  • Project Management

    Case Studies + Tools

    Kin Fun Li Electrical and Computer Engineering

    University of Victoria [email protected]; www.ece.uvic.ca/~kinli

  • Sep. 21 Presentation Recap

    •  Definition of project and management areas – Communication – Risk – Change control

    •  Triple constraints and their effects •  Cost estimating and budgeting

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 2

    ects Cost estimating and budgeting

    Quality

    Scope Cost

    Time

  • Quality Control

    •  Industrial certification •  Canadian Standards Association: safety & quality •  International Standards Organization •  ISO 9000 family of quality management systems –  9000: covers basic concepts and language –  9001: sets the requirement of a quality management

    system –  9004: makes a quality management system more

    efficient and effective

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 3

  • Scope of Work

    •  Public Tenders – Request for Proposal – Request for Quotation

    •  MERX: Canadian Public Tenders – www.merx.com

    •  BC Bids: B.C. government portal – www.bcbid.gov.bc.ca

    •  Quote: project management (present/future)

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 4

  • Process Management Resource Management

    Risk Management

    Change Management

    Risk Management

    Time Management

    •  Daily basis •  Example: Work to do Saturday evening – Laundry – Study for test – Cook and eat dinner – Call Mom for her birthday – Go to SUB and party

    •  Individual versus Group

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 5

    Cost Management

  • Cost Management

    •  Local embedded system company •  Submitted and Won a bid in early 2012 •  Quotation based on March 2012 pricing •  Delivery on March 2013 •  Production ramped up December 2012 •  Systems required DRAMs •  Sensitivity to price fluctuation

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 6

  • DRAM Pricing

    •  1GB DRAMs Pricing (thememoryguy.com)

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 7

  • International Project: Airbus

    •  France, Germany, Spain, United Kingdom •  A320 – first fly-by-wire •  A380 – 1988 started development •  Delivery: 2005 scheduled; 2007/8 actual •  Problems: –  Incompatible CAD – Parts shipping logistics

    •  Consequence: late delivery penalty October 3, 2015 Kin Fun LI, University of Victoria Project Management 8

  • Airbus A380

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 9

  • Boeing 787 Dreamliner

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 10

  • International Project: Bombardier

    •  Global 7000/8000 •  2-year delay – Cost overrun

    •  Metro trains •  2-year delay – Design changes

    •  Penalties •  Corporate image October 3, 2015 Kin Fun LI, University of Victoria Project Management 11

  • International Project Issues

    •  Import duty •  Taxation •  National, provincial, and offshore •  Measurement unit •  Web meetings: – Cultural differences – Time differences

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 12

  • International Project Issues

    •  Exchange rate (www.oanda.com)

    •  Contingency !!! October 3, 2015 Kin Fun LI, University of Victoria Project Management 13

  • Engineering Economics

    •  Money, interest rate, growth •  Cash flow, financial statement •  Risk and uncertainty •  Industry and product life cycles •  Entrepreneurship •  Taxation •  Sensitivity and scenario analysis •  Project management

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 14

  • Project Management Issues

    •  Planning – Resource and risk management

    •  Budgeting (forecasting) – Labour and material

    •  Decision making – Alternatives and milestones

    •  Quality control and certification –  ISO, CSA

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 15

  • Labour and Equipment

    •  Labour: – Wages and salaries – Fringe benefits – Learning curve

    •  Equipment: – Capital cost – Operating cost – Buy or rent

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 16

  • Project Management Tools

    •  PERT chart •  GANTT chart •  MS Project •  CMM (Capability Maturity Model) – Software development process

    •  Six Sigma – Process improvement techniques

    •  Project Management Institute (PMP) October 3, 2015 Kin Fun LI, University of Victoria Project Management 17

  • Microsoft Project Visual

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 18

  • Project Planning Process-1

    1.  Set project start date

    2.  Set project completion date

    3.  Identify internal & external milestones

    4.  List tasks in sequence

    5.  Estimate personnel/resources for each task

    October 3, 2015 Kin Fun LI, University of Victoria Project Management 19

  • Project Planning Process-2

    6.  Determine task dependencies: || or -- --

    7.  Determine review points

    8.  Estimate project resource requirements and cost

    9.  Task assignment

    10.  Do initial milestone chart October 3, 2015 Kin Fun LI, University of Victoria Project Management 20