BUILDING CONSTRUCTION 1 (ARC 1523) DEGREE YEAR 1 SEM 2 (MAR 14) PROJECT 2: Construction Activities and Process YAP ZHI JUN 0310738

Transcript of Bungalow

Page 1: Bungalow

BUILDING CONSTRUCTION 1 (ARC 1523)

DEGREE YEAR 1 SEM 2 (MAR 14)

PROJECT 2: Construction Activities and Process

YAP ZHI JUN 0310738

Page 2: Bungalow

Week 1

Construction Activity 1: Earthwork

Duration: 6 Days

Skilled worker: Land surveyor (1), land surveyor assistant (1), civil engineer (1), civil engineer

assistant (1)

Technical information: Survey topography for measurement of earthwork quantities.

Week 2

Construction Activity 1: Earthwork

Duration: 6 Days

Equipment: Backhoe (1), excavator (1), dumper (1)

Skilled worker: Backhoe operator (1), dumper operator (1), general worker (1)

Technical information: Site is cleared of trees, topsoil, shrubs and rubbish.

Page 3: Bungalow

Week 3 & 4

Construction Activity 1: Earthwork

Duration: 12 Days

Equipment: Portable penetrometer (1)

Skilled worker: Geotechnical engineer (1), geotechnical engineer assistant (1), civil

engineer (1), civil engineer assistant (1)

Technical information: Mackintosh Probe (MP) test carried out for testing soft soils

and determining suitable materials.

Page 4: Bungalow

Week 5

Construction Activity 1: Earthwork

Duration: 6 Days

Equipment: Vibrating plate compactor (1), backhoe (1), excavator (1), paver (1), dumper (1)

Skilled worker: Backhoe operator (1), excavator operator (1), paver (1), dumper operator (1),

general worker (1), grader (1), rollers (1)

Technical information: Site is excavated to required lengths, depths, breadths, inclinations

and curvatures

Week 6

Construction Activity 1: Earthwork

Duration: 6 Days

Materials: Timber formwork, gravel

Equipment: Table saw (2), shovel (2), long tape measurer, steel tape, strong threads, wire

nails, theodolite, wooden pegs, drill hammer

Skilled worker: Carpenter (2), general worker (1)

Technical information: Filling materials to lines, levels and grades required to complete

permanent construction.

Page 5: Bungalow

Week 7

Construction activity 1: Transporting piles

Duration: 2 days

Materials: piles

Equipment: Lorry (2), Crane (1)

Skilled worker: Lorry driver (4), Crane Operator (1)

Technical information: Transporting piles from factory, lift the piles by using crane from lorry

after reaching the site.

Week 8 Construction activity 1: Pile driving process

Duration: 12 days

Materials: piles, pile cushion, bituminous paint

Equipment: Hydraulic drop hammer (1)

Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (3)

Technical information: Mobilize the hydraulic drop hammer to the intended pile position after marking penetration of the piles, set out the position of drop hammer above the pile point, pile driving, weld the joints between the piles, and apply bituminous paint around the joints of welded piles to prevent rusting.

Page 6: Bungalow

Week 9

Construction activity 1: Cut off process

Duration: 3 days

Equipment: Multipurpose excavator (1), Pneumatic hammer (1), Oxy-cutter (1)

Skilled worker: Excavator operator (1), General worker (2)

Technical information: Excavate 1m to 1.5m depth by using multipurpose excavator, cut the

piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in

the pile is cut by oxy-cutter.

Week 10

Construction activity 1: Set up formwork for pile cap

Duration: 5 days

Material: Plywood, nails, reinforcement

Equipment: hammer, measuring tape, drill, handsaw

Skilled worker: general worker (3)

Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and

set up the reinforcement for column stump before pouring the concrete.

Page 7: Bungalow

Week 11

Construction activity 1: Pour concrete into the formwork

Duration: 2 days

Material: Concrete

Equipment: Concrete mixer truck, Skip, Concrete vibrator

Skilled worker: Concrete mixer truck operator (1), general worker (3)

Technical information: Pour the concrete into the formwork through skip from concrete

mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its

strength by preventing air pockets.

Construction activity 2: Pile cap harden process

Duration: 7 days

Technical information: Let the concrete pile cap harden for 7 days to wait it mature and

sufficient strength, open formwork after completed.

Page 8: Bungalow

Week 12

Construction activity 1: Set up formwork for column stump

Duration: 2 days

Material: Plywood, nails

Equipment: hammer, measuring tape, drill, handsaw

Skilled worker: General worker (2)

Technical information: Set up formwork for column stump before pouring the concrete.

Construction activity 2: Underground services

Duration: 6 days

Material: Metal conduit, steel/ aluminium tubing or PVC tubing, hexagonal plumbing fitting,

plumbing sealant

Equipment: Plow chute, winch

Skilled worker: Electrician (1), general worker (2), plumber (1)

Technical information: Bury cable preinstalled in cable-in-conduit (CIC) and main plumbing

pipes at excavated level.

Page 9: Bungalow

Week 13

Construction activity 1: Pour concrete into the formwork

Duration: 2 days

Material: Concrete

Equipment: Concrete mixer truck, Skip, Concrete vibrator

Skilled worker:

Technical information: Pour the concrete into the formwork through skip from concrete

mixer truck, vibrate the concrete to increase its strength.

Construction activity 2: Column stump harden process

Duration: 7 days

Technical information: Let the concrete column stump harden for 7 days to wait it mature

and sufficient strength, open formwork after completed

Page 10: Bungalow

Week 14

Construction activity 1: Back filling the pile foundation

Duration: 1 day

Material: soil

Equipment: Multipurpose excavator (1)

Skilled worker: Multipurpose excavator Operator

Technical information: After the harden process, fill up the excavated part around the

foundation to move on to the next process.

Page 11: Bungalow

Week 15

Construction Activity 1: Construction of ground beam (Ground floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete

(1)

Skilled worker: Carpenter (2), bar bender (1), general worker (1)

Technical information: Determine material, marking form panels, erecting the formwork,

provision a camber, brace the wood with stringer and support by struts and cleat, slump test,

and pour cement concrete.

Page 12: Bungalow

Week 16

Construction Activity 1: Slab (Ground floor)

Duration: 6 Days

Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20

Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck,

concrete vibrator, tipper, wheelbarrow.

Skilled worker: General worker (2), carpenter (1), bar bender (2)

Technical information: build formwork with plywood, fix reinforced steel, construction

slab formwork, slump test and pour concrete.

Thickness range of plywood: 7mm - 32mm

Page 13: Bungalow

Week 17

Construction Activity 1: Construction of columns (Ground floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1), bar bending machine (1), table saw

Skilled worker: Carpenter (2), bar bender (1), general worker (1)

Technical information: Place reinforcement bar and secured to the column formwork and

the floor, slump test and poured concrete.

Page 14: Bungalow

Week 18

Construction Activity 1: Construction of beam (First floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete

(1)

Skilled worker: Carpenter (2), bar bender (1), general worker (1)

Technical information: Determine material, marking form panels, erecting the formwork,

provision a camber, brace the wood with stringer and support by struts and cleat, slump test,

and pour cement concrete.

Page 15: Bungalow

Week 19 Construction Activity 1: Construction of slab (First Floor)

Duration: 6 Days

Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20

Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete

vibrator, tipper, wheelbarrow.

Skilled worker: General worker (2), carpenter (1), bar bender (2)

Technical information: build formwork with plywood, fix reinforced steel, construction slab

formwork, slump test and pour concrete.

Thickness range of plywood: 7mm - 32mm

Page 16: Bungalow

Week 20

Construction Activity 1: Staircase (Ground floor)

Duration: 3 Days

Materials: Ply Woods, Timber Battens

Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw

Skilled worker: Carpenter (1), Joinery (1)

Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the

side to represent the top of the stair slab and mark the riser and tread

Construction Activity 2: Staircase (Ground floor)

Duration: 3 Days

Materials: Timber, Metal or Prefabricated Formwork

Equipment: Drill, Hammer, Hand Saw

Skilled worker: Bar Benders (1), Formwork Carpenters (1)

Technical information: Construct formwork by laying out riser heights and tread widths

followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut

and nailed cleats to plank, nail riser form boards to the ends of cleats.

Page 17: Bungalow

Week 21

Construction Activity 1: Staircase (Ground floor)

Duration: 2 Days

Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve

Equipment: Measuring Tape, chalk line, drill, hammer, hand saw

Skilled worker: Bar Benders (1), Formwork Carpenters (1)

Technical information: Create strong grid of rebar, two or more pieces of rebar cross are

joined together. Secure riser form board with cleats attached about an inch above the stairs

layout to the slide form.

Construction Activity 2: Staircase (Ground floor)

Duration: 4 Days

Materials: Concrete, Long screws, Nails

Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board

Skilled worker: Carpenters (2)

Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to

prevent cracks for up to one week while it cures.

Page 18: Bungalow

Week 22

Construction Activity 1: Construction of columns (First floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1), bar bending machine (1), table saw

Skilled worker: Carpenter (2), bar bender (1), general worker (1)

Technical information: Place reinforcement bar and secured to the column formwork and

the floor, slump test and poured concrete.

Page 19: Bungalow

Week 23

Construction Activity 1: Construction of beam (Second floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete

(1)

Skilled worker: Carpenter (2), bar bender (1), general worker (1)

Technical information: Determine material, marking form panels, erecting the formwork,

provision a camber, brace the wood with stringer and support by struts and cleat, slump test,

and pour cement concrete.

Page 20: Bungalow

Week 24

Construction Activity 1: Slab (Second Floor)

Duration: 6 Days

Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20

Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete

vibrator, tipper, wheelbarrow.

Skilled worker: General worker (2), carpenter (1), bar bender (2)

Technical information: build formwork with plywood, fix reinforced steel, construction slab

formwork, slump test and pour concrete.

Thickness range of plywood: 7mm - 32mm

Page 21: Bungalow

Week 25

Construction Activity 1: Staircase (First floor)

Duration: 3 Days

Materials: Ply Woods, Timber Battens

Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw

Skilled worker: Carpenter (1), Joinery (1)

Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the

side to represent the top of the stair slab and mark the riser and tread

Construction Activity 2: Staircase (First floor)

Duration: 3 Days

Materials: Timber, Metal or Prefabricated Formwork

Equipment: Drill, Hammer, Hand Saw

Skilled worker: Bar Benders (1), Formwork Carpenters (1)

Technical information: Construct formwork by laying out riser heights and tread widths

followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut

and nailed cleats to plank, nail riser form boards to the ends of cleats.

Page 22: Bungalow

Week 26

Construction Activity 1: Staircase (First floor)

Duration: 2 Days

Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve

Equipment: Measuring Tape, chalk line, drill, hammer, hand saw

Skilled worker: Bar Benders (1), Formwork Carpenters (1)

Technical information: Create strong grid of rebar, two or more pieces of rebar cross are

joined together. Secure riser form board with cleats attached about an inch above the stairs

layout to the slide form.

Construction Activity 2: Staircase (First floor)

Duration: 4 Days

Materials: Concrete, Long screws, Nails

Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board

Skilled worker: Carpenters (2)

Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to

prevent cracks for up to one week while it cures.

Page 23: Bungalow

Week 27

Construction Activity 1: Construction of columns (Second floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1), bar bending machine (1), table saw

Skilled worker: Carpenter (2), bar bender (1), general worker (1)

Technical information: Place reinforcement bar and secured to the column formwork and

the floor, slump test and poured concrete.

Page 24: Bungalow

Week 28 Construction Activity 1: Construction of beam (Third floor)

Duration: 6 Days

Materials: Concrete Grade 30, reinforcement, timber formwork

Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix

concrete (1)

Skilled worker: Carpenter (2) , bar bender (1), general worker (1)

Technical information: Determine material, marking form panels, erecting the formwork,

provision a camber, brace the wood with stringer and support by struts and cleat, slump test,

and pour cement concrete.

Page 25: Bungalow

Week 29

Construction Activity 1: Brickwork (Ground floor)

Duration: 5 days

Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh

Equipment: Rose Brick Trowels, carpenter level, brick jointer

Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).

Technical information: Brickwork process including bricks, beds and perpends. The bed is

made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled

with mortar.

Construction Activity 2: Installation of door frame (Ground floor)

Duration: 2 days

Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties,

hinges, spreader bars.

Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,

measuring tape, stapler, and screwdriver

Skilled worker: general worker (1), door and window installer (1)

Technical information: Mark door and bricks area, use timber to prop up door to standing

position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place

mortar into gap of the brick and frame, insert wire brick ties.

Page 26: Bungalow

Week 30

Construction Activity 1: Brickwork (First floor)

Duration: 5 days

Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh

Equipment: Rose Brick Trowels, carpenter level, brick jointer

Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).

Technical information: Brickwork process including bricks, beds and perpends. The bed is

made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled

with mortar.

Construction Activity 2: Brickwork – Rendering (Ground floor)

Duration: 3 Days

Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White

Cement

Equipment: Masonry Brushes, Sled Runners,

Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).

Technical information:

Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch

first coat of render before it set to provide key for second layer. Skim coat mixed blended

white cement on it.

Page 27: Bungalow

Week 31

Construction Activity 1: Brickwork (Second floor)

Duration: 5 days

Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh

Equipment: Rose Brick Trowels, carpenter level, brick jointer

Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).

Technical information: Brickwork process including bricks, beds and perpends. The bed is

made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled

with mortar.

Construction Activity 2: Brickwork – Rendering (First floor)

Duration: 3 Days

Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White

Cement

Equipment: Masonry Brushes, Sled Runners,

Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).

Technical information:

Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch

first coat of render before it set to provide key for second layer. Skim coat mixed blended

white cement on it.

Page 28: Bungalow

Week 32

Construction Activity 2: Brickwork – Rendering (Second floor)

Duration: 3 Days

Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White

Cement

Equipment: Masonry Brushes, Sled Runners,

Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).

Technical information:

Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch

first coat of render before it set to provide key for second layer. Skim coat mixed blended

white cement on it.

Construction Activity 2: Installation of door frame (First and Second floors)

Duration: 2 days

Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties, hinges, spreader bars.

Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler, measuring tape, stapler, and screwdriver

Skilled worker: general worker (1), door and window installer (1)

Technical information: Mark door and bricks area, use timber to prop up door to standing position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place mortar into gap of the brick and frame, insert wire brick ties.

Page 29: Bungalow

Week 33

Construction Activity 1: Roof

Duration: 6 Days

Materials: Meranti timber formwork, metal trusses

Equipment: Crane (1), lorry (1), handsaw, driller, dip-galvanised nails, hammer,

measuring tape

Skilled worker: Roofer (1), general worker (1), crane operator (1), lorry driver (1)

Technical information: Check trusses, interior/exterior alignment, prepare clear access

to worksite, prepare storage for trusses.

Week 34

Construction Activity 1: Roof

Duration: 6 Days

Materials: Meranti timber formwork

Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring

tape

Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffolder (1)

Technical information: Attach bearers to bearer block and wall scab, timber scaffolding.

Construction Activity 2: Roof

Duration: 6 Days

Materials: Meranti timber formwork

Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring

tape

Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffolder (1)

Technical information: Progressively install temporary bracing as scaffolding is erected.

Page 30: Bungalow

Week 35 Construction Activity 1: Roof

Duration: 6 Days

Materials: Metal trusses Equipment: Driller, screw driver, spiral screw, measuring tape

Skilled worker: General worker (1), truss erector (1)

Technical information: Fix truss. Construction Activity 2: Roof

Duration: 6 Days

Materials: Meranti timber formwork

Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring tape

Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffold (1)

Technical information: Progressively install temporary brace as scaffolding is erected. Construction Activity 3: Roof

Duration: 6 Days Materials: Metal trusses

Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape

Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)

Technical information: Install permanent lateral bracing to truss.

Page 31: Bungalow

Week 36

Construction Activity 1: Roof

Duration: 6 Days

Materials: Metal trusses

Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape

Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)

Technical information: Install permanent lateral bracing to truss.

Construction Activity 2: Roof

Duration: 6 Days

Materials: Metal anchor sling, roof anchor bracket

Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender

Skilled worker: Roofer (1), general worker (1), bar bender (1)

Technical information: Install anchor slings.

Week 37

Construction Activity 1: Roof

Duration: 3 Days

Materials: Chicken netting

Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter

Skilled worker: Roofer (1), general worker (1)

Technical information: Install chicken netting.

Construction Activity 2: Roof

Materials: Aluminium sheet

Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter

Skilled worker: Roofer (1), general worker (1)

Technical information: Install aluminium sheathing.

Page 32: Bungalow

Week 38

Construction Activity 1: Roof

Duration: 6 Days

Materials: Metal batten strips (aluminium)

Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter

Skilled worker: Roofer (1), general worker (1)

Technical information: Install batten.

Week 39

Construction Activity 1: Roof

Duration: 6 Days

Materials: Cement tiles

Equipment: Measuring tape, dip-galvanised nails, hammer

Skilled worker: Roofer (1), general worker (1), roof tiler (1)

Technical information: Place cement tiles and nail every third row

Page 33: Bungalow

Week 40

Construction Activity 1: Roof

Duration: 6 Days

Materials: Ridge metal (aluminium), ridge bracket, ridge vent

Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender

Skilled worker: Roofer (1), general worker (1), bar bender (1)

Technical information: Install ridge block.

Construction Activity 2: Roof

Duration: 6 Days

Materials: Fascia board ribbon, fascia board bracket

Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender

Skilled worker: Roofer (1), general worker (1), bar bender (1)

Technical information: Install fascia board.

Page 34: Bungalow

Week 41

Construction Activity 1: Wall Finishes – primer (Ground floor and First floors)

Duration: 3 Days

Materials: Primer

Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair,

Caulks, Sealants and Caulking Tools

Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)

Technical information: Before applying primer, the wall need to be patched if there is any

holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well.

Construction Activity 2: Wall Finishes – 1st layer painting (Ground floor and first floors)

Duration: 3 Day

Materials: paint

Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking

Skilled worker: Painter (2)

Technical information: Wall painting with colour chosen.

Page 35: Bungalow

Week 42

Construction Activity 1: Installation of door (Ground floor)

Duration: 3 days

Materials: Required door, door lock, doorknob and screws

Equipment: Screw driver, measuring tape

Skilled worker: general worker (1), window and door installer (2)

Technical information: Install required door types and measurement with door lock and

doorknob

Construction Activity 2: Wall Finishes – primer (Second floor)

Duration: 3 Days

Materials: Primer

Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair,

Caulks, Sealants and Caulking Tools

Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)

Technical information: Before applying primer, the wall need to be patched if there is any

holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well.

Construction Activity 3: Wall Finishes – 1st layer painting (Second floor)

Duration: 3 Day

Materials: paint

Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking

Skilled worker: Painter (2)

Technical information: Wall painting with colour chosen.

Page 36: Bungalow

Week 43

Construction Activity 1: Installation of door (First and Second floors)

Duration: 3 days

Materials: Required door, door lock, doorknob and screws

Equipment: Screw driver, measuring tape

Skilled worker: general worker (1), window and door installer (2)

Technical information: Install required door types and measurement with door lock and

doorknob

Construction Activity 2: Installation of door trim (All floors)

Duration: 3 days

Materials: nails, door trim panels

Equipment: Finish hammer, hand plane, measuring tape, carpenter’s glue, sandpaper, jigsaw,

combination square, compass, pencil, utility knife, putty knife, miter saw, drill with bit

Skilled worker: general worker (1), carpenter (2)

Technical information: Mark the reveals, cut all miters, cut and test-fit side casings, make

adjustments, secure casing, and cross-nail miters.

Page 37: Bungalow

Week 44

Construction Activity 1: Installation of windows (All floors)

Duration: 3 days

Materials: Required windows, backer rod, insulation, shims, roofing nails, screws, silicone

sealant, flashing, fastener, corner guard

Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,

measuring tape, stapler, and screwdriver

Skilled worker: general worker (1), door and window installer (2)

Technical information: Verify window opening, apply weather resistant barrier, create

flashing, prepare window for installation, set the unit and secure, apply flashing at jambs

and head, seal and insulate interior cavity, insert backer rod.

Page 38: Bungalow

Week 45 Construction Activity 1: Installation of plumbing

Duration: 4 days

Materials: cast iron pipe, galvanized iron pipe, and galvanized steel pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum

Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threaded, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter

Skilled worker: Plumber (1), General worker (1)

Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping.

Construction Activity 2: Installation of main electrical panel

Duration: 1 day

Materials: Sheet steel/cold role steel, breakers, plastic

Equipment: Driller, locknut, screw

Skilled worker: Electrical Contractor (1), Electrician (1) Technical information: The panel distributes the electricity to all the electrical circuits that

are installed in the house to protect the wiring from damage by “tripping” when an electrical short or overcurrent occurs.

Page 39: Bungalow

Week 46

Construction Activity 1: Installation of railings

Duration: 3 days

Materials: Ordered glass railing, stainless steel screws

Equipment: level, scaffolding, measuring tape, sealant, gloves and screwdriver

Skilled worker: general worker (1), railing installer (1)

Technical information: Insert measured bottom rail and top plate and insert glass panel, fix

them with sealant or screws.

Page 40: Bungalow

Week 47

Construction Activity 1: Installation of ceiling

Duration: 3 days

Materials: Steel brandering, insulation, jointing strip, drywall screw, plasterboards, Lafarge

access panel

Equipment: ladder, gloves and screwdriver

Skilled worker: ceiling installer (1), general worker (1)

Technical information: Determine amount of steel brandering needed, planning the

direction of plasterboard, calculate number of plasterboard needed, install it on one by one.

Construction Activity 2: Installation of tiles

Duration: 6 days

Materials: Cement board, tiles, thinset mortar, grout

Equipment: Floor cleaner, measuring tape, square, trowel, level and brush

Skilled worker: Tiler (1), general worker (1)

Technical information: Calculate surface area, decide types and size of tiles to use, apply

mortar, install tiles, grout the joints and clean.

Page 41: Bungalow

Week 48

Construction Activity 2: Wall Finishes (Whole house 2nd layer painting)

Duration: 6 Days

Materials: Selected paints

Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking

Skilled worker: painters (2)

Technical information: Wall painting with colour chosen.

Week 49

Construction Activity 1: Bathroom Equipment Installation

Duration: 3 days

Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC pipes

Equipment: clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe vice, pipe

bending machine, pipe cutter

Skilled worker: Plumber (1), General worker (1)

Technical information: Materials are installed at first fix stage as they need to be fitted prior

to the commencement of tiling. This is essential to get professional watertight seals, as

water ingress resulting from doing things in the wrong order can cause massive problems

later on.

Construction Activity 2: Installation of receptacle

Duration: 1 day

Materials: Nickel/silver, beryllium copper, plastic

Equipment: Screw, screwdriver

Skilled worker: Electrician (2)

Technical information: Electrician installs receptacles for outlets, lights and switches and

runs wires from the breaker panel to each receptacle. Wiring for telephones, TV cable and

network cable is included in this work.

Week 50

Construction Activity 1: Landscaping

Duration: 4 days

Materials: Grass, soil, stone, trees, plants

Equipment: wheelbarrow, shovel, hoe, shears

Skilled worker: General worker (1), landscape designer (1)

Technical information: Design of landscaping make the whole house look more attractive

and lively. (Porches, sidewalks, decks, driveways, final grade and seed)

Page 42: Bungalow

Week 51

Construction Activity 1: Final touch up

Duration: 2 days

Technical information: punch out walk-thru list, trim and adjust doors, paint touch-up

Week 52

Construction Activity 1: Cleaning

Duration: 3 days

Equipment: Cleaning tools

Skilled worker: General worker (5)

Technical information: Windows, floors final clean.