BSMIan Pain, UK ATC SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL 1 Beam...
-
Upload
cornelius-barber -
Category
Documents
-
view
214 -
download
0
description
Transcript of BSMIan Pain, UK ATC SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL 1 Beam...
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
1
Beam Steering Mirror Sub-SystemIIDR Overview
Ian Pain
UK ATC
Colin Cunningham, System engineer + BSM consultantDavid Henry, Optical Engineer, BSM systems assistBrian Stobie, Electronics/Servo engineerIan Pain, Project Manager + Lead/Mechanical EngineerTom Paul, Mechanical Design EngineerKen Wilson, Project TechnicianGillian Wright Local Co-I + Project ScientistGayle Reynolds Project Assistant
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
2
Agenda
• BSM Design drivers• The status of the design • Open areas• Development Plan• Qualification• Prototyping testing• Summary
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
3
15:33:
40AG
R
REV.SP501/Reflect.arm
SURFACE 73
13-Jun-00
60.0 MM
X= 0.000
Y=0.0
00
footprint at 27mm above focal surfacefull range of m4 tilts
Telescope axis
BSM design Drivers• Stability Specification confirmed & achievable
• Flex pivots Power consumption vs. vibration survival
• Launch protection now a baseline– launch damping of motor coils– flex pivot protection sleeves– deployable end stop
• limits chop travel to +/- 1 degree • retract after launch to allow +/- 2.5 degrees motion• no Single point Failure• ensures spectrometer field of view retained
– review following qualification testing
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
4
• Re-designed for PACS chopper motors• Connectors/Harness and PCAL
incorporated. • Structure interface complete
Design Status
PCALStructure interface
Chop Axis
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
5
Design status (continued)
• Optical Beam interfaces OK• Baffle concept design achieved
Baffle Beams
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
6
Design status (continued)
Electronics• Top level design complete
– circuit design complete– Deliveries to LAM - tight, but programme rolling
• ESA procurement requests made– Harness, Thermometers, Connectors specified– BSMe parts - via LAM
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
7
BSM Wiring
ChopMotor
JiggleMotor
FlexibleLink
ChopSensor
JiggleSensor
DeployableEndstop CONNECTOR
MechanismTem perature
Sensor
PCAL
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
8
BSM Circuit (10 IC’s, 6 Transistors)
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
9
Open areas - Design• Motor selection
– Confirm PACS thin or thick motors (torque performance)– Detail Motor packaging & any structural mods– FEA
• Launch Lock – design & analyse. – Trade off study (cost/complexity vs benefits)
• Lucas Flexures – determine required pre-ship tests
• Sensors – instability in test data ID’d. Re-confirm OK.
• Baffle– confirm interfaces (finish, location, shape)– complete design (ATC+RAL)
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
10
Development Plan
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
11
Milestone (org) DatePDR (SPIRE) CompleteDelta PDR (SPIRE) CompleteBSM Simulink Model Del'y to LAM (ATC) CompleteBSM Analogue Board Design Del'y to LAM CompletePrototype Design Release CompleteBSM Prototype2 Del'y to LAM (ATC) Jun.01BSM Analogue Board Detailed Design Del'yto LAM (ATC)
Complete
SMEC, BSM Detailed Design Review (SPIRE) Jul.01BSM DM2 Deliver to LAM (ATC) Mar.01WFL Dewar required (ATC) Aug.01DM tests complete (ATC) Mar.02BSM STM delivery to RAL (ATC) Jul.02CQM BSM Del'y to LAM (ATC) Aug.02CQM BSM Del'y to RAL (LAM) Nov.02BSM Design CDR (SPIRE) Apr.03System Design CDR (SPIRE) Apr.03CQM Del'y to ESA (RAL) Jul.03WE Critical Design Review (SPIRE) Jul.03PFM BSM Del'y to LAM (ATC) Oct.03PFM BSM Del'y to RAL (LAM) Nov.03PFM Del'y to ESA (RAL) Oct.04FS BSM Del'y to LAM (ATC) Jan.04FS BSM Del'y to RAL (LAM) Mar.04FS Available to ESA (RAL) Jul.05Launch Jan.07
Activity Start EndPreliminary Design 10 Apr '00 13 Feb '01PDR 26 Jun '00 27 Jun '00Detail Design & Prototypes 10 May '00 27 Aug '01Detailed Design Review (prep) 19 Jun '01 22 Jun '01DM 22 Mar '01 22 Mar '02DM tests complete, indicatedesign concept valid
22 Mar '02 22 Mar '02
STM 04 Feb '02 09 Oct '02confirm QM design loads 09 Oct '02 09 Oct '02QM 22 Jun '01 27 Feb '03QM tests complete, indicateflight design valid
27 Feb '03 27 Feb '03
CQM 04 Feb '02 05 Jun '03Critical Design Review 02 Apr '03 04 Apr '03 PFM 13 Mar '01 20 May '04Deliver FPU PFM to ESA 29 Oct '04 01 Nov '04 FSM 18 Apr '03 13 Dec '04Deliver FPU FSM to ESA 19 Apr '05 21 Apr '05
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
12
• Single Axis Prototype – motors & sensors
• Two Axis Prototype– cooldown, cross talk,
manufacture
• Development Model (DM) – warm shake tests, cold
performance
• Structural & Thermal Model (STM)
– SPIRE vibration environment
• Qualification Model (QM)– survival & life tests, cold
performance
• Cryogenic Qualification Model (CQM)
– SPIRE system integration & function
• Proto-Flight Model (PFM) – flight hardware
• Flight Spare Model (FSM)– spare
Qualification
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
13
Qualification issues• STM
– to have flex pivots or be fixed mass?– STM vibration delivery too late to work into QM design/build ‘sensibly’. – Will mitigate by procuring backup (stiffer) flex pivots
• Life tests – Life tests are dominated by ground test (PFM AIV plan TBC needs TBD!)
• 1.25 x(orbit life) + 4x(ground test duration) / accel factor• (1.25 x (4.25x12/6) + (4 x 3) ) / 10= 1.5 months approx.
• Cold Vibration tests v.costly• Long lead items:
– flex pivots (Lucas TRW) …. 4-6 months– motors (via MPIA/Zeiss) …. TBD
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
14
Prototype Testing• Single axis prototype chopping under closed
loop control. – Motors obtained from PACS via MPIA– Laser measurement device delivered (CDL)– D-Space & Simulink environment established
closed loop control of prototype– working to characterize actual components
and refine control system– alternate (last gasp) prototype delivered (CDL)
• test dewar commissioned – 10-16hr hold time, for prototype tests only– closed cycle cooler dewar will be used for QM
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
15
Single Axis Prototype
BSM chop axis
PACS motor
Tilt Measurement Device
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
16
2-Axis Prototype
BSM jiggle frame
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
17
Prototype Test DataDamping Comparisons
-1500.0000
-1000.0000
-500.0000
0.0000
500.0000
1000.0000
1500.0000
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Sample Number
Posi
tion
Short
Open
Decay times: 0.42s, 1.68s
Mirror Posisiton
-2800
-2700
-2600
-2500
-2400
-2300
-2200
-2100
-2000
-19000 200 400 600 800 1000 1200 1400 1600 1800 2000
Sample Number
Posi
tion
X axisMotor Force Constant (N/Amp) vs. Angle
6.38
6.40
6.42
6.44
6.46
6.48
6.50
6.52
6.54
6.56
6.58
-0.006 -0.004 -0.002 0 0.002 0.004 0.006
Angle (Rad)
Kf (N
/A)
BSM Ian Pain, UK ATC
SPIRE Instrument Intermediate Design Review April 23, 24 2001 RAL
21
BSM summary
• Mechanical & Electronic Design in good shape• BSM designed at assembly level + 3D components. • Interfaces defined
– Harness– Structure– Baffle/Optics (concept)– PCAL
• DDR schedule (Jul.01) – tight but achievable– Motor selection tests critical, but in hand– Deployable end stop at space envelope level only.