Build Operate Transfer (BOT)

download Build Operate Transfer (BOT)

of 25

Transcript of Build Operate Transfer (BOT)

  • 8/13/2019 Build Operate Transfer (BOT)

    1/25

  • 8/13/2019 Build Operate Transfer (BOT)

    2/25

    period, the concessionaire acts as owner. At the end of the concession period, the concessionaire

    transfers the ownership of the facility free of liens to the principal at no cost [3].

    In the broader sense, the BOT model may be defined as the realization of a public

    structure, investment or service through the financing by a private company and its operation by

    the latter for a period determined by the public, and its selling to public institutions any goods or

    services, which the it has produced during this period, pursuant to a tariff mutually determined

    by the parties, and its transferring the facilities, which it is operating, in a well-maintained,

    complete and functional manner, to the public institution at the end of the period [4].

    Again, according to another definition made based on contracts executed, the BOT model

    is a regime where any public service or activity or public works are prepared as project, financed,

    built, protected by realization of an investment based on a fixed amount, all expenses being

    provided for by a private enterprise, under the guarantee that the country purchases the goods or

    services produced, and which ensures the transfer and delivery to the relevant public institution

    or establishment of the facility and management at the end of the period upon amortization of the

    capital invested and realization of the profit through its operation for a certain period [5].

    1.3 Purposes of implementing the Build-Operate-Transfer model

    i. Decreasing the financial burden in the publics infrastructure projects and thus toincrease the public productivity,

    ii. To make the country gain foreign financial resources, advanced technology, know-how and experience accumulation in terms of the project. To provide new enterprise

    and profit areas and to make contributions to the public finances by forming tax

    assessments,

    iii. To remove any probable need for foreign borrowing in the said investment areas andthus not to increase the countrys foreign debt burden,

    iv. To bring in management efficiency, responsibility, timing, total quality concept andstandardization properties to the public sector regarding profitable and efficient

    private sector operations especially as a result of cooperation and joint ventures,

  • 8/13/2019 Build Operate Transfer (BOT)

    3/25

    v. To make a favourable contribution to the policies of narrowing the public share ineconomy and increasing the efficiency and productivity of public resources, along

    with the privatization model, to use the BOT model as an indirect privatization

    method,

    vi. To make a favourable contribution to the employment problem, which the labor-intensive capital preferences could not solve for years, by technology-intensive

    capital [8].

  • 8/13/2019 Build Operate Transfer (BOT)

    4/25

    CHAPTER 2

    CHARACTERISTICS OF BOT MODEL [4]

    2.1 Main CharacteristicsThe main characteristic of the model is to solve the problem of financing required by

    certain public structure investments and consequently to ensure the realization of the investment.

    The reason for the models emergence is essentially the publics financing straits. By means of

    this method, the financing straits is overcome in the investment period and the financing is

    realized by being spread over time, through the consideration taken from the users for any goods

    or services produced during the operational period.

    Along with focusing essentially on the publics financing straits in terms of benefiting

    from the model, the increase of service efficiency per the private sector in view of the public

    establishments failure to function efficiently, has also arisen as a reason. At the same time, the

    fact that the private sector brings in advanced technology for this kind of projects both at the

    stage of investments as well as operation increases the projects production, service efficiency

    with the concept of efficient operation and management.

    The functioning of the BOT model is not only limited to new investments. Reference

    may be made to this model for complementary investments or renewal investments as well. The

    model is applicable for new investments as well as for the renewal of existing facilities, which

    have fallen behind in terms of technology, or for the completion of unfinished investments. BOT

    models are conducted in the framework of implementation agreements (CONCESSION

    CONTRACTS) made between the parties. In these agreements, one party is the public institution

    or establishment, whereas the other party is the private company in charge of realizing the

    project.

  • 8/13/2019 Build Operate Transfer (BOT)

    5/25

    One party of the contract is the public institution or establishment, whereas on the other

    hand, there are consortiums which generally include international establishments as well. In

    order to realize the investment, sponsor companies establish a separate company (Project

    Companyjoint investment company or Project Company) the subject of activity of which is to

    realize the relevant project. If requested, the public may also participate in the established

    company with a limited capital share.

    At the end of the contractual period, the facility shall be transferred free of charge to the

    state or any establishment deemed appropriate by the state, free of all kind of liabilities and

    commitments in a sound und functional condition, whereas prior to the end of the contractual

    period the same liabilities shall be applicable as well (except for force majeure) [6].

    2.2 The Parties

    There are many parties in the realization of the investment projects by the BOT model. In

    a typical BOT project there is, for instance, the host country, the state establishment holding the

    position of the projects holder, lending establishments, insurance establishments, technical,

    financial and legal consultants, construction companies to realize and execute the project (Joint-

    Venture Corporation) and sponsor firms.

    In the build-operate-transfer model, there is a system established with the relation of

    many parties in comparison to other construction models. The number of contracts regulating the

    relations between these parties is quite high, and even though the parties and the number of

    contracts varies according to factors such as the structure, magnitude of the project, the parties

    and contracts existing in most of them have been briefly described as follows. (Figure 2.1).

    The host country is the country where the project is realized. It denotes the establishment

    in charge of the project, the State establishment (administration), the joint investment company

    as well as the institution executing the implementation-concession-contract. The joint-venture

    company denotes the company, which has been founded by the companies realizing the

    investment, pursuant to the concession contract in accordance with the countrys law.

    The Investor Banks are the banks providing the financing of the investment. These banks

    are defined as lending establishments and loan agreements are made with them. Joint investment

  • 8/13/2019 Build Operate Transfer (BOT)

    6/25

    company holding parent companies (sponsors) are companies who establish the joint investment

    company in the framework of the concession contract, who have come together in the framework

    of the agreement and have a separate legal personality. Apart from these; parties such as the

    Trustee Bank, Export credit banks and export insurance companies, subcontractor firms,

    insurance companies, consultancy firms, standby credit and bridging loan banks are components

    in the operation of this model.

    In the BOT model, an international consortium bidding for a certain project designs the

    project, ensures and assures the financing necessary for the construction, builds the project in the

    host country and operates it throughout the duration stated in the contract. The realization of

    these procedures requires a quite complex structure. In a BOT project, there are many parties and

    more than one contract regulating the relations between these parties [7].

    Figure 2.1: Structure and Operation of BOT Projects

  • 8/13/2019 Build Operate Transfer (BOT)

    7/25

    2.3 Expectations of the parties in the Build-Operate-Transfer model

    2.3.1 The Public (User)

    Ability to render the service Provision of permanence of the service Increase of service efficiency Increase of service quality and variety Protection of environment and community health Optimization of service tariffs Public Administration Provision of investment and investment funding by out-of-budget means Convenience, permanence and efficiency in the performance of legal duties Decrease and keeping under control of operational costs Ability to reserve more equity for investments Decrease of financial costs Ensuring regular and preventive professional maintenance of the assets Optimization of life-span of assets and decrease of need for new investment Decrease of management burden of the business and focusing on essential duties Benefiting from the elasticity and speed of the private sector Easy realization of technology transfer and innovations

    2.3.2 Operator and/or investor

    Profit (anyone who cannot produce profit in the private sector cannot sustain itselfand cannot produce service)

    Ensuring customer satisfaction (Public institution and consumers) Increase of competitive facilities (technological, corporate and organizational

    development)

    Becoming trademark and increasing esteem Increase of business volume and ensuring its permanence

  • 8/13/2019 Build Operate Transfer (BOT)

    8/25

    CHAPTER 3

    ADVANTAGES, DISADVANTAGES & PROBLEMS OF BOT MODEL

    3.1 Advantages of the Model

    a) Creating new and additional financing resources (Financial Additionality): One of themodels most important aims brought forward for developing countries is to increase the

    foreign capital entry to the country and to able to benefit from its influences on the

    economy. In this framework, it is suggested that the BOT model gives the opportunity to

    realize any projects which shall not be able to be realized otherwise.

    b) Advanced Technology Transfer and Training: In case projects requiring advancedtechnology are realized per foreign companies, advanced technology shall enter the

    country. Likewise, in case of a BOT project, there shall also be a training program to be

    presented regarding usage prior to the transfer of the facility. Therefore, possibility is also

    given for the training of the employees.

    c) Efficiency: It is suggested that the private sector may make a better evaluation in terms ofthe realization of which project would be more feasible, and that it shall realize the

    projects design, building and operation more efficiently, and it is considered that the

    economic efficiency shall thus increase.

    d) Measure of Evaluation (Benchmark): As an extension of the property mentioned in theprevious item, a project conducted per private sector may be used as a measure in terms

    of evaluating the efficiency of similar projects available with the public.

    e) Decrease of Public Share in Infrastructure Investments: Thanks to the model, the stateshall get away from the financial pressure regarding the realization of infrastructure

    investments; this circumstance shall have favorable influences on the budget.

  • 8/13/2019 Build Operate Transfer (BOT)

    9/25

    f) Privatization: The BOT model shall also be an important step made towards privatizationof some activities traditionally conducted per the private sector. However, taking into

    consideration that the facilities shall be transferred to the state at the end of the

    contractual period, it is not possible to speak entirely of a privatization.

    g) Facilitating the Choice between Investments: In the BOT model, the state, in a sense,assigns the task of evaluating the projects, which are presented to it and among which it

    has to choose, to the private enterprise, and thus, the private sector realizes the project

    that is most appropriate in economical terms by the profit maximization criteria.

    3.2 Disadvantages of the Model

    a) Requiring a Complex and Long Process: The model features a quite complex andsophisticated structure. Many parties have to negotiate and reach an agreement on a great

    number and variety of documents. Whereas this takes a certain time, money and requires

    that people trained in this matter concentrate on this matter.

    b) High Costs: The second criticism made regarding BOT is that the cost of any projectrealized by this model is higher in comparison to any project realized by budgetary or

    credit means. Especially in case where a certain profit yield is given and goods and

    services are priced on the cost + profit basis, there is the probability that investment

    and operational costs are kept as high as possible. It may be expected that this model is

    more expensive than any investment to be realized by means of domestic and foreign

    resources to be provided by the public by its own means. It shall be strived for obtaining

    the profit, which shall be gained both at the investment stage (Contracting services) as

    well as at the operational stage (as Operator), at the top points.

    c) The ability to draw this profit to a reasonable level is closely related to the skill of theteam conducting the negotiations in the public.

    d) Excessive Sensitivity to Political, Economical Stability: Another disadvantage of themodel is that the investment to be made reaches very high amounts, which its return is

    long and that due to the fact that the other party in the contract is the public

  • 8/13/2019 Build Operate Transfer (BOT)

    10/25

    administration, especially foreign capital shows very much sensitivity regarding political

    and economical stability for making an investment.

    e) Eddy/Tornado Effect: In case any of the decisions adopted at any stage unfavorablyaffect the decision of any party, this circumstance does also affect the other parties in the

    same way and the negative effects gradually increase and even prevent the realization of

    the project. In order to avoid this circumstance which is called the eddy effect, it is

    necessary to ensure that the other parties also contribute to the decisions favorably at

    every stage, what causes the above mentioned delay [9].

    3.3 Problems related to the operation of the Build-Operate-Transfer model [8]

    3.3.1 Technical Problems

    Generally, the feasibility reports (comprising also technical reviews to a certain extent)

    are given to entrepreneurs, who wish to make any investment in the framework of this model,

    during the tender stage by the relevant public institution. The better these reports are prepared,

    the less the contracts, which shall be built on them, shall create any problems in the future and

    the more they shall be reports not leading the parties to disputes. It is clear that if these studies

    are reported without being made very well, they shall be accompanies with great problems. The

    entrepreneur has almost not the chance to study the technical data of the feasibility report in the

    limited period during this tender stage.

    3.3.2 Economical and Financial Problems

    The basic problem is to find financing for projects put out to tender. In other words, to

    find and ensure the coming up of entrepreneurs (generally foreign) to be realized the projects.

    This is to a great extent directly related to the political and economical stability of a country.

    Another problem is that, since qualification is a precondition in tenders, many domestic firms

    and especially contracting firms, domestic firms having applied to these tenders and having been

    awarded the contract, have been seeking foreign partners and this has mostly remained as

    symbolic partnerships on paper, and the targeted operational experience has not been transferred.

  • 8/13/2019 Build Operate Transfer (BOT)

    11/25

    CHAPTER 4

    SELECTING & SUCCESSING BOT MODEL

    4.1 Factors in Choosing the Build-Operate-Transfer Model

    By means of this model, it is aimed at realizing extensive investment projects such as

    tunnels, ports, power plants, barrages, waste water clarifying plants, natural gas and oil pipelines,

    aerodromes, motorways. As is known, the development of developing countries depends on

    investment, whereas investment depends on resources which may be allocated for this purpose.

    In developing countries there are straits of resources, mainly of investment capital, and

    consequently the resources available have to be directed to investments in a planned,

    programmed, balanced and rational manner. Therefore, in countries where public resources are

    insufficient, the BOT model is considered as a suitable solution. In investments projects to be

    realized by the BOT model, there are many factors providing the contribution of foreign capital

    by international establishments and the private sector.

    In the BOT model; the fact that the increase of population and economic growth

    constantly give rise to the need for additional infrastructure investment and that it is difficult or

    impossible that these investment projects can be realized by public resources, that there is an

    intensive competition between manufacturers and commission houses active in the energy and

    transport sectors, that the private sector discipline and dynamism is also formed in public sector

    investments, that the business volume of international contractual firms has narrowed, as in the

    early 80s, etc. factors are stimulating participation.

    The Build-Operate-Transfer model is an important financing model used in the

    realization of infrastructure investments. The BOT model is rather used in underdeveloped

    and/or developing countries where the public resources are insufficient, where there is financing

  • 8/13/2019 Build Operate Transfer (BOT)

    12/25

    straits in investments foreseen to be made. The most important characteristic of the model is that

    investment requested can be made with out-of-budget resources. The BOT model requires the

    gathering of many parties depending on the structure of the project. Consequently, subjects such

    as the relations between the parties and division of labour are ultimately significant for the

    successful conduct of the project.

    Factors such as the magnitude of the amount of the investment to be made, finding the

    financing resources of the project, the completion of the investment on time and the high rate of

    borrowings give rise to certain risks in terms of the parties in the realization of the BOT projects.

    Therefore, while evaluating the BOT projects, any risks probable to be encountered should be

    analyzed in detail. These may be outlined as follows [10]:

    Nature of the projects to be made Realization of the projects based on the foreign currency Cost of the project Determination of the price of the goods or products to be produced Uncertainty in obtaining the revenues requested Political and economic conditions of the country in which the investment shall be made Financial risks Inflation risk Interest rate risk Foreign exchange risk

    Figure 4.1: Risk Encountered with BOT Model

  • 8/13/2019 Build Operate Transfer (BOT)

    13/25

    Risk distribution in BOT, Each sector risk transfer in BOT is shown in the below table.

    Table 4.1: Risk distribution in BOT

    4.2 Factors which may affect the Success of the BOT Model [11]

    i. Formation of the legal frameworkii. Structure of the economic framework

    iii. The fact that the project is powerful, feasible and appropriate in financial termsiv. The fact that the credit change is high and the country risk manageablev. Stability of politics

    vi. The fact that the firms realizing the project are experienced and reliablevii. The fact that the construction firm has sufficient experience and resources

    viii. An open and accurate bidding processix. The properties of the sector and determination of the projects priority x. Forming profit-based cooperation in the public and private sector

    xi. Structuring the project in a manner to be completed on time and with a suitablecost

    xii. Distribution of the project risks among the parties in a rational mannerxiii. Rational feasibility studiesxiv. The countrys political stability

  • 8/13/2019 Build Operate Transfer (BOT)

    14/25

    CHAPTER 5

    PROCEDURE OF BOT MODEL

    5.1 Stages of BOT Procurement System

    Generally, BOT project mostly will go through 6 different stages which include

    preliminary study of the project, selection of the suitable project company, project

    implementation, construction of the facility, operation of the facility and lastly transfer of

    ownership of the facility. It can then be sub-divided into two parts which include pre-

    implementation of the project and the concession period of the project. In the first part, a

    feasibility study of the project is carried out and a reliable project company is selected. In the

    second process, the selected project company is awarded the concession to construct and manage

    the facility. In the end of the concession period, the concessionaire has to hand over the

    ownership of the facility back to the government. Figure 5.1 below shows different stages that

    BOT project will go through.

    Figure 5.1: Stages of BOT Procurement System

    5.1.1 Preliminary Study

    The government determines project requirements by using information at his disposal.

    The government identifies the services needed in the project and listed down the facility needed

  • 8/13/2019 Build Operate Transfer (BOT)

    15/25

    to be built. Perhaps, the government may employ experts to help with the project definition and

    conduct a feasibility study to identify the practicability of the project.

    5.1.2 Selection

    There are two forms of proposal in BOT project which include the solicited and the

    unsolicited project proposals. The former generally refers to public tendering process which the

    government takes the initiative to request f or submission of proposal f or those who are

    interested in the infrastructure project. Whereas under the unsolicited mode, the private company

    take the first step to submit their project proposal. After the submission of proposals by the

    private companies, an evaluation process is done by the government to study and select the most

    suitable private company. Here, the project is granted to the selected private company

    (concessionaire).

    5.1.3 Project Implementation

    Once the project is granted to the concessionaire, the concessionaire will start to produce

    a detailed working program which involving the design work of the project. The concessionaire

    has to first obtain legal permit f rom the related institution to develop the project.

    5.1.4 Construction

    After the necessary legal proceeding, the contractor executes the construction in

    accordance with plans and specification. In the same time, the contractor will also hire a few

    numbers of subcontractors, consultants in order to deliver the project on time.

    5.1.5 Operation

    After completing the construction of the facility, the concessionaire will then secure an

    operator to operate and manage the facility. The operator is also responsible to the maintenance

    job of the facility.

    5.1.6 Transfer

  • 8/13/2019 Build Operate Transfer (BOT)

    16/25

    After completion of the concession period, the ownership of the facility is then

    transferred to the government at no cost. The government may operate the facility by itself or

    hire another operator.

    5.2 Operation of the Build-Operate-Transfer Model

    The Build-Operate-Transfer (BOT) is considered as an important project financing model

    used in the realization of infrastructure investments. The model has been rather developed for the

    purpose of providing means for the realization of any large-scale investments required, by using

    resources to be provided by the private sector and international establishments, by means of out-

    of-budget resources, in the realization of projects aiming at the cooperation of the public and the

    private sector, in underdeveloped and/or developing countries with insufficient public resources.

    By means of this model, it is aimed at realizing large scale investment projects such as

    tunnels, ports, power plants, barrages, waste water clarifying plants, natural gas and oil pipe lines,

    aerodromes, motorways, etc. As is known, the development of developing countries depends on

    investment, whereas investment depends on the resources to be allocated for this purpose. In

    developing countries, there are straits of resources mainly regarding investment capital;

    consequently the resources available have to be directed to investments in a planned, program,

    balanced and rational manner. Therefore, in countries and in our country where public resources

    are insufficient, the BOT model is considered as a suitable solution.

    There are many factors providing the contribution of international establishments, private

    sector and foreign capital to investment projects to be realized by means of the BOT model. In

    the BOT model; the fact that the increase of population and economic growth constantly give

    rise to the need for additional infrastructure investment and that it is difficult or impossible that

    these investment projects can be realized by public resources, that there is an intensive

    competition between manufacturers and commission houses active in the energy and transport

    sectors, that the private sector discipline and dynamism is also formed in public sector

    investments, that the business volume of international contractual firms has narrowed, as in the

    early 80s, etc. factors are stimulating participation.

    There are many parties in the realization of investment projects with the BOT model. In a

    typical BOT project there are, for instance, the host countries, the state establishment holding the

    position of the projects holder, lending establishments, insurance establishments, technical,

  • 8/13/2019 Build Operate Transfer (BOT)

    17/25

    financial and legal consultants, the company to realize the project (Joint-Venture Corporation)

    and sponsor firms. The operation of the BOT model is shown in the following diagrams.

    Figure 5.1: Stages in a BOT competitive procurement procedure

  • 8/13/2019 Build Operate Transfer (BOT)

    18/25

    Figure 5.2: Actual Operation of BOT Model Providing the Financing from Out-of-Budget

    Resources

    5.3 Tender Evaluation in the BOT ModelSince the said method adopts the aim of speeding up for grand and special public

    investments, the elements forming the basis of the tender decision should have been associated

    with the concepts of speed and time as well. The relevant public units have, in the investment of

    extending and developing the Airport terminal buildings, both assumed the period of competing

    the investment and putting the facility in commission as a factor as well as considered the

    operational period prior to the delivery of the facility by the investing group to the public as

    basic distinctive element. Therefore, the guaranteed passenger numbers, the incomes left and the

    period of construction have been shaped accordingly.

    The contractual articles having foreseen the inclusion of the period, yield from the period

    of construction, to the operational period have been a basic parameter for the firms having

    participated the tender and been awarded the contract. In this framework, the period of the

    investments realization has been determined by the Administration as reasonable, but as short as

  • 8/13/2019 Build Operate Transfer (BOT)

    19/25

    possible. On the other hand, the period during which the group, who shall be awarded the

    contract from among the participants and who shall realize the investment, shall operate the

    facility on their own behalf after the end of the constructional period has been determined as a

    basic parameter of comparison. In order to stimulate and encourage the rapid realization of the

    investment, it has been foreseen that in case the task is completed and the facility is put in

    commission earlier, this period gained shall be added to the operational period bid by the

    investor during the tender.

    This concept has resulted in the emergence of rational, practical and meaningful bid

    evaluation criteria. The incomes left to the contractor firm and the guaranteed passenger numbers

    havebeen important elements influencing the firms bids. In the contractual specifications these

    matters have been explicitly determined. Another important matter effecting the tenders was the

    necessity that the building firms have had a similar operational experience before. This has

    brought with it the joint venture-consortium with foreign aerodrome operating firms.

    5.4 Framework of the Concession (Implementation) Contract

    The framework of the Concession Contracts mainly consists of the following items:

    The parties, subject of the contract, its duration, general principles of the investment and services,

    standard and quality of the goods and services, determination of the financing charge,

    commissioning, acceptance and business operation date, delay and cost variations in the

    completion of the task during the investment period, nationalization, guarantee, monthly and

    annual activity reports, supervision, security, safety and environmental measures, force majeure,

    insurance, maintenance and repair, assignment of duty, termination, transfer of facility at the end

    of the period, transfer prior to the end of the period, credits, responsibility and compensation,

    administrative fault, training, applicable law and settlement of disputes, contractual expenses,

    notices, language of the contract, amendments in the contract, other contracts, other matters,

    enforcement date of the contract.

    As parties in the concession contracts, the ministry or any establishment associated with

    the ministry or any municipality denotes the administration, whereas the company commissioned

    denotes the contractor. The subject of the contract is the preparation of the project of the facility

  • 8/13/2019 Build Operate Transfer (BOT)

    20/25

    and its supplementary (supplied parts), their construction, the building of all technical

    installations, their operation and transfer in accordance with the contract. Principles of the

    investment and the service as well as the total investment amount and the standards of the goods

    or services to be produced are included in the contract. Along with determining the form of

    financing the investment, increases required in the financing parallel to the increase occurring in

    the investment amount, the administrations approval of the credit conditions, the agreement of

    the administration in the determination of the operational capital and similar matters are included

    in the relevant articles [12].

  • 8/13/2019 Build Operate Transfer (BOT)

    21/25

    CHAPTER 6

    FINANCING CONSIDERATION

    6.1 Economical Sustainability of the Project

    The economical sustainability of the BOT Project should be proved to the potential

    investors and creditors. That is to say, the project should be able to produce income in a

    proportion ensuring the repayment of the earnings yield to be provided in consideration of the

    principal and interest payments of the credits obtained the equity and equity return. Since the

    income to be obtained from the project should be at a level sufficient to provide for the projects

    debt service, the total cost of the project should be estimated and assurance should be given to

    the creditors as well as the investors that the project shall be realized and operated as planned [9].

    6.2 Cost of the BOT Projects

    The most important matter to be taken into consideration in the framework of this model

    is the determination whether the cost of the BOT project is higher than the project cost financed

    by the state by means of direct borrowing, whether this cost to be used is reasonable in the

    framework of the project which is inapplicable due to budgetary impossibilities. If as a result of

    the analysis it turns up that the models cost is high, its chargeshall be paid by the state and the

    final users [13].

  • 8/13/2019 Build Operate Transfer (BOT)

    22/25

    6.3 Components of the Total Investment Cost in BOT Projects

    Despite the fact that cost items vary according to the characteristics of the projects, it is

    necessary to determine the cost items of an infrastructure project and, as a result of this, the total

    investment cost. These cost items are as follows [14].

    6.3.1 Cost Items

    Construction Expenses First Draft and Final Project Expenses Machinery and Equipment Expenses Project Preparation/Coordination

    6.3.2 Total Construction Cost

    Consultancy and Control Services Management Expenses Insurance Expenses

    6.3.3 Total Engineering and Control Services

    Nationalization

    6.3.4 Operational capital

    Operational expenses Taxes

    6.3.5 Total Other Expenses

    Conditional Expenditure

    6.3.6 Total Capital and Cost

    Financing expenses Interest expenses

    6.3.7 Total Financing Expenses

  • 8/13/2019 Build Operate Transfer (BOT)

    23/25

    6.3.8 Total Investment Cost

    The above described costs are included in the projects feasibil ity study. In the BOT

    projects, the total investment cost are revised by taking into consideration the cost arising until

    the project reaches the enforcement stage [15]. The BOT projects consist of two different and

    long stages being the construction and the operational period. The values of the goods and

    services provided from abroad during the construction period until the date of the projects

    enforcement and the date on which the investment is put in operation, may be subject to

    escalation taking into consideration the inflation indexes of that country and the exchange rate

    changes occurring between the local currency and the foreign currency, whereas in the

    operational term of the project, only administrative and operational expenses are subject to

    escalation [16].

  • 8/13/2019 Build Operate Transfer (BOT)

    24/25

    REFERENCES

    [1] Prof. Drs. Ir. Sebastiaan C.M. Menheere, P. S, Case Studies on Build Operate Transfer.

    Delft, The Netherlands, Delft University of Technology, 1996.

    [2] Argyris G. Kagiannas, K. D., The role of Build Operate Transfer in promoting, Athens:

    National Technical University of Athens, December 2003.

    [3] Verhoeven, L., BOT in netherlands, university of technology, Delft, Netherlands, 1997.

    [4] mre, E., Trkiyede Yap-let-Devret Modeli; Yasal ats, Uygulamas, Yksek

    Denetleme Kurulu,34 ( 2001).

    [5] Uur, O. Yap-let-Devret Giriim Modelinin Hukuksal Yn ve Ekonomik ve Mali

    Etkileri, 1993 Yl Hesap Uzmanlar Kurulu Konferanslar IV, Maliye

    BakanlmYaynlar, Ankara, 245 (1993).

    [6] Gne, C., Yap let, Yap-let-Devret, letme Hakk Devirleri ve Vergi Uygulamalar,

    Yaklam Yaynlar,Ankara, 43-44 (1999).

    [7] Uyduranolu, N., Trk Hukukunda Yap-let-Devret Modeli ve Benzeri Messeseler,

    Uzmanlk Tezi,Hazine ve D Ticaret Mstearl, Ankara, (1994).

    [8] Etiolu, E., Bte D Finans Teknii Yap-let-Devret Modeli ve Trkiye

    Uygulamasnn Analizi, Trk Dnyas Aratrma Vakf Yaynlar, stanbul, 14-15

    (1997).

    [9] Private Sector Participation in Power Through BOT Schemes, Working Paper, The

    World Bank Industry and Energy Department, 5 (1990).

    [10] Atasoy, V., Trkiyede Kamu ktisadi Teebbsleri ve zelletirme Sorunu, Trk

    Dnyas Aratrma Vakf Basm Evi, stanbul, 187 (1993).

    [11] Augenblick, M., Custer S.B., The Build Operate and Transefer (BOT) Approach to

    Infrastructure Projects in Developing Countries, Washington DC, The World Bank,Working Paper Series, No:498, 132-34 (1990).

  • 8/13/2019 Build Operate Transfer (BOT)

    25/25

    [12] Polatkan, V., Yap-let-Devret, Yaklam Yaynlar, Ankara, 16 (1997).

    [13] Ersnmez, C., Yap let Devret Modeli ve Modelin Finansmanna likin Bir Analiz,

    Uzmanlk Tezi,Hazine ve D Ticaret Mstearl, Ankara, 31 (1995).

    [14] Hadi, S. E., Ramirez, M. T., Institutions, Infrastructure, and Economic Growth, Journal

    of Development Economics, 70: 443-477 (2003).

    [15] Kadyrov, H., Projelerin Finansmannda Yap-let-Devret Modeli,Yksek Lisans Tezi,

    Ankara n.Sosyal Bilimler Ens., Ankara,1 (2003).

    [16] Atalan, N. K., Yap let Devret Modeli le lgili Tarihe, Dnyada ve lkemizdeki

    Uygulamalar, Tatbikattaki Zorluklar, Uzmanlk Tezi, Hazine ve D Ticaret

    Mstearl, Ankara, 87 (1995).