Canadian Nuclear Commission canadienne Safety Commission ... · The presentation provided an...
Embed Size (px)
Transcript of Canadian Nuclear Commission canadienne Safety Commission ... · The presentation provided an...

Canadian Nuclear Commission canadienne Safety Commission de sûreté nucléaire
P.O. Box 1046 Station B 280 Slater Street Ottawa, Ontario Canada K1P 5S9
C.P. 1046 Succursale B 280, rue Slater Ottawa (Ontario) Canada K1P 5S9
Meeting MinutesE-Docs #:3422389 File/Dossier: 4.01
Date: August 24, 2009 Task #16200
MEETING
MINUTES SENT TO
*CEAA J. Adams R.L. Virtue D. Haddon *DFO B. Hood M-L. Tremblay L. Neil *NRCAN A. Dixit R. Sano
*MPMO S. Skocylas K. Mousseau *OPG L. Swami A. Webster R. MacDonald
*CNSC A. McAllister K. Lun L. Andrews M. de Vos D. Miller D. Wismer P. Wong S. Mihok M. Phaneuf M. Ilin H. Zhang Y. Zeng A. Banas A. Salway F. Harrison A. Gaw J. Churchill G. Smith V. Khotylev C. Laude S. Lei A. Mongeon
S. Munger Y. Zeng M. Xu P. Adams P. St Michael A. Bouchard P. Lahaie cc: D. Newland M. Couture L. Sigouin D. Howard A. Blahoianu R. Avadhanula G. Cherkas B. Schimmens H. Mulye S. Nguyen B. Dowsley A. Ray
SUBJECT
OBJET Workshop on Darlington New Nuclear Project – EIS and LTPS
Canadian Nuclear Safety Commission 280 Slater Street, Ottawa (Ontario)
(Room #14-032) Date: Monday, August 24, 2009
LOCATION OF
MEETING
ENDROIT DE LA RÉUNION
Time/Heure: 9 am to 5 pm

REMARKS
REMARQUES
Attendees: Attendance Sheet is found under EDOCS # 3421098. All of the attendees were present for Session 1. For Session 2, only OPG and some CNSC staff were present. Session 1 OPG made a presentation to Federal Agencies/Departments located in the Ottawa Region. A similar presentation to the federal review team located in the Greater Toronto Area will be made on August 28, 2009. The presentation provided an overview of their EIS and LTPS submission. OPG plans to submit the EIS/LTPS package on September 30, 2009. The questions/comments raised during the presentation were addressed in a satisfactory manner and was within the scope of the presentation. The presentation package is found under EDOCS # 3421673 and 3421674. However, OPG will be issuing their own package to all attendees that includes copies of the presentations along with meeting minutes. Session 2 CNSC staff made a presentation to OPG on the following topics:
a. Overview of CNSC Project Management b. Overview of the CNSC Assessment Plan c. Documents generated as a result of Review d. General Information on Lessons from Bruce Power EIS/LTPS
Submission Comments/questions made during Session 2 are listed below:
1. Does CNSC interact with other federal agencies to coordinate the review of the EIS/LTPS submission (including issuing Information Requests [IRs])?
• Yes. CNSC will brief federal agencies on staff’s planned review approach so that other federal agencies review processes can better align with that of the staff. However, each department completes its own review and submits directly to the JRP.
2. Since CNSC has multiple projects ongoing (such as new mines,
refurbishment, etc), how do the reviews get prioritized? • CNSC has a management steering committee to decide which
project gets priority. CNSC has the adequate staffing resources to deal with the review of OPG’s EIS/LTPS.
3. OPG stated that their LTPS submission will only deal with issues up to

the point of concrete pour (i.e. foundation of the plant will not be laid). However, they will likely begin excavating the plant footprint regardless of that fact that technology has not yet been selected.
4. If incremental information (i.e. licensing related) for LTPS is
submitted during CNSC review, then the 6 month JRP review clock will be stopped since it’s considered new information.
5. OPG indicated that the managing of the clock during the Bruce JRP
process appeared confusing from an outsider’s perspective and was wondering how it would be managed for this review. CNSC staff indicated that the managing of the clock is at the discretion of the JRP; however, one could assume that the stopping of the clock could be made once the JRP receives a number of proposed IRs from various parties. Likewise, the clock could be started again once the JRP issued IRs were responded to.
6. Communication Protocol – Can OPG/CNSC contact each other
directly to obtain clarifications re: IRs, where information is located in their submissions, etc?
• This process will have to be clarified with the JRP panel once it has been formed. The JRP will also need to decide what is considered a clarification/right level of detail to be considered clarification.
• OPG will make a proposal to the JRP on these process related issues; the JRP will make the final decision whether or not the proposal should be adopted.
7. OPG wanted clarification on what is completeness review and what is
technical sufficiency review in the Conformity Review process. Completeness Review is checking to make sure information in EIS/LTPS guidelines are submitted while technical sufficiency review would check to ensure enough technical information is available to execute SRGs. Staff clarified that staff’s Conformity Review was not to be confused with the 2 week period that the JRP has to determine whether to commence the 6 month review once they receive the EIS and LTPS submissions (as per the JRP Agreement).
8. Clarification was provided regarding the need for Review Summary
Report and why there was a need to have unresolved IRs included. CNSC staff stated that this is needed as it provides the NMFLD/EAD officer with a complete picture of what issues need to be addressed when working on the EIS PMD and LTPS CMD.

9. CNSC staff will clarify issues related to billing for the JRP.

Canadian Nuclear Commission canadienne Safety Commission de sûreté nucléaire
P.O. Box 1046 Station B 280 Slater Street Ottawa, Ontario Canada K1P 5S9
C.P. 1046 Succursale B 280, rue Slater Ottawa (Ontario) Canada K1P 5S9
NOTICE OF MEETINGE-Docs #:3414912 File/Dossier: 2.01
Date: August 24, 2009 Task #16200
*CEAA J. Adams R.L. Virtue D. Haddon *DFO B. Hood K. Code M-L. Tremblay *NRCAN A. Dixit R. Sano Assisting to session 1
*MPMO S. Skocylas *OPG L. Mitchell L. Swami A. Webster Assisting to both sessions
*CNSC A. McAllister K. Lun L. Andrews M. De Vos D. Miller G. Schwarz G. Cherkas H. Mulye D. Wismer P. Wong S. Mihok M. Phaneuf
M. Ilin H. Zhang A. Mongeon Y. Zeng A. Banas D. Newland G. Smith A. Salway F. Harrison C. Dodkin A. Gaw J. Churchill
TO A
* PLEASE REPORT TO THE RECEPTIONIST ON THE 2ND FLOOR UPON ARRIVAL.
SUBJECT OBJET Workshop on Darlington New Nuclear Project – EIS and LTPS
Session 1 1. Introduction 2. OPG Presentation to Government Department/Agencies
a. Roadmap to Environmental Impact Statement and Associated Technical Support Documents
i. Presentation ii. Question and Answer Period
15 minutes 60 minutes 30 minutes
Break 15 minutes b. Roadmap to License to Prepare a Site Application
and Associated Technical Support Documents i. Presentation ii. Question and Answer Period
30 minutes 30 minutes 60 minutes
Lunch 60 minutes
AGENDA
OR REMARKS
ORDRE DU JOUR
OU REMARQUES
Session 2 3. CNSC Presentation to OPG
a. Overview of CNSC Project Management b. Overview of the CNSC Assessment Plan c. Documents generated as a result of Review d. General Information on Lessons from Bruce Power
EIS/LTPS Submission that are applicable to OPG/Federal interactions
20 minutes
2 hours
Canadian Nuclear Safety Commission
280 Slater Street, Ottawa (Ontario) (Room #14-032)
Date: Monday, August 24, 2009
LOCATION OF
MEETING
ENDROIT DE LA RÉUNION

Time/Heure: 9 am to 5 pm ARRANGED BY ORGANISÉ PAR
Name/Nom: K. Lun / A. McAllister
Tel: 947-9924 / 943-9650

August 21, 2009
OPG New Nuclear at Darlington Project Contact Information for Federal Authorities
Name Contact Area of Responsibility Laurie Swami (905) 837-4540
Ext. 5203 Director Licensing and Environment
Irene Dias (905) 837-4540 Ext. 5219
Admin. Assistant to L. Swami
Leslie Mitchell (905) 837-4540 Ext. 5233
Manager Licensing and Approvals
John Peters (905) 837-4540 Ext. 5202
Manager Overall Environmental Assessment, EIS, Physical Environment Assessment
Donna Pawlowski (905) 837-4540 Ext. 5201
Manager Consultation, Communications, Aboriginal Relations
Don Williams (905) 837-4540 Ext. 5204
Manager Design and Engineering



www.opg.com/newbuild
WELCOME!
We are here to:n� Share information about the New Nuclear at Darlington project
n� Update you on the progress of the EA
n� Answer any questions you may have
n� Get your feedback on our:
• Preliminaryresults
• Approachtothedeterminationofsignificance
OPGstaffandtechnicalspecialistsareonhandtoansweryourquestions – look for their nametags.
This is an opportunity to learn more about the project and discuss your views and provide input.
Pleasetakeafewminutestotalktotheteamandfilloutcommentsheets while you are here.
Welcome to Ontario Power Generation’s (OPG’s) fifth round of Community Information Sessions on the environmental assessment (EA) for OPG’s New Nuclear at Darlington project.

www.opg.com/newbuild
IndICatIvE tIMELInE and KEy MILEstOnEs
Infrastructure OntarioInfrastructureOntarioisresponsibleforNuclearProcurement–managing a competitive request for proposal process to select a nuclear reactor vendor and technology. Three vendors are participating: n��� AREVANP n��� AECL n��� Westinghouse Electric Company A preferred vendor is to be selected in 2009, as per the Infrastructure Ontario schedule and will be responsible for the construction of the new nuclear power plant.
Ontario Power GenerationOntarioPowerGenerationisresponsibleforthefederalapprovalsprocess for the new nuclear power plant at Darlington, including: n��� An environmental assessment (EA) n��� LicencetoPrepareSite n��� Licence to Construct
OntarioPowerGenerationwillprovideoversighttotheconstructionoftheplant.OntarioPowerGenerationwillbetheoperator of the new plant, once it is commissioned.
Joint Review PanelTheJointReviewPanelisresponsiblefortheconductoftheenvironmentalassessmentoftheProjectandreviewstheApplicationfortheLicencetoPreparetheSite.TheJointReviewPanelwillissueinstructionsandatimetableforthereviewthatwill include a public hearing. When complete, the Joint Review PanelwillprepareaJointReviewPanelReportandsubmitittothe Minister of the Environment.

www.opg.com/newbuild
FEdEraL EnvIrOnMEntaL assEssMEnt rOLEs and rEspOnsIbILItIEs
Federal Responsibilities
Review Panel Responsibilities
Proponent Responsibilities
Opportunities for Public Input
Federal Authorities
Federal EA is required when:• A Federal Authority provides a licence, permit or approval enabling a project to be carried out.
Announcement of EA Commencement -
Comprehensive Study (April 2007)
• Determination of whether Project will be referred to a Review Panel (March 2008)• Determination of Responsible Federal Authorities (August 2007)• Determination of Participant Funding (April 2008)
• Participant FundingPhase 2
Issue for Public Review:• EA Guidelines - Scope of Proposed Project - Factors to be Considered
• Panel Terms of Reference - Review Steps and Procedures - Timelines
Panel Established
Panel holds PublicConsultations on the Adequacy of the EIS
Panel determinationif additional
information is required
Notice of Public Hearings
Public Hearing
Submits Report toFederal Minister of Environment and
Responsible Authorities and
is released to Public
Cabinet Responds to PanelRecommendations and
Determines Acceptability of EA
• Submitted Application for Site Preparation (September 2006)
• Submitted Project Description (April 2007)
Prepares and submits
Environmental Impact
Statement based on EIS guidelines
Providesadditional
information
Responds to Questions from
Review Paneland other
Participants
Review Panel OPG (Proponent)

www.opg.com/newbuild
LICEnCEs
TheLicencetoPrepareSiteensuresthatthesite characteristics which have an impact on health, safety, security and the environment can, and will be taken into consideration in the design and operation of the new nuclear power plant. The Licence permits works and activities that result in being ready to start construction. The application must meet the requirements of the Canadian Nuclear Safety Commission and includes information on:
n� Applicant,Purpose,SiteDescriptionn� �QualityAssuranceProgram,including
oversight of contractorsn� SiteEvaluationandEnvironmentalEffectsn� PublicConsultationProgramn� NuclearSecurityProgram
TherevisedLicencetoPrepareSiteApplication is expected to be submitted at the same time as the Environmental Impact Statement. The application will be subject to the same public hearing process under the JointReviewPanel.
The Licence to Construct permits the works and activities to construct the new reactors and associated buildings. The Licence to Construct application is expected to be submitted in 2010.

www.opg.com/newbuild
ELEMEnts In anEnvIrOnMEntaL assEssMEnt
ENVIRONMENTAL IMPACT STATEMENT
DETERMINE HOW THE PROJECT
INTERACTS WITHTHE ENVIRONMENT
Environmental Effects – Mitigations – Residual Effects
• CUMULATIVE EFFECTS• SIGNIFICANCE OF RESIDUAL EFFECTS
• FOLLOW-UP AND MONITORING PROGRAMS
Summer 2007 – Spring 2008
Fall 2008 – Spring 2009
2009
MALFUNCTIONSAND ACCIDENTS
DESCRIBE THE PROJECT
Project Scope Alternatives• Reactor • Site Layout
• Condenser Cooling • Nuclear Waste• Used Fuel
Project Phases• Site Preparation & Construction
• Operations• Decommissioning
DESCRIBE THE ENVIRONMENT
Study Areas -• Site, Local and Regional
Environmental ComponentsBaseline Characterization/Studies
Valued Ecosystem Components
EFFECTS OFENVIRONMENTON PROJECT

www.opg.com/newbuild
prOjECt OvErvIEW WOrKs and aCtIvItIEs
For EA purposes, the project is to construct and operate a nuclear power plant to generate up to 4,800 MW of baseload electricityfromuptofournuclearreactors,tomeetthefutureelectricityrequirementsoftheProvinceofOntario. Toassesstheeffectsoftheproject,assumptionsaremadeonthenumberofworkersandkeyactivities.Theseinclude:
SItE PrEPArAtION AND CONStruCtION (approximately six to eight years for two units)
SitePreparationmayinvolveupto400workers (100on-site;300off-site).Keyactivitiesinclude:
n Vegetation removal and earth-moving (cutting, grading, creating berms, stockpiles)
n Soil excavation and grading n Bedrock excavation for foundationsn Installation of power, water supply,
sewage systems, etc.n Marine and shoreline works (includingcofferdamandlakeinfill)
Construction may involve a peak workforce of up to 3,500workersfortwounits.Keyactivitiesinclude:n Installation of reactor components, steam
generators, turbines, transmission linesn Construction of nuclear waste management facilitiesn Concrete batching plant on site, (unless product
trucked to the Darlington site)n Components, equipment and materials transported
to site by transport, rail, ship or barge
OPErAtIONS (approximately 60 operating years for each set of reactors)
Operations may involve up to 1,400 workers per year for each set of two units. Mid-Life Replacement orRefurbishment may include an additional workforce of approximately2,000.Keyactivitiesinclude:
n Reactor commissioning (verifying systems, fuelling, connecting to the grid, etc.)
n Plantoperationsandmaintenancen Waste/used fuel management (transfer of wastes
and used fuel for interim or long-term storage)n Mid-life major component replacement and/or
refurbishment: steam generators; fuel channels (ACR1000);reactorvesselhead(EPRandAP1000)
DECOmmISSIONING (50 years for each set of reactors)
The key activities in decommissioning include:n Preparationforsafestorage(de-fuellinganddraining
reactors, removal and non nuclear materials, plant systems drained, de-energised and secured)
n Safe storage and monitoring (approximately 30 years)n Dismantling, disposal and site restoration
(approximately 10 years)
Site Preparation & Construction Phase(2010 to 2025)
Operation Phase(2016 to 2100)
Decommissioning Phase(2100 to 2150)
Not to Scale
Unit 1 & 2
Site Preparation& Construction
Operations
(Approx. 15-16 years)
2010 2014 2018 2022 2026 2100 2150
(Approx. 60 years)
(Approx. 50 years)
Decommissioning
Unit 3 & 4
Unit 1 & 2
Unit 3 & 4
Unit 1 & 2
Unit 3 & 4 EA Bounding TimelineThe dates shown are for EA study purposes. Actual start and in-service dates have yet to be determined.

www.opg.com/newbuild
prInCIpaL buILdIngs and struCturEs
n� A reactor building to house the reactors
n� A turbine and generator buildingn� A switch yardn� A condenser cooling system
(cooling towers are illustrative)n� A used fuel dry storage building
n� A radioactive waste storage building
n� A security building n� Secure fencing around the siten� An area for parkingn� An administration building n� Ancillary buildings
To help describe the project, we consider what buildings and structures are needed to operate and maintain a nuclear power plant. These may include:

www.opg.com/newbuild
How does a nuclear reactor work?Nuclear power stations require heat to produce steam to drive turbines and generators. In a nuclear powerstation,thefission(splitting)ofuraniumatoms creates the heat in the reactor. The primary coolant system transfers the heat from the reactor to thesteamgenerator.InaPWRtheprimarycoolantisalso used as a moderator.
The steam formed in the steam generator is transferred by the secondary coolant system to the main steam turbine which spins the generator and creates electricity.
After passing through the turbine, the steam is routed to the main condenser. The condenser removes excess heat from the steam, which allows the steam to condense. The condensed water is then pumped back to the steam generator for reuse.
n The ArEVA NP EPr and Westinghouse AP1000 reactor core consists of a vertical reactor vessel containing fuel assemblies. Both the coolant and moderator both use normal (light) water. The reactor operates with up to 5% enriched uranium fuel (low enriched fuel).
n The ACr-1000 core consists of horizontal fuel channels in a reactor vessel called a calandria. Heavy water is used to slow down (or moderate) the neutrons released from the fuel. Normal (light) water is used as the secondary coolant. For this reason the AECL ACR-1000 is considered a PressurizedHybridLightandHeavyWaterReactor.The reactor operates with an average of 2.5% enriched uranium fuel (slightly enriched fuel).
rEaCtOrs
ThethreereactortypesunderconsiderationfortheprojectaretheAECLACR-1000,theAREVANPEPRandtheWestinghouseAP1000.
n AECL ACr-1000 has a rated electrical power of 1,085 MWe (net) n ArEVA NP EPr has a rated electrical power of 1,580 MWe (net) n Westinghouse AP1000 has a rated electrical power of 1,037 MWe (net)
Thesereactorsareallconsideredpressurizedwaterreactors(PWR).

www.opg.com/newbuild
COndEnsEr COOLIng OptIOns
IntheEA,OPGconsideredalternativemeansofprovidingcondensercooling:
For All Cooling towersn One or more ponds may be required to maintain circulating water qualityn A trench would be required for the intake or outfall pipe, installed at a depth of approximately 10 metres n Water vapour plumes will be visible coming from the towers
Lake Water Coolingn Heat is transferred from the condenser via cooling water to the lake through a
discharge tunneln Large volumes of lake water are brought through the plant by a lake bottom intake tunnel which is approximately 800 metres long (from the forebay to the intake structure) and approximately 7.5 metres diameter n The discharge tunnel has a nine metre diameter face area and is approximately
1,700 metres longn The tunnels may be constructed using a tunnel boring machine or by blasting
Natural Draft Cooling towersn Heat is transferred from the cooling water to the atmosphere by evaporation in large
concrete towersn Up to two natural draft cooling towers may be constructed for each unit
(depending on the design)n Natural draft cooling towers are typically a hyperbolic shape (upside down funnel) and may extend to approximately 150 metres in height and 100 metres in diametern Constructed of steel reinforced concrete
Fan Assisted Natural Draft Cooling towersn The tower uses natural draft cooling processes with the addition of fans placed around the base of the tower to increase the air flow raten Towers have a large base and are a hyperbolic shape similar to natural
draft towern Towers are about 50 metres in height
mechanical Draft Cooling towersn Heatistransferredfromthecoolingwatertotheatmospherebyafinewatersprayn Long pipes in the towers spray downward and large fans (on top) pull air across
the dripping water to remove the heat n Mechanical draft cooling towers are typically 20 metres in height and cover an
area between 4 to 20 hectares

www.opg.com/newbuild
usEd FuEL ManagEMEnt
Used nuclear fuel is fuel that has been used by a nuclearpowerplanttogenerateelectricity.OPGhas safely managed used nuclear fuel for nearly 40 years. The used nuclear fuel is managed in a two-stage process: wet storage, which allows for initial cooling, followed by dry storage for longer interim storage.
Used nuclear fuel from the new station will also be managed using a two-stage, wet and then dry storage process.
For environmental assessment (EA) planning purposes, two interim on-site storage options will be considered:
1. Expand the existing Darlington Waste Management storage structures
2. Build an additional used fuel dry storage processing facility on the site
For EA purposes, there are two potential dry storage systems being considered for ACR1000 type used nuclear fuel, these include:
1. Dry storage containers (DSCs) stored in a warehouse type building similar to current operations at the Darlington Waste Management Facility
2. Above-ground, air cooled storage modules (AECL MACSTOR system) with fuel placed in canisters and transferred from the reactor to the storage facility in reusable casks
ThefuelsfortheAP1000andUSEPRareverysimilarto each other. Three potential dry storage systems forpressurizedwaterreactor(PWR)usednuclearfuel are being considered:
n� Metal casks that may be stored either indoors or outdoors on a concrete pad
n� Concrete canisters with an outer vertical concrete shield and inner steel liner that are generally used outdoors, on a concrete pad
n� Concrete modules within an outer horizontal or vertical concrete shield vault and inner steel liner that are generally located outdoors, on a concrete pad
Pressurized Water reactor dry storage cask and transPort
above-ground storage modules at aecl macstor gentilly Quebec

www.opg.com/newbuild
LOW and IntErMEdIatE-LEvEL WastE ManagEMEnt
tyPICAL LOW-LEVEL WAStE StOrAGE buILDING
LOW-LEVEL WAStE StOrAGE CONtAINErS INSIDE LICENSED FACILIty
trANSPOrtAtION OF LOW AND INtErmEDIAtE-LEVEL WAStE IN quALIFIED trANSPOrtAtION PACkAGES
Low-level radioactive waste includes materials such as mop heads, rags, paper towels, floor sweepings and protective clothing.
Intermediate-level radioactive waste includes materials such as used reactor components, refurbishedcomponents,andresinsandfilters used to keep the reactor clean.
Low and intermediate-level waste from the new reactors will be safely stored in a similar manner as currently used regardless of the reactor selected and in a way that minimizes the volume of waste produced and stored.
The EA includes two alternative means of managing low and intermediate-level waste:
1) Store the waste on the Darlington site in an above ground storage building
2)Transportwasteoff-siteinqualifiedtransportation packages to an appropriately licensed facility

www.opg.com/newbuild
COnCEptuaL pLant LayOuts
Conceptualplantlayoutshavebeendevelopedthatrepresentdifferentconfigurationsofhowthesite will be developed. The actual layout will be determined and designed by the vendor selected toconstructtheproject.Thefollowinggraphiclayoutsillustratethedifferentconceptualplantlayouts that have been considered in the environmental assessment.
Layout 1 is four reactor units with once through lake water cooling. This option provides the most space for the reactors
pLant LayOut 1
Expanded Transmission
Station
Trail
Soil Stockpile
401
401South Service Road
Maple G
rove Road
Holt Road
Park Road
401
Darlington A
Existing Discharge and Intake
Proposed DischargeChannel
ProposedIntakeChannel
Lake Ontario
Lake Ontario
ConstructionLandfill
Parking
ReactorPowerBlock
Mechanical DraftCooling Towers Office
Area
Park
ing
Temporary
Constructi
on Facility
Soil Stockpile
Lakefill
Construction Laydown Area
Wharf Lakefill
Not to Scale
Layout 2 is two reactor units with mechanical draft atmospheric cooling. A large land area is required for mechanical draft cooling towers
pLant LayOut 2
Expanded Transmission
Station
Trail
401
401South Service Road
Maple G
rove Road
Holt Road
Park Road
401
Darlington A
Existing Discharge and Intake
ProposedIntakeChannel
Lake Ontario
ConstructionLandfill
ReactorPowerBlock
Natural DraftCooling Towers
OfficeArea
Park
ing
Temporary
Constructio
n Facilities
Parking
Soil Stockpile
Construction Laydown Area
Wharf
Lakefill
Lake Ontario
Not to Scale
Proposed DischargeChannel
Layout 3 is two reactor units with natural draft atmospheric cooling. A large land area is required for natural draft cooling towers
pLant LayOut 3

www.opg.com/newbuild
LaKE InFILL
Site preparation will involve excavation and handling of millions of cubic metres of soil and rock. For EA planning purposes we have assumed that the maximum amount of soil that may need to be excavated is 12 million cubic metres.
OPGisexaminingtherangeofpossibilitiesformanaging the excavated soil and rock. The intention is to store as much of this soil and rock on the Darlington site as possible. However, up tofivemillioncubicmetresmaybetransportedoffsiteupto25km.
Up to four million cubic metres may be placed in the northeast quadrant on the Darlington site. Up to one million cubic metres may be placed in and adjacent to the existing Darlington soil stockpile in the northwest quadrant of the Darlington site.
Up to three million cubic metres may be placed aslakeinfill.Thenewlandformmaybeupto 40 hectares in area:
n� Fronting the shoreline from the westerly limit of the existing Darlington Nuclear Generating Station intake channel to the easterly limit of the Darlington site
n� Extending approximately 100 metres into the lake at its westerly limit to approximately 450 metres at its easterly limit
n� Theincreasedlandcreatedbylakeinfillmaybe utilized for construction and operational activities
1978 2008

www.opg.com/newbuild
ELEMEnts In an EnvIrOnMEntaL assEssMEnt
ENVIRONMENTAL IMPACT STATEMENT
DETERMINE HOW THE PROJECT
INTERACTS WITHTHE ENVIRONMENT
Environmental Effects – Mitigations – Residual Effects
• CUMULATIVE EFFECTS• SIGNIFICANCE OF RESIDUAL EFFECTS
• FOLLOW-UP AND MONITORING PROGRAMS
Fall 2008 – Spring 2009
2009
MALFUNCTIONSAND ACCIDENTS
EFFECTS OFENVIRONMENTON PROJECT
CurrEnt WOrK

www.opg.com/newbuild
atMOsphErIC EnvIrOnMEnt
Valued Ecosystem Componentsn� Pathwaytohumanhealth
n� Pathwaytonon-humanbiota
n� PathwaytoVECsandotherenvironmentalcomponents (for example noise transfer to animals in the Terrestrial Environment)
Likely Environmental Effects DuringSitePreparationandConstruction:
n� Localized increase in dust concentrations and noise levels
During Operations:
n� Possibleon-sitefogging,waterdepositionandicing events from cooling tower operations (if used)
Identified Mitigation Measuresn� Implement good dust and noise management
practices to control dust emissions and noise levels at the source
n� Ensure construction equipment is well maintained
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects

www.opg.com/newbuild
Valued Ecosystem Componentsn� Cultural meadow and thicket ecosystemn� Shrubbluffecosystemn� Wetland ecosystemn� Woodland ecosystemn� Breeding birdsn� Waterfowl staging areas and winter habitatn� Migrant songbirds and their habitatn� Winter raptor feeding and roosting areasn� Breeding and key summer habitat of amphibians
and reptiles n� Breeding mammalsn� Dragonflies and damselfliesn� Migrant butterfly stopover arean� Wildlife corridors
Likely Environmental Effects DuringSitePreparationandConstruction:n��Loss of wildlife habitat and linkages n��Removal of Bank Swallow nesting habitatn��Loss of rare plant species (Common Water Flaxseed,
CupPlantandLoesel’sTwayblade)
During Operations:n��Potentialbirdstrikesonnewbuildingsand
bird entanglement in security fencing during construction and operations
Identified Mitigation Measuresn��Limit habitat alteration during bird breeding seasonn��Naturalize disturbed areas with native plants to
restore communities and habitatsn��Develop opportunities to inform and educate the
public on Bank Swallow habitatn��Implement stormwater management techniques in Coot’sPondduringSitePreparation&Construction
n��Createnewfish-freewetlandpondswithriparianplantings
n��Verify wildlife usage of wildlife corridor and incorporate practical measures to maintain access for wildlife travel
n��RelocaterareplantspeciespriortoSitePreparationn��DevelopartificialBankSwallowandotheraerialforagespecies(ChimneySwift,PurpleMartin)habitatonsite
n��Acquire lands with existing Bank Swallow coloniesn��Develop partnerships to research declines in aerial
foragers in Ontarion��Implement good industry management practices in
the development of lighting systems and structures to reduce bird strikes and in the development of security fencing to reduce bird entanglement
Likely Residual Adverse Effect (after mitigation)n��Loss of approximately 40 to 50 hectares of cultural
meadow ecosystem on-siten��Loss of approximately 24 to 34 hectares of habitat
currently used as butterfly stopover arean��Decreased population of breeding birds on-siten��Loss of nesting habitat for Bank Swallown��Bird strike mortality with cooling towers, if usedn��Periodicandshorttermdisruptiontowildlife
travel (east-west corridor) during site preparation and construction
These are carried forwardtoassesssignificance.
tErrEstrIaL EnvIrOnMEnt

www.opg.com/newbuild
aquatIC EnvIrOnMEnt
Valued Ecosystem Componentsn� Benthic invertebratesn� Round Gobyn� Emerald Shinern� Alewifen� White Suckern� Lake Sturgeonn� RoundWhitefishn� American Eeln� Lake Troutn� Sportfish(SalmonandTrout)n� Lake Ontario near shore habitatn� Darlington Creek and Darlington Creek
tributaries
Likely Environmental Effects DuringSitePreparationandConstruction:n� Loss of aquatic habitat during site development,
lakeinfillingandmarineconstructionn� Alteration of Darlington Creek habitat
During Operations:n��Loss of local aquatic biota due to impingement
and entrainment
Identified Mitigation Measuresn� Naturalization of new stormwater
management pondsn� Salvage and relocation of aquatic plants and biota,
where practical, to a suitable existing or created habitat in advance of site preparation activities
n� Reduce impingement and entrainment with design and location of intake structure
n� Reduceextentofthermaleffectswithdesignandlocationofdischargediffuser
n� Developmentoffishhabitatcompensationplann� Captureandreleasefishfromin-waterworkareas
as work advances
Likely Residual Adverse Effect (after mitigation)n� Loss of some VEC species (benthic invertebrates, RoundGoby)fromlakeinfillandcoolingservicewater intake and discharge
n� Impingement mortality or entrainment losses associated with operation of once-through lake water cooling option and less with the cooling tower option
Thesearecarriedforwardtoassesssignificance.
Near shoreline habitat at Darlington site.

www.opg.com/newbuild
surFaCE WatEr EnvIrOnMEnt
Valued Ecosystem Componentsn� Pathwaytohumanhealthn� Pathwaytonon-humanbiotan� PathwaytoVECsinotherenvironmental
components (for example, changes in surface water qualitymayaffectfishintheAquaticEnvironment)
Likely Environmental Effects DuringSitePreparationandConstruction:n� Changes in near-shore lake circulation patternsn� Dredging in the lake and construction of the wharf
would disturb lake sediments and create turbidity
During Operations:n� Reduced sediment loading to lake due to
shoreline stabilizationn� Thermal discharges from service water and
cooling water systems will likely result in minor increased near-shore lake water temperature
n� Warmer water temperatures and increased algae in Lake Ontario at the mouth of Darlington Creek may result from the embaymentcreatedastheresultoflakeinfill
n� Coolingtowerbleed-offwillresultintheongoing discharge into Lake Ontario
n� Removal of water from lake ongoing basis to be released as water vapour into atmosphere
Identified Mitigation Measuresn� Implement good on-site stormwater managementn� Implement good industry management
practices during any activities such as lake dredging,lakeinfillandlakeblasting
n� Design discharge structure to mitigate potential environmentaleffectsofthermalplume
n� Employ dust and sediment control measures to minimize suspended sediment concentrations
n� Test and treat all effluents associated with service water system and the pumphouse trash-racks of the once-through cooling water system (if used) to comply with appropriate criteria for surface water discharges to Lake Ontario
n� Implement an adaptive management strategy to monitor and address any nuisance conditions in the embayment
n� Allcoolingtowerbleed-offwillbedirectedto appropriate treatment system. Discharge is likely to ultimately be to Lake Ontario via management measures designed to accommodate sufficient volume for the system
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects
Beaver pond on Darlington site

www.opg.com/newbuild
gEOLOgICaL and hydrOgEOLOgICaL EnvIrOnMEnt
Valued Ecosystem Componentsn� Pathwaytohumanhealth
n� Pathwaytonon-humanbiota
n� PathwaytoVECsinenvironmentalcomponents(for example, loss of groundwater input to stream couldaffecthabitatinAquaticEnvironment)
Likely Environmental Effects n� Stormwatermanagementfacilitiesmayaffect
soil quality and groundwater quality
n� Possibleincreaseintheconcentrationofcontaminants in groundwater
n� Groundwater flow conditions will be changed permanently, however, the ultimate discharge point will remain to be Lake Ontario
Identified Mitigation Measuresn� Stormwater management facilities will be
designed and implemented so as to optimize opportunities to recharge surface water to the groundwater regime
n� Good stormwater management practices includes sediment control practices, stormwater conveyance systems and conventional stormwater treatment methods
n� Design and implement stormwater management features to contribute additional baseflow into Darlington Creek and reduce groundwater drawdown area north of the Darlington site
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects
ExaMpLE OF gEOLOgICaL subsurFaCE LayErs

www.opg.com/newbuild
abOrIgInaL IntErEsts and physICaL and CuLturaL hErItagE
Valued Ecosystem Componentsn��Aboriginal community characteristicsn��Huntingandfishingforsubsistencen��Fishing, trapping and traditional harvesting
and collecting for sustenance recreational and economic purposes
n��Locations and features of cultural or spiritualsignificance
Likely Environmental Effects n��Nolikelyenvironmentaleffects
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects
Valued Ecosystem Componentsn��Aboriginal and Euro-Canadian archaeological
resourcesn��Euro-Canadian built heritage resourcesn��Euro-Canadian cultural landscapes resources
Likely Environmental Effects DuringSitePreparationandConstruction:n��Displacement of three Euro-Canadian
archaeological sites that have potential heritage value
n��IftheProjectWorksandActivitiesencroachinto the area, displacement of Burk Cemetery, monument and plaque
Identified Mitigation Measuresn� Archaeological excavation and documentationn� Ifnecessary,relocatetheBurkPioneer
CemeteryMonumentandPlaquetoasuitableoff-sitelocation
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects
abOrIgInaL IntErEsts physICaL and CuLturaL hErItagE
BurkPioneerCemeteryMonument

www.opg.com/newbuild
sOCIO-ECOnOMIC EnvIrOnMEnt
Valued Ecosystem Componentsn�� Local and regional populationn�� Educationn��Health and safety servicesn�� Local and regional economic developmentn�� Tourismn��Agriculturen��Municipalrevenuesandfinancialstatusn��Housingn��Residential property valuesn��Community character and imagen��Municipal infrastructure and servicesn��Community and recreational facilities and servicesn��Ability to use and enjoy propertyn��Community cohesion
Likely Environmental Effects DuringSitePreparationandConstruction:n�� Reduced uses and enjoyment of community and
recreational features on the Darlington site n�� Some residents living along truck haul routes may
experience disruption to their use and enjoyment due to nuisanceeffects(dust,noise,traffic)
During Operations:n��Negative change in character of community if natural
draft cooling towersn�� Reduced enjoyment of private property due to visual
dominance of natural draft cooling towers
Identified Mitigation Measuresn��Continue to share information with local and
regionalstaffonthetimingandmagnitudeoflabourrequirements of the project
n��Continue to work in partnership with government, labour groups, educational institutes through existing liaison mechanisms and programs
n��Ensuresecurity,emergencyhealthcareandfireservicesonsite for the construction workforce
n��Establish a comprehensive, mutually agreeable Community Agreement with Municipality of Clarington and Region of Durham
n��ImplementaTrafficManagementPlantoreducedisruption and maintain safe traffic conditions
n��ImplementaNuisanceEffectsManagementPlanforresidential properties along transportation route
n��Maintain contribution to community through CommunityCitizenshipProgram
n��Continue to keep neighbours and public informed about project activities
n��Develop and implement a plan to establish full access to and use of Waterfront Trail in stages after site preparation is complete
n��Seektoestablisharesolutiontoaddressanyeffectsonupperandlowersoccerfields
Likely Residual Adverse Effect (after mitigation)n��Negative change in community character where cooling
towers would be a prominent feature of the landscape, particularly in the immediate vicinity of Darlington site
n��Reduced use and enjoyment of Darlington site recreational features during site preparation and construction
n��Someresidentsalongthetruckhaulroutesandoffsitesoil storage areas may experience disruption to their use and enjoyment of property during site preparation and construction
Thesearecarriedforwardtoassesssignificance.
Employment (average # direct and indirect jobs per year over phase)
Factor
Implications for Durham Region (based on 2 units)
Existing DNGS
Site Preparation and Construction
Operations and Maintenance
5,200
3,800
17,200
5,700
$ 365 M
1,900
1,250
5,400
1,800
$ 130 M
2,500
1,800
6,700
2,250
$ 175 M
Employment (average # of induced jobs per year over phase)
Associated Population (average # persons per year over term)
Associated Housing (average # units over term)
Household Income (annual average $ per year over term)

www.opg.com/newbuild
Land usE
Valued Ecosystem Componentsn� Land use planning regime in Local Study Area
n� Visual aesthetics
Likely Environmental Effects DuringSitePreparationandConstruction:n��Increased activities on the Darlington site likely
to result in changes to land use and development patterns
n��Changes in visual setting due to soil stockpiling andgradingofexistingbluffformationsonthelakefront
During Operations:n��Changes in visual setting due to cooling towers
(if used) and vapour plume
Identified Mitigation Measuresn� Implement good industry management
practices in the design and construction of the project to optimize opportunities to visually screen onsite features
n� Implement landscape design to reduce the visibility of the operating facility
n� Implement good industry management practice in the design and development of lighting systems that will, among other considerations (navigation safety, bird strikes), reduce to the extent possible the night time visibility of the overall site and cooling towers (if used)
n� Continue to engage in discussions with local municipalities on the appropriate planning policy format and land use structure in the primary and contiguous zones to ensure maintenanceofeffectiveemergencyresponse
Likely Residual Adverse Effect(after mitigation)n� Permanentchangesinthequalityofthe
existing views of the Darlington site from viewing locations in the Local and Regional Study Areas as a result of the presence of natural draft cooling tower structures, if used and the presence of cooling tower plume
Thisiscarriedforwardtoassesssignificance.
Visual simulator, illustrating view of cooling towers on Darlington site from Highway 401 West at Waverly Road.

www.opg.com/newbuild
huMan hEaLth
Valued Ecosystem Componentsn��Members of the public
n��WorkersonOPG’sNewNuclearatDarlingtonproject
Likely Environmental Effects n��Annual radiation dose to public will be well
below the regulatory limit (less than natural background radiation)
n��Radiation dose to nuclear energy workers will remain well below regulatory limits
Identified Mitigation Measuresn��All internal and external doses received by
nuclear workers will be monitored and reported as part of the operational dose management program.Thissystemwillbeineffectduring the operation and maintenance and decommissioning phases of the project
n��An “As Low As Reasonably Achievable” (ALARA) analysiswillbeundertakenandspecificmeasures to reduce collective worker dose to the extent practical will be determined during detailed planning and design of the project
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects

www.opg.com/newbuild
radIatIOn and radIOaCtIvIty EnvIrOnMEnt and nOn-huMan bIOta hEaLth
Valued Ecosystem Componentsn� Pathwaytohumanhealthn� Pathwaytonon-humanbiota
Likely Environmental Effects n��PotentialExposureofmembersofthepublic
to very low levels of radiation from normal operations
n��PotentialExposureofnuclearenergyworkerstolow levels of radiation from normal operations
n��PotentialExposureofnonhumanbiotatoverylow levels of radiation from normal operations
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects
Valued Ecosystem Componentsn��Birds and mammalsn��Insects and invertebratesn��Amphibians and reptilesn��Terrestrial vegetationn��Aquatic macrophytesn��Benthosn��Fish
Likely Environmental Effects DuringSitePreparationandConstruction:n��Nolikelyenvironmentaleffects
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects
radIatIOn and radIOaCtIvIty nOn-huMan bIOta hEaLth

www.opg.com/newbuild
traFFIC and transpOrtatIOn
Valued Ecosystem Componentsn��Transportation system efficiency and adequacy
n��Transportation system safety
Likely Environmental Effects DuringSitePreparationandConstruction:n��Increased traffic may contribute to the ongoing
degradation of road system and result in an increased likelihood of safety related incidents
Identified Mitigation Measuresn� Collaborate with responsible agencies to ensure
that the project related traffic is considered in thedesignandimplementationofoffsiteroadimprovements
n� Collaborate with and support on a continued basis, the Municipality of Clarington and Regional Municipality of Durham to identify systemdeficienciesandfacilitateroadsafetyimprovements
Likely Residual Adverse Effect (after mitigation)n� Noresidualadverseeffects

www.opg.com/newbuild
MaLFunCtIOns, aCCIdEnts and MaLEvOLEnt aCts
OPGmustconsidertheenvironmentaleffectsassociated with the unlikely event of Malfunctions, Accidents or Malevolent Acts.
Conventional malfunctions and Accidents involve the inadvertent release of chemicals with the potential of causing harm to workers or the environment, or events that may result in personal injuries.
n� Spill of fuel to Lake Ontario• Nolongtermeffectsareexpectedonaquatic
biota or human health
n� Steam generator water treatment chemical spill• Noadverseeffectsareexpectedtoworkersor
members of the public
radiological malfunctions and Accidents involve the inadvertent release of radioactivity from components other than the reactor (e.g. nuclear waste management facilities).
n� Drop of a refurbishment waste container containing radioactive waste
n� Fire in a radioactive waste storage building
In both examples, worker doses would be a small fraction of the regulatory limit and non-human biota (animals,birds)arenotlikelytobeaffected.
Nuclear Accidents involve the reactor with damage to the fuel bundles and/or the reactor core and could result in release of radioactivity to the environment.
Anassessmentwasdonetoconfirmthatthereactorsbeing considered in this EA will meet the intent of regulatory requirements:
n�� Itwasconfirmedthattheextentofpotentialevacuation and relocation are consistent with the intent of regulations and the current emergency planning protocols
n�� Itwasconfirmedthattherewouldbenolongtermeffectsonhumanhealthoronthehealthofnon-human biota
Out of Core criticality malfunctions and Accidents involve events outside the reactor core, such as in a fresh or used fuel storage area that may result in an acute release of radioactivity.
n� These events are unlikely and would require a combination of failures to occur
n� A stringent criticality safety assessment will be performed and reviewed by the CNSC
n� The design and administrative barriers will be in place, supported by detailed safety analysis, to ensure that inadvertent criticality is not likely
malevolent Acts are the intentional attempt to cause damage. Security measures generally consist of:
n� Physicalprotection–barriers,intrusiondetection,access limitation
n� Administrative protection – security screening of personnel, training of personnel, procedures and audits
n� Personnel–highlyqualifiedsecurityresponsepersonnel, emergency preparedness
Sucheventsarenotlikelytocauseasignificantrelease of radioactivity to the public

www.opg.com/newbuild
EFFECts OF thE EnvIrOnMEnt On thE prOjECt
The EA also considers how the environment may affecttheproject.OPGisconductingstudiesoneffectsoftheenvironmentontheprojectsuchas:
Flooding n��� Coastal floodingn�� Darlington Creek n���� Directsurfacerunoffandotherflooding
hazards
Severe Weathern���� Meteorological hazard assessmentn���� Tornadoesn���� Tropical cyclonesn���� Thunderstorms and hail stormsn���� Freezing rain
Biophysical Effectsn���� Zebra and Quagga Mussels n���� Attached algaen���� Fish
Seismicityn Seismic hazard and ground motionn Seismic-related phenomenan� Geotechnical investigationn Potentialsurfacefaulting
Climate Changen� Effectsofgreenhousegasemissionsn� Potentialclimatechange
Summary of Mitigationn� The project will be designed so that nuclear
safety systems would continue to operate in theeventofanyenvironmentaleffect
n� Projectdesignandcontingencyfeatureswillbe incorporated to withstand environmental effects
n OPGwilldevelopanadaptivemanagementstrategy to address changes in the environmentthatcouldadverselyaffectthenew station in the future
n� Integrate design, management and monitoring to systematically test assumptions and adapt to changing environmentaleffects
n� Noeffectsoftheenvironmentonthe project are anticipated based on design and mitigation options
Likely Residual Adverse Effect (after mitigation)� � ��n� Noresidualadverseeffects

www.opg.com/newbuild
sustaInabILIty assEssMEnt
TheEAconsiderstheextenttowhichtheProjectcontributestosustainabledevelopment.Aprojectthatissupportive of sustainable development must strive to integrate the objective of net ecological, economic andsocialbenefitstosociety.
The sustainability assessment relies on sustainable development considerations articulated by the Municipality ofClarington,RegionofDurhamandtheCityofOshawaintheirrespectiveOfficialPlans,StrategicPlansorSustainability Strategies. These were used to create community visions, goals and objectives. The extent to which theProjectcontributestowardsachievingthestatedgoalsandobjectivesisindicatedinthegraphicbelow.
EcologicalBenefits
SocialBenefits
Economic Benefits
Green space in urban areas
Ecological
Biodiversity and ecosystem integrity
Environmental stewardship
Energy conservation
Capacity of renewable resources
Balanced development
E�cient use of infrastructure and access to services
Live, work and play communities
Community pride and identity
Personal well being
New job opportunities
Business retention, expansion and creation
Durham energy hub
Diversi�cation of the skills base
Healthy municipal �nance
Diminish Maintain Enhance
Economy
VisionTo ensure that biodiversity, ecosystem integrity and the capacity of renewable resources are maintained and enhanced in order to meet the needs of current and future generations
GoalTo protect and enhance the ecosystem
GoalTo promote balanced growth and healthy livable communities
GoalTo promote economic development
VisionTo encourage the ongoing development of vibrant, safe, healthy and caring communities that provide current and future residents with a sense of satisfaction and pride as a place to live, work and play
VisionTo promote economic development through employment and business growth, diversification of the skills base and fiscal health of municipalities in order to meet the needs of current and future residents
Social Diminish Maintain Enhance
Diminish Maintain Enhance

www.opg.com/newbuild
CuMuLatIvE EFFECts
OPGexaminedprojectsandactivitiesthatmightbecarriedout during the same time period as the New Nuclear at Darlingtonprojectandwhichcouldresultinsimilareffectsin the shared study areas. These project include: n BowmanvilleGOTrainStationProject*n ClaringtonEnergyBusinessParkdevelopment*n ExpansionofCourticeWaterPollutionControlPlant*n ExpansionofDuffinCreekWaterPollutionControlPlant
ProjectorActivity*n Expansion of Other Municipal Water Treatment and PollutionControlPlants
n Growth and Development in Regional Communitiesn Highway407EastLinktoHwy401*n Highway401Improvements&HoltRoadInterchange*n OshawaEthanolPlant*n Other(Non-OPG)FacilitiesLicensedbyCanadianNuclear
Safety Commissionn PickeringAirportn PortDarlingtonAreaEnhancements*n PortHopeAreaInitiativeProjects:� � - PortHopeProject� � - PortGranbyProject� � - OtherPortHopeAreaProjectsn PortHopeAreaWastesn St.MarysCementOperations*
n Upgradeof500kVTransmissionSystem*n YorkDurhamRegionEnergyfromWasteFacility*n ProjectandactivitiesbyOPGduringoperations,
refurbishment and continued operation and decommissioning for:
n DarlingtonNuclearGeneratingStation* n DarlingtonWasteManagementFacility*� � n OPG’sNewNuclearatDarlington (Decommissioning)*� � n PickeringNuclearGeneratingStationA - Operations(Units1&4fullyoperational, Units2&3currentlyinGuaranteed Shutdown State)
- ModificationofUnits2&3toGuaranteedDefuelled State
- Decommissioning� � n PickeringNuclearGeneratingStationB(Units5-8)� � n PickeringWasteManagementFacility
Preliminaryresultsindicatethatanycumulativeeffectsareminor and it is unlikely that additional mitigation measures are necessary.
Planned Projects and Activities 2005 2010 2015 2020 2025 2030
New Nuclear at Darlington Units 1 and 2
New Nuclear at Darlington Units 3 and 4
Hwy 407 East Extension
Energy from Waste Facility
Development of Clarington Energy Park
Extension of GO Rail Service from Oshawa to Bowmanville
Highway 401/Holt Road Interchange Improvements
Planning Construction Operations
*Projectsandactivitieswithin10kmofOPG’sNewNuclearatDarlington. All other projects and activities are beyond 10km.

www.opg.com/newbuild
sIgnIFICanCE assEssMEnt MEthOdOLOgy
Adverseenvironmentaleffectsthatarelikelytoresult from the project (after mitigation measures have been incorporated) are called “residual effects”.Allresidualadverseeffectsareassessedforsignificance.Residualadverseeffectsfromtheprojectareassessedforsignificanceusingthefollowing criteria:
Each criterion is ranked as low, medium or high using professional judgment by technical experts considering both quantitative and qualitative measurement, where appropriate. Thensignificanceofeachresidualadverseeffectis evaluated using the methodology in the diagram above.
Magnitude The size or degree of the effect compared against baseline conditions or thresholds.
Geographic Extent The area over or throughout which the effects will be measurable.
Duration The time period over which the effect will last.
Frequency and Probability The rate of recurrence of the effect.
Reversibility The degree to which the effect can or will be reversed (typically measured by the time it will take to restore the environmental attribute or feature).
Physical Human Health The degree to which the physical aspects of human health may be affected.
Psycho-social Human Health The degree to which psychological or social behaviour of the public may be affected.
Ecological Importance The importance of the environmental attribute or feature to ecosystem health and function.
Societal Value The value of the environmental attribute or features to society.
Sustainability The degree to which the effect would impact the ability for the attribute or feature to meet the needs of the present without compromising the ability of future generations to meet their own needs.

www.opg.com/newbuild
prELIMInary assEssMEnt OF rEsIduaL advErsE EFFECts FOr sIgnIFICanCE
residual Adverse Effects(after mitigation)
residual Adverse Effects(after mitigation)
Why the residual Effects are Considered minor Adverse Effects, but Not Significant
Why the residual Effects are Considered minor Adverse Effects, but Not Significant
Loss of aquatic species within footprints of lake infillandcoolingwaterintake and discharge structure
• Nearshoreenvironmentofproposedinfillhasfew documented invertebrates
• Roundgobiesareaninvasivespecies• Footprintofcooling/serviceintakeand
discharge structure is small, and habitat loss is notsignificantrelativetoentirearea
L L L M H L L L L L
Fish impingement and entrainment
• Once-through-coolingintakehasbeendesignedspecificallytoreduceentrainment&impingementoffish
• Intakeincorporatesdesignfeaturesbasedonfishbehaviourandislocatedoffshoreatdepthswhich are less productive
• ExpectedlosseswillbelowrelativetoLakeOntario populations
L L H H H L L L L L
Loss of approximately 40-50 hectares of mostly Cultural Meadow Ecosystem
• Culturalmeadowsarewidespreadintheenvironment in southern Ontario, and in the Local and Regional Study Areas
• Manyofculturalmeadowsonsiteareseedmixoroflowecologicalfunctionandtheeffectisconfinedtothesite
• VECswillstillpersistatthesite
L L H M H L L M M L
Loss of approximately 24 to 34 hectares of on site habitat currently used as a butterfly habitat during migration
• Culturalmeadowsarewidespreadintheenvironment in southern Ontario, and in the Local and Regional Study Areas
• Manyofculturalmeadowsonsiteareseedmixoroflowecologicalfunctionandtheeffectisconfinedtothesite
• VECswillstillpersistatthesite
L L H H M L M M L L
Decrease in populations of breeding birds on site
• Noneofthebreedingbirdhabitatsbeingreduced are unique to the site
• ThehabitatsoccurcommonlyintheLocalandRegional Study Areas
• BreedingbirdswillcontinuetobeattheDarlington site
L L H H M L L M M L
Loss of nesting areas for Bank Swallows
• Mitigationincludesthelong-termprotectionof important nesting areas, design and constructionofartificialBankSwallowcolonies and research into declines in aerial foraging birds
• Theseactionsareexpectedtobringlong-termtangiblebenefitstothespeciesandperhaps others
• TheportionsofthecolonybeingremovedareconfinedtotheSiteStudyAreaandalargerportion of the associated colony will still remain viable
M L H H H L L M L M
Bird strike mortalities associated with natural draft cooling towers
• Theseanticipatedstrikenumbersarelowcompared to the huge numbers of migrant birds passing over the site in spring and fall, or to the known level of mortalities at lit buildings in Toronto or due to other sources (e.g., residential windows, pet cats)
• Theeffectwilloccurinarelativelysmallareaassociated with the tower structures in the Site Study Area only
• Theeffectsareunlikelytoresultinmeasurablechange to bird populations
L L H M H L L M M L
Short-term disruption to wildlife travel along wildlife corridor during site preparation and construction
• Amajorcorridorisnotcurrentlypresentalthough the function does exist
• Wildlifeusingtheeast-westcorridorthroughthe site are already adapted to the road network and high levels of human disturbance that characterize both the Site and the Local Study Area
• Thesiteremainsopentopassageformanyofthese species and the period of disturbance will be relatively limited and reversible
L L M M L L L L L L
Permanentchangesinthe quality of views of the Darlington Nuclear site in the Local and Regional Study Areas as a result of the presence of natural draft cooling towers
• Althoughthereisavisualimpact,theprojectwillnot preclude the use and enjoyment of private property in the Local Study Area communities
• Althoughtheconditionscreatingtheeffectwill not be reversible, the magnitude of the effectwilldiminishwithtimeasthestructuresbecome a familiar feature of the landscape and the project establishes a positive track record
H H M H H L L L L L
Change in the character of communities if natural draft cooling towers are implemented
• Althoughthereisavisualimpact,theprojectwill not change the unique and distinctive qualities of Local Study Area communities
• TheareaintheimmediatevicinityoftheDarlington site is a mix of industrial, commercial and residential land uses
• Thepresenceofindustrialandcommerciallanduses is increasing
L M H H H L M L M L
Reduced use and enjoyment of community and recreational features on the Darlington Nuclear site during SitePreparationandConstruction
• Theprojectdoesnotpreventtheuseofthesitefor recreational purposes
• Thereduceduseandenjoymentofthesiteforrecreational purposes likely be experienced by a small number of users for a few years prior to its restoration
M M M H L L L L L L
Disruption to residential use and enjoyment of property during SitePreparationandConstruction due to nuisance-relatedeffects(dust, noise, traffic)
• Althoughthoseaffectedwilllikelynoticeincreased traffic, noise and dust, these effectsarenotanticipatedtobeofsufficientmagnitude to preclude continued use of private property
• Effectswillalsobelimitedtoafewpropertiesalong the haul route and a soil storage area within the Local Study Area
M M M M L L M L L L
Reduced enjoyment of private property due to visual dominance of natural draft cooling towers
• Althoughthereisavisualimpact,theprojectwillnot preclude the use and enjoyment of private property in the Local Study Area communities
• Althoughtheconditionscreatingtheeffectwill not be reversible, the magnitude of the effectwilldiminishwithtimeasthestructuresbecome a familiar feature of the landscape and the project establishes a positive track record
• Highlyunlikelytooccur• Eventwouldbeofshortdurationandany
needed cleanup or remediation would begin immediately
• Off-siteprotectiveactionssuchasshort-termevacuation or sheltering may be implemented
• Emergencyresponseplans(Ontario,municipalities,OPG)willbeinplace
L M H H H L M L L L
Noresidualeffectfrommalfunctions accidents or malevolent acts, but carried forward to assess due to general public interest
M H L L M L H L H L
mag
nitu
de
mag
nitu
de
Spat
ial E
xten
t
Spat
ial E
xten
t
Dur
atio
n/ti
min
g
Dur
atio
n/ti
min
g
Freq
uenc
y
reve
rsib
ility
reve
rsib
ility
Freq
uenc
y
Effec
t on
Phys
ical
Hum
an H
ealt
h
Effec
t on
Phys
ical
Hum
an H
ealt
h
Effec
t on
Psyc
ho-s
ocia
l Hum
an H
ealt
h
Effec
t on
Psyc
ho-s
ocia
l Hum
an H
ealt
h
Ecol
ogic
al Im
port
ance
of V
EC
Ecol
ogic
al Im
port
ance
of V
EC
Soci
etal
Val
ue
Soci
etal
Val
ue
Sust
aina
bilit
y
Sust
aina
bilit
y
L - Low, M - Medium, H - High

www.opg.com/newbuild
FOLLOW-up and MOnItOrIng prOgraM
After the environmental assessment is complete a follow-up and monitoring program is developed. The purpose of the follow-up program is to:
n� Assist in determining if the environmentaleffectsoftheprojectare as predicted from the EA
n� Determine whether assumptions made during the EA are accurate
n� Confirmwhethertheproposedmitigationmeasuresareeffectiveandifnew mitigation strategies are required
Thefollow-upprogramidentifiescommitmentsforSitePreparationandConstruction and Operations.
The development of the follow-up and monitoring program includes:
n� Identificationofthegeneraltimeframefor the follow-up program
n� Identificationofthepreliminaryscopeof the follow-up studies related to the general timeframe
n� Proposalofaprocessfordevelopingthefinalscopeandtimingofthefollow-up program with details such as monitoring parameters, locations and frequencies
OPGhasidentifiedover100possiblecommitments to follow-up and monitor.
The follow-up and monitoring program will be included in the environmental assessment and reviewed by the Joint ReviewPanel.Theresponsibleauthority,likely the Canadian Nuclear Safety Commission will ensure the follow-up and monitoring program is implemented.

www.opg.com/newbuild
Ea sChEduLE/nExt stEps
Below is a preliminary schedule of major milestones for the New Nuclear at Darlington EA
FEb/MarCh 2007 Pre-submission Consultation on Project Description (Round #1) √
aprIL 2007 OPG submits EA Project Description to CNSC √
junE 2007 Define Study Areas √
FaLL 2007 Public Consultation Round #2 √
FaLL 2007-suMMEr 2008 Establish Environmental Baseline √ (environmental components, valued ecosystem components)
sprIng 2008 Public Consultation Round #3 √
sprIng/suMMEr 2008 Determine Possible Project - Environment Interactions √
suMMEr/FaLL 2008 Identify Environmental Effects, Possible √ Mitigation, Determine Residual Effects
FaLL 2008 Public Consultation Round #4 √
FaLL/WIntEr 2008 Identify Malfunction and Accidents, Cumulative Effects and Significance of Residual Effects Underway
FaLL/WIntEr 2008 Examine Effects of Environment on Project; Follow-up and monitoring Underway
sprIng 2009 Public Consultation Round #5 Underway
2009 Environmental Impact Statement Report Submission and Licence to Prepare the Site
datE aCtIvIty status

www.opg.com/newbuild
pubLIC COnsuLtatIOn - suMMary OF IssuEs and COMMEnts raIsEd
ThroughouttheEA,OPGhassoughtcommunityconfirmationoftheworkundertaken to date, and community direction for the next steps in the assessment. OPGreceivedandincorporatedfeedbackon:
n� The project description (before it was submitted)
n� The Valued Ecosystem Components
n� EA methodology
n� Potentialeffectsandpossiblemitigation measures
n� The projects to consider in a cumulativeeffectsassessment
n� Criteria to aid in the determination ofsignificance
We’vereceivedandrespondedtothousandsofquestions and comments. At the outset, there was a high degree of interest in matters such asOntario’selectricitysystemandthelong-term plan for energy, the reactor technology and vendor selection process, long- term management of nuclear waste and use fuel, financialconsiderationsandrelationshipofvarious decision making processes.
For a full listing of questions and answers, please take a “Frequently Asked Questions” handout.
We want your input!
Today we are looking for your input on preliminary results.
Comment forms are available for you to completeanddropoffhere,ortakehomeand mail back to us. You can also have a discussionwithoneofthestaffmembershere.
Your comments will be documented and included in the EA study. Your knowledge of the local area and environment will help OPGanditsconsultantsperformamoreaccurate EA!



OPG New Nuclear at Darlington Environmental AssessmentLaurie Swami, Director Licensing and Environment
Darlington New Nuclear Project
New Nuclear at Darlington
Overview of the Environmental Impact Statement Presentation to Federal Agencies and MinistriesAugust 24, 2009

1 Contents
BackgroundProject OverviewFederal Review ProcessEA Work to Date
1 Contents

2 Purpose of Today’s Workshop
Context SettingOPG will submit to government, an Environmental Impact Statementfor the OPG New Nuclear at Darlington Project this fall
Large quantity of materials to be providedEarly comments encouraged
Interest in establishing protocol for ongoing contact to ensure efficient review
Today’s ObjectiveTo familiarize federal authorities with OPG’s documentation

3Describe the Project:
Phases3 Background
June 2006: OPG was directed by the Ontario Minister of Energy to begin a federals approvals process, including an environmental assessment, for new nuclear units at an existing site
September 2006: OPG submitted Application for Approval to Prepare a Site for the Future Construction of a Nuclear Power Generating Facility to the CNSC
April 2007: OPG submitted a Project Description to the CNSCSeptember 30, 2009: OPG will submit the Environmental Impact Statement (approx. 1,000 pages), 28 Technical Support Documents (over 9,000 pages) and LTPS (approx. 4,000 pages)

4 Overview of the Project
The “Project” defined as:
Preparation of the Darlington Nuclear Site for up to four nuclear power reactors and up to 4,800 MW of electrical capacity, and associated facilities
Construction, operation and maintenance of nuclear reactors and associated facilities for approximately 60 years of full power electricity operation
Construction, operation and maintenance of appropriate nuclear waste management facilities, and
Preliminary planning for decommissioning and eventual abandonment of the nuclear reactors and associated facilities

5 Technology Selection
In March 2008, Ontario initiated a 2 phase competitive bidding process to select a nuclear vendor to build 2 new nuclear units at the Darlington site.
In February 2009, bids were received from 3 potential vendors (AECL, Areva and Westinghouse)
On June 29, 2009, the Ontario Minister of Energy and Infrastructure announced that the Government of Ontario had suspended the “Request for Proposal” process to procure two reactors for the Darlington Site due to concern about pricing and uncertainty around AECL’s future.

6 Reactor Technologies
Reactor Vendor Single Size Type
AP-1000 Westinghouse 1100 MW New
EPR (Evolutionary Pressurized Reactor)
AREVA 1600 MW Innovative
ACR-1000 (Advanced Candu Reactor)
AECL 1200 MW New
These reactors are all considered pressurized water reactors (PWR), with the ACRincluding a heavy water moderator system
All require the use of slightly enriched uranium

77 New Nuclear Project - Major Structures/Facilities

8
Project DescriptionSite Preparation & Construction Phases
Site Preparation Phase: Activities to prepare the site for construction including receipt and transport of heavy equipment
Removal of up to 13 million cubic meters of soil
Approximately 2 years
Construction Phase:Activities to construct the nuclear reactors & associated buildings
Approximately 6 years (for first set of reactors) Darlington Nuclear Generating Station site during Site Preparation
(1980)

9
Project DescriptionOperations & Decommissioning Phases
Operations Phase: Work & activities that would occur on site during routine operation and maintenance of the plant
Assumes 60 years of full power operation per reactor
Mid-life refurbishment, if required
Decommissioning Phase:Major activities associated with decommissioning the reactors
Typically occurs about 30 years after the end of operation
Dismantling may take an additional 5 to10 years
Darlington Turbine Hall
Darlington Generator

1010Alternatives Considered in the EA
Condenser Cooling SystemsLake Water Cooling
Natural Draft Cooling Towers
Fan Assisted Natural Draft Cooling Towers
Mechanical Draft Cooling Towers
Used Fuel ManagementExpand existing facility/storage structures Build a design-specific dry storage processing facility
Low and Intermediate-Level Waste ManagementNew above ground storage facility on siteTransport off-site in licensed containers to licensed facility
Harris Nuclear Power Plant, US

1111 Bounding Condition for Potential Lake Infill
Lake Ontario shoreline along Darlington property, up to 40 hectaresCreate cofferdam, dewater the area, fill with soil/rock from excavationsRequires permits/approvals from provincial and federal authorities
1978 2008 2012

12 Conceptual Plant Layouts
Principle buildings and structures
Site access
Switchyard expansion
Parking, construction facilities
Soil stockpiles, lake fill, land fill
Used fuel & nuclear waste storage

13 EA Study Areas/Spatial Boundaries
Site Study Area –existing Darlington siteLocal Study Area ~ 10 km from the Project Site
Predict most environmental effects within LSA
Regional Study Area ~ 50 km from the Project site
Largely socio-economic effectsCumulative effects

1414Bounding EA Timelines/Temporal Boundaries
The dates shown are for EA study purposes. Actual start and in service dates have yet to be determined

15 Regulatory Schedule
Step Target Completion DatesEIS Guidelines Finalized Complete
September 30 2009
Intervenor FundingJRP Announcement September 2009
JRP determines whether to proceed with public review 14 days
LTPS Issued April 2011
DFO, TC Approvals 90 Days Post-EA Approval(*Contingent upon proponent's submission of
required information )
October to April/May 2010
(not included in schedule)
May 2010
Hearing August/September 2010
December 2010
February 2011
OPG Submission of EIS and LTPS Application,Submission of DFO and TC Applications
Six Month Public and Technical Review EIS and LTPS Application
Additional Information Request Response Time
Hearing Notice
JRP Report
Federal Government Response to JRP Report

16 JRP Sufficiency Review
Conformity Check/Public Review (October 2009 to April/May 2010)
Purpose: to determine whether there is sufficient information to proceed to public hearing
EIS, LTPS application and all supporting documents (43) released by JRP for government and public review (notice posted – TCD: October 15 2009)
Federal Authorities, Review Agencies, Public and Intervenors undertake reviews on sufficiency of information
JRP issues information requests to OPG for clarification and/or additional information
OPG response to information requests
JRP determination - sufficient information to proceed to hearing
OPG contacts will be available to provide clarification if needed (see package)

17 Environmental Impact Statement
Chapter Contents TSDs1 Introduction
Description of the ProjectMethodologiesDescription of the Existing EnvironmentEffects Assessment and MitigationsOther Likely EffectsMalfunctions, Accidents and Malevolent ActsCumulative Effects AssessmentSignificance of Residual EffectsCommunications and ConsultationFollow-up and MonitoringPreliminary Decommissioning Plan
13 Conclusions14 References
Special Terms
2 234 115 146 107 58910 11112
15

18 Chapters 1 and 2
Framework of EIS described for the readerProject overview (e.g. location, need, timelines, proponent)Regulatory requirements being metScope of the assessmentEIS content and organization
7-page table provides detailed linkages between EA Guideline Requirements and the EIS
EIS is a detailed summary reportTechnical Support Documents are where detailed analysis is performed
Chapter 1 - Introduction
Chapter 2 – Description of the ProjectAlternative meansProject scope for EA purposes
Site Preparation and ConstructionOperations and Maintenance
Model site layouts describedPlant Parameter Envelopes introduced

19 Chapter 3
Explanation of the EA process steps
Description of how the EA is used as a planning tool
EA Methodology
Unique to this EIS is the use of a Plant Parameter Envelope (PPE)
The EA uses PPE to effectively assess potential effects from a range of reactor types and units
PPE represents limiting reactor and plant values. It serves as the conservative bounding framework for EA planning purposes
Any reactor fitting within the PPE as assessed will be bounded by this EA
Plant Parameter Approach

20 Chapters 4 and 5
Chapter 4 - Description of the Existing EnvironmentSummary of the baseline conditions
Chapter 5 - Effects AssessmentStructured approach to provide the overview of likely effects:
Summarizes effects on Valued Ecosystem Components Describes mitigation measures that may be appliedIdentifies residual adverse effectsSummary table provided for all effects, mitigation and residual adverse effectsDetailed analyses are identified in references to supporting TSDs

21Chapter 6
Other Considerations in Effects Assessment
Three distinct sections:
1. Sustainability (assessed against 3 goals):Ecosystem protectionHealthy living communitiesEconomic development
2. Effects of the Environment on the Project:FloodingSevere weatherBiophysical changeSeismicity
3. Climate Change Considerations:Climate change models/potential effectsGreenhouse gas emissions summary

22 Chapter 7
Malfunctions, Accidents and Malevolent Acts
Study includes:Conventional - oil spills, fallsRadiological & Nuclear - radiation release from drop of nuclear waste container, damage to the fuel bundles, out of core criticalityMalevolent Acts - intentional attempt to cause damage, such as airplane crash
Mitigations:Robust plant designQualified staffComprehensive programs (environmental, safety)Extensive security program
Examined effects of unlikely radioactive release:Ontario Nuclear Emergency Plan

2323 Chapter 8
Over 30 other projects and activities examinedSome nearby projects overlap in time
Detailed examination to determine whether any effects overlapConstruction activities may coincide
Traffic, nuisance effects
Anticipated to be minor
OPG will continue to work with other agencies responsible for these projects to ensure project effects are managed
Cumulative Effects

24 Chapter 9
13 environmental areas studied in detail 9 areas all measurable effects can be effectively mitigated and managed4 areas with some remaining (residual) adverse effects, after mitigation:
AquaticLoss of some benthic invertebrates, Round Goby, from lake infill and cooling water intake and discharge structure during construction
Impingement mortality & entrainment losses from cooling water usage during operations
TerrestrialFrom site preparation activities, loss of: cultural meadow ecosystem, butterfly migratory habitat; and bank swallow nesting areas.
Disruption to wildlife travel during site preparation and construction
VisualChanges in visual setting due to cooling towers (if used) and vapour plumes
Socio-economicReduced enjoyment of private property and Darlington Nuclear site community & recreational featuresNegative change in community character associated with atmospheric cooling towers (visual effects)
Significance of Residual Effects

25 Chapter 10
Initiated in fall 2006, inputs to environmental studies
Six rounds to date, typically each round includes:Stakeholder Briefings/Updates/Presentations EA Newsletters , Stakeholder Project Update Letters Community Information Sessions
Ongoing ActivitiesStakeholder/Public Inquiry/ResponseEmployee information sessions/lunch and learnCommunity Events, Presentations to Community Groups, etc.
Ongoing engagement with First Nations and Métis
OPG Participant Funding Program
Darlington Planning & Infrastructure Information Sharing Committee
Communications and Consultation

26 Chapter 11
Key Commitments include:
Minimize fish effects from water intake and discharge
Restore biodiversity to the environment by incorporating native plants, wetland areas and aquatic habitat in the restoration plan after site preparation is completed
Protect and promote bank swallows and aerial foragers
Undertake controlled removal and recording of archaeological and cultural features on site
Implement Traffic and Nuisance Effects Management Plans

27 Chapter 13
Minimal environmental effects predicted from New Nuclear at Darlington
Primarily during site preparation and construction phase
Primarily within 3 km of the site
Can be managed, mitigated
Proposed commitment to mitigation & follow-up actions
Socio-economic Benefits
EIS and Licence to Prepare Site application, when submitted, will be posted to OPG’s project website
Chapter 13 - Conclusions

28 Conclusion
Submission of EIS and LTPS documentation – September 2009Large amount of information materials for reviewEarly comments are encouraged
OPG is available to support federal authority post-submission

29
Questions?
Please contact us:www.opg.com/newbuild
1-866-487-6006
Contact Us29

New Nuclear at Darlington Overview of the CNSC Licence to Prepare Site and Other Early ApplicationsPresentation to Federal Agencies and MinistriesAugust 24, 2009
OPG New Nuclear at Darlington Environmental AssessmentLaurie Swami, Director Licensing and Environment
Darlington New Nuclear Project

1 Contents
Project for the Purpose of the ApplicationsOverview of Licence to Prepare Site Application
Other Federal, Provincial and Municipal Permits and Licences
1 Contents

2 Contents
Purpose of the Licence to Prepare Site Application:
Demonstrates the site is appropriate for a nuclear power plant
Define site layout, activities to be undertaken
Describes the management programs that govern the activities to be carried out
September 21, 2006 – OPG submitted to the CNSC a preliminary application for Approval to Prepare a Site for the Future Construction of a nuclear power generating facility
2 Purpose of the Application

3 Project for Purpose of the Applications
Site preparation activities will include all activities within the portion of the site necessary to facilitate the subsequent construction of the reactor buildings and other related structures, and operation of the new nuclear plant
For this application, site preparation is more narrowly focused and definitive than that described in the EA
Site preparation activities include, for example:
Land clearing, excavation and grading for the nuclear facility
Construction of environmental monitoring & mitigation systems, and monitoring activities
Installation of fencing and access control infrastructure
Site access control

4 Application Structure
Application is structured to demonstrate CNSC regulation requirements are met.Introduction includes a table identifying where requirements of CNSC regulations are found
Like information is grouped in approximately 6 chapters
LTPS and supporting documents equals approximately 4,000 pages
Application references would form a necessary part of licensing basis for site preparation phase, e.g. site evaluation report. These will be submitted with the application (and will form part of the application)
Application (where possible) relies on the EA and is cross referenced as appropriate.
Note: Additional supporting information that may assist reviewers will be provided separately

5 LTPS Documentation
Submission #1The following documents which will accompany the Application and formpart of the licensing basis:
Site Evaluation for OPG New Nuclear at Darlington – Nuclear Safety ConsiderationsEmergency Preparedness Site Evaluation for OPG New Nuclear at DarlingtonExclusion Zone Determination for Darlington New Nuclear ProjectPreliminary Decommissioning Plan OPG New Nuclear at Darlington Site –PreparationPlant Parameter Envelope ReportDNNP Management System (the Charter), if available

6 Site Evaluation
CNSC RD-346 “Site Evaluation for New Nuclear Power Plants” describes expected evaluations to determine if proposed site(s) are acceptable
Based on IAEA safety requirements for site evaluation
OPG conducted a site evaluation in accordance with RD-346Results incorporated in application
Section includes a table indicating where RD-346 requirements are addressed, e.g. flooding, emergency planning, extreme weather and security.

7
Submission #2 We intend to provide the following Supporting Evidentiary Materials in a separatesubmission:
Site Boundary Considerations for New Nuclear – DarlingtonSite Evaluation Studies for Nuclear Installations at Darlington Site: Evaluation of External Human Induced EventsSite Evaluation of the OPG New Nuclear at Darlington – Part 6: Evaluation of Geotechnical AspectsSite Evaluation of the OPG New Nuclear at Darlington – Part 5: Flood Hazard AssessmentSite Evaluation of the OPG New Nuclear at Darlington – Part 4: Evaluation of Meteorological EventsSite Evaluation for OPG New Nuclear at Darlington – Probabilistic Seismic Hazard Assessment Site Evaluation for OPG New Nuclear at Darlington – Part 3: Summary of Seismic Hazard EvaluationsSite Evaluation for OPG New Nuclear at Darlington – Part 2: Dispersion of Radioactive Materials in Air and WaterSite Evaluation of the OPG New Nuclear at Darlington - Additional ConsiderationsQuality Report for Darlington Site Evaluation StudiesEIS will also be referenced as evidentiary material although it will not actually be submitted in recognition that JRP are receiving the EIS under separate submission
LTPS Documentation

8 Programs During Site Preparation
Application references OPG’s overall quality management for the project during site preparation
Execution of site performance is delegated to EPC Company
OPG as owner/operator and licensee retains overall accountability for the project
Describes key programs (e.g. health and safety, project management) and OPG’s oversight of the EPC Company and OPG activities in support of the project
Oversight programs to demonstrate competency in executing project work and activities.

9 Radiation Protection and Site Security
Specific RP program is not required – no nuclear substances under this licence
Only high level information provided for security
Demonstration of how project meets overall nuclear security requirements will be provided as prescribed information
I.e. prescribed information is not included in the public version of the Application

10 Other Early Federal Applications
Federal applications for water-related activities (e.g. lake infilling and wharf construction) will be filed at the same time as EIS
Department of Fisheries and Oceans (Fisheries Act)Authorization for Works Affecting Fish HabitatAuthorization to Destroy Fish by Means Other Than Fishing
Transport Canada (Navigable Waters Protection Act)Approval for works that may interfere with navigation
Approval Application information will include:Preliminary engineering illustrative of works to be approved and potential construction methodologies, e.g. maximum lake infilling bounding scenario.Steps taken to date to develop Fish Habitat Compensation Plan (DFO)Fish and fish habitat existing conditions and environmental effects (DFO)

11 Other Early Federal Applications
Specific applications for rail line will not be provided at this timeTransportation activities e.g. bridge over CN railway
OPG has had an ongoing discussion with CN Rail about the project, and will continue to do so with EPC Co. to reach a final agreement
If an agreement regarding a bridge over the rail line cannot be achieved, Canadian Transport Agency would be involved

12 Provincial / Municipal Requirements
Over 50 different permits and approvals may be required over thecourse of the project.
Examples of activities that may require provincial approvalsShoreline Work – Work Permit Construction – Ontario Ministry of Natural Resources
Storm Water Management System – Ontario Ministry of Environment
Examples of activities that may require municipal approvalsApprovals to tie into municipal water supply and sanitary sewer services – Region of Durham and Municipality of Clarington
Upgrades to Regional/Municipal Roads – Region of Durham and Municipality of Clarington
Dumping of fill, removal of fill, alteration of grades – Municipality of Clarington

13 Conclusion
Work reflected in LTPS and supporting documents will demonstrate:
The site is appropriate for a nuclear power plant
CNSC regulatory requirements are satisfied
OPG will continue to support federal authorities as needed and appropriate for their review of the submissions

14
Questions?
Please contact us:www.opg.com/newbuild
1-866-487-6006
Contact Us14