SPL power coupler
description
Transcript of SPL power coupler
Eric Montesinos / CERN-BE-RF-SR
Possible proposed designsPart II : designs comparison
SPL power coupler
16/03/2010
2
Eric Montesinos / CERN-BE-RF-SR
Summary
Comparison of proposed designs: SPL-CEA coaxial disk
water cooled window SPL-SPS coaxial disk air
cooled window SPL-LHC cylindrical air
cooled window Design issues
Waveguides Titanium coating RF simulations Coupling box
Construction process
Conditioning process
Mass production
New proposed schedule
Conclusion16/03/2010
Eric Montesinos / CERN-BE-RF-SR
3
Three possible remaining designs
16/03/2010
All use the same double walled tube All use the same vacuum gauge, electron monitor and arc
detector We have designed them to be compatible without modifying
the cryomodule
Eric Montesinos / CERN-BE-RF-SR
4
Three possible remaining designs
16/03/2010
SPL-CEA HIPPI coaxial disk water cooled window SPL-SPS coaxial disk air cooled window SPL-LHC cylindrical air cooled window
5
Eric Montesinos / CERN-BE-RF-SR
Coaxial disk water cooled window
CEA design based on a coaxial disk ceramic window as in operation at KEKB and SNS, modified for 704MHz
Advantages High power capability, tested up to 1MW with
2ms / 50Hz on warm test cavity and on cold cavity last week
Matched window, this allows to easily change the waveguide position
Commercially produced window (Toshiba)
Drawbacks Window and antenna are water cooled:
Not following CERN vacuum group recommendations
Needs accurate mounting Difficult DC HV biasing due to water:
Need insulating pipes (X-rays, radiation,... More maintenance and operational costs)
Need a second air cooling circuit for the waveguide: Doubles the operational needs: water and air
systems
16/03/2010
Antenna and outer ceramic water cooling
Waveguide air cooling
6
Eric Montesinos / CERN-BE-RF-SR
Coaxial disk water cooled window
Quite complex brazing process (compare to SPS and LHC)
Water seal to be modified from organic (acceptable for test) to metallic (for long term operation without maintenance)
the tolerances are very tight
No flexibility for the antenna: Stress to the ceramic RF contact depends on tolerances Possible water leak if misalignment
(already happened)
16/03/2010
7
Eric Montesinos / CERN-BE-RF-SR
Coaxial disk air cooled window
Design based on a coaxial disk ceramic window similar as the one in operation on the CERN SPS TWC 200MHz power load
Advantages Very simple and well mastered brazing of
ceramic onto a titanium flange High power capability (500kw cw) Very easy to cool with air Waveguide as “plug and play” mounting,
absolutely no stress to the antenna DC HV biasing very simple, with again a
“plug and play” capacitor fitting, and again no stress to the ceramic due to finger contact
Least expensive of the three couplers !
Minor drawback Ceramic is part of the matching system,
fixes the waveguide position
16/03/2010
Antenna and outer ceramic air cooling
Ceramic and waveguide air cooling
8
Eric Montesinos / CERN-BE-RF-SR
Coaxial disk air cooled window
Very simple brazing process: Titanium outer flange:
Dilatation coefficient near ceramic Surface hard enough for vacuum
copper seals Inner tube in copper 1.2mm
thickness to allow easy brazing
Antenna inner upper part has been designed: With spring washers for a good
RF contact between the upper and lower inner conductor sections
Without any stress to the ceramic Allowing a correct air flow
16/03/2010
Spring washers
RF contact
SPS Window: very simple brazing process
RF contact without stress to the ceramic by compression of the outer line through the
air “cane”
Air “cane”
9
Eric Montesinos / CERN-BE-RF-SR
“Plug and play” waveguide system
Need additional 50 Ω outer lines: Vacuum side for monitoring
vacuum, electron, light, … Air side for RF matching and for air
cooling of the ceramic
“Plug and play” waveguide and biasing capacitor
There is a finger contact all around the capacitor to avoid stress on the ceramic
This waveguide mounting method has already been used successfully for the LHC couplers
16/03/2010
10
Eric Montesinos / CERN-BE-RF-SR
Cylindrical air cooled window
Design based on the same cylindrical window as the LHC couplers: Long and difficult process to achieve reliability of
the window, the final design was obtained after more than six years of studies
As the design was complex, we keep it exactly as it is
Instead of changing the ceramic design we have adapted the line to the ceramic
Advantages High power capability window, LHC proven (575kW
cw full reflection, could be more…) Simple to cool with air Absolutely free of mechanical stress on the
antenna Same “plug and play” waveguide and DC capacitor
as previous design, no stress to the ceramic Simplest version to assemble !
Drawbacks Ceramic is part of the matching system, fixes the
waveguide position Possible multipacting due to the outer conical
outer line
16/03/2010
Ceramic and waveguide air cooling
11
Eric Montesinos / CERN-BE-RF-SR
Cylindrical air cooled window
LHC window is a huge improvement over the LEP window, with less losses and higher power capability
We still not know the upper power limit of the LHC window The LHC coupler were powered up to
575kW cw full reflection (SW) for several hours all phases
Klystrons failed, not the coupler !
The LHC window appears to be really robust To date 30 LHC couplers have been built
and tested, 16 are in operation in LHC
A new coupler using exactly the same ceramic window is under construction for ESRF and SOLEIL → Standardization of the ceramic
16/03/2010
ESRF-LHC new design
First EB welding(mechanical)
Second EB welding(mechanical and vacuum)
Third EB welding(mechanical and vacuum)
LHC window:Two solid copper collars brazed to the ceramic
12
Eric Montesinos / CERN-BE-RF-SR
“Plug and play” waveguide system
Same “Plug and play” waveguide and biasing capacitor as with the coaxial air cooled window
The waveguide has just one contact with the body line
There is a finger contact all around the capacitor to avoid stress on the ceramic
16/03/2010
13
Eric Montesinos / CERN-BE-RF-SR
Comparison: Titanium coating
LHC, coating done twice: First coating on the top and the
bottom edges of the ceramic (electrical continuity)
Brazing of the copper collars Second coating on the inside of the
ceramic → Double the costs
SPS, only one coating: Straight forward Done after brazing
Toshiba process: Probably one coating What about the part of ceramic
masked by the chokes?
16/03/2010
First coating:R = 0.5 MΩ
Second coating:R = 2 MΩ
One coating:R = 2 MΩ
One coating:R = 2 MΩ
What about the part of ceramic behind the choke ?
?
14
Eric Montesinos / CERN-BE-RF-SR
Comparison: S11 simulations
Cavity bandwidth704 MHz / Qext (1.2 x 106) =
586 HzDesign
Center frequency
[MHz]
Bandwidth< - 25 dB
[MHz]CEA 702.8 25.2LHC 704.2 13.2SPS 704.4 26.2
16/03/2010
SPL-CEA
SPL-SPSSPL-LHC
15
Eric Montesinos / CERN-BE-RF-SR
Comparison: Field Strength
16/03/2010
SPL-CEA
SPL-LHC SPL-SPS
Max 751 kV/mwith 1MW
Max 880 kV/mwith 1MW
Max 866 kV/mwith 1MW
Hodgman, Charles D. & Norbert A. Lange. Handbook of Chemistry and Physics 10th Edition. Cleveland, OH: Chemical Rubber Publishing Co, 1925: 547.
"Spark length (cm), .10; Point electrodes, 3720;
Ball electrodes, 1 cm diameter:
Steady potential, 4560; Alternating potential, 44
00"
3.7–4.5 MV/m
Tipler, Paul A. College Physics. Worth, 1987: 467.
"This phenomenon, which is called dielectric breakdown, occurs in air
at an electric field strength of about
Emax = 3 × 106 V/m."
3.0 MV/m
Rigden, John S. Macmillan Encyclopedia of Physics. Simon & Schuster, 1996: 353.
Air; Dielectric Constant, 1; Strength Es (kV/mm),
33.0 MV/m
Riley, Lewis A. Dielectrics. 1999-2000.
"The dielectric strength of air is about 3 × 106 V/m"
3.0 MV/m
16
Eric Montesinos / CERN-BE-RF-SR
Waveguides options
If needed, LHC design could be done with a “coaxial conical” extension line to change the waveguide position
We simulated the waveguide with steps to check effects on the field distribution, it reduces the field strength
Using a waveguide without doorknob considerably eases the mounting and reduces the cost (as LHC)
Immediately after the coupler waveguide flange, there will be a flexible waveguide to reduce mechanical stresses
Nevertheless, a supporting tool will be necessary for the coupler waveguide, still to be studied
16/03/2010
Doorknob / reduced height: ~ same field strength
Two steps waveguide: slightly reduces the field strength
LHC design with a
possible conical coaxial
extension to change the waveguide
axis
Eric Montesinos / CERN-BE-RF-SR
17
Comparison
16/03/2010
Item Coaxialwater cooled
Coaxialair cooled
CylindricalAir cooled
A single window coupler
Possible adjustable coupler
Integration in the cryomodule Vertically above or below the cavity
DC biasing
Air cooled
Matched window
“Plug and play waveguide”
18
Eric Montesinos / CERN-BE-RF-SR
Coupling box
Will be used to: Connect two couplers in the vertical
position for conditioning Storage and transport chamber with
springs to damp shocks
Solid copper: Low RF losses Strong enough to sustain deformation
due to strong pressure effects Extra external mechanical
adjustment for frequency tuning
Could be EB soldered or assembled from two parts: Vacuum seal Easy to clean, we want to re-use it for
250 couplers !
16/03/2010
Springs to avoid any
shock while transporting
19
Eric Montesinos / CERN-BE-RF-SR
Construction process We plan to follow an upgraded
LHC coupler construction process:
Build all components: Metrologic controls Mechanical and thermal tests
In clean room (class 100): clean all parts in contact with beam
vacuum with pure water or pure alcohol
Particle counting to validate the cleaning
In clean room (class10): assemble a pair of couplers and
mount them on a test cavity Bake out RF conditioning In clean room (class 10):
mounting of coupler with its double walled tube on SPL cavity
Build all components
In clean room: clean all parts in contact with beam vacuum
In clean room: assemble a pair of couplers and mount them onto a coupling box
Bake out
RF conditioning
Double walled tube and coupler mounted onto the cavity
16/03/2010
Vacuum leak detections after each
major operation
20
Eric Montesinos / CERN-BE-RF-SR
Construction process
To be carefully followed-up: Assembly tooling Handling with special gloves only,
avoid contamination of surfaces by hydrocarbons, finger prints,…
Optimize the process to minimize the number of handlings
Avoid intermediate packing in polymeric sealed bags (contamination)
Specially designed transport containers
Visit tomorrow of the three facilities: Building 252 class 100 clean room Building 252 class 10 clean room Building SM18 class 10 clean room Would like advice on what we could
improve for high gradient cavities
16/03/2010
21
Eric Montesinos / CERN-BE-RF-SR
Conditioning process
Install one cavity with its two power couplers and prepare for conditioning
List of interlocks and monitoring: Vacuum gauges Directional couplers
Light detector Electron monitor Thermal measurements Gas analyzer Air flow meter Water flow meter (power load) …
The tests will be done at CEA Saclay
16/03/2010
TTF III power coupler test bench
Eric Montesinos / CERN-BE-RF-SR
22
Conditioning process
16/03/2010
The conditioning loop will be the same as the one used since 1998 with the SPS and LHC couplers: A first direct vacuum loop (red) ensures RF is never applied if pressure exceeds 5.0 x 10 -7 mbar A second vacuum loop (blue), cpu controlled, executes the automated process The interlock vacuum threshold of 5.0 x 10-7 mbar will be chosen, guided by our experience, to protect
the couplers, but also to have an as short as possible conditioning time The settings are adjusted to have minimum attenuation under 1.0 x 10-8 mbar and maximum attenuation
over 2.5 x 10-7 mbar (~40 dB dynamic range with the attenuator)
HF + AM + FMGenerator
Computer controlled attenuator
Vacuum controlled attenuator
RF switch Amplifier CavityInput Coupler Output Coupler Terminating load
CPU
Vacuum analog loop
Vacuum distribution
Vacuum Gauges
Vacuum Gauges
Power measurment
Power measurment
23
Eric Montesinos / CERN-BE-RF-SR
Conditioning process
The conditioning process will be similar to the LHC one:
The process always starts, under vacuum control, with very short pulses of 20 µs every 20 ms
Power level is increased using short pulses up to full power passing slowly through all power levels to avoid “de-conditioning”
Same procedure repeated for initially short then longer and longer pulses up to the maximum length
The conditioning process will be considered finished when the vacuum level decreases below a predefined level (1 x 10-8 mbar for example), while ramping the maximum length pulse
16/03/2010
24
Eric Montesinos / CERN-BE-RF-SR
Double walled tube rough estimate: 15’000 CHFCoupling box rough estimate: 25’000 CHF
16/03/2010
Part List coupling boxRep Nb Désignation Matière
Prix matière (CHF)
Prix MO (CHF)
Prix global (CHF)
1 1 COUVERCLE SUPERIEUR CUIVRE OFE 2000 1600 3600
2 1 COUVERCLE INFERIEUR CUIVRE OFE 2000 800 2800
3 1 BRIDE ENTRÉE INOX 316 LN 444 1200 1644
4 1 BRIDE SORTIE INOX 316 LN 444 1200 1644
5 1 TUBE PIQUAGE VIDE CUIVRE OFE 15 400 415
6 1 BRIDE VIDE INOX 316 LN 164 400 564
Equipement de protection pour le transport 14500
Total 5067 5600 25167
Part List tube double SPLRep Nb Désignation Matière
Prix matière (CHF)
Prix MO (CHF)
Prix global (CHF)
1 1 TUBE CONNECTION HELIUM INOX 10 400 410
2 1 FLASQUE VIDE D ISOLATION INOX 2000 2000 4000
3 2 CORPS INOX FORGE 3D 1500 6000 7500
4 1 1/2 COQUILLES INOX 50 2000 2050
5 1 TUBE CONNECTION HELIUM INOX 10 400 410
Total 3570 10800 14370
25
Eric Montesinos / CERN-BE-RF-SR
SPL-CEA rough estimate:53’000 CHF
16/03/2010
Part List coupleur SPL type CEARep Nb Désignation Matière
Prix matière (CHF)
Prix MO (CHF)
Prix global (CHF)
1 1 BRIDE SUPERIEURE BODY CUIVRE 100 1600 17002 1 ENTRETOISE SUPERIEUR BODY CUIVRE 230 1600 18303 1 COUPELLE SUPERIEUR BODY CUIVRE 180 2000 21804 1 RACCORD ANTENNE CUIVRE 80 800 880
5 1BAGUE SUPERIEUR DE CENTRAGE ANTENNE CUIVRE 40 1000 1040
6 1 TUBE INTERIEUR CERAMIQUE CUIVRE 25 1000 10257 1 CERAMIQUE OXYDE D' ALUMINIUM 300 3000 33008 1 ENTRETOISE CENTRALE INTERNE BODY CUIVRE 1 800 8019 1 TUBE CONNECTION REFROIDISSEMENT INOX 2 400 402
10 1 PATTE CONNECTION REFROIDISSEMENT CUIVRE 300 400 70011 1 CAPOT DE REFROIDISSEMENT BODY CUIVRE 180 2000 218012 1 COUPELLE INFERIEURE BODY CUIVRE 180 2000 218013 1 ENTRETOISE CENTRALE EXTERNE BODY CUIVRE 180 1600 178014 2 TUBE DE BRIDE UHV CUIVRE 5 500 50515 1 BRIDE UHV INOX 10 200 21016 1 DETECTEUR 800 2500 330017 1 BRIDE INFERIEURE BODY INOX CUIVRE 150 1400 155018 1 BRIDE UHV JAUGE INOX 116 400 51619 1 JAUGE A VIDE PENNING IKR 070 900 90020 1 CONNECTION DOORKNOBS ANTICORODAL 20 400 42021 1 DOORKNOBS ANTICORODAL 150 2000 215022 1 BRIDE DOORKNOBS ANTICORODAL 70 1000 107023 1 GUIDE D' ONDE ANTICORODAL 300 2000 230024 1 ENTRETOISE GUIDE D' ONDE ANTICORODAL 10 400 41025 1 BRIDE GUIDE D' ONDE ANTICORODAL 20 800 82026 1 TUBE ALLEE REFROIDISSEMENT INOX 2 200 20227 1 COUVERCLE ANTENNE INOX 2 200 20228 1 JOINT TORIQUE Ø3 EPDM 2 229 1 BRIDE COUVERCLE ANTENNE CUIVRE 6 500 50630 1 TUBE SORTIE REFROIDISSEMENT INOX 2 200 20231 1 ANTENNE SUPERIEURE CUIVRE FORGE 1500 1800 330032 1 VIS SPECIALE ACOUPLEMENT ANTENNES VIS INOX 1 400 40133 1 CONNECTION ANTENNE SUPERIEURE CUIVRE 4 500 50434 1 JOINT TORIQUE Ø3 EPDM 2 235 1 CANNE SUPERIEURE INOX 10 200 21036 1 FIXATION CANNE INFERIEURE INOX 5 400 40537 1 ACOUPLEMENT ANTENNE CUIVRE FORGE 800 1200 200038 1 ANTENNE INFERIEURE CUIVRE FORGE 1700 800 250039 1 BOUCHON ANTENNE CUIVRE FORGE 50 200 25040 1 CANNE INFERIEURE INOX 20 400 42041 1 BOUCHON CANNE INOX 5 800 80542 1 CANAL DE REFROIDISSEMENT INOX 10 200 210
Total 8470 37800 46270
26
Eric Montesinos / CERN-BE-RF-SR
SPL-SPS rough estimate:27’000 CHF
16/03/2010
Part List coupleur SPL type SPSRep Nb Désignation Matière Prix matière
(CHF)Prix MO (CHF)
Prix global (CHF)
1 1 CAPOT DE PROTECTION TOLE GRILLAGEE 15 400 415
2 2 BAGUE DE PROTECTION KAPTON PEEK NATUREL 1000 400 1400
3 1 CONDENSATEUR EXTERNE ANTICORODAL 135 800 935
4 1 KAPTON KAPTON 10 400 410
5 1 BAGUE DE SERRAGE ANTICORODAL 2 200 202
6 1 CONDENSATEUR INTERNE ANTICORODAL 40 800 840
7 1 CONTACT RF CUIVRE + DORAGE 50 200 250
8 1 SOCLE CONDENSATEUR ANTICORODAL 35 200 235
9 1 GUIDE D' ONDE ANTICORODAL 300 2000 2300
10 1 BONCHON GUIDE D' ONDE ANTICORODAL 35 200 235
11 1 SOCLE BODY ANTICORODAL 35 200 235
12 1 JOINT RF CUIVRE + DORAGE 0
13 1 BODY ANTICORODAL + CUIVRAGE 80 1000 1080
14 1 CAPOT DE VENTILATION INOX 20 500 520
15 1 JOINT PROFILE U EPDM 2 10 12
16 1 JOINT TORIQUE Ø2.5 EPDM 15 10 25
17 1 BRIDE TITANE TITANE 400 16 416
18 1 CERAMIQUE TITANISEE OXYDE D' ALUMINIUM 300 3000 3300
19 1 EXTENTION JAUGE A VIDE (2 BRIDES + TUBE) INOX + CUIVRAGE 1500 400 1900
20 1 JAUGE A VIDE PENNING IKR 070 900 900
21 1 BRIDE JAUGE A VIDE INOX 116 400 516
22 1 BAGUE DE SERRAGE ANTENNE INOX 2 1000 1002
23 1 BAGUE FILETEE INOX 5 1600 1605
24 1 CANNE INOX 20 400 420
25 1 ANTENNE SUPERIEURE CUIVRE 1700 1200 2900
26 1 INSERT TARAUDE INOX + ARGENTAGE 10 800 810
27 1 TUBE CERAMIQUE + INSERT INOX CUIVRE FORGE 200 800 1000
28 1 ANTENNE INFERIEURE CUIVRE FORGE 1700 800 2500
29 1 BOUCHON ANTENNE CUIVRE FORGE 50 200 250
Total 8677 17936 26613
27
Eric Montesinos / CERN-BE-RF-SR
SPL-LHC rough estimate:30’000 CHF
16/03/2010
Part List coupleur SPL type LHCRep Nb Désignation Matière Prix matière
(CHF)Prix MO (CHF)
Prix global (CHF)
1 1 CAPOT DE PROTECTION TOLE GRILLAGEE 15 400 415
2 2 BAGUE DE PROTECTION KAPTON PEEK NATUREL 1000 400 1400
3 1 CONDENSATEUR EXTERNE ANTICORODAL 135 800 935
4 1 KAPTON KAPTON 10 400 410
5 1 CONDENSATEUR INTERNE ANTICORODAL 40 800 840
6 1 CONTACT RF CUIVRE + DORAGE 50 200 250
7 1 SOCLE CONDENSATEUR ANTICORODAL 35 200 235
8 1 GUIDE D' ONDE ANTICORODAL 300 2000 2300
9 1 BONCHON GUIDE D' ONDE ANTICORODAL 35 200 235
10 1 SOCLE BODY ANTICORODAL 35 200 235
11 1 JOINT RF CUIVRE + DORAGE 0
12 1 COLLET SUPERIEUR CUIVRE FORGE 800 1600 2400
13 1 CERAMIQUE OXYDE D'ALUMINE 800 2000 2800
14 1 COLLET INFERIEUR CUIVRE FORGE 700 1600 2300
15 1 BODY CUIVRE 1800 2000 3800
16 1 BRIDE SUPERIEUR BODY INOX 90 400 490
17 1 BRIDE JAUGE A VIDE INOX 116 400 516
18 1 JAUGE A VIDE PENNING IKR 070 900 900
19 1 BRIDE TOURNANTE BODY INOX 500 400 900
20 1 BRIDE UHV BODY INOX 500 1600 2100
21 1 BAGUE DE SERRAGE ANTENNE INOX 2 400 402
22 1 CANNE INOX 20 200 220
23 1 BAGUE DE CENTRAGE ANTENNE INOX 2 400 402
24 1 ANTENNE SUPERIEURE CUIVRE FORGE 600 1200 1800
25 1 TUBE ANTENNE CUIVRE FORGE 2000 1200 3200
26 1 BOUCHON ANTENNE CUIVRE FORGE 50 200 250
Total 10535 19200 29735
Eric Montesinos / CERN-BE-RF-SR
28
Mass production
16/03/2010
Coaxial water cooled
Coaxialair cooled
CylindricalAir cooled
Unit prototype price: Coupler 53 kCHF 27 kCHF 30 kCHFEight bare couplers 424 kCHF 216 kCHF 240 kCHFUnit price: Double walled tube 15 kCHF 15 kCHF 15 kCHFUnit price: Coupling box 25 kCHF 25 kCHF 25 kCHFUnit price: Miscellaneous (clean room, leak detections, bake out, transports, …)
15 kCHF 15 kCHF 15 kCHF
Eight peripherals 340 kCHF 340 kCHF 340 kCHF
Eight couplers (+ 2 spare ceramics) 775 kCHF 550 kCHF 600 kCHF
Coupler unit price (no quantity reduction, including double walled tube 15kCHF, and Misc. 10kCHF)
78 kCHF 52 kCHF 55 kCHF
275 couplers(no test cavities, no conditioning process)
21’500 kCHF 14’500 kCHF 15’000 kCHF
29
Eric Montesinos / CERN-BE-RF-SR
ID Task Name
1
2 Design
3 Execution Drawings
4
5 Purchasing of CERN prototype ceramics
6 Coaxial air cooled coupler
7 Cylindrical air cooled coupler
8
9 Double walled tube Execution drawings
10 Double walled tube Construction
11
12 Tests Cavities Execution drawings
13 Tests cavities Construction
14
15 Prototypes Assembly + Bake out
16 Prototypes Conditioning and Tests
17
18 Series construction (for 8 + 2 couplers total)
19 Series bake out and conditioning
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May JunQtr 4, 2009 Qtr 1, 2010 Qtr 2, 2010 Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011 Qtr 3, 2011 Qtr 4, 2011 Qtr 1, 2012 Qtr 2, 2012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013
New proposed schedule
16/03/2010
Confirm the Saclay test stand availability in 2011:February and end of year?
Integrate advice and launch as soon as possible: One pair of coaxial air cooled window One pair of cylindrical air cooled
window
Have 2 pairs ready for tests beginning 2011
Decide which ones to construct in March 2011 (still three possible choices)
Construct remaining couplers in 2011
Have 8 fully ready and conditioned couplers beginning 2012
Today: coupler review
30
Eric Montesinos / CERN-BE-RF-SR
Conclusion: still a lot to do…
Eight couplers could be ready within two years: Necessarily based on
existing designs and very well known processes
Coaxial air cooled and cylindrical air cooled versions to be tried: Potentially inexpensive
for mass production Interesting for large
machines
Keep the coaxial water cooled option open: Study the modification
of the cooling from water to air
Redesign the waveguide transition for: Less stress to the
ceramic Easier DC biasing
16/03/2010
Eric Montesinos / CERN-BE-RF-SR
Many thanks for your patience
16/03/2010