Outer line of a coaxial
transmission Line)With same interface flange
to cryomodule
Same Waveguide with integrated matching step (instead of a doorknob)And same DC capacitor
SPL meeting, CERN
10
Cylindrical window• Advantages
▫ LHC window with high power capability due to its solid copper collars
▫ Simple to cool down with air▫ Absolutely free of mechanical
stress onto the antenna▫ “plug and play” waveguide
and DC capacitor, no stress to the ceramic
• Drawbacks▫ Ceramic is part of the
matching system, imposing the waveguide position
5-6 December 2012
SPL meeting, CERN
11
Coaxial Disk window• Advantages
▫ Very simple and well mastered brazing of ceramic onto a titanium flange
▫ Simple to cool down with air
▫ “plug and play” waveguide and DC capacitor, no stress to the ceramic
• Drawback▫ Ceramic is part of the
matching system, fixing the waveguide position
5-6 December 2012
SPL meeting, CERN
12
SPL coupler project (June 2010)• Four vacuum lines:
▫ 4 cylindrical window couplers
▫ 4 disk window couplers▫ 8 Double walled Tubes▫ 4 test boxes
• DESY clean process assembly▫ (Jlab also proposed to help)
• CERN LLRF measurements
• CEA RF power tests▫ (BNL also proposed to help)
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
13
Couplers construction• All parts have been
produced by May 2011 (10 months)
• All components have been individually vacuum leak free tested before being sent to DESY for assembly
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
14
Couplers construction• All parts have been
produced by May 2011 (10 months)
• All components have been individually vacuum leak free tested before being sent to DESY for assembly
• Specific transport boxes with springs as per tetrodes have been designed to avoid any shocks
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
15
Assembly in DESY clean room• In June 2011, the four
cavities were assembled in DESY clean room
• Use of a specially designed helicoflex seal
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
16
Assembly in DESY clean room• In June 2011, the four
cavities were assembled in DESY clean room
• Use of a specially designed helicoflex seal
• Thanks to DESY colleagues who have performed a very good job and to a very good preparation job of the jointing surfaces all four cavities were leak free
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
17
Double walled Tube (DT)• Copper sputtering removed with
simple water Ultra Sonic cleaning process
• Mistake in the machining process :▫ An additional machining step not
included in the lists has erased all the care put into the preparation of DT
• Decision to continue the first two vacuum lines with NOT copper sputtered DT :▫ Lead into a very important delay
onto the schedule▫ Will limit average power during
tests
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
18
LLRF measurements at CERN (summer 2011)
5-6 December 2012
• S11 with 2 x N/WG adaptors + 2 couplers + 2 DT + test box :▫ Cylindrical windows = -26.5 dB▫ Coaxial planar disk = -18 dB
• Pfwd/Prev (S11) at CEA premises with 2 couplers + 2 DT + test box :▫ Cylindrical window = -17 dB▫ Coaxial planar disk = -40 dB
• Even with only -16 dB, 1 MW will reverse 25 kW, acceptable with CEA premises, thanks to their circulator
2009 2010 2011 2012 2013
SPL meeting, CERN
19
RF power tests at CEA cylindrical window• First test were to check RF,
so No bake out to take no risk with the test box helicoflex gasket
• Static vacuum ~ 2 x 10-7 mbar
• Pulse mode process
• After 3 weeks, 50 kW 20 s - 20 Hz
• We Stopped the test
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
20
RF power tests at CEA disk windows• In the meantime, second test box
with two disk window couplers has been baked out at CERN
• No helicoflex leak▫ Very slow heating up and
heating down ramps 10 C / hour▫ Maximum temperature during
48 hours was only 150 C▫ Nitrogen onto copper rings to
avoid any oxidization
• Very good static vacuum after the process ~ 1 x 10-10 mbar (vs 5 x 10-7 mbar before starting the bake out)
• Pulse mode process
• After two weeks :▫ 1000 kW 2 ms - 20 Hz
• Ultimate goal of 1000 kW 2 ms - 50 Hz was not possible due to losses in uncoated DT limitation
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
21
RF power tests at CEA cylindrical window• We also baked out the first
test box with two cylindrical windows at CERN
• No helicoflex leak
• Very good static vacuum after the process ~ 1 x 10-10 mbar (vs 2 x 10-7 mbar before starting the bake out)
• Pulse mode process
• After 1 week:▫ 1000 kW 2 ms - 20 Hz
• Ultimate goal of 2 ms - 50 Hz was not possible due to losses in uncoated DT limitation
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
22
TW tests ok (May 2012)
•Both coupler versions have reached TW maximum values of 1 MW 2 ms - 20 Hz
•Limitation of average power to 20 Hz instead of 50 Hz due to uncoated TD
•Successful TW tests
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
23
SW tests with cylindrical window• A variable short
circuit has been designed and constructed at CERN for SW test
• Steps of 20 mm to have enough accuracy performing tests within all phases
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
24
SW tests with cylindrical window• We started SW tests in pulse
mode
• With 500 µs – 8Hz :▫ Up to 500 kW, no trouble▫ Arcing when reached 575 kW
• It seemed to be air side as there was no vacuum activity
• There was no arc detector to stop the test, a photomultiplier modulated RF, and it was possible to hear arcing in the WG system
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
25
SW tests with cylindrical window• Air side arcing were
confirmed when dismounting WG
• Input coupler presented some impressive arcing traces
• Output coupler was without any trouble
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
26
SW tests with cylindrical window• Analyzing black deposit, we
only identified :▫ Gold coming from upper
gold platted copper collar▫ Copper coming from lower
copper collar
• There were without any doubt electrical arcing (>1’000) between two copper brazed collars
• The only positive point is that ceramic remained vacuum leak free
5-6 December 2012
2009 2010 2011 2012 2013
0 2 4 6 8 10Energy (keV)
0
10
20
30
cps
C
OCu
Au
Cu
Cu
Au
0 2 4 6 8 10Energy (keV)
0
10
20
30
cps
O
Cu
Al
Cu
Cu
SPL meeting, CERN
27
Improvement of cylindrical window• A trick given by Michel
Langlois (ex-Thales tube designer) is to improve air flow in the critical area in order to avoid ionization of the air around the ceramic itself
• improve air cooling around ceramic with a short circuit as air inlet
• Inserting PEEK screen all around ceramic
5-6 December 2012
Air inlet throughWG short circuit
PEEK Screen all around ceramic
SPL meeting, CERN
28
SW tests with coaxial disk windows• We then decided to start
SW tests with coaxial disk windows
• Up to date, we performed:▫ 1000 kW 1.5 ms – 4 Hz
• Some RF leaks were observed
• CEA was finally not sure if these RF leaks were coming form couplers
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
29
SW tests with coaxial disk windows• Last week, while
preparing test box with copper coated DT, we observed some arcing traces on the outer line in front of the inner contact
• These traces were not present after TW test
• There were no arc detector fault during the whole SW test (interlock active)
5-6 December 2012
2009 2010 2011 2012 2013
Arcing traces on inner line
Arcing traces on outer line
SPL meeting, CERN
30
SW tests with coaxial disk windows
• Still waiting items to find an explanation
• Possible candidates :
▫ Not enough springs ensuring specific 1MW RF contact :
1. Inner ceramic is brazed with a stainless steel nut
2. Air cane is built with a specific bolt
3. Air cane is screwed compressing springs which when relaxed ensure 1 MW RF contact
▫ Contact surfaces were not flat enough
5-6 December 2012
1.
2.3.
2009 2010 2011 2012 2013
SPL meeting, CERN
31
SW tests conclusion• Cylindrical window couplers have performed
575 kW 500 µs - 8 Hz full reflection all phases -> very strong arcing, interlock not operative
• Coaxial disk window couplers have performed1000 kW 1.5 ms - 4 Hz full reflection all phases, no interlock (operative), but few arcing traces (to be understood and explained)
• SW tests are not conclusive, work still have to be done
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
32
Coated DT• 6 DT with new copper sputtering have been processed :
▫ Test with 150 Bars water have been performed▫ TD qualified▫ 2 have been provided to cryomodule team
• Unfortunately DESY clean room was not anymore available
• CEA proposed to assemble couplers and copper sputtered DT onto test boxes in ‘L’orme les Meurisiers’ premises :▫ One Test box with two copper plated DT and two coaxial disk
window has been assembled last week
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
33
Next steps
• Second test box will be assembled beginning 2013
• Cylindrical or Disk windows ? Decision after cylindrical arcing analysis
• Beginning 2013, final tests at CEA with :▫ 1000 kW TW 2 ms – 50 Hz▫ 1000 kW SW limited to 200 µs – 50 Hz
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
34
Next steps• EB welding of cryostat
flanges will be done afterward
• Study of clean room tooling for assembly onto SPL cavity has started
• Assembly of couplers onto cavities in CERN clean room goal remains mid-2013
• RF power tests on cavity asap
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
35
Next steps• Provide a CERN clean assembly premises for
couplers
• Continue all remaining couplers power tests with CERN amplifiers when available
• Longer term basis :▫ After qualification of SPL cavities, make a test with
‘dirty’ couplers (ISO 7 instead of ISO 4 for example, tbd), to quantify coupler cleanliness impact onto cavity field
5-6 December 2012
2009 2010 2011 2012 2013
SPL meeting, CERN
36
Key R&D resultsMono bloc waveguides
• ‘Plug and Play’ waveguide with matching step and DC capacitor included :
1. Connect the waveguide to the body line2. Insert the contacts ring3. Final assembly of air cooling system
• No doorknob, reduced height, with no mechanical stress to the ceramic
5-6 December 2012
1. 2.
3.
SPL meeting, CERN
37
Key R&D resultsTest box
• All in one, only two covers conditioning test box
• Pros :▫ Easier (not easy) copper
sputtering▫ Self supporting shape▫ Easily cleanable for SRF needs,
can be used for several sets of coupler (if large series : SPL, ESS, …)
• Cons :▫ Helicoflex faces to be very well
prepared▫ Self-supporting structure : heavy
weight
5-6 December 2012
SPL meeting, CERN
38
• Successfully made available 3D printing for RF tests with a special silver paint
5-6 December 2012
S21 = 0.01 dBS11 = -40 dB
S21 = 0.03 dBS11 = -25 dB
@ 400 MHz
Machined 3D printed
Delay [days] Cost [CHF]
Machined 3D Machined 3D
15 5 9000 3800
Key R&D results3D printing & RF
SPL meeting, CERN
39
Key R&D results High average power air cooled couplers
• Cylindrical window : ▫ TW : 1000 kW 2 ms - 20
Hz▫ SW : 550 kW 500 µs - 8
Hz
• Coaxial disk window : ▫ TW : 1000 kW 2 ms - 20
Hz▫ SW : 1000 kW 1.5 ms - 4
Hz
5-6 December 2012
SPL meeting, CERN
40
Acknowledgements• SPL coupler review committee :
▫ Ali Nassiri, Wolf Dietrich Moeller, Mark Champion, Sergey Kazakov, Mircea Stirbet, Amos Dexter, Rama Calaga, Miguel Jimenez, Sergio Calatroni, Ofelia Capatina, Vittorio Parma
• DESY :▫ Wolf-dietrich Moeller, Axel Matthaisen,
Birte Van der Horst, and local team
• CEA :▫ Stephane Chel, Guillaume Devanz, Michel
Desmond, and local team
• ESRF :▫ Jorn Jacob, Vincent Serriere, Loys, Jean-
Maurice Mercier, Didier Boillot
• APS :▫ Ali Nassiri, Doug Horan, Gian Trenko, Dave
Brubenker, and local team
• CERN :
▫ Mechanical & Material Engineering group : Francesco Bertinelli, Ramon Folch, Serge
Mathot, Agostino Vacca, Thierry Tardy, Thierry Calamand, Thierry Renaglia, Ofelia Capatina, Marc Polini, Laurent Deparis, Philippe Frichot, Jean-Marie Geisser, Jean-Marc Malzacker, Pierre Moyret, Alain Stadler
▫ Vacuum, Surface & Coating group : Miguel Jimenez, Sergio Calatroni,
Wilhelmus Vollenberg, Marina Malabaila, Nicolas Zelko
▫ Magnets, Superconductors & Cryostats : Vittorio Parma, Arnaud Van de Craene,
▫ RF group : Sebastien Calvo, Antoine Boucherie, all
FSU-BE03 members
5-6 December 2012
SPL meeting, CERN
41
Thank you very much for your attention
5-6 December 2012