Case Study: Hazard Assessment of Ethylene and LNG Loading ...eurocorr.efcweb.org/2017/abstracts/PS...
Transcript of Case Study: Hazard Assessment of Ethylene and LNG Loading ...eurocorr.efcweb.org/2017/abstracts/PS...
1
Case Study: Hazard Assessment of Ethylene and LNG Loading-Unloading Process in
Cirebon Port
Hary DEVIANTO1, Mitra EVIANI2, Isdiriayani NURDIN3, Pramujo WIDIATMOKO4
1Institut Teknologi Bandung, Bandung, Indonesia, [email protected]
2Ministry of Energy and Mineral Resources Republic of Indonesia LEMIGAS, Jakarta,
Indonesia, [email protected] 3Institut Teknologi Bandung, Bandung, Indonesia, [email protected]
4Institut Teknologi Bandung, Bandung, Indonesia, [email protected]
Abstract
Cirebon Port under PT Pelabuhan Indonesia II (Persero) Cirebon is located in West Java, Indonesia,
which has spacious work and water area that provides opportunities for Cirebon port to be developed
in industrial sectors, particularly the petrochemical industries. One of the petrochemical industry
activities that is done in the port area is loading and unloading the raw materials, such as liquefied
natural gas (LNG) and ethylene.
In atmospheric condition, ethylene and LNG is classified as volatile gas. Ethylene in the storage
system still has a probability to be released to the environment and may lead to a fire or explosion, and
is increased in the existence of coal stock pile in the port area which can evoke a fire if it reaches its
autoignition temperature. Therefore, a safety study is needed to identificate the hazard and risk of the
ethylene and LNG loading and unloading activities. From the safety study, a suitable handling and
safety system can be recommended to ensure the activities’ safety viability. The safety study for this
activity was done between two regions of the port; close to the sea and coal stockpile.
Keywords
Hazard assessment; LNG; ethylene; loading and unloading process; quantitative risk assessment
(QRA)
2
Introduction
Cirebon Port, managed by PT. Pelabuhan Indonesia II (PELINDO II), located on the north
coast of West Java approximately 250 km from Jakarta to the east. Geographically, this port is
located at coordinates 6° 42' 55.6" S and 108° 34' 13.89" E. This harbor area has a working
area of 51 hectares and seawater area of 8.410,91 hectares. In this area, Cirebon Port is
expected to accommodate all needs in supporting the loading and unloading activities of
goods including petrochemical industry raw materials such as ethylene, propylene, LNG,
LPG, and butadiene. Figure 1 shows the map of Cirebon Port area.
Figure 1. Map of Cirebon Port.
Problems
This Cirebon Port (PELINDO II) will be used as a place for loading and unloading certain
chemicals for petrochemical industry raw materials, such as Liquefied Natural Gas (LNG) and
Ethylene. The loading and unloading terminal are located at the former location of Pelita
Stock Pile Coal.
The loading and unloading process of LNG and Ethylene is done without using a temporary
storage tank on the ground (floating storage/direct from ship to filling shed using pipeline).
LNG and ethylene are included in hazardous materials because it is highly flammable and
must be stored in cryogenic temperatures. In addition, LNG and ethylene storage adjacent to a
coal deposit may cause explosion and fire hazards. Therefore, it is necessary to study the
identification of the potential hazards of the plan for placing the filling shed in the Pelita
Stock Pile area.
3
Methods
The analysis of risk assessment of LNG loading and unloading at Cirebon Port was conducted
using the following methodologies:
1. Literature study
2. Determine the jetty location
In this step, the selection of jetty location is done by considering several factors such as
economic considerations and the effectiveness of gas transmission to the filling shed.
3. Identification of hazardous nodes
Nodes are identified based on potential hazards that may serve as initiating events. The
reference used is CCPS (Center for Chemical Process Safety) issued by AIChE (American
Institute of Chemical Engineers).
4. Qualitative risk assessment
From the nodes that have been identified are selected nodes that can cause accidents with
the most harmful impacts if occurred. The selection is based on the operating conditions,
the type of fluid, and the possibility of corrosion in the relevant nodes. In the selected
nodes, the hazards are further evaluated along with possible accident scenarios.
5. Quantitative risk assesment
The risks then evaluated quantitatively by:
a. Calculate the frequency and probability of the consequences of each occurrence that
often occurs on hazardous nodes using event tree and fault tree analysis. This analysis
is intended to facilitate in quantifying the consequences of each hazard. Each initial
event along with possible event stages that culminate in a given scenario are
evaluated. References used in determining frequency and probability are OREDA
(Offshore Reliability Database) textbooks and from UK HSE Body (UK).
b. Calculate the consequences of each hazard by using dispersion analysis. Analysis is
done with the help of ALOHA ver 5.4.4 software taking into account the assumptions.
From each dispersion model it can be estimated the number of accidents (N) based on
literature such as IRPA and PLL as well as a logical consideration of other similar
events. The number of accidents (N) states the likelihood of an accident causing
fatality.
c. Put the frequency and consequences of each of the dangers on the F-N curve
(Frequency to the Consequences) so that the tolerability of the hazard can be known,
for example the danger is included in the category acceptable, ALARP (as low as
reasonably practicable), or unacceptable. Therefore, it can be said that the F-N curve
can give a conclusion whether a risky event is safe or not. Note that events with
ALARP or unacceptable categories that need to be anticipated.
6. Finally, recommendations and their implementations are selected as a solution to reduce
the risk of incidents that belong to ALARP or unacceptable categories, so that all events
are safe; most importantly, the loading and unloading can be done as desired. Risk
reduction efforts must be balanced with cost considerations. In other words, the risk is
attempted to be tolerable or eliminated at the lowest possible cost.
Considerations and assumptions used in this assessment are:
1. The location of the filling shed area is at the coordinate range of 6° 42' 46.92" S - 6° 42'
47.49" S to 108° 34' 12.75" E - 108° 34' 16.42" E. There are several areas adjacent to the
filling shed locations such as floating storage, coal stock piles, workshop, and office
buildings.
2. Wind speed and direction data at Port-Cirebon is obtained from BMKG (Meteorology
Climatology and Geophysics Agency) on 26-27 April 2015. Wind speed of 6.94 m / s
4
leads to the Northwest. In addition, the height at related sites is 2.1 - 2.4 meters above sea
level. The ambient temperature is 24-33 ° C with an average of 28.5 ° C with an air
humidity of 57-92% with an average of 75% (wet).
3. Assumed, the rate of air change: 1.33/ hour (unsheltered single storied), the environment
around the land is open country (terrain terrain, many buildings). Cloud-covered weather
conditions: 5 tenths (partly cloudy), and stability Class is D (auto).
4. LNG and ethylene loading and unloading is done without using a temporary storage tank
on the ground (floating storage from ship to filling shed using pipes, then transported to
the truck tank).
5. The assumption of LNG in the vessel has a pressure of 10 barg and temperature of -
125°C.
6. Horizontal cylindrical LNG tank on truck with capacity 25,000 L, 2 m in tank diameter
and 7.96 m in length. The amount of LNG inserted into the tank meets 80% of the volume
of the tank. For the tank on the truck, it is assumed the leak occurs only at the bottom of
the tank.
Results and Discussions
Evaluation of Jetty Location and Nodes
The jetty is selected to be in the same area as the filling shed location. The reason for this
selection is that as compared to the ship's dock at the other two locations, the distance
between the unloading point and the filling shed entry point becomes the shortest so that:
1. The cost of procurement and installation of pipes becomes the cheapest
2. Pipeline maintenance and maintenance needs become smaller
3. Possible location of leakage occurrence becomes the least
4. In case of pipeline leakage, the leak point becomes more easily detected and found.
Nodes that become the probable point of initiating event are presented in Table 1. Nodes
become dangerous because they contain flammable matters and electricity.
Table 1. Nodes list.
Node (s) Description
Node 1 Storage tanker
Node 2 Unloading arm
Node 3 Piping System
Node 4 Filling shed
Node 5 Container
Node 6 Coal stockpile
Node 7 Compressor
Node 8 Genset
Node 9 Electricity substation
Node 10 Water storage tank
Node 11 Pump House PMK
The nodes are then evaluated to prioritize nodes that can generate the most likely accident
with the most harmful impacts if they occur. The selection is based on the operating
conditions, the type of fluid, as well as the possibility of corrosion in the relevant nodes.
Therefore, nodes 1-6 are selected, because:
1. Equipment at nodes 1-5 operates at a high pressure, ie 12 bar and a temperature of -25.8 °
C so at risk of sudden increase in pressure and temperature
2. The equipment on nodes 1-5 is made of carbon steel material so that the possibility of
high corrosion can end up in leakage
5
3. Equipment in nodes 1-5 contains flammable fluids which when released into the air due to
leakage and there is a source of fire, there may be a fire or even an explosion if the release
of energy is so rapid
4. Node 6 contains an open flammable matters mound of coal that is very easily ignited due
to heat from the outside
5. The possibility of accidents on nodes 1-6 is generally difficult to prevent from the
beginning except with regular inspections and maintenance. Meanwhile, nodes 7-10 are
not selected even though it is possible to cause a fire because the possibility of accident on
nodes 7-11 more likely to be prevented from the beginning.
The evaluation of these Nodes 7-11 is shown in Table 2.
Table 2. Preventive actions on Nodes 7-11.
Nodes Description Hazard Risk Mitigation
Node 7 Compressor The fluid flow rate
inside the
compressor is too
small or too large
(outside the safe
operating range)
There is a vibration
that leads to the
explosion of the
compressor
because the area of
operation is on the
surging line or
stone wall
The operation on
the surging line is
prevented by
recycle and the
operation on the
stone wall is
prevented by the
bypass
Node 8 Genset Short-circuit
happened
The emergence of
sparks that can
ignite leaking
ethylene gas / other
combustible gas
components
resulting in a fire
Short-circuit is
prevented by
grounding
The generator
temperature rises
drastically due to
excessive load
It ignites the
flammable gas
components around
the genset at the
autoignition
temperature so that
there is a fire
Overload is
prevented by load
control and
grounding
Node 9 Electricity
substation
Short-circuit due to
internal
components not
working properly /
overheating
It ignites the
flammable gas
components around
the PLN substation
at the autoignition
temperature so that
there is a fire
Short-circuit is
prevented by
grounding
Node 10 Water storage
tank
Leakage of water Resulting accidents
due to slippery
workplace
Accidents are
prevented by
personal safety to
be more careful
Node 11 Pump House
PMK
Pump does not
work when a fire
occurs
The fire is getting
bigger causing an
explosion
Prevented by the
availability of
external fire
6
extinguisher
LNG Hazard Identification
From the evaluation nodes that have been done hazard identification can be done that may
occur in this port area. The hazards are shown in Table 3. The total hazards associated with
this process are 16.
Table 3. Hazard identification for LNG loading-unloading process.
No. Hazard Consequence Impact Mitigation
1. Flow stops during transfer from tank ship to onshore
- Incorrect connections
- Excessive movement
of the loading arm.
- Extreme waves and
winds
Leakage of LNG
in small quantities
Impacts the
environment
- Implement
bunkering procedure
- Maintain
communication with
all bunkering workers
- Ensure ESD system
function
- Using PPE
- Create an
emergency response
plan
- Install a flammable
detector
- Perform inspection
of equipment before
bunkering
LNG leakage
causes cryogenic
hazard to workers
Injury or death
2. Leakage on pumps, pipes, hoses as it flows LNG from ship to Filling Station
- Corrosion
- Erosion
- External interference
- Fatigue failure
- Gasket failure
- Hose failure
- Improper hose
connection
- Material defect
- Seal failure
- Improper pipes materal
selection
- Leaks on the valve
- Vibration
- Excessive movement
on the loading arm
- Earthquake
LNG Leakage Environment
impact
- Implement
bunkering procedure
- Maintain
communication with
all bunkering workers
- Ensure ESD system
function
- Using PPE
- Create an
emergency response
plan
- Install a flammable
detector
- Perform inspection
of equipment before
bunkering
- Pressure testing
Leakage LNG
resulting in brittle
fracture on deck,
fire / explosion
hazard on
surrounding
equipment
Economy impact
Causes cryogenic
hazard
Injury or death
3. ESD system can not work in the event of a leak / Problem on pipeline connection
- Failure of ESD
instruments
- Freezing of pipes /
valve connected to ESD
LNG leakage in
large quantities
Environment
impact
- Set up manual ESD
procedure
- Using a control
system for bunkering Leakage LNG
that causes brittle
Economy impact
7
No. Hazard Consequence Impact Mitigation
- There is no ESD
system on the truck
- Operator errors
- Programming error
- Using nonstandard
equipment
fracture, fire,
explosion in the
environment
equipment
- Run bunkering
procedure
- Checking ESD
system periodically
- Use of PPE
- Classification of
electrical connections
in the bunkering area
- Preparing
emergency
procedures
Causes cryogenic
hazard
Injury or death
4. Excessive movement in the loading arm
- External hazards
- Maintenance is wrong
- Failure of control
system on loading arm
- Operator error
- Structural failure
- Extreme wind
- Earthquake
Leakage of LNG
on pumps, pipes,
hoses during
LNG transfer
Environment
impact
- Implement
bunkering procedure
- ESD system
- Standard loading
arm checking
- Implement
maintenance
procedures
- Fire caused by
passengers
- Hole 1 "on the transfer
pipe to the filling shed
due to corrosion
Leakage of LNG
into the air. May
cause vapor cloud
explosion or zet
fire if there is an
ignition source
Injury, death,
economic loss,
death and
damage
- Run an emergency
response
- Installation of gas
detector, use of PPE
(personal protective
equipment),
inspection of
equipment on a
regular basis
Pipe broken by vibration
or corrosion
LNG leak into the
air. May cause a
vapor cloud
explosion if there
is an ignition
source
Economic
losses, death and
damage
Installation of gas
detector, use of PPE,
inspection of
equipment on a
regular basis and do
the replacement of
pipes.
5. Leakage of LNG on the filling shed pipe connection to the truck
1 inch hole at the end of
the filling shed pipe due
to damage to the gasket
LNG leak into the
air. May cause
vapor cloud
explosion or jet
fire if there is an
ignition source
Economic
losses, death and
damage
Installation of gas
detector, gasket
replacement
periodically, use of
PPE
6. Leakage of LNG occurs at the bottom of the truck tank at the filling shed location
1 inch hole at the bottom
of LNG tank in truck
near filling shed. The
holes are formed by
LNG leak into the
air. May cause
vapor cloud
explosion or jet
Economic
losses, death and
damage
Installation of gas
detector, gasket
replacement
periodically, use of
8
No. Hazard Consequence Impact Mitigation
corrosion fire if there is an
ignition source
PPE
7. LNG leakage occurs from piping during pumping to filling shed
1 inch hole at the bottom
of LNG transfer pipe to
filling shed. The holes
are formed by corrosion
LNG leak into the
air. May cause
vapor cloud
explosion or jet
fire if there is an
ignition source
Economic
losses, death and
damage
Installation of gas
detector, gasket
replacement
periodically, use of
PPE
Pipe broken by vibration
or corrosion
LNG leak into the
air. May cause
vapor cloud
explosion or jet
fire if there is an
ignition source
Economic
losses, death and
damage
Installation of gas
detector, gasket
replacement
periodically, use of
PPE
8. LNG leakage occurs in the filling shed pipe connection to the truck
1 inch hole at the end of
the filling shed pipe due
to damage to the gasket
LNG leak into the
air. May cause
vapor cloud
explosion or jet
fire if there is an
ignition source
Economic
losses, death and
damage
Installation of gas
detector, gasket
replacement
periodically, use of
PPE
9. LNG leakage occurs from piping during pumping to filling shed
1 inch hole at the
transfer pipe to filling
shed. The holes are
formed by corrosion
LNG leak into the
air. May cause
vapor cloud
explosion or jet
fire if there is an
ignition source
Economic
losses, death and
damage
Installation of gas
detector, gasket
replacement
periodically, use of
PPE
10. LNG leakage occurs on the boil-off gas pipes at the discharge flow of the compressor
- Corrosion
- Vibration caused by
compressur surging
Boil-off gas leak
into the air.
Economic
losses, VCE, jet
fire, death and
damage
Choose standard
material, design
standard PSV, install
gas detector
LNG Quantitative Risk Assessment and Dispersion Analysis
After identifying dangerous nodes, then a quantitative risk analysis is conducted to determine
whether the impact of each malicious node is acceptable or not. Quantitative risk analysis is
done by calculating the frequency of events using the event tree and fault tree and calculating
the consequences of death by dispersion analysis. The frequency of occurrence analysis is
done by compiling scenarios of several frequent events using the event tree and scenarios of
some dangerous events using the fault tree. The preparation of the event tree begins the
initiating event as shown in the Table 5. Then proceeds with wind direction to the office or
stock pile of coal, then the failure of the shutdown valve that does not open, then continued
with the possibility of ignisi or not causing the jet fire or vapor vloud explosion. The
frequency of occurrence and probability of safety function failures are obtained from the HSE
UK and OREDA Textbook Guidelines.
9
Table 5. Event simulation variation for LNG process.
Event Impact Frequency
(impact/yr)
1” hole in the
transfer pipe
VCE 6,03x10-9
Jet fire 6,70x10-9
Toxic release 5,43x10-8
Fracture of transfer
pipe
VCE 5,85x10-10
Jet fire 6,50x10-10
Toxic release 5,27x10-9
1” hole in the
filling shed pipe
VCE 4,50x10-7
Jet fire 5,00x10-7
Toxic release 4,05x10-6
1” hole in the
connection between
platform and ship
VCE 3,60x10-6
Jet fire 4,00x10-6
Toxic release 3,24x10-5
1” hole in the boil-
off pipe
VCE 6,03x10-9
Jet fire 6,70x10-9
Toxic release 5,43x10-8
After an occurrence frequency analysis, dispersion analysis was performed to calculate the
consequences of death from each accident scenario.
1. 1” Hole in Platform Connection with Tank Ship
Figure 2. A 1-inch leakage simulation result on platform connection with LNG tank for
the case: (a) Toxic release, (b) Jet fire, and (c) Flammable area.
(a) (b)
(c)
10
The leak area profile is divided into three areas indicated by red lines, yellow inner lines
and outer yellow lines. From the Figure 2(a), red bounded areas are potentially deadly
areas where the LNG compounds contain concentrations of 17000 ppm. If the area is
multiplied by the assumed uniform human density then the area will be 6.75 x 10-2 per
year.
From the Figure 2(b), red-bounded areas are potentially deadly areas where there is heat
radiation greater than 10 kW / m2. If the area is multiplied by the assumed uniform human
density then the area will be 8.06 x 10-2 per year.
2. 1” Hole in Transfer Pipe
There are three impacts that can be generated by leakage of 1" in the transfer pipeline,
such as toxic release, jet fire, and VCE. The simulation and calculation of the source
model can be seen the amount of LNG leakage to the environment of 27.1 kg/s with the
assumption leakage duration for 1 hour. There are 3 danger zone results from the
simulation for each incident, where the red zone is the zone causing death when exposed
to the hazard at the concentration of exposure. Table 6 resumed the zone division of each
case.
Table 6. Zone division for 1” Hole in Transfer Pipe case.
Case Distribution Distance (m) / Concentration Exposure
Red Zone Orange Zone Yellow Zone
Toxic release 168 17000 ppm - - 440 2900 ppm
Jet fire 21 10 kW/m2 29 5 kW/m2 44 2 kW/m2
VCE - - - - 149 1 psi
3. 1” Hole in Filling Shed
There are three impacts that can be generated by leakage of 1" in the filling shed, such as
toxic release, jet fire, and VCE. Through the simulation and calculation of source model
can be known the amount of leakage of LNG to the environment of 27.1 kg / s with the
assumption of leakage duration for 1 hour. There are 3 hazard zones resulting from the
simulation for each event, in which the red zone is the zone causing death if exposed to
the hazard at the concentration of the exposure. Table 7 resumed the zone division of each
case.
Table 7. Zone division for 1” Hole in Filling Shed case.
Case Distribution Distance (m) / Concentration Exposure
Red Zone Orange Zone Yellow Zone
Toxic release 168 17000 ppm - - 440 2900 ppm
Jet fire 21 10 kW/m2 29 5 kW/m2 44 2 kW/m2
VCE - - - - 149 1 psi
4. Rupture of Transfer Pipe
There are three impacts that can be generated by leakage of 1" in the filling shed, such as
toxic release, jet fire, and VCE. Through the simulation and calculation of source model
can be known the amount of LNG leakage to the environment of 1069.5 kg / s with the
assumption of leakage duration for 1 hour. There are 3 hazard zones resulting from the
simulation for each event, in which the red zone is the zone causing death if exposed to
the hazard at the concentration of the exposure. Table 8 resumed the zone division of each
case.
Table 8. Zone division for Rupture of Transfer Pipe case.
11
Case Distribution Distance (m) / Concentration Exposure
Red Zone Orange Zone Yellow Zone
Toxic release 1400 17000 ppm - - 4400 2900 ppm
Jet fire 173 10 kW/m2 252 5 kW/m2 392 2 kW/m2
VCE - - - - 1100 1 psi
5. Leakage in Boil-off Gas Pipe
Figure 3(a) shows the affected area when boil off gas leaks from a pipe with a 1” hole.
The red line indicates the most fatal area with a gas concentration of 17,000 ppm. The
area of yellow line boundary contains a leaking gas concentration of 2900 ppm. The
orange area is the confidences line from the wind direction. From this simulation obtained
the number of deaths as many as 4 people.
Figure 3(b) shows the thermal affected areas due to the occurrence of jet fire. The red
circle shows the most fatal area with a thermal impact of 10 kW / m2. The circumscribed
area of the orange circle is subject to a thermal impact of 5 kW / m2. The area inside the
yellow circle gets a thermal impact of 2 kW / m2 with the risk of burns. From this
simulation obtained the number of deaths as many as 13 deaths.
Figure 3(c) shows the area affected by the explosion from a boil off gas leak in a pipe with
a 1 inch hole. The area bounded by the yellow line is impacted by an explosion with a
pressure of 1 psi with damage to the glass.
Figure 3. A leakage simulation result on Boil-off Gas Pipe for the case: (a) Toxic release,
(b) Jet fire, and (c) Flammable area.
(a) (b)
(c)
12
LNG F-N Curves
After obtaining the frequency value of the Event Tree Analysis (ETA) and the number of
deaths, an F-N curve can be made indicating the safety level of a possible accident incident on
a processing device. The F-N curve is divided into three zones, namely acceptable, ALARP,
and unacceptable. A process device can be said to be safe if it is in acceptable zone. When in
the ALARP zone, additional security equipment is required to reduce the frequency value of
the incident, so that the position of the point on the F-N curve can be moved to the acceptable
zone. In this report, the F-N curve is used in accordance with the British HSE standard.
The results of the incident analysis are plotted, as shown in Figure 4. The detailed frequency
and number of deaths are presented in Table 9. From the analysis results, no accident incident
scenarios exist in the unacceptable zone. However there are 7 incident scenarios in the
ALARP zone. Therefore, an additional safety tool design is required to enable the processing
equipment to be used with a tolerable level of security.
Table 9. Results of Security Level Analysis of Possible Incidence with F-N Curve
Event Impact Frequency
(impact/year) Fatality Zone
1” hole in the
transfer pipe
VCE 6,03x10-9 85,56 Acceptable
Jet fire 6,70x10-9 2,12 ALARP
Toxic release 5,43x10-8 24,95 Acceptable
Fracture of
transfer pipe
VCE 5,85x10-10 4078,63 ALARP
Jet fire 6,50x10-10 228,93 Acceptable
Toxic release 5,27x10-9 1380,45 ALARP
1” hole in the
filling shed pipe
VCE 4,50x10-7 85,56 ALARP
Jet fire 5,00x10-7 2,12 Acceptable
Toxic release 4,05x10-6 24,95 ALARP
1” hole in the
connection
between
platform and
ship
VCE 3,60x10-6 4,42 ALARP
Jet fire 4,00x10-6 9,83 ALARP
Toxic release 3,24x10-5 8,24 ALARP
1” hole in the
boil-off pipe
VCE 6,03x10-9 3,16 Acceptable
Jet fire 6,70x10-9 12,56 Acceptable
Toxic release 5,43x10-8 25,29 ALARP
13
Figure 4. F-N curve analysis.
Ethylene Hazard Identification
From the evaluation nodes that have been done hazard identification can be done that may
occur in this port area. The hazards are shown in Table 10.
Table 10. Hazard identification for ethylene loading-unloading process.
No. Unit Hazard Impact Mitigation
1. Platform There is a gap
between the
unloading arm
and the pipe due
to improper
installation or
movement of
ships due to
ocean waves
Occurrence of ethylene
release which can cause
jet fire if directly
ignited or culminate in
VCE (Vapor Cloud
Explosion)
Ensure perfect unloading
arm installation procedure
and install double ball
safety release on arm and
complete system unloading
with emergency shutdown
system
2. Pipe Pipe leakage due
to corrosion of
materials or
cracks due to
construction
defects
Occurrence of ethylene
release which can cause
jet fire if directly
ignited or culminate in
VCE (Vapor Cloud
Explosion)
Perform monitoring and
checking periodically so
that the possibility of leak /
rift can be detected as early
as possible
3. Filling shed There is a gap
between the
container hose
and the ethylene
filler station due
to incomplete
Occurrence of ethylene
release which can cause
jet fire if directly
ignited or culminate in
VCE (Vapor Cloud
Explosion)
Ensure perfect unloading
arm installation procedure
and install double ball
safety release on arm and
complete system unloading
with emergency shutdown
14
No. Unit Hazard Impact Mitigation
mounting system
4. Container There was a leak
of ethylene tank
Occurrence of ethylene
release which can cause
jet fire if directly
ignited or culminate in
VCE (Vapor Cloud
Explosion)
Install a leak detector and
regularly check the tank so
that leaks may be prevented
An increase in
temperature of the
ethylene tank
resulting from an
increase in
environmental
temperature
drastically or
other heat sources
The occurrence of
BLEVE (Boiling
Liquid Expanding
Vapor Explosion)
resulting in an
explosion
Install the insulator in the
tank and adjust the distance
of the tank with the source
of heat exposure within the
safe limits and install a fire
protection system
The occurrence of
excessive
pressure on the
container tank
due to excessive
loading of
ethylene (overfill)
The occurrence of
BLEVE (Boiling
Liquid Expanding
Vapor Explosion)
resulting in an
explosion
Monitor the amount of gas
put into containers and
install relief systems to
reduce overpressure and
emergency shutdown
system
An electron
accumulates due
to friction on the
connection during
charging
The emergence of
sparks that can ignite a
fire
Ensure all connections are
neutralized by connecting
them to the ground
(grounding). Additionally it
can add anti-static agent
(The electron carrier) and
enter the gas slowly.
There is air in the
container tank
There is a fire when the
oxygen content meets
the limit
Clear air in the container
tank before loading through
purging and inerting during
loading
Leakage of the
channel of
ethylene to the
container
The presence of
ethylene may cause fire
and explosion if ignited
Perform regular checks and
install emergency shutdown
system
The emergence of
sparks from the
container vehicle
engine due to free
or hot electric
charge
There will be a fire
when there is an
inflammable
combustible gas
component
Install a fire alarm system
to detect sparks
5. Compressor The fluid flow
rate inside the
compressor is too
small or too large
(outside the safe
There is a vibration that
leads to the explosion
of the compressor
because the operation is
on the surging line or
Monitor the operation of the
compressor in the safe
range
15
No. Unit Hazard Impact Mitigation
operating range) stone wall
6. Genset Short-circuiting The emergence of
sparks that can ignite
leaking ethylene gas /
other combustible gas
components resulting in
a fire
Break the power outlet and
prevent it by fitting the fuse
Genset
temperature
increases
drastically due to
excessive load
It ignites the flammable
gas components around
the genset at the
autoignition
temperature so that
there is a fire
Monitor the generator load
and place the generator at a
safe range from the
ethylene tank
7. Pump
House PMK
Pumps do not
work when there
is an increasingly
severe fire
The fire is getting
bigger causing the
explosion
Install standby pumps and
equip other fire
extinguishers such as
hydrant and FMD gas
cylinders
8. Electricity
substation
Short-circuit due
to internal
components not
working with balk
/ overheating
It ignites the flammable
gas components around
the PLN substation at
the autoignition
temperature so that
there is a fire
Break the power outlet and
prevent it by fitting the fuse
9. Water tank Water leakage Resulting in work
accidents (workers fall
due to slippery surface)
Make a ditch under a water
tank so it can fit before
water seeps into the work
area
10. Coal
pilestock
The emergence of
sparks due to high
environmental
temperatures
It ignites a fire when
there is an ethylene
dispersion or other
flammable gas
Install a fire alarm system
to detect sparks
11. Natural
disasters
Earthquake The occurrence of
cracks resulting in
leakage, especially in
the pipe and ethylene
tank so that a fire
occurs when ignited
Evacuate workers to secure
areas and build earthquake-
resistant construction
equipment
Ethylene Quantitative Risk Assessment and Dispersion Analysis
The preparation of the event tree begins the initiating event as shown in the Table 11.
16
Table 11. Event simulation variation for ethylene process.
Variation Component
Type of event 0.25” hole
1” hole
4” hole
Rupture of pipe
Type of dispersion Puff
Plume
From the simulations that have been done can be shown three zones consisting of red zone
(most dangerous zone), orange zone, and yellow zone. These three zones have their own
limitations depending on the type of accident that occurs such as the spread of toxic
substances, the spread of combustible substances, and explosions. From the simulation of this
dispersion obtained range of area from each zone to do the calculation of the number of
accidents that may occur. The number of accidents is shown in Table 12 to Table 14.
Table 12. The number of people affected by the leak (toxic release).
No. Dispersion Type Diameter (inch) Zone No. of people
1. Puff 0.1 Red 0
2. Orange 0
3. Yellow 20
4. 0.25 Red 0
5. Orange 111
6. Yellow 31
7. 0.5 Red 9
8. Orange 45
9. Yellow 306
10. 1 Red 15
11. Orange 90
12. Yellow 1195
13. Rupture Red 26
14. Orange 158
15. Yellow 2116
16. Plume 0.1 Red 0
17. Orange 0
18. Yellow 0
19. 0.25 Red 0
20. Orange 0
21. Yellow 13
22. 0.5 Red 0
23. Orange 5
24. Yellow 43
25. 1 Red 3
26. Orange 11
27. Yellow 198
28. Rupture Red 38
29. Orange 243
30. Yellow 2263
17
Table 13. The number of people affected by the leak (flammable area).
No. Dispersion Type Diameter (inch) Zone No. of people
1. Puff 0.1 Red 0
2. Orange 0
3. Yellow 6
4. 0.25 Red 7
5. Orange 0
6. Yellow 23
7. 0.5 Red 31
8. Orange 0
9. Yellow 81
10. 1 Red 35
11. Orange 0
12. Yellow 291
13. Rupture Red 69
14. Orange 0
15. Yellow 252
16. Plume 0.1 Red 0
17. Orange 0
18. Yellow 0
19. 0.25 Red 0
20. Orange 0
21. Yellow 5
22. 0.5 Red 3
23. Orange 0
24. Yellow 7
25. 1 Red 5
26. Orange 0
27. Yellow 21
28. Rupture Red 91
29. Orange 0
30. Yellow 482
18
Table 14. The number of people affected by the leak (explosion).
No. Dispersion Type Diameter (inch) Zone No. of people
1. Puff 0.1 Red 0
2. Orange 2
3. Yellow 10
4. 0.25 Red 0
5. Orange 19
6. Yellow 65
7. 0.5 Red 0
8. Orange 61
9. Yellow 211
10. 1 Red 0
11. Orange 266
12. Yellow 854
13. Rupture Red 0
14. Orange 210
15. Yellow 789
16. Plume 0.1 Red 0
17. Orange 0
18. Yellow 1
19. 0.25 Red 0
20. Orange 2
21. Yellow 6
22. 0.5 Red 0
23. Orange 6
24. Yellow 20
25. 1 Red 0
26. Orange 23
27. Yellow 64
28. Rupture Red 0
29. Orange 330
30. Yellow 1077
The results of this Quantitative Risk Analysis show some potential hazards in ALARP or
intolerable zones. This QRA is represented in Table 15 to Table 35.
Table 15. QRA for 0.1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Pool Fire 4.77584E-05 6 0.00028655
Flash Fire +
Pool Fire 8.1852E-06 6 4.91112E-05
VCE 1.22816E-05 12 0.000147379
SDV Failed
to Close
Pool Fire 5.3124E-06 6 3.18744E-05
Flash Fire +
Pool Fire 1.3604E-06 6 8.1624E-06
VCE 0.000000912 12 0.000010944
Detection
and SDV
Failed
Pool Fire 1.292E-07 6 7.75E-07
Flash Fire +
Pool Fire 3.8E-08 6 2.28E-07
19
VCE 2.28E-08 12 2.74E-07
Plume
SDV
Succeed to
Close
Pool Fire 4.77584E-05 0 0
Flash Fire +
Pool Fire 8.1852E-06 0 0
VCE 1.22816E-05 0 0
SDV Failed
to Close
Pool Fire 5.3124E-06 0 0
Flash Fire +
Pool Fire 1.3604E-06 0 0
VCE 0.000000912 0 0
Detection
and SDV
Failed
Pool Fire 1.292E-07 0 0
Flash Fire +
Pool Fire 0.000000038 0 0
VCE 2.28E-08 0 0
Table 16. QRA for 0.25” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Pool Fire 4.77584E-05 30 0.001432752
Flash Fire +
Pool Fire 8.1852E-06 30 0.000245556
VCE 1.22816E-05 258 0.003168653
SDV Failed
to Close
Pool Fire 5.3124E-06 30 0.000159372
Flash Fire +
Pool Fire 1.3604E-06 30 0.000040812
VCE 0.000000912 258 0.000235296
Detection
and SDV
Failed
Pool Fire 1.292E-07 30 3.88E-06
Flash Fire +
Pool Fire 3.8E-08 30 1.14E-06
VCE 2.28E-08 258 5.88E-06
Plume
SDV
Succeed to
Close
Pool Fire 4.77584E-05 5 0.000238792
Flash Fire +
Pool Fire 8.1852E-06 5 0.000040926
VCE 1.22816E-05 8 9.82528E-05
SDV Failed
to Close
Pool Fire 5.3124E-06 5 0.000026562
Flash Fire +
Pool Fire 1.3604E-06 5 0.000006802
VCE 0.000000912 8 0.000007296
Detection
and SDV
Failed
Pool Fire 1.292E-07 5 0.000000646
Flash Fire +
Pool Fire 0.000000038 5 0.00000019
VCE 2.28E-08 8 1.824E-07
Table 17. QRA for 0.5” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Pool Fire 4.77584E-05 112 0.005348941
Flash Fire +
Pool Fire 8.1852E-06 112 0.000916742
VCE 1.22816E-05 272 0.003340595
SDV Failed
to Close
Pool Fire 5.3124E-06 112 0.000594989
Flash Fire + 1.3604E-06 112 0.000152365
20
Pool Fire
VCE 0.000000912 272 0.000248064
Detection
and SDV
Failed
Pool Fire 1.292E-07 112 1.45E-05
Flash Fire +
Pool Fire 3.8E-08 112 4.26E-06
VCE 2.28E-08 272 6.2E-06
Plume
SDV
Succeed to
Close
Pool Fire 4.77584E-05 10 0.000477584
Flash Fire +
Pool Fire 8.1852E-06 10 0.000081852
VCE 1.22816E-05 26 0.000319322
SDV Failed
to Close
Pool Fire 5.3124E-06 10 0.000053124
Flash Fire +
Pool Fire 1.3604E-06 10 0.000013604
VCE 0.000000912 26 0.000023712
Detection
and SDV
Failed
Pool Fire 1.292E-07 10 0.000001292
Flash Fire +
Pool Fire 0.000000038 10 0.00000038
VCE 2.28E-08 26 5.928E-07
Table 18. QRA for 1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Pool Fire 4.77584E-05 326 0.015569238
Flash Fire +
Pool Fire 8.1852E-06 326 0.002668375
VCE 1.22816E-05 1120 0.013755392
SDV Failed
to Close
Pool Fire 5.3124E-06 326 0.001731842
Flash Fire +
Pool Fire 1.3604E-06 326 0.00044349
VCE 0.000000912 1120 0.00102144
Detection
and SDV
Failed
Pool Fire 1.292E-07 326 4.21 E-05
Flash Fire +
Pool Fire 3.8E-08 326 1.24E-05
VCE 2.28E-08 1120 2.55E-05
Plume
SDV
Succeed to
Close
Pool Fire 4.77584E-05 26 0.001241718
Flash Fire +
Pool Fire 8.1852E-06 26 0.000212815
VCE 1.22816E-05 87 0.001068499
SDV Failed
to Close
Pool Fire 5.3124E-06 26 0.000138122
Flash Fire +
Pool Fire 1.3604E-06 26 3.53704E-05
VCE 0.000000912 87 0.000079344
Detection
and SDV
Failed
Pool Fire 1.292E-07 26 3.3592E-06
Flash Fire +
Pool Fire 0.000000038 26 0.000000988
VCE 2.28E-08 87 1.9836E-06
Table 19. QRA for rupture pipe.
Release Case Incident type Frequency Consequence Risk
Puff SDV Pool Fire 4.77584E-05 321 0.015330446
21
Succeed to
Close
Flash Fire +
Pool Fire 8.1852E-06 321 0.002627449
VCE 1.22816E-05 999 0.012269318
SDV Failed
to Close
Pool Fire 5.3124E-06 321 0.00170528
Flash Fire +
Pool Fire 1.3604E-06 321 0.000436688
VCE 0.000000912 999 0.000911088
Detection
and SDV
Failed
Pool Fire 1.292E-07 321 4.15E-05
Flash Fire +
Pool Fire 3.8E-08 321 1.22E-05
VCE 2.28E-08 999 2.28E-05
Plume
SDV
Succeed to
Close
Pool Fire 4.77584E-05 573 0.027365563
Flash Fire +
Pool Fire 8.1852E-06 573 0.00469012
VCE 1.22816E-05 1407 0.017280211
SDV Failed
to Close
Pool Fire 5.3124E-06 573 0.003044005
Flash Fire +
Pool Fire 1.3604E-06 573 0.000779509
VCE 0.000000912 1407 0.001283184
Detection
and SDV
Failed
Pool Fire 1.292E-07 573 7.40316E-05
Flash Fire +
Pool Fire 0.000000038 573 0.000021774
VCE 2.28E-08 1407 3.20796E-05
Table 20. QRA for 0.1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 6 0.00058489
Vertical Jet Dispersion
9.71346E-05 6 0.000582808
Gaussian Dispersion
2.15736E-05 20 0.000431472
Horizontal Flame Jet
5.9274E-06 6 3.55644E-05
Vertical Flame Jet
5.9007E-06 6
3.54042E-05
SDV Failed
to Close Fireball 1.4151E-06 6 8.4906E-06
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 6 1.76E-06
Vertical Jet Dispersion
0.000000267 6 1.6E-06
Gaussian Dispersion
2.937E-07 20 5.87E-06
Horizontal Flame Jet
1.335E-08 6 8.01 E-08
Vertical Flame Jet 1.335E-08 6 8.01 E-08
Plume SDV
Succeed to
Horizontal Jet Dispersion
9.74817E-05 0 0
Vertical Jet 9.71346E-05 0 0
22
Close Dispersion Gaussian
Dispersion 2.15736E-05 0 0
Horizontal Flame Jet
5.9274E-06 0 0
Vertical Flame Jet
5.9007E-06 0 0
SDV Failed
to Close Fireball 1.4151E-06 0 0
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 0 0
Vertical Jet Dispersion
0.000000267 0 0
Gaussian Dispersion
2.937E-07 0 0
Horizontal Flame Jet
1.335E-08 0 0
Vertical Flame Jet
1.335E-08 0 0
Table 21. QRA for 0.25” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 30 0.002924451
Vertical Jet Dispersion
9.71346E-05 30 0.002914038
Gaussian Dispersion
2.15736E-05 142 0.003063451
Horizontal Flame Jet
5.9274E-06 30 0.000177822
Vertical Flame Jet
5.9007E-06 30 0.000177021
SDV Failed
to Close Fireball 1.4151E-06 30 0.000042453
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 30 8.81 E-06
Vertical Jet Dispersion
0.000000267 30 8.01 E-06
Gaussian Dispersion
2.937E-07 142 4.17E-05
Horizontal Flame Jet
1.335E-08 30 4.01 E-07
Vertical Flame Jet 1.335E-08
30 4.01 E-07
Plume
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 5 0.000487409
Vertical Jet Dispersion
9.71346E-05 5 0.000485673
Gaussian Dispersion
2.15736E-05 13 0.000280457
Horizontal Flame Jet
5.9274E-06 5 0.000029637
Vertical Flame 5.9007E-06 5 2.95035E-05
23
Jet
SDV Failed
to Close Fireball 1.4151E-06 5 7.0755E-06
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 5 1.47E-06
Vertical Jet Dispersion
0.000000267 5 1.34E-06
Gaussian Dispersion
2.937E-07 13 3.82E-06
Horizontal Flame Jet
1.335E-08 5 6.68E-08
Vertical Flame Jet
1.335E-08 5 6.68E-08
Table 22. QRA for 0.25” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 112 0.01091795
Vertical Jet Dispersion
9.71346E-05 112 0.010879075
Gaussian Dispersion
2.15736E-05 360 0.007766496
Horizontal Flame Jet
5.9274E-06 112 0.000663869
Vertical Flame Jet
5.9007E-06 112
0.000660878
SDV Failed
to Close Fireball 1.4151E-06 112 0.000158491
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 112 3.29E-05
Vertical Jet Dispersion
0.000000267 112 2.99E-05
Gaussian Dispersion
2.937E-07 360 0.000106
Horizontal Flame Jet
1.335E-08 112 1.5E-06
Vertical Flame Jet 1.335E-08 112 1.5E-06
Plume
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 10 0.000974817
Vertical Jet Dispersion
9.71346E-05 10 0.000971346
Gaussian Dispersion
2.15736E-05 48 0.001035533
Horizontal Flame Jet
5.9274E-06 10 0.000059274
Vertical Flame Jet
5.9007E-06 10
0.000059007
SDV Failed
to Close Fireball 1.4151E-06 10 0.000014151
Detection
and SDV
Horizontal Jet Dispersion
2.937E-07 10 2.94E-06
Vertical Jet 0.000000267 10 2.67E-06
24
Failed Dispersion Gaussian
Dispersion 2.937E-07 48 1.41E-05
Horizontal Flame Jet
1.335E-08 10 1.34E-07
Vertical Flame Jet
1.335E-08 10
1.34E-07
Table 23. QRA for 0.5” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 326 0.031779034
Vertical Jet Dispersion
9.71346E-05 326 0.03166588
Gaussian Dispersion
2.15736E-05 1300 0.02804568
Horizontal Flame Jet
5.9274E-06 326 0.001932332
Vertical Flame Jet
5.9007E-06 326 0.001923628
SDV Failed
to Close Fireball 1.4151E-06 326 0.000461323
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 326 9.57E-05
Vertical Jet Dispersion
0.000000267 326 8.7E-05
Gaussian Dispersion
2.937E-07 1300 0.000382
Horizontal Flame Jet
1.335E-08 326 4.35E-06
Vertical Flame Jet 1.335E-08 326 4.35E-06
Plume
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 26 0.002534524
Vertical Jet Dispersion
9.71346E-05 26 0.0025255
Gaussian Dispersion
2.15736E-05 212 0.004573603
Horizontal Flame Jet
5.9274E-06 26 0.000154112
Vertical Flame Jet
5.9007E-06 26
0.000153418
SDV Failed
to Close Fireball 1.4151E-06 26 3.67926E-05
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 26 7.64E-06
Vertical Jet Dispersion
0.000000267 26 6.94E-06
Gaussian Dispersion
2.937E-07 212 6.23E-05
Horizontal Flame Jet
1.335E-08 26 3.47E-07
Vertical Flame 1.335E-08 26 3.47E-07
25
Jet
Table 24. QRA for pipe rupture.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 321 0.031291626
Vertical Jet Dispersion
9.71346E-05 321 0.031180207
Gaussian Dispersion
2.15736E-05 2300 0.04961928
Horizontal Flame Jet
5.9274E-06 321 0.001902695
Vertical Flame Jet
5.9007E-06 321 0.001894125
SDV Failed
to Close Fireball 1.4151E-06 321 0.000454247
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 321 9.43E-05
Vertical Jet Dispersion
0.000000267 321 8.57E-05
Gaussian Dispersion
2.937E-07 321 9.43E-05
Horizontal Flame Jet
1.335E-08 2300 3.07E-05
Vertical Flame Jet 1.335E-08
321 4.29E-06
Plume
SDV
Succeed to
Close
Horizontal Jet Dispersion
9.74817E-05 573 0.055857014
Vertical Jet Dispersion
9.71346E-05 573 0.055658126
Gaussian Dispersion
2.15736E-05 2544 0.054883238
Horizontal Flame Jet
5.9274E-06 573 0.0033964
Vertical Flame Jet
5.9007E-06 573 0.003381101
SDV Failed
to Close Fireball 1.4151E-06 573 0.000810852
Detection
and SDV
Failed
Horizontal Jet Dispersion
2.937E-07 573 0.000168
Vertical Jet Dispersion
0.000000267 573 0.000153
Gaussian Dispersion
2.937E-07 2544 0.000747
Horizontal Flame Jet
1.335E-08 573 7.65E-06
Vertical Flame Jet
1.335E-08 573 7.65E-06
Table 25. QRA of pressure build-up for 0.1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff SDV
Succeed to
Cloud Fire 0.0001172 6 0.0007032
Explosion 0.0001115 12 0.001338
26
Close Flash Fire 5.02E-05 6 0.00030138
SDV Failed
to Close
Cloud Fire 1.43454E-05 6 8.60727E-05
Explosion 1.36692E-05 12 0.000164031
Flash Fire 6.1203E-06 6 3.67218E-05
Detection
and SDV
Failed
Cloud Fire 3.588E-07 6 2.1528E-06
Explosion 3.4155E-08 12 4.0986E-07
Flash Fire 1.518E-07 6 9.108E-07
Plume
SDV
Succeed to
Close
Cloud Fire 0.000117162 0 0
Explosion 0.000111539 0 0
Flash Fire 0.000050232 0 0
SDV Failed
to Close
Cloud Fire 1.43454E-05 0 0
Explosion 1.36692E-05 0 0
Flash Fire 6.1203E-06 0 0
Detection
and SDV
Failed
Cloud Fire 3.588E-07 0 0
Explosion 3.4155E-08 0 0
Flash Fire 1.518E-07 0 0
Table 26. QRA of pressure build-up for 0.25” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Cloud Fire 0.000117162 30 0.00351486
Explosion 0.000111539 258 0.028776933
Flash Fire 0.000050232 30 0.00150696
SDV Failed
to Close
Cloud Fire 1.43454E-05 30 0.000430363
Explosion 1.36692E-05 258 0.003526665
Flash Fire 6.1203E-06 30 0.000183609
Detection
and SDV
Failed
Cloud Fire 3.588E-07 30 0.000010764
Explosion 3.4155E-08 258 8.81199E-06
Flash Fire 1.518E-07 30 0.000004554
Plume
SDV
Succeed to
Close
Cloud Fire 0.000117162 5 0.00058581
Explosion 0.000111539 8 0.000892308
Flash Fire 0.000050232 5 0.00025116
SDV Failed
to Close
Cloud Fire 1.43454E-05 5 7.17272E-05
Explosion 1.36692E-05 8 0.000109354
Flash Fire 6.1203E-06 5 3.06015E-05
Detection
and SDV
Failed
Cloud Fire 3.588E-07 5 0.000001794
Explosion 3.4155E-08 8 2.7324E-07
Flash Fire 1.518E-07 5 0.000000759
Table 27. QRA of pressure build-up for 0.5” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Cloud Fire 0.000117162 112 0.013122144
Explosion 0.000111539 272 0.030338472
Flash Fire 0.000050232 112 0.005625984
SDV Failed
to Close
Cloud Fire 1.43454E-05 112 0.00160669
Explosion 1.36692E-05 272 0.003718035
Flash Fire 6.1203E-06 112 0.000685474
Detection
and SDV
Cloud Fire 3.588E-07 112 4.01856E-05
Explosion 3.4155E-08 272 9.29016E-06
27
Failed Flash Fire 1.518E-07 112 1.70016E-05
Plume
SDV
Succeed to
Close
Cloud Fire 0.000117162 10 0.00117162
Explosion 0.000111539 26 0.002900001
Flash Fire 0.000050232 10 0.00050232
SDV Failed
to Close
Cloud Fire 1.43454E-05 10 0.000143454
Explosion 1.36692E-05 26 0.0003554
Flash Fire 6.1203E-06 10 0.000061203
Detection
and SDV
Failed
Cloud Fire 3.588E-07 10 0.000003588
Explosion 3.4155E-08 26 8.8803E-07
Flash Fire 1.518E-07 10 0.000001518
Table 28. QRA of pressure build-up for 1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Cloud Fire 0.000117162 26 0.003046212
Explosion 0.000111539 1140 0.12715389
Flash Fire 0.000117162 26 0.003046212
SDV Failed
to Close
Cloud Fire 1.43454E-05 26 0.000372982
Explosion 1.36692E-05 1140 0.015582939
Flash Fire 6.1203E-06 26 0.000159128
Detection
and SDV
Failed
Cloud Fire 3.588E-07 26 9.3288E-06
Explosion 3.4155E-08 1140 3.89367E-05
Flash Fire 1.518E-07 26 3.9468E-06
Plume
SDV
Succeed to
Close
Cloud Fire 0.000117162 26 0.003046212
Explosion 0.000111539 87 0.00970385
Flash Fire 0.000050232 26 0.001306032
SDV Failed
to Close
Cloud Fire 1.43454E-05 26 0.000372982
Explosion 1.36692E-05 87 0.001189224
Flash Fire 6.1203E-06 26 0.000159128
Detection
and SDV
Failed
Cloud Fire 3.588E-07 26 9.3288E-06
Explosion 3.4155E-08 87 2.97149E-06
Flash Fire 1.518E-07 26 3.9468E-06
Table 29. QRA of pressure build-up for rupture pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
Cloud Fire 0.000117162 321 0.037609002
Explosion 0.000111539 999 0.111426962
Flash Fire 0.000050232 321 0.016124472
SDV Failed
to Close
Cloud Fire 1.43454E-05 321 0.004604888
Explosion 1.36692E-05 999 0.013655576
Flash Fire 6.1203E-06 321 0.001964616
Detection
and SDV
Failed
Cloud Fire 3.588E-07 321 0.000115175
Explosion 3.4155E-08 999 3.41208E-05
Flash Fire 1.518E-07 321 4.87278E-05
Plume
SDV
Succeed to
Close
Cloud Fire 0.000117162 573 0.067133826
Explosion 0.000111539 1407 0.15693467
Flash Fire 0.000050232 573 0.028782936
SDV Failed
to Close
Cloud Fire 1.43454E-05 573 0.00821994
Explosion 1.36692E-05 1407 0.019232628
28
Flash Fire 6.1203E-06 573 0.003506932
Detection
and SDV
Failed
Cloud Fire 3.588E-07 573 0.000205592
Explosion 3.4155E-08 1407 4.80561 E-05
Flash Fire 1.518E-07 573 8.69814E-05
Table 30. QRA of temperature rise for 0.1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
BLEVE 7.3527E-05 12 0.000882324
Cloud Fire 0.000134875 6 0.000809248
Explosion 2.17034E-05 12 0.000260441 Flash Fire 1.91101E-05 6 0.00011466
SDV Failed
to Close BLEVE 1.0492E-06 12 1.25904E-05
Detection
and SDV
Failed
BLEVE 0.000000516 12 6.19E-06
Cloud Fire 0.000000129 6 7.74E-07
Explosion 0.000000172 12 2.06E-06
Flash Fire 0.000000215 6 1.29E-06
Plume
SDV
Succeed to
Close
BLEVE 7.3527E-05 0 0
Cloud Fire 0.000134875 0 0
Explosion 2.17034E-05 0 0
Flash Fire 1.91101E-05 0 0
SDV Failed
to Close BLEVE 1.0492E-06 0 0
Detection
and SDV
Failed
BLEVE 0.000000516 0 0
Cloud Fire 0.000000129 0 0
Explosion 0.000000172 0 0
Flash Fire 0.000000215 0 0
Table 31. QRA of temperature rise for 0.25” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
BLEVE 7.3527E-05 258 0.018969963
Cloud Fire 0.000134875 30 0.00404624
Explosion 2.17034E-05 258 0.005599475 Flash Fire 1.91101E-05 30 0.000573302
SDV Failed
to Close BLEVE 1.0492E-06 258 0.000270694
Detection
and SDV
Failed
BLEVE 0.000000516 258 0.000133
Cloud Fire 0.000000129 30 3.87E-06
Explosion 0.000000172 258 4.44E-05
Flash Fire 0.000000215 30 6.45E-06
Plume
SDV
Succeed to
Close
BLEVE 7.3527E-05 8 0.000588216
Cloud Fire 0.000134875 5 0.000674373
Explosion 2.17034E-05 8 0.000173627
Flash Fire 7.3527E-05 8 0.000588216
SDV Failed
to Close BLEVE 1.0492E-06 8 8.3936E-06
Detection
and SDV
Failed
BLEVE 0.000000516 8 4.13E-06
Cloud Fire 0.000000129 5 6.45E-07
Explosion 0.000000172 8 1.38E-06
29
Flash Fire 0.000000215 5 1.08E-06
Table 32. QRA of temperature rise for 0.5” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
BLEVE 7.3527E-05 272 0.019999341
Cloud Fire 0.000134875 112 0.015105962
Explosion 2.17034E-05 272 0.005903322 Flash Fire 1.91101E-05 112 0.002140327
SDV Failed
to Close BLEVE 1.0492E-06 272 0.000285382
Detection
and SDV
Failed
BLEVE 0.000000516 272 0.00014
Cloud Fire 0.000000129 112 1.44E-05
Explosion 0.000000172 272 4.68E-05
Flash Fire 0.000000215 112 2.41 E-05
Plume
SDV
Succeed to
Close
BLEVE 7.3527E-05 26 0.001911702
Cloud Fire 0.000134875 10 0.001348747
Explosion 2.17034E-05 26 0.000564288
Flash Fire 7.3527E-05 10 0.000191101
SDV Failed
to Close BLEVE 1.0492E-06 26 2.72792E-05
Detection
and SDV
Failed
BLEVE 0.000000516 26 2.72792E-05
Cloud Fire 0.000000129 26 1.34E-05
Explosion 0.000000172 10 1.29E-06
Flash Fire 0.000000215 26 4.47E-06
Table 33. QRA of temperature rise for 1” leakage of pipe.
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
BLEVE 7.3527E-05 1120 0.082350229
Cloud Fire 0.000134875 326 0.043969139
Explosion 2.17034E-05 1120 0.024307797 Flash Fire 1.91101E-05 326 0.00622988
SDV Failed
to Close BLEVE 1.0492E-06
1120 0.001175104
Detection
and SDV
Failed
BLEVE 0.000000516 1120 0.000578
Cloud Fire 0.000000129 326 4.21 E-05
Explosion 0.000000172 1120 0.000193
Flash Fire 0.000000215 326 7.01 E-05
Plume
SDV
Succeed to
Close
BLEVE 7.3527E-05 87 0.006396848
Cloud Fire 0.000134875 26 0.003506741
Explosion 2.17034E-05 87 0.001888195
Flash Fire 7.3527E-05 26 0.000496862
SDV Failed
to Close BLEVE 1.0492E-06
87 9.12804E-05
Detection
and SDV
Failed
BLEVE 0.000000516 87 4.49E-05
Cloud Fire 0.000000129 26 3.35E-06
Explosion 0.000000172 87 1.5E-05
Flash Fire 0.000000215 26 5.59E-06
Table 34. QRA of temperature rise for rupture pipe.
30
Release Case Incident type Frequency Consequence Risk
Puff
SDV
Succeed to
Close
BLEVE 7.3527E-05 999 0.073453463
Cloud Fire 0.000134875 321 0.043294766
Explosion 2.17034E-05 999 0.021681687 Flash Fire 1.91101E-05 321 0.006134329
SDV Failed
to Close BLEVE 1.0492E-06 999 0.001048151
Detection
and SDV
Failed
BLEVE 0.000000516 999 0.000515
Cloud Fire 0.000000129 321 4.14E-05
Explosion 0.000000172 999 0.000172
Flash Fire 0.000000215 321 6.9E-05
Plume
SDV
Succeed to
Close
BLEVE 7.3527E-05 1407 0.103452475
Cloud Fire 0.000134875 573 0.07728318
Explosion 2.17034E-05 1407 0.03053667
Flash Fire 7.3527E-05 573 0.010950064
SDV Failed
to Close BLEVE 1.0492E-06 1407 0.001476224
Detection
and SDV
Failed
BLEVE 0.000000516 1407 0.000726
Cloud Fire 0.000000129 573 7.39E-05
Explosion 0.000000172 1407 0.000242
Flash Fire 0.000000215 573 0.000123
Table 35. QRA of other source.
Source Incident
Type
Frequency Consequency Risk
Static
electricity
source
Explosion 0.00000928 999 0.009271
Inlet air Explosion 1.17292E-06 999 0.001172
Conclusions
LNG
Based on the results of QRA, it is concluded that there are 9 events included in the ALARP
category (As Low As Reseanobly Practicable) and the remainder is included in the acceptable
category. Incidents included in the ALARP category include the impact of jet fire from hole
leak occurrence 1" in the transfer pipeline, VCE (vapor cloud explosion) and toxic release of
the fracture in the middle of the transfer pipeline, VCE (vapor cloud explosion) and toxic
release from the occurrence of a 1" leakage leak on the filling shed pipe, VCE, jet fire and
toxic release from a 1" hole leak on the platform connection to the vessel, and toxic release of
hole leak occurrence 1 "in the boil-off pipeline. A more detailed category classification is
shown in Figure 5. Any incidents included in the ALARP category should be prevented in the
form of recommendations to be tolerable or acceptable risk categories tolerable or acceptable
categories.
31
Figure 5. ALARP region.
Table 36. Explanation of ALARP region.
No. Incident
1. VCE, 1" hole transfer pipe
2. Jet Fire, 1" hole transfer pipe
3. Toxic Release, 1" hole transfer pipe
4. VCE, rupture transfer pipe
5. Jet Fire, rupture transfer pipe
6. Toxic Release, rupture transfer pipe
7. VCE, 1" hole on platform connection
8. Jet Fire, 1" hole on platform connection
9. Toxic Release, 1" hole on platform connection
10. VCE, 1" hole on boil-off gas pipe
11. Jet fire, 1" hole on boil-off gas pipe
12. Toxic Release, 1" hole on boil-off gas pipe
13. VCE, 1" hole on pipa filling shed pipe
14. Jet Fire, 1" hole on pipa filling shed pipe
15. Toxic Release, 1" hole on pipa filling shed pipe
Ethylene
1. The most common hazards are pipe leaks that may pose risks of jet dispersion, flame jet,
gaussian dispersion, and fireball. These Hazards have a frequency level of 1.19 x 10-5 to
9.75 x 10-5.
2. The most dangerous Hazards are rupture tank leaks due to increased temperatures that can
cause BLEVE, cloud fire, flash fire, explosion, and flash fire. These hazards have a fire
severity of 321, a 2300 explosion, and a 999 toxic vapor spread.
3. Evacuation measures against workers and local residents need to be done when the
rupture tank leaks due to the increase in temperature occur.
32
Recommendations
LNG
1. Installation of Gas Detector
Gas detector is a tool to detect the presence of a gas in the factory area, especially in the
event of gas leakage. Because it can be detected at the beginning, it is expected that
personnel within the factory can handle it quickly. Typically, gas detectors are installed at
vulnerable points of leakage, such as in pipelines, joints / welding joints, and on
platforms. The detector gas will be connected to the alarm which the operator will get
notified if there is a leak. Figure 6 shows the location of the gas detector. This tool will be
placed at simulated and analysis locations using F-N curves in the ALARP zone.
2. Installation of Green Belt
Green Belt can be used as a protector in case of leakage of substance in an accident at the
factory. Green belt in the form of green and high plants are placed in certain areas. The
purpose of putting green belt siantaranya ie reduce gas concentration, break down the
concentration of vapor cloud, and sabagai barrier of toxic substances. Figure 6 shows
where the green belt is installed. These protective plants will be placed around the factory
area so as to reduce the risk of impact.
Figure 6. Design of Installation of Green Belt and Gas Detector.
No. Name
1. Workshop and workplace area
2. Platform/loading dock area
3. Pump house and water tank area
4. Filling shed area
5. Border area with coal stockpile
6. Border area with coal stockpile
7. Border area with coal stockpile
8. Compressor area
9. Parking area
33
3. Scenarios and Results of Recommendation Implementation
In implementing the recommendation, 3 scenarios of recommendation were first installed
gas detector, second installed green belt, third installed gas detector and green belt
simultaneously. Figure 7 to Figure 9 shows the F-N curve of the implementation results of
each scenario. The probability of implementation failure of the gas detector and the green
belt is obtained from the literature.
Based on the analysis it can be said that the implementation of gas detector can reduce all
the risk of occurrence belonging to ALARP category, but still left 5 events that still
belong to ALARP category. Likewise with the implementation of the green belt can not
reduce all the risk of occurrence to belong to the category acceptable, because there are
still 3 events that belong to ALARP category. At the time of implementation of the third
scenario is the installation of gas detectors and green belt simultaneously, it is obtained a
good result where all events can be reduced to acceptable categories. Therefore, the
proposed recommendation is a third scenario where the installation of gas detectors and
green belts simultaneously.
Figure 7. F-N Curve after addition of gas detector.
34
Figure 8. F-N Curve after addition of green belt.
Figure 9. F-N Curve after addition of gas detector and green belt.
Ethylene
Based on the QRA that has been done, it can be seen that for all scenarios generated risks
categorized in ALARP and intolerable groups. In general, the most dangerous and most
frequent risks are initiated events in the form of release of ethylene vapor into the air. The
scenario with the greatest impact of risk is the tank rupture due to the increase in temperature,
while the most frequent scenario is caused by a pipe leak at the tip of the filling shed.
35
Rupture of the tank due to an increase in storage tank temperatures is a case with risk grouped
as intolerable with the greatest number of fatalities compared to other cases, namely 321
persons (fire), 999 (toxic vapor spreading), and 2300 (explosion). The radius of the hazardous
area generated from this incident is as far as 1.2 km. This risk is most likely to occur by
preceding the leakage of ethylene vapor from the tank and the presence of an ignition source
resulting in a fire around the tank that ultimately increases the temperature of the ethylene
fluid in the tank. Increased temperatures of ethylene tanks have the potential to trigger
BLEVE. BLEVE occurring under fire conditions around the tank area will result in an
explosion followed by fireball.
To mitigate the occurrence of this risk, it is necessary to build a blast wall in the area around
the ethylene loading and unloading terminal which aims to protect the area around the loading
terminal of ethylene from the widespread explosive effect. The blast wall is preferably built in
a location that leads to a coal stockpile. With the construction of the blast wall is not expected
to occur escalation of hazard areas due to the occurrence of BLEVE or fire in coal stockpile,
so that the level of risk can be decreased and classified as ALARP.
For the prevention of this risk, it is recommended to install the temperature element connected
to the alarm temerature in the storage tank. If it is identified that there is an increase in
temperature above the safe limit, it should immediately cool down the tank by spraying it
using a refrigerant.
References
ABS, Bunkering of Liquefied Natural Gas-fueled Marine Vessels in North America
American Chemistry Council. 2004. “Ethylene Product Stewardship Guidance Manual”.
American Chemistry Council. 2004. “Handling and Transportation Guide for Ethylene,
Refrigerated Liquid (Cryogenic Ethylene)”. Arlington.
A. Crowl, Joseph F. Louvar, 2011, Chemical Process Safety Fundamentals with Applications,
3rd Ed, Pearson Education, Inc.
Center for Chemical Process Safety. 1994. “Guidelines for Evaluating the Characteristics of
Vapor Cloud Explosions, Flash Fires, and BLEVEs”. American Institute of Chemical
Engineers. New York.
Danielle Holden, 2014, Liquefied Natural Gas (LNG) Bunkering Study, Maritime
AdministrationDaniel.
Ronza, Felez.; Darbra, Carol.; Vilchez, Casal. 2003. “Predicting the Frequency of Accidents
in Port Areas by Developing Event Trees from Historical Analysis”. Barcelona.
Suhardi, 2011, Orientasi Umum Seksi Process Train, Technical Department PT Badak LNG.
Michelle Michot Foss, 2012, LNG Safety And Security, Center for Engergy
Econimics (CEE), Texas.
http://meteo.bmkg.go.id/prakiraan/propinsi/13