K2partneringsolutionspresentation 13118580048926 Phpapp02 110728080107 Phpapp02
ce352chapter4bpipenetwork-121231034001-phpapp02
-
Upload
realmak-awa -
Category
Documents
-
view
217 -
download
0
Transcript of ce352chapter4bpipenetwork-121231034001-phpapp02
![Page 1: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/1.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 1/32
Civil Engineering Department
Prof. Majed Abu-Zreig
Hydraulics and Hydrology – CE 352
Chapter 4Chapter 4
Water Distribution Systems
6/29/2012 1
![Page 2: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/2.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 2/32
Node, Loop, and Pipes PipeNode
Loop
6/29/2012 2
![Page 3: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/3.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 3/32
Pipe Networks
• The equations to solve Pipe network must
satisfy the following condition:
• The net flow into any junction must be zero
• The net head loss a round any closed loop must
be zero. The HGL at each junction must have one
and only one elevation
• All head losses must satisfy the Moody and
minor-loss friction correlation
0=
∑Q
6/29/2012 3
![Page 4: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/4.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 4/32
Hydraulic AnalysisAfter completing all preliminary studies and
layout drawing of the network, one of themethods of hydraulic analysis is used to
• Size the pipes and• Assign the pressures and velocities
required.
6/29/2012 4
![Page 5: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/5.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 5/32
Hydraulic Analysis of Water Networks
• The solution to the problem is based on the same
basic hydraulic principles that govern simple andcompound pipes that were discussed previously.
• The following are the most common methods used
to analyze the Grid-system networks:1. Hardy Cross method.
2. Sections method.
3. Circle method.
4. Computer programs (Epanet,Loop, Alied...)
6/29/2012 5
![Page 6: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/6.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 6/32
Hardy Cross Method• This method is applicable to closed-loop pipe
networks (a complex set of pipes in parallel).
• It depends on the idea of head balance method
• Was originally devised by professor Hardy Cross.6/29/2012 6
![Page 7: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/7.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 7/32
Assumptions / Steps of this method:
1. Assume that the water is withdrawn from nodes only; notdirectly from pipes.
2. The discharge, Q , entering the system will have (+) value,and the discharge, Q , leaving the system will have (-) value.
3. Usually neglect minor losses since these will be small withrespect to those in long pipes, i.e.; Or could be included as
equivalent lengths in each pipe.4. Assume flows for each individual pipe in the network.
5. At any junction (node), as done for pipes in parallel,
∑ ∑= out in QQ Q =∑ 0or
6/29/2012 7
![Page 8: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/8.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 8/32
6. Around any loop in the grid, the sum of head losses must
equal to zero:
– Conventionally, clockwise flows in a loop are considered (+) and
produce positive head losses; counterclockwise flows are then (-) and
produce negative head losses.
– This fact is called the head balance of each loop, and this can be valid
only if the assumed Q for each pipe, within the loop, is correct.
• The probability of initially guessing all flow rates correctly is
virtually null.
• Therefore, to balance the head around each loop, a flow rate
correction ( ) for each loop in the network should becomputed, and hence some iteration scheme is needed.
h f loop
=∑ 0
∆
6/29/2012 8
![Page 9: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/9.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 9/32
7. After finding the discharge correction, (one for each
loop) , the assumed discharges Q0 are adjusted and anotheriteration is carried out until all corrections (values of ) become zero or negligible. At this point the condition of :
is satisfied.
Notes:• The flows in pipes common to two loops are positive in one
loop and negative in the other.
• When calculated corrections are applied, with carefulattention to sign, pipes common to two loops receive bothcorrections.
∆
∆
h f loop
≅∑ 0 0.
6/29/2012 9
![Page 10: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/10.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 10/32
How to find the correction value ( )∆
William Hazenn
Manning Darcyn
kQh nF
85.1
,2
)1(
⇒=
⇒= ⎯→ ⎯ =
)2( ⎯→ ⎯ ∆+= oQQ
( ) ( )
⎥⎦
⎤
⎢⎣
⎡
+∆
−
+∆+=∆+== −−
....2
1
2&1
221
f
n
o
n
o
n
o
n
o
n
Q
nn
nQQk Qk kQh
from
( )∆+== −1
f
n
o
n
o
nnQQk kQhNeglect terms contains 2∆
For each loop
6/29/2012
( ) 0
0
1=∆+=∴
==
∑∑∑
∑∑
−nno
n
loop
n
loop
F
nkQkQkQ
kQh
10
![Page 11: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/11.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 11/32
( )
∑
∑∑
∑ −=
−=∆
−
o
F
F
n
o
n
o
Q
h
n
h
nkQ
kQ
1
• Note that if Hazen Williams (which is generally used in this method) is
used to find the head losses, then
h k Q f = 185.(n = 1.85) , then
∆ =− ∑
∑
h
h
Q
f
f 185.
• If Darcy-Wiesbach is used to find the head losses, then
h k Q f = 2(n = 2) , then
∆ =
−∑
∑
h
h
Q
f
f 26/29/2012 11
l
![Page 12: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/12.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 12/32
Example
Solve the following pipe network using Hazen William Method CHW
=100
6/29/2012 12
DLpipe
150mm305m1
150mm305m2
200mm610m3
150mm457m4
200mm153m5
1
23
4
5
37.8 L/s
25.2 L/s
63 L/s
24
3 9
1 1 .
4
1 2 . 6
2 5. 2
0 71 L
![Page 13: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/13.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 13/32
6/29/2012 13
( )24.0
64.085.1
28.01 −=
−=
−=∆
∑
∑
o
F
F
Q
hn
h
{ }
1002.6
1000
0.71
L/s ,100 0.71
852.1
852.1
87.4
9
852.1
87.4852.1
852.1
87.4852.1
QK h
Q D
Lh
Q
DC
Lh
inQC Q DC
Lh
f
f
HW
f
HW
HW
f
=
⎭⎬⎫
⎩⎨⎧
×=
⎟
⎠
⎞⎜
⎝
⎛ =
==⇒=
−
( )57.0
43.085.1
45.02 −=
−=
−=∆
∑
∑
o
F
F
Q
hn
h
1
23
4
5
12
21
2loopin2 pipefor
1loopin2 pipefor
∆−∆=∆
∆−∆=∆
![Page 14: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/14.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 14/32
1
23 4
5
6/29/2012 14
( )15.0
64.085.1
18.01 −=
−=
−=∆
∑
∑
o
F
F
Q
hn
h ( )( )
09.042.085.1
07.01 −=
−=
−=∆
∑
∑
o
F
F
Q
hn
h
12
21
2loopin2 pipefor
1loopin2 pipefor
∆−∆=∆
∆−∆=∆
![Page 15: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/15.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 15/32
General Notes
6/29/2012 15
• Occasionally the assumed direction of flow will be incorrect. In suchcases the method will produce corrections larger than the originalflow and in subsequent calculations the direction will be reversed.
• Even when the initial flow assumptions are poor, the convergencewill usually be rapid. Only in unusual cases will more than threeiterations be necessary.
• The method is applicable to the design of new system or toevaluation of proposed changes in an existing system.
• The pressure calculation in the above example assumes points are at
equal elevations. If they are not, the elevation difference must beincludes in the calculation.
• The balanced network must then be reviewed to assure that the
velocity and pressure criteria are satisfied. If some lines do not meetthe suggested criteria, it would be necessary to increase thediameters of these pipes and repeat the calculations.
![Page 16: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/16.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 16/32
Summary
6/29/2012 16
• Assigning clockwise flows and their associated head
losses are positive, the procedure is as follows:
Assume values of Q to satisfy ∑Q = 0.
Calculate HL from Q using hf = K1
Q 2
. If ∑hf = 0, then the solution is correct.
If ∑hf ≠ 0, then apply a correction factor, ∆Q, to all
Q and repeat from step (2). For practical purposes, the calculation is usually
terminated when ∑hf < 0.01 m or ∆Q < 1 L/s.
A reasonably efficient value of ∆Q for rapidconvergence is given by;
∑
∑−=∆
QH2
HQ
L
L
∑
∑−=∆
QH2
HQ
L
L
![Page 17: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/17.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 17/32
Example
6/29/2012 17
• The following example contains nodes with different
elevations and pressure heads.• Neglecting minor loses in the pipes, determine:
• The flows in the pipes.
• The pressure heads at the nodes.
![Page 18: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/18.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 18/32
Assume T= 150C
6/29/2012 18
![Page 19: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/19.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 19/32
Assume flows magnitude and direction
6/29/2012 19
![Page 20: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/20.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 20/32
First Iteration
• Loop (1)
Pipe L
(m)
D
(m)
Q
(m3 /s) f
h f
(m)
h f /Q
(m/m3 /s)
AB 600 0.25 0.12 0.0157 11.48 95.64
BE 200 0.10 0.01 0.0205 3.38 338.06
EF 600 0.15 -0.06 0.0171 -40.25 670.77
FA 200 0.20 -0.10 0.0162 -8.34 83.42
-33.73 1187.89
L/s20.14/sm01419.0)89.1187(2
73.33 3==
−−=∆
6/29/2012 20
![Page 21: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/21.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 21/32
First Iteration
• Loop (2)
Pipe L
(m)
D
(m)
Q
(m3 /s) f
h f
(m)
h f /Q
(m/m3 /s)
BC 600 0.15 0.05 0.0173 28.29 565.81
CD 200 0.10 0.01 0.0205 3.38 338.05
DE 600 0.15 -0.02 0.0189 -4.94 246.78
EB 200 0.10 -0.01 0.0205 -3.38 338.05
23.35 1488.7
L/s842.7/sm00784.0)7.1488(2
35.23 3−=−=−=∆
6/29/2012 21
14 20
![Page 22: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/22.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 22/32
14.20
14.20
14.20 7.8414.20
Second Iteration
• Loop (1)
6/29/2012 22
Pipe L
(m)
D
(m)
Q
(m3 /s) f
h f
(m)
h f /Q
(m/m3 /s)
AB 600 0.25 0.1342 0.0156 14.27 106.08
BE 200 0.10 0.03204 0.0186 31.48 982.60
EF 600 0.15 -0.0458 0.0174 -23.89 521.61
FA 200 0.20 -0.0858 0.0163 -6.21 72.33
15.65 1682.62
L/s65.4/sm00465.0)62.1682(2
65.15 3−=−=−=∆
7 84
![Page 23: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/23.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 23/32
Second Iteration14.20
7.84
7.84
7.84 7.84
• Loop (2)
Pipe L
(m)
D
(m)
Q
(m3 /s) f
h f
(m)
h f /Q
(m/m3 /s)
BC 600 0.15 0.04216 0.0176 20.37 483.24
CD 200 0.10 0.00216 0.0261 0.20 93.23
DE 600 0.15 -0.02784 0.0182 -9.22 331.23
EB 200 0.10 -0.03204 0.0186 -31.48 982.60
-20.13 1890.60
L/s32.5/sm00532.0)3.1890(2
13.20 3==−−=∆
6/29/2012 23
![Page 24: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/24.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 24/32
Third Iteration
• Loop (1)
Pipe L
(m)
D
(m)
Q
(m3 /s) f
h f
(m)
h f /Q
(m/m3 /s)
AB 600 0.25 0.1296 0.0156 13.30 102.67
BE 200 0.10 0.02207 0.0190 15.30 693.08
EF 600 0.15 -0.05045 0.0173 -28.78 570.54
FA 200 0.20 -0.09045 0.0163 -6.87 75.97
-7.05 1442.26
L/s44.2/sm00244.0)26.1442(2
05.7 3==
−−=∆
6/29/2012 24
![Page 25: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/25.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 25/32
![Page 26: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/26.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 26/32
After applying Third correction
6/29/2012 26
![Page 27: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/27.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 27/32
Velocity and Pressure Heads:
pipeQ
(l/s)
V
(m/s)
h f
(m)
AB 131.99 2.689 13.79
BE 26.23 3.340 21.35
FE 48.01 2.717 26.16
AF 88.01 2.801 6.52
BC 45.76 2.589 23.85
CD 5.76 0.733 1.21
ED 24.24 1.372 7.09
1.2121.35
13.79 23.85
6.52
26.16 7.09
6/29/2012 27
![Page 28: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/28.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 28/32
Velocity and Pressure Heads:
Node p/ γ +Z
(m)
Z
(m)
P/ γ
(m)
A 70 30 40
B 56.21 25 31.21
C 32.36 20 12.36
D 31.15 20 11.15
E 37.32 22 15.32
F 63.48 25 38.48
1.2121.35
13.79 23.85
6.52
26.16 7.09
6/29/2012 28
![Page 29: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/29.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 29/32
Example
For the square loop shown, find the discharge in all the pipes.All pipes are 1 km long and 300 mm in diameter, with a friction
factor of 0.0163. Assume that minor losses can be neglected.
6/29/2012 29
S l ti
![Page 30: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/30.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 30/32
•Solution:
Assume values of Q to satisfy continuity equations allat nodes.
The head loss is calculated using; HL = K1Q 2
HL = hf + hLm
But minor losses can be neglected: ⇒ hLm = 0
Thus HL = hf
Head loss can be calculated using the Darcy-Weisbach
equation
g2
V
D
Lh
2
f λ=
6/29/2012 30
g2
V
D
LhH
2
f L λ==
![Page 31: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/31.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 31/32
First trial
Since ∑HL > 0.01 m, then correction has to be applied.
554'K
Q'K H
Q554H
3.0x4
Qx77.2
A
Q77.2H
81.9x2
Vx
3.0
1000x0163.0H
g2D
2L
2L
22
2
2
2
L
2
L
=∴
=
=
⎟ ⎠
⎞⎜⎝
⎛ π==
=
Pipe Q (L/s) HL (m) HL/Q
AB 60 2.0 0.033
BC 40 0.886 0.0222
CD 0 0 0
AD -40 -0.886 0.0222
Σ 2.00 0.0774
6/29/2012 31
![Page 32: ce352chapter4bpipenetwork-121231034001-phpapp02](https://reader030.fdocuments.in/reader030/viewer/2022021121/5695cf5c1a28ab9b028dbdb4/html5/thumbnails/32.jpg)
7/23/2019 ce352chapter4bpipenetwork-121231034001-phpapp02
http://slidepdf.com/reader/full/ce352chapter4bpipenetwork-121231034001-phpapp02 32/32
Second trial
Since ∑HL ≈ 0.01 m, then it is OK.
Thus, the discharge in each pipe is as follows (to the nearest integer).
s/L92.120774.0x2
2
QH
2
HQ
L
L −=−=∑
∑−=∆
Pipe Q (L/s) HL (m) HL/Q
AB 47.08 1.23 0.0261
BC 27.08 0.407 0.015
CD -12.92 -0.092 0.007
AD -52.92 -1.555 0.0294
Σ -0.0107 0.07775
Pipe Discharge
(L/s)
AB 47
BC 27
CD -13
AD -536/29/2012 32