By: Matthew Forbes DO 1: PROJECT MANAGEMENT. Taking last weeks do 1 to the next level Duration and...

8
By: Matthew Forbes DO 1: PROJECT MANAGEMENT

description

SCHEDULE

Transcript of By: Matthew Forbes DO 1: PROJECT MANAGEMENT. Taking last weeks do 1 to the next level Duration and...

Page 1: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

By: Matthew Forbes

DO 1: PROJECT MANAGEMENT

Page 2: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

Taking last weeks do 1 to the next levelDuration and completionPlanned expenses

To be able to know more systems, I used Merlin

PURPOSE

Page 3: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

SCHEDULE

Page 4: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

?- indicates this is an estimation and not net completed

Only A-C have been completed

The total duration is 65 days

SCHEDULE EXPLANATION

Page 5: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

The critical Path isA-B-D-E-F-H

Before work started C was on the critical path in the place of AA’s work took 4 weeks (not 2)C’s work took 3 weeks (as expected)

CRITICAL PATH

Page 6: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

PERFORMANCE

Page 7: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

Total expected duration is 17 weeks2 weeks behind scheduleA took 1 week longer than CB took 1 week longer

Expected duration for activities D-H is 11 weeks

PERFORMANCE

Page 8: By: Matthew Forbes DO 1: PROJECT MANAGEMENT.  Taking last weeks do 1 to the next level  Duration and completion  Planned expenses  To be able to know.

The critical path can be altered from the duration projection to what the actual completed time

It is important to use Project Management to keep track of any changes

This was the first time we also planned ahead with money

INTROSPECTION