Business Case Template

24
Business Case Title Subtitle Department Title [This should be the publication title for the initiative, if it were to be funded in the budget process.] [Please note: 1. This template can be used for both capital and output proposals with modification for output initiatives as appropriate. 2. When completing this template you should refer to the investment lifecycle and high value/high risk guidelines and associated technical guidelines for more detailed explanations. 3. The extent of detail should be scaled to the relative complexity of the proposal and some areas may not be relevant for all proposals. 4. The project options analysis (Section 4) requires a consistent methodology applied to analysis of options with a level of accuracy consistent with ‘concept estimate’ at a minimum. The analysis should be evidence based and defensible with estimates of capital costs, cash flows and ongoing output or operating costs sufficient to robustly compare options. 5. The recommended solution (Section 5) requires a detailed cost buildup with significant rigor based on a design brief or project scope statement. Accuracy of information in relation to the recommended solution should be at a level of accuracy consistent with that of a ‘preliminary design estimate’. 6. Any text included in [ ] is for guidance only and should be deleted. 7. Forward any comments to [email protected]]

Transcript of Business Case Template

  • BusinessCaseTitleSubtitle

    DepartmentTitle[Thisshouldbethepublicationtitlefortheinitiative,

    ifitweretobefundedinthebudgetprocess.]

    [Pleasenote:1. Thistemplatecanbeusedforbothcapitalandoutputproposalswith

    modificationforoutputinitiativesasappropriate.2. Whencompletingthistemplateyoushouldrefertotheinvestment

    lifecycleandhighvalue/highriskguidelinesandassociatedtechnicalguidelinesformoredetailedexplanations.

    3. Theextentofdetailshouldbescaledtotherelativecomplexityoftheproposalandsomeareasmaynotberelevantforallproposals.

    4. Theprojectoptionsanalysis(Section4)requiresaconsistentmethodologyappliedtoanalysisofoptionswithalevelofaccuracyconsistentwithconceptestimateataminimum.Theanalysisshouldbeevidencebasedanddefensiblewithestimatesofcapitalcosts,cashflowsandongoingoutputoroperatingcostssufficienttorobustlycompareoptions.

    5. Therecommendedsolution(Section5)requiresadetailedcostbuildupwithsignificantrigorbasedonadesignbrieforprojectscopestatement.Accuracyofinformationinrelationtotherecommendedsolutionshouldbeatalevelofaccuracyconsistentwiththatofapreliminarydesignestimate.

    6. Anytextincludedin[]isforguidanceonlyandshouldbedeleted.7. [email protected]]

  • Contents

    Executivesummary..............................................................................................11. Part1Problem..........................................................................................2

    1.1 Background........................................................................................................................21.2 Definitionoftheproblem..................................................................................................21.3 Evidenceoftheproblem....................................................................................................21.4 Timingconsiderations........................................................................................................21.5 Considerationofthebroadercontext...............................................................................3

    2. Part2Benefits...........................................................................................42.1 Benefitstobedelivered.....................................................................................................42.2 ImportanceofthebenefitstoGovernment......................................................................42.3 Evidenceofbenefitdelivery..............................................................................................42.4 Interdependencies.............................................................................................................4

    3. Part3Strategicresponse..........................................................................53.1 Methodandcriteria...........................................................................................................53.2 Strategicoptionsanalysis..................................................................................................53.3 Recommendedstrategicoption........................................................................................8

    4. Part4Projectoptionsanalysis..................................................................94.1 Projectoptionsconsidered................................................................................................94.2 Stakeholderidentificationandconsultation.....................................................................94.3 Socialimpacts..................................................................................................................104.4 Environmentalimpacts....................................................................................................104.5 Economicimpacts............................................................................................................104.6 Overallevaluationofsocioeconomicandenvironmentalimpacts................................104.7 Financialanalysis.............................................................................................................114.8 Riskcomparison...............................................................................................................114.9 Integratedanalysisandoptionsranking..........................................................................11

    5. Part5:Deliverabilityofrecommendedsolution.....................................145.1 Detailsofrecommendedsolution...................................................................................145.2 Commercialandfinancial................................................................................................145.3 Management...................................................................................................................175.4 Delivery17

    AppendixA:BenefitManagementPlan.............................................................19AppendixB:Financialdatapresentation............................................................20AppendixC:Signoffchecklist............................................................................22

  • BusinessCaseTitleSubtitle 1

    Executivesummary

    [TheExecutiveSummaryisanessentialstandalonepartofafullbusinesscasehighlightingtheoverallstoryandkeypointsoftheFullBusinessCase.WhiletheExecutiveSummaryisthefirstsectionofthefullbusinesscase,itisoftenthelastareacompleted.ItshouldbeaclearandconciseplainEnglishoutlineofthewholeproposalandasaguidelessthan10pageslong.Includesummarytablesifappropriatee.g.toestablishcontext.TheExecutiveSummaryshould: Describetheinvestmentproposalinonetotwosentences.

    Thisdetailedbusinesscaseseeksformalapprovaltoinvest$[xxx]millionin[20yy/yy]to.....(Thisshouldincludebothcapitalandoutputfactorsincludingongoingresourcingandexpectedoutcomes.)(Note:Thisdescriptionshouldserveasthesummarydescriptionrequiredforbudgetpublications.)

    Statewhatdecisionmakersarebeingaskedtoconsiderordecideand,ifrelevant,anyrecenthistoryofconsiderationsuchasthestrategiccase.

    IdentifyanyoverarchingcontextualfactorsForexamplespecifyiftheproposalisrelatedtoanelectioncommitmentandprovideabriefoverviewofhowtheproposalrelatestothatcommitment.Iftheproposalisextensionorsubsequentstageofanexistinginvestmentoutlinethepreviousfundingorcommitmentanditsimpacttodate.

    Brieflyidentifythedifferentoptionsconsideredandasummaryoftheevaluationofthoseoptions(includingasummarisedoptionsrankingtable).

    TheExecutiveSummaryneedstoconveythattheinvestmentproposal: meetsanimportantneed issupportedbystrongstrategicandpolicymerit; optimisesvalueformoneyfromawholeoflifeperspective;and isachievablei.e.itcanbedeliveredontimeandonbudgetandwillrealisetheintendedbenefits

    itsetsouttoachieve.Whereaproposalfacesconsiderableuncertaintytheexecutivesummaryandbusinesscaseshouldconveyoptionstoflexiblydealwiththatuncertaintyratherthanlockinacompletesolutiontoosoon.AttheendoftheExecutiveSummary,insertupdatedInvestmentConceptBrief(includingInvestmentLogicMap)ifavailable.Providereferencetokeysupportingdocumentation.AddanykeydocumentsorextractstotheAppendixofthefullbusinesscase.]

  • 2 DepartmentTitle

    1. Part1 Problem

    [Foroutputproposalsthefullbusinesscaseislikelytobethefirstpresentationoftheproposaltogovernment.Giventhis,theStage1:ConceptualiseguidelinemayassistincharacterisingtheproblemforthepurposeofthisPart.ForassetproposalsthisPartshouldrevisitandconfirmthecurrencyoftheanalysisoftheproblemintheearlierstrategicbusinesscase(strategicassessmentorpreliminarybusinesscase).Thiswillinvolverepresentingtheinformationfromthestrategicbusinesscase,reassessingitsvalidityandfurthersubstantiatingtheexistenceoftheproblemwithevidencewhereappropriate.Theintentistostrengthenthecasefortheproblem,andbrieflyoutlineanysignificantchangessincethestrategicbusinesscase.Rememberthataproblemcanincludeaserviceneed,issue,orlostopportunity.ForfurtherinformationonpopulatingthisPartforassetsubmissionsseetheStage2:Proveguideline.]

    1.1 Background[Describethecontextandbackgroundnecessarytosetthescenetointroducetheproblemandbenefitsfromaddressingtheproblem.Outlinetheexistingservicerelatedoutputs,existingassetbaseandresourcecommitmentsincludinglapsingstatus.Thismightincludeadiscussionontheneedforgovernmentinterventionandroleofgovernment,currentservicefunding,servicedistributionandlevels,andunderlyingdriversofthoseservices.Thissectionmayalsointroduceprovidersandstakeholdersrelevanttotheproblem.]

    1.2 Definitionoftheproblem[ExplaininplainEnglishandinlessthanonepagetheproblem(s)needingtobesolved.Presentthecauseofeachproblem,whoisaffected,andhowtheyareaffected.Describethenatureoftheproblemforexamplewhetheritisimmediate,transitory,ongoingorescalating.]

    1.3 Evidenceoftheproblem[Providetheevidenceofboththecauseandeffectoftheproblem.Evidencemightinclude: demandforecastswithassumptions; keyperformanceindicators(KPIs)oncurrentperformancelevels;and/or facts/examplesoftheproblem.]

    1.4 Timingconsiderations[Describewhytheproblemneedstobesolvedbygovernmentatthistime,notinganyconnectionstolongtermplanningdocuments.Explorewhethertheproblemissuitedtoastagedresponse.Explaintheimplicationsofdelayingaresponsetothedefinedproblemsuchas: physicalorcapacitylimitswillbereached significantreductionsinthelevelofservice(quality/quantity)willbeexperienced failuretomeetspecificgovernmentcommitmentsorlegislativerequirements requirementforurgentactionatadditionalcostduetoassetfailure,systemoverloadetc; leadtimeforinvestmenttobecomeoperational;and anycriticaldependencieswithrelatedservicerequirements.]

  • BusinessCaseTitleSubtitle 3

    1.5 Considerationofthebroadercontext[Explainwhethersimilarneedsoropportunitiesexisteitherinsideoroutsideyourorganisationthatmightbeaddressedtogetherwiththisproposal.Forexample,benefitsofawidersectoralapproach,integrationopportunities,pilotstudiesinothersectorsthatmayimpactthetypeofresponse.]

  • 4 DepartmentTitle

    2. Part2 Benefits

    [ForassetproposalsthisPartshouldrevisitandconfirmthecurrencyoftheanalysisofthebenefitsintheearlierstrategicbusinesscase(strategicassessmentorpreliminarybusinesscase).Thiswillinvolverepresentingtheinformationfromthestrategicbusinesscase,reassessingitsvalidityandfurthersubstantiatingtheevidenceofbenefitdeliverywhereappropriate.Theintentistostrengthenthecaseforthebenefits,andbrieflyoutlineanysignificantchangessincethestrategicbusinesscase.ForagenciesusingtheInvestmentManagementStandardtomapbenefits,notethatnotallbenefitsidentifiedaspartofaninvestmentlogicmappingprocesswillbesuitableforinclusioninaneconomicevaluationofaninvestmentproposal.Economicevaluationsfocusonwelfareimpactsonsocietyratherthanagencyspecificimpactsandtransferbenefits.Economicbenefitswhichwouldbesuitableforinclusionineconomicevaluationsaretypicallyspecific,tangible,andabletobemonetisedandcanbelinkedunambiguouslytoaninvestmentoractivity.DTFcanprovidecasebycaseguidancetoagenciesonthisissueasneeded.]

    2.1 Benefitstobedelivered[Explainthekeybenefitsthatflowiftheproblemissolved.(Thesecanbedrawnfromtheinvestmentlogicmapandbenefitmapifavailable.)Listkeyhighleveleconomic,socialandenvironmentalbenefitstheinitiativewilldeliver.Anydisbenefitsornegativeconsequencesresultingfromaddressingtheproblemmustbeoutlinedclearly.]

    2.2 ImportanceofthebenefitstoGovernment[Showhowthisinvestmentwillhelptoadvancethegovernmentand/ororganisationtomeetitsobjectives.Thismightincludereferencetothesizeandtimingofthosebenefits.Describehowthisinitiativeconnectstogovernmentprioritiesandthedepartmentscorporate,strategicandlongtermplanningdocuments.]

    2.3 Evidenceofbenefitdelivery[Definethemeasuresandkeyperformanceindicatorsthatwillshowwhetherthebenefitshavebeendelivered.Thesebenefitsprovideevaluationcriteriaandobjectivesforthedevelopmentandselectionofinterventionsandoptions.Detailsofbaseline,interimandtargetmeasures,datesfortheKPIsandtheperson/positionresponsiblefordeliveringthebenefitsshouldbeincludedinanappendedbenefitmanagementplanorequivalent,whichhasbeenupdatedtoreflecttherecommendedoption.Referenceorincludethebenefitsmanagementmap.Whereappropriate(asanalternativetoaBenefitManagementPlan)anevaluationstrategy/frameworkshouldbeincludedorattached.]

    2.4 Interdependencies[Identifykeyinterdependenciescriticaltobenefitdelivery.Forexamplerelianceonotherprojectsordecisions.Theseinterdependenciesmayrequirealevelofflexibilitytobebuiltintotheproposal.]

  • BusinessCaseTitleSubtitle 5

    3. Part3 Strategicresponse

    [ForassetproposalsthisPartshouldrevisitandconfirmthecurrencyoftheanalysisintheearlierstrategicbusinesscase.Thiswillinvolverepresentingtheinformationfromthestrategicbusinesscase,reassessingitsvalidityandfurthersubstantiatingtheevidence,feasibilityandassessmentofthestrategicoptionsanalysisprocess.Theintentistostrengthenthecaseforthepreferredstrategicresponse,andbrieflyoutlineanysignificantchangessincethestrategicbusinesscase.

    3.1 Methodandcriteria[Outlinethemethodandcriteriausedtoselectthestrategicresponse.Criteriashouldincludetheextenttowhichinterventionswillachievetheproposedbenefitsandoffervalueformoney.Identifyassumptionsandconstraintsusedtoinformthedevelopmentofstrategicoptions.]

    3.2 Strategicoptionsanalysis3.2.1 Strategicinterventions

    [Explainthepotentialstrategicinterventions.Describeandprovideevidenceorreasoningastowhytheseinterventionsmighthaveanimpact.Thetablemaybeusedtooutlinestrategicinterventions.Noteitisnotmandatory.]StrategicInterventionsIntervention1Intervention2Intervention3Intervention4Intervention5Intervention6Intervention7Intervention8Intervention9Intervention10TableXSummaryofpotentialstrategicinterventions[Thenumberofstrategicinterventionsthatshouldbeconsidereddependsonthescaleandcomplexityoftheproblem/investment.]

  • 6 DepartmentTitle

    3.2.2 Strategicoptions[Explainhowthestrategicinterventionscanbepackagedintostrategicoptions.Thiscanbeimportedfromthepreliminarybusinesscase,providedthatongoingcurrencyofinformationhasbeenrevalidated.Thetablemaybeusedtooutlinestrategicinterventions.Noteitisnotmandatory.]

    Strategicoptions Option1 Option2 Option3 Option4 Option5 Option6StrategicInterventions Intervention1 Intervention2 Intervention3 Intervention4 Intervention5 Intervention6 Intervention7 Intervention8 Intervention9 Intervention10

    TableX:Strategicoptions[Listedinthelefthandcolumnsarestrategicinterventionsthatcouldrespondtotheidentifiedproblemanddelivertheexpectedbenefits(andtheirKPIs).Againstthelistedstrategicinterventions,aspreadofstrategicoptionsshouldbestructuredtoprovidegenuinealternativestrategicresponsestotheproblem.Theseareintherighthandcolumns.Shadeboxesandallocatepercentagestoshadedboxestoindicatetherelativeimportanceofeachspecificinterventionwithintheoption.Todecideontheimportanceofeachspecificinterventionwithintheoption,balancetwofactors:theimportanceoftheinterventionindevelopingtheKPIsandthelikelycost/effortinvolved.]

  • BusinessCaseTitleSubtitle 7

    3.2.3 Rankingofstrategicoptions[Evaluatethestrategicoptionstodeterminetheproposedstrategicresponse.Thiscanbeimportedfromthepreliminarybusinesscase,providedthatongoingcurrencyofinformationhasbeenrevalidated.Provideevidencetosupportthishighlevelassessment.Thetablemaybeusedtooutlinestrategicinterventions.Noteitisnotmandatory]

    Strategicoptions Option1 Option2 Option3 Option4 Option5 Option6 BenefitsPercentageoffullbenefittobedelivered 0% 0% 0% 0% 0% 0%Benefit1 % Benefit2 % Benefit3 % Cost Estimatedcapitalinvestmentcost(Range) $nmil$nmil $nmil$nmil $nmil$nmil $nmil$nmil $nmil$nmil $nmil$nmilEstimatedoperationalcosts(Range) $nmil$nmilpa $nmil$nmilpa $nmil$nmilpa $nmil$nmilpa $nmil$nmilpa $nmil$nmilpaTime(Range) mmmm mmmm mmmm mmmm mmmm mmmmRisksRisk1 Risk2 DisbenefitsDisbenefit1 Disbenefit2 Ranking13

    TableX:Evaluationofstrategicoptions[Costshereareindicative/orderofmagnitudeanddonotneedtobepreciselycalculated,butneedtobereasonableestimateoflikelyfinancialimpactofeachoption.]

  • 8 DepartmentTitle

    3.3 Recommendedstrategicoption[Presenttherecommendedstrategicoption,summarisingtheresponseandtherationalebehinditsselection.Forexample,therecommendedoptionmayhavebeenselectedbecauseitprovidesalevelofflexibilityrequiredtodealwithuncertaintysurroundingtheproblem.]

  • BusinessCaseTitleSubtitle 9

    4. Part4 Projectoptionsanalysis

    [Accuracyofdatausedtocompareprojectoptionsshouldbesufficienttorobustlycompareoptions.Analysisofprojectoptionsrequiresalevelofaccuracyconsistentwithconceptestimates(ataminimum)ofcapitalcosts,cashflowsandongoingoutputoroperatingcosts.Aconceptestimateisanapproximationoftheprobablecostofaprogramorprojectbasedonavailableverifiableinformation.Thelevelofaccuracyusedtopresentestimatesshouldreflectthescaleandcomplexityoftheinvestment.Thelevelofanalysisshouldprovidesufficientinformationforaneffectivecomparisonoftheprojectoptionsandtodemonstratethatanadequaterangeofoptionshavebeenconsidered.Themethodologyusedshouldbeconsistentacrossalloptions.Indicativecostsshouldbesupportedbyevidenceanddefensible.Thetablesinthissectionareaguideonlyandshouldbeused,modifiedornotusedasappropriate.ProjectswhichareHVHRshouldprovidemoredetailedinformationtosupportassessmentofrobustness.Incharacterisingtheprojectoptionsandconsideringtheirimpacts,agenciesshouldaddresssustainabilityinvestmentopportunitiesofprojectoptions.Forexamplewheresignificantoperationalsavingscanbederivedthroughspecificapproaches.Thefocusshouldbetoidentifyupfrontsustainabilityinvestmentsinareasofneedandwhicharelikelytodeliveragoodinvestmentreturn.FurtherinformationFormoreinformationoncompletingthissectionseethe: Stage2:Proveguideline. Technicalguideline:SustainabilityinvestmentguidelinesforVictoriaspublicassets.]

    4.1 Projectoptionsconsidered[Expandeachofthestrategicinterventionsincludedinthestrategicresponseintoseveralmoredetailedpotentialprojectoptions,includingabasecaseandatleastonemarketbasedsolution.Aimforamaximumofaroundfive.RefertotheStage2:Proveguidelineforanexplanationofthebasecaseandmarketbasedsolutions.DescribethemethodandrationaleusedtoselecttheprojectoptionsDescribeprojectoptions,including: scope assetandoutputoptions(orcombinations); atleastonemarketbasedsolutionwherepossible; potentialfor3rdpartyrevenues; criticalassumptionsorconstraints(orwindowsofopportunity)ofeachoption; outlineanyprojectoptionsconsideredbutnotevaluatedandstaterationalefornon

    consideration;and atahighlevel,theextenttowhicheachofthefeasibleoptionsconformstoGovernmentand

    relevantagencylegislation,policies,standardsandstrategies.]

    4.2 Stakeholderidentificationandconsultation[Atabroadlevel,provideanoverviewofthelikelyrelativeimpactonkeystakeholdersofthevariousprojectoptions,andoutlinetheirpositioninrelationtotheproject.]

  • 10 DepartmentTitle

    4.3 Socialimpacts[Outlinethesocialimpactsandopportunitiesoftheproposalandidentifyanysignificantsocialissuesspecificallyrelevanttoparticularprojectoptions(i.e.differentiatingbetweentheprojectoptions).]

    4.4 Environmentalimpacts[Provideahighleveloverviewoftherelativeenvironmentalimpactanalysisoftheoptionsincludingspecificactionsrequiredtomeetallrelevantlegislativerequirementsandidentifiedlikelycommunityconcerns.]

    4.5 Economicimpacts[Provideahighleveloverviewofallsignificanteconomicimpactsandopportunitiesoftheoptions.Economicimpactsinthiscasereferstoimpactsonkeyeconomicvariables,suchasvalueadd,productivity,workforceparticipation,unemploymentandothers.Thiscouldbedoneinaqualitativemanner(e.g.bydescribingpossiblechangesandtheirlikelyorderofmagnitude),orthroughactualeconomicmodellingtocomeupwithrobustquantitativeestimates.Thelatershouldonlybedonewherethemagnitudeoftheprojectwarrantsthisadditionaleffort.ThereisawealthofdataavailablefromtheAustralianBureauofStatisticsandothersources,whichcanassistinthisendeavourparticularlywhenprovidingqualitativedescriptionsofpossibleimpacts.Wherethemagnitudeoftheprojectwarrantsprovidingquantitativeestimates,thenComputableGeneralEquilibrium(CGE)modellingisrecommended.Likeallmodelling,thisneedstobebasedonrobustassumptions/inputsthataretransparentinorderforittobeseenasreliable.]

    4.6 Overallevaluationofsocioeconomicandenvironmentalimpacts[Theexpectedsocioeconomicandenvironmentalimpactsoftheprojectoptionsneedtobeassessedandconsolidatedwithinarobustframeworkthatappropriatelycapturesandweighstheseimpacts.TheassessmentofsocioeconomicandenvironmentalimpactsisveryimportantbecauseiteffectivelyoutlineswhattheGovernmentwouldbepurchasingforitsinvestment(intermsofthenetbenefitstosociety).Thepreferredmethodologyforintegratingsocial,economicandenvironmentalimpactsisacostbenefitanalysis(alsoknownasaneconomicevaluation).Thismaybecombinedwithamulticriteriaanalysisforimpactsthatareunsuitedtothecostbenefitanalysisframework,suchaswherebenefitsaredifficulttomonetise,.Thesetoolsshouldenableallkeyimpactstobecapturedintheassessment.]

    4.6.1 Costbenefitanalysis(economicevaluation)[Identifywelfareimpactsonsociety,bothcostsandbenefits,foreachprojectoptiontheseimpactsincludebothmarketandnonmarketspecificimpactsintheareaspreviouslydescribedassocial,environmentalandeconomic.Describethemethodologytobeused;ingeneralthiswillbeanetpresentvalueassessmentatanaggregatelevelrelativetothebasecase.Quantifyandmonetisecostsandbenefitsatthelevelofaccuracyofconceptestimatetodevelopedconceptestimate.Notethatthelevelofaccuracyshouldbedeterminedbasedonthescaleandcomplexityofthisinvestment.Assumptionsshouldbeprovidedtojustifyestimatesused.Oncecostsandbenefitshavebeenestimated,agenciesshoulddiscountimpactsbacktopresentvaluesandranktheprojectoptions.Notedistributionalimpacts,whileanimportantfactorforgovernmentdecisionmaking,arenotincludedintheheadlineresults(e.g.thenetpresentvalue)oftheeconomicevaluation(whichaddresseswelfareimpactstosocietyasawhole).ForfurtherinformationoncompletingthispartseeStage2:Proveguideline.Outlinetheoutcomeoftheeconomicanalysis.]

  • BusinessCaseTitleSubtitle 11

    4.7 Financialanalysis[Provideanestimateofthecapitalandwholelife(output)costsoftheprojectoptionsanddescribetheprocessbywhichtheestimatewasderived(e.g.workshop,previousproject).Costingsforthissectionofthefullbusinesscaseareatconceptestimatelevelataminimum,andnotextensivelydetailed,butshouldconsiderwholeoflifedifferencesbetweenoptionsoveranappropriateperiod.Theyneedtobeareasonableevidencebasedrealisticestimatesbutarenotintendedtobecomprehensivelyconstructedfromfirstprinciple.TheyneedtoprovidesufficientdetailtoallowtheNetPresentValue(NPV)comparisonofoptions.Theanalysisshouldallowdecisionmakerstoconsidertheoptionthatwilldeliverthebestoutcomesinlinewithgovernmentobjectives,includingBudgetconsiderations,andwillhaveademonstrableeffectonoutput/servicedeliveryperformance.]

    4.8 Riskcomparison[Riskassessmenthereishighlevelandneedstobesufficienttoenablerelativecomparisonofoptions.Describeriskassessmentprocessfortheprojectoptionsanalysis,whichmayincludeariskworkshop.Risksidentifiedshouldconsiderthefinancial,economic,socialandenvironmentalanalyses.Provideasummaryofkeyriskswhicharecriticaltodifferentiatethesuccessoftheinvestmentinrelationtotheprojectoptionsconsidered.Significantuncertaintiesmaywarrantadifferentapproachtotheinvestmenttoincorporateflexibilitytomanagetheuncertainty.Toassistinidentifyingthekeyriskstoconsider,thefollowingisa(nonexhaustive)listofriskcategories:Changeinlaw/policy;commercial;commissioning;completion/construction;contractual;demand;economic;environmental;financial;implementation;investmentplanning;management;obsolescence;operations;organisational;political;privatesector;regulatorytechnological;residualvalue;upgrade.]

    4.9 Integratedanalysisandoptionsranking[Thissectionsummarisesatahighleveltherelativemeritsoftheoptionsconsidered.Detailsinthissectionareexpectedtobeataconceptuallevelonly.Totheextentthatcosts,benefitsandriskshavebeenquantifiedandvaluedrobustly,thepreferredoptionistypicallytheonewiththehighest,riskadjusted,NPV.Astheheadlineresultoftheeconomicevaluationdoesnotincludedistributionalimpactsorwhereaprojectoptionhassignificantintangible(ornonmonetised)benefits,theseimpactscanoutweighthedifferenceinNPVbetweenalternativeoptions.Thiscanalterthechoiceofthepreferredoptionandthesetradeoffsneedtobeclarifiedfordecisionmakers.Multicriteriaanalysis(MCA)canbeausefultooltodothis.Selectionofoptionscanbeaffectedbytherisk/uncertaintyassessment.Further,wheretheNPVofanoptionissubjecttosignificantuncertainty,itcanbedifficulttodistinguishbetweenalternatives.Alowrisk,lowNPVoptionmaybepreferredtoanalternativewithhigherbutmoreuncertainnetbenefits.Thelevelofuncertaintymaysuggestthatflexibilityneedstobebuiltintotherecommendedapproach,forexampleallowingdecisionstobemadeprogressivelyasmoreinformationbecomesavailable.Inasummarytable,provideanintegratedassessmentoffinancialandnonfinancialimpactstoarriveatarankingofprojectoptions.Whereamulticriteriaanalysisisincludedintheintegratedassessment,outlinetherelativeweightingofthefinancialandnonfinancialcomponents.Seetwoalternativeexamplesofpossiblefinancialandsocioeconomicanalysissummarytablesbelow.Note,choosewhichtableofthesetwooptionsismostappropriatetoyourintegratedanalysis.Donotfilloutboth.]

  • 12 DepartmentTitle

    Tablexx:Presentingtheresultsoftheoptionsanalysis

    Projectoption1:DoNothing

    Projectoption2:

    Projectoption3:

    Projectoption4:

    Projectoption5:

    AnalysisPeriod(years) CapitalCosts($m) OutputCosts($m) CostBenefitAnalysis(ofmonetarycostsandbenefitsdiscountedattheappropriateDiscountRate)PresentValueofBenefits($m)

    PresentValueofCosts($m)

    BenefitCostRatio NetPresentValue($m) Otherimportantconsiderations(seetheexamplesprovided)Intangiblecosts/benefits(e.g.small,med.,large)

    Distributionalimpacts(e.g.small,med.,large)

    Preferredoption

    Tablexx:Presentingtheresultsoftheoptionsanalysis,withmulticriteriaanalysis

    Projectoption1:DoNothing

    Projectoption2:

    Projectoption3:

    Projectoption4:

    Projectoption5:

    AnalysisPeriod(years) CapitalCosts($m) OutputCosts($m) CostBenefitAnalysis(ofmonetarycostsandbenefitsdiscountedattheappropriateDiscountRate)PresentValueofBenefits($m)

    PresentValueofCosts($m)

    BenefitCostRatio NetPresentValue($m) MultiCriteriaAnalysis(rankingofintangiblecostsandbenefits,ifany)Criteria1 Criteria2 Criteria3 Preferredoption

    4.9.1 Testingtherobustnessoftheoptionsanalysis[Conductingasensitivityanalysisisaformofquantitativeanalysistoexaminehownetpresentvalues,benefits,costsorotheroutcomesvaryasindividualassumptionsorvariableschange.Thisapproachmaybeusedtotesttherobustnessoftheprojectoptionsanalysis,particularlyforlargerinvestments.Provideahighlevelsummaryofthekeyassumptionsfortheoptionsassessment.Provideadescriptionontherobustnessoftheoptionsanalysisinrelationtokeyassumptionsmade.Thetablebelowisoptional.]Tablexx:SensitivitytestingresultsScenarioOne:.

  • BusinessCaseTitleSubtitle 13

    Projectoption1:DoNothing

    Projectoption2:

    Projectoption3:

    Projectoption4:

    Projectoption5:

    AnalysisPeriod(years) CapitalCosts($m) OutputCosts($m) CostBenefitAnalysis(ofmonetarycostsandbenefitsdiscountedattheappropriatediscountrate)PresentValueofBenefits($m)

    PresentValueofCosts($m)

    BenefitCostRatio NetPresentValue($m) OtherimportantconsiderationsorMultiCriteriaAnalysis(rankingofintangiblecostsandbenefits,ifany)Criteria1 Criteria2 Criteria3 Preferredoption

  • 14 DepartmentTitle

    5. Part5:Deliverabilityofrecommendedsolution

    [ThefullbusinesscaseisthefirsttimedepartmentsareaskedtoaddresstheinformationrequiredinPart5andspeakstothequestion:Canthesolutionreallybedelivered?,thissectionisakeypartofthefullbusinesscaseandshouldputforwardarigorouscaseclearlyjustifyingwhytherecommendedsolutionisthemosteffectiveandactionablesolution.Thissectionshouldincludeconfirmationoftheaboveanalysisinthelightofdetailedcostingandscopingoftherecommendedsolutionaswellasadditionaldetailedinformationrelatingspecificallytothedeliverabilityoftherecommendedsolution,asspecifiedbelow.Toavoidduplication,refertoearliersectionswhereappropriate.Thissectionshouldalsojustifywhytherecommendedsolutionispreferredinrelationtoeachcomponentoftheanalysis.]

    5.1 Detailsofrecommendedsolution[Clearlystatewhichprojectoption(whichmaycompriseoneoranumberofprojects)istheRecommendedSolution,addressingtherationaleforitsselectioninlightoftheintegratedassessment,statingitsdetails(includingobjectivesandaprojectscopestatement).Ifamajorassetisrequired,provideabriefsummaryofthedesignandspecificationstotheextenttheyhavebeendeveloped.Note:detaileddesignsarenotexpectedatthisstage,howeverdepartmentsmustprovideenoughinformationonscopetosupportarigorouscosting.ProvidedetailsonoutputrequirementsassociatedwithchangesproposedtoservicedeliveryincludingVPSandnonVPSstaffingimplications.Whereappropriateincludeasummaryofkeyelementsofthedesignfeasibilitystudywhichdemonstratesthelongtermvisionforthepreferredoptioninthebroaderurban/environmentalcontext.ProvideaDesignIntentStatementtodemonstratetheintendedlevelofdesignqualityandidentifywhatdesignaspectsoftheprojectneedspecialconsideration.Provideinformationonpreferredsequencingorstagingoftheprojectsolutionandjustifywhystaging/sequencingisrequiredordesired.DescribesignificantbroaderimpactsspecifictotheimplementationoftheRecommendedSolution.Indicatelocationaldetailsandserviceareaimpacts.Outlinehowthesolutionisconsistentwith,oraddresses,publicinterestissuessuchasequity,accessetc.]

    5.2 Commercialandfinancial5.2.1 Procurement

    [Outlinetheprocurementoptionsanalysismethodandprocess,showingrankingofoptionsagainstcriteriausedtoselectedrecommendedprocurementstrategy.Detailtherecommendedprocurementstrategyforthisinvestment,justifyingwhyitisthebestvalueformoneyoption,forexampleduetoitscapacitytoincludeflexibilityorbettermanagerisk.Thisshouldbebalancedwiththerelatedissuesoftime,cost,wholeoflifevalueandquality.Outlinetheorganisationsexperienceandcapabilitytodeliverthepreferredprocurementmethodaswellaskeyrisksandcontractualissues.(Includestrategytoaddressdeficiencieswhereappropriateforexampleintentiontoengageexperthelp.)

  • BusinessCaseTitleSubtitle 15

    Formulateadaptationstothepreferredprocurementmethodtoensurethatqualityandgooddesignareembeddedintheprocess.TheOfficeoftheVictorianGovernmentArchitectcanprovideadviceontheselectionofprocurementmodelsandpotentialadaptationsandthedesign,siteutilisationetc.IfaPPPprocurementapproachisbeingproposedthePartnershipsVictoriaGroupatDTFcanadviseontheadditionaldetailsrequired.Ifprojectalliancingisbeingconsidered,fullbusinesscaserequirementsaredifferent,pleasecontactDTFCommercialDivisionforfurtheradviceorconsulttheNationalguidelines.]

    5.2.2 Riskassessmentandmanagement[Provideadetailedriskassessmentoftherecommendedsolution,outliningkeyrisksandmanagementstrategies.]Risk Managementstrategy[Describerisk] [Outlinestrategyformanagement] TableX:Keyriskstothesuccessofthisinvestment[Therisksmayhighlighttheneedforaflexibleapproachtotheinvestment.Forexamplewheretheuncertaintiesmayberesolvedatapointintime(e.g.successorfailureofapilotstudy)andflexibilitycanbebuiltintoallowaninformeddecisionatthistime(whethertoproceedwiththefullinvestment).Thissectionshoulddescribedesiredflexibilityandcircumstanceswhichmakeflexibilitydesirable.Provideanoverviewofproposedarrangementsforongoingriskmonitoringandmanagement.Includeappendixwithriskmanagementstrategyandriskregister.]

    5.2.3 Detailedcostingandeconomicevaluation[ProvideadetailedoverviewofthecostingfortheRecommendedSolution,includingcapitalTEIandoutputcosts.Includebudgetcashflowoverarelevantperiodforbothcapitalandoutputamounts.Theprojectbudgetestimateincluding:basecostestimate,baseriskallocationandcontingencyshouldbebasedonaprojectscopestatementatthepreliminarydesignestimatelevel.Identifytheimpactonoutputfundingandthebreakdownofoperatingcoststokeycomponentssuchasstaffing,maintenance,depreciation,CACetc.Thisdetailshouldextendoverareasonableperiodofyearstoallowawholeoflifecostingperspective.Attachappropriatetablesintheappendices,referAppendixBforexampletables.DepartmentsshouldconsultwithDTFtoagreecostingsbeforesubmittingthebusinesscaseforBudgetfundingconsideration.ForAssetprojects:RefertotheInvestmentLifecyclesProjectBudgetGuidelinewhichprovidesspecificguidanceondevelopmentoftheprojectbudget.Thetablesbelowarebasedonthatguidanceandmaybemodifiedtoincorporateappropriatedetails.]Element Estimate TablereferenceBasecostestimate $XXXm (Table2)Baseriskallocation $XXm (Table3)Projectcostestimate $XXXm Contingency $XXm (Table3)Projectbudget $XXXm Table1:Headlineprojectcostelementsummary

  • 16 DepartmentTitle

    BASECOSTESTIMATEEffectivedateofBCE:dd/mm/yyEstimateddateofcommencementofconstruction:dd/mm/yy1 DirectCosts 1.1 Materials 1.2 Labour 1.3 PlantHire Subtotal $2 IndirectCosts 2.1 Recurrentoverheads 2.1.1 Sitefacilities 2.1.2 Plant&Equipmentsitemaintenance 2.1.3 Projectmanagementcosts 2.1.4 Commercial 2.1.5 QAandSafety 2.2 Nonrecurrentoverheads 2.2.1 Establishmentandmobilisation 2.2.2 Disestablishmentanddemobilisation 2.2.3 Projectinsurances 2.2.4 Professionalfeesdesign,legal,financial,etc Subtotal $3 OwnersCost 3.1 Contractedprofessionalstaff 3.2 Investigations 3.3 Landcosts&resumptions 3.4 Authorityfees 3.5 Ownersuppliedplantandequipment Subtotal $4 ContractorsFee 4.1 Profitmargin 4.2 CorporateOverheads Subtotal 5 ProvisionalSums 5.1 Subtotal $TOTALOFBASECOSTESTIMATE $Table2:BasecostestimateBASERISKALLOCATIONANDCONTINGENCY6 BaseRiskAllocation 6.1 Escalation (periodbetweenBCEandconstruction) 6.2 ProjectRiskA 6.3 ProjectRiskBetc Subtotal $ 7 Contingency 7.1 Subtotal $TOTALOFPROJECTRISKS $Table3:Projectrisks[TheNetPresentValueestimateshouldberecalculatedbasedontherefinedcostsandamoredevelopedassessmentofthebenefitsfortherecommendedsolution.Fortherecommendedsolutionagenciesmayneedtoinvestinvaluationtechniquessuchasmarketbasedvaluation,revealedpreferences,statedpreferenceorbenefittransfermethodtobetterassessthemonetaryvalueofbenefits.Note:thisshouldonlybeundertakeniftheadditionaleffortandexpenseincurredinassigningmonetaryvaluesreflectsthelikelysizeofthoseimpacts.

  • BusinessCaseTitleSubtitle 17

    Basedonthedetailedcostingofcapital,outputsandbenefitsfortherecommendedsolutionformalisetheeconomicanalysis(e.g.NPVandBCR)todemonstratetheeconomicimpactoftheinvestment.]

    5.2.4 Fundingsources[Discussproposedfundingsourcesincludingpotentialcontributionsfromotherlevelsofgovernment,privatesector,saleofassetsetc.Thissectionshouldpresentasummaryofthesourcesoffundingrequirementforcapitalandoutputcostswhichwillberequiredforbudgetdeliberations.Thisshouldincludeoffsetsortheconsequencesofadoptingamarketbasedsolution.TypicallythispresentsbudgetandforwardestimateswithabalanceofTEIandongoingoutputfunding.ReferAppendixBforexamplesofhowthisinformationmightbepresented.]

    5.3 Management5.3.1 Governance

    [Fortherecommendedsolution,detailtheproposedprojectgovernancestructuredemonstratingitsappropriateness.Note:ForHVHRprojects,DTFmustbeincludedintheprojectgovernancestructure.ASeniorResponsibleOwnerneedstobeidentified(orproposedforallinvestments.]

    5.3.2 Stakeholderengagementandcommunicationsplan[Providedetailedinformationaboutkeystakeholdersinrelationtotherecommendedsolution.Provideanoutlineofkeyelementsofstakeholderandcommunicationsanalysisdescribingstakeholders,theirlikelypositionontheprojectandplanstomanagethat.Ifavailableattachasanappendixaproposedhighlevelstakeholderengagementandcommunicationsstrategycoveringtheapproachtodealingwithstakeholdersbothuponprojectannouncementandongoingduringproject.]

    5.3.3 Projectmanagementstrategy[Outlinetheproposedprojectmanagementstrategydemonstratingitssuitabilityandrobustness,appendinganydetailedplansasanappendixifnecessary.Describetheorganisationalcapabilityandgenericsystems,standardsandmethodologywhichwouldallowtheprojecttobedeliveredsuccessfully.Demonstrateinthissectionthattheimplementingorganisationhasthecapacityandcapabilitytomobiliseanddeliverthisinvestment.]

    5.4 Delivery5.4.1 Changemanagement

    [Outlinethescopeoforganisational/processchangemanagementrequiredtoeffectivelydeliverthebenefits.Thismayinvolveprocessreengineering,staffretrainingetc.requiredtotransitionfromexistingarrangementstosupporttheoperationofthenewinvestment.Ifchangemanagementrequirementsaresignificantconsiderappendinganoutlineofthechangemanagementstrategy.Notethisdoesnotincludemanagementofproposedscopechangesduringimplementation.]

    5.4.2 Timelinesandmilestones[Listthemajormilestonesanddeliverablesandtheirdeliverytimelinesandcontingencies.Outlinethehighlevelprojectschedule,includingprocurementstepsandstatutoryapprovalsandkeydecisionpointsforprojectprogression,terminationorotherwise.Provideinformationonpotentialcompetingpriorities,dependencyanalysis,skills,capabilities,availabilityofagencystaffetc.Provideadviceonpubliccommunicationofprojecttimelines(tobeconsistentwithcommunicationsstrategy).]

  • 18 DepartmentTitle

    5.4.3 Performancemeasures[Provideastatementofinvestmentbenefits.Analysehowwelltherecommendedsolutionaddressestheproblemandkeybenefits.Thissectionaddressestheeffectivenessandefficacyoftheproposal.Providereferencestotheevidenceofbenefitdeliveryidentifiedinsection4andprovidefurtherspecificinformationonperformancemeasurementfortheproposedproject,thisshouldbeadetaileddescriptionof: howwelltherecommendedsolutiondeliversidentifiedbenefits;and thespecificKPIsthatrelatetotherecommendedsolution.Refertotheappendedupdatedbenefitmanagementplantoinformthissection.Mostinvestmentswillaffectoutputperformancemeasures.Theimpactonexistingoutputsandperformancemeasuresshouldbespecifiedindicatingboththechangestooutputmetricsrelativetocurrentlevelsandthetimingofthatimpact.]Outputname:PerformanceMeasures

    Unitofmeasure

    Changeintargetifproposalisendorsed201213201314201415201516201617

    Quantity Quality Timeliness

    5.4.4 Readinessandnextsteps[Explainplanstotransitiontheinvestmenttothenextstage(Stage3:Procure)Explainthemainareasofuncertaintytoberesolvedinthenextstage,forexample,informationregardingstaffing,approvals,andlandacquisitionetc.]

    5.4.5 Signoff[Signoffsarerequiredby: Primaryauthor Theseniorresponsibleowner(ordepartmentalChiefFinancialOfficer)onGatewaysProject

    ProfileModel(PPM)includedtoupdateproposalrisks. Theseniorresponsibleowner(orChiefFinancialOfficer)andthedepartmentsSecretarythese

    arerequiredforfullbusinesscasestobeconsideredbytheGovernment.InestablishingtheprojectbudgetestimatetheSROshouldsignoffon: Thestatementsoftheservicebenefitsandprojectscope. Theadequacyoftheprojectbudgetincludingthebasecostestimate,riskassessment,baserisk

    allocationandcontingency. Thisshouldbesupportedbyadditionalsignoffsfrom:

    Thebasecostestimator;and Theagencyanditsadvisersonbaseriskallocationandcontingency.

    Providedetailsofanyreviewprocess(e.g.forHVHRGatewayreviewsaremandatory).Sothatdecisionmakersknowthatthebusinesscaseisthoroughandcomplete,pleaseprovideaqualityassurancechecklistsuchassetoutinAppendixC,withbusinesscasesubmissionsseekingendorsementfromdepartmentalSecretaries.SeetheStage2:Proveguidelineformoredetails.]

    5.4.6 Exitstrategy[Detailtheexitstrategyandthefactorsthatwouldleadtowantingtoexiteitherearlyoratterm.Investmentsmaybetimelimitedormayinvolvepilotstudies.Thissectionallowsforconsiderationofwhatterminationrightsaredesirableatkeyreviewordecisionpointsforexamplelapsingprograms.]

  • BusinessCaseTitleSubtitle 19

    AppendixA:BenefitManagementPlan

    [PasteSpecialasanEnhancedMetafileforoptimumpicturequality.]IncludeabenefitmanagementorevaluationplanifavailableorcompletethefollowingtableforeachKPI.]KPI Baseline Source Interimtarget Reportingforum Startdate Frequency Enddate Responsibility

  • 20 DepartmentTitle

    AppendixB:Financialdatapresentation

    Thefollowingtablesareintendedasaguidetodatainclusionandshouldbeusedorsupplementedasappropriate.Operatingcostsshouldbeaddressedoverareasonableperiodtoallowawholeoflifeperspectiveinanappropriatetable.Modifytablesasrequired,forexamplebyadjustingperiodtocaptureoutputcostsfromcommencementoftheoperationofnewfacility.B.1FundinghistoryInthetablebelowprovidedetailsofthefundinghistoryforthisorsimilar/relatedinitiatives.Thistableshouldincludefundingforanearlierstageinamultistageproject,fundingforbusinesscasedevelopmentorscopingstudy,fundingforalapsingprogram,orfundingforarelatedprogramthathasbroadlythesamepolicyobjectiveasthisinitiative.Descriptionoffundingprovided 200809

    $m200910$m

    201011$m

    201112$m

    201213$m

    B.2ExistingfundingbaseInthetablebelowprovidedetailsoftheexistingfundingbasethathasbeenprovidedforthisorsimilar/relatedprograms.Thisshouldincludefundingthatisinthedepartmentsbaseaswellasfundingforanyrelatedlapsingprograms.Descriptionoffundingprovided 201213

    $m201314$m

    201415$m

    201516$m

    201617$m

    B.3Budgetimpact 201213

    $m201314$m

    201415$m

    201516$m

    201617$m

    TEI$m

    capitalfundingEstimatedassetinvestmentcashflow

    (Componenta) 0.000 0.000 0.000 0.000 0.000 0.000(Componentb) 0.000 0.000 0.000 0.000 0.000 0.000(Componentc) 0.000 0.000 0.000 0.000 0.000 0.000Subtotal(grossassetpriceincrease) 0.000 0.000 0.000 0.000 0.000 0.000Fundsfromothersources(e.g.assetsaleproceeds,Commonwealthfunding,trustaccounts)pleasespecify

    (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)

    NetImpactoncapitalappropriation 0.000 0.000 0.000 0.000 0.000 0.000outputfundingPricechangerequestedforprovisionofoutput

    (Componentx)grossoutputprice 0.000 0.000 0.000 0.000 0.000 0.000

  • BusinessCaseTitleSubtitle 21

    201213$m

    201314$m

    201415$m

    201516$m

    201617$m

    TEI$m

    (Componenty)grossoutputprice 0.000 0.000 0.000 0.000 0.000 0.000Capitalassetcharge 0.000 0.000 0.000 0.000 0.000 0.000Depreciationexpense 0.000 0.000 0.000 0.000 0.000 0.000Offsetfrominternalreprioritisation (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)Subtotal(netoutputpriceincrease) 0.000 0.000 0.000 0.000 0.000 0.000Offsetfromrevenue (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)Offsetfromanotherfundingsource(eg.Commonwealthfunding,CSF,trustaccount)pleasespecify

    (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)

    NetImpactonoutputappropriation 0.000 0.000 0.000 0.000 0.000 0.000B.4RevenueRevenueincrease/decrease 201213

    $m201314$m

    201415$m

    201516$m

    201617$m

    Ongoing$m

    Revenueinitiative1 0.000 0.000 0.000 0.000 0.000 0.000Revenueinitiative2 0.000 0.000 0.000 0.000 0.000 0.000Lessrevenuealreadyinbudget/forwardestimates

    (0.000) (0.000) (0.000) (0.000) (0.000) (0.000)Netrevenueimpact 0.000 0.000 0.000 0.000 0.000 0.000

  • 22 DepartmentTitle

    AppendixC:Signoffchecklist

    Investmenttitle:Agency:

    Y/N

    Istheneedclearlyestablished(e.g.investmentconceptbrief)? Arethelinkstogovernmentpolicy(ies)andcontributionsexplicit? Isthereaclearstatementoftheservicebenefitsandprojectscopeandarefuture

    implicationsnoted?

    Arecostestimatesprovidedforcapitalandoperationalphases? Havecostandriskestimatorssignedoffontheadequacyoftheirwork? Istheprojectbudgetincludingthebasecostestimate,riskassessment,baserisk

    allocationandcontingencyadequate?

    Docostandbenefitestimatesandanalysesshowvalueformoney? Aretheprojectdeliverablesclearlystated? Isabenefitmanagementorevaluationplanincluded? Areriskmanagementprocessesinplaceandassumptionsstated? Doestheproposalassesstheprojectscheduleandreadiness(includingmarketappetite)? Aregovernancestructuresidentified? Arestakeholderinterfacesdetailed? Areregulatoryrequirementsidentified? IstheprojectHighValue/HighRisk? HaveGatewayreviewsbeenundertaken?Gate1 Gate2 Thismodelchecklistisdesignedfortheprojectproponentsendorsement.Preparedby:.. Date:Approvedby:.. Date:... .(nameofapprovingofficerordelegate) (title)Secretary:.. Date: