BP Additional Impacts for Cape Vincent Wind Complex

download BP Additional Impacts for Cape Vincent Wind Complex

of 22

Transcript of BP Additional Impacts for Cape Vincent Wind Complex

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    1/22

    Town of Cape Vincent Review January 20, 2013

    Additional Potential Adverse Environmental Impacts & Other Recommended Studies & Issues

    BP Article 10 Cape Vincent Wind Farm Proposal 2012

    I. Health, Safety and General Welfare1. COMPREHENSIVE PLAN Article 10 rules state, A statement

    as to whether the municipality has an adopted comprehensiveplan and whether the proposed land use (wind project) isconsistent with such comprehensive plan. BP's 124-turbineproject proposal is strikingly incompatible with the 2003and 2012 Joint Comprehensive Plan for the Town and Villageof Cape Vincent. BP should provide an explanation as towhy they are proposing a project so counter to the valuesespoused by the Town and Village's Joint Comprehensive Plan.

    2. SLEEP DEPRIVATION Sleep deprivation is now a wellestablished health risk associated with the noise producedby industrial wind turbines (B. Berglund et.al. 1999, C.Hanning & Evans 2012, M. Nissenbaum et.al. 2012, E.Pedersen et.a.l 2007, Pedersen & Waye 2004, N. Pierpont2009, D. Shepherd et.a. 2011 and G. van den Berg et.al.2008). BP should provide a comprehensive analysis of the

    scientific literature, including the aforementioned papers,to describe the negative health impacts associated withsleep disturbance regardless of the cause, and then to alsoassess the potential for sleep disruptions, and otherdirect and indirect health effects, with BP's proposed 124-turbine project. Assessing the potential for sleepdisruption in Cape Vincent from industrial wind developmentshould be keyed to BP's predicted sound levels. Therestrictions imposed in Cape Vincent's zoning law wereformulated with the expressed purpose of minimizing healthimpacts, such as sleep deprivation. Alignment with thoserestrictions should help ensure BP that potential adversehealth effects from their proposed development will beminimized.

    3. WIND TURBINE NOISE Among all the issues related toindustrial wind development, turbine noise is likely theissue that has the greatest potential for annoyance andadverse health impacts on Cape Vincent's population. Aftera careful review by knowledgeable acoustic professionals,including Town's engineering consultants, Cape Vincent

    1

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    2/22

    Town of Cape Vincent Review January 20, 2013

    adopted a zoning law that limits nighttime industrial noiseto no more than 35 dBA, 40 dBA and 45 dBA; and 55 dBC, 58dBC and 63 dBC, for night, evening and daytime periods,

    respectively. Predictive modeling should furnish octaveband sound pressure levels, basing these predictions on awind turbine model that reflects worst case noise impacts.Modeling should provide an appropriate adjustment for modeland turbine variability and with Gs= 0, Gm= 0, and Gr= 0.9.In the preparation of maps to describe potential noiseimpacts, property lines should be clearly defined so thatland owners, those with leases and good neighbor agreementsas well as non-participants, can examine noise impacts ontheir property. In addition, the predictive analysisshould include a tabled format of sound levels for allresidences keyed to the the sound level map. The tabledprojections should provide predicted A-Weighted and C-Weighted sound levels at each residence and somedesignation as to whether the resident is a participant,either lessee or good neighbor, or non-participant. Thenoise impact analysis should include three operationalscenarios: 1) noise levels at cut-in speeds, 2) noiselevels at power output and 3) noise levels at full outputof the wind turbine. Finally, a summary tally should becompleted to estimate the number of Cape Vincent propertieswhere turbine noise levels will exceed 35 dBA.

    4. INFRASOUND & LOW FREQUENCY NOISE (LFN) The WisconsinPublic Service Commission just recently released and postedon their website 1 a ground-breaking study of wind turbineinfrasound noise impacts at the Shirley Wind project, BrownCounty, Wisconsin. The study, authored by four independentacoustic consulting firms with experience in assessing windturbine noise impacts, concluded: The four investigating firms are of the opinion that enough evidence and hypotheses have been given herein to classify LFN and infrasound as a serious issue, possibly affecting thefuture of the industry. Because infrasound levels wereinaudible, but nevertheless problematic for some residentsof the Shirley Wind project, the acoustical engineers alsorecommended conducting a follow-up study: A Threshold of Perception test with participating and non-participating Shirley residents . Until the perception study iscompleted a conservative recommendation in their report waswind turbine noise levels should not exceed 33.5 dBA.

    1A Cooperative Measurement Survey and Analysis of Low Frequency and Infrasound at the Shirley Wind Farm inBrown County, Wisconsin [Wisc. PSC Report Number 122412-1 Issued: December 24, 2012] .

    2

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    3/22

    Town of Cape Vincent Review January 20, 2013

    Section 1001.19 (k) of the Article 10 rules outline issuesto evaluate that may have potential community noiseimpacts. Included in the list to evaluate are industrial

    or medical activities that are sensitive to vibration orinfrasound. The Town wants the following evaluation addedto industrial and medical activities referenced in therules: residences, schools and other facilities wherepeople live, gather or congregate. In addition, BP shallprovide an evaluation of low frequency noise annoyance andepidemiological evidence that low frequency sound generatedby the turbine model selected for the proposed project isnot, and will not be associated with the advent of adversehealth effects such as sleep and mood disorders, inabilityto concentrate, tinnitus, vestibular problems andhypertension in residents living within or in closeproximity to the project. Again, the criterion should be33.5 dBA, as suggested from the Wisconsin PSC report. Thepredicted levels of infrasound shall then be compared withthose referenced in the recent Wisconsin PSC study.

    5. TURBINE FAILURE - By far the biggest number of incidents(turbine accidents) found was due to blade failure. Bladefailure can arise from a number of possible sources, and results in either whole blades or pieces of blade being thrown from the turbine. 2 Pieces of blade have beendocumented as traveling up to one mile. For this reason

    some municipalities have adopted setbacks for wind turbinesto account for the risk of fragments thrown from the rotorrather than arbitrarily adopting a wind industry standarddeveloped for optimizing a project layout. The windturbine setbacks described in Cape Vincent's zoning lawwere designed for safety and are six times (6X) the totalheight of a turbine from property lines of non-participants, homes, roads and project boundaries. BPshould provide a comprehensive assessment of rotor failureand debris scatter for modern industrial scale wind turbinefailures as well as a well reasoned explanation forsetbacks they may use that are not compliant with the CapeVincent zoning law. In the Article 10 rules (Exhibit 31)they note, Setbacks requirements would have to beconsidered on a case by case basis by looking at the

    purpose for their establishment and the circumstances of aspecific site or case [p.78]. Furthermore, also in theArticle 10 rules (Exhibit 18) ...setback considerationsfor facility components which may present hazards to public

    2 http://www.caithnesswindfarms.co.uk/accidents.pdf

    3

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    4/22

    Town of Cape Vincent Review January 20, 2013

    safety. The town's purpose in establishing turbinesetbacks is public safety and these limits are compatiblewith the intent of Article 10 rules.

    6. SHADOW FLICKER BP shall provide epidemiological evidencethat shadow flicker caused by wind turbines of the modelchosen by BP does not and will not induce photosensitiveseizures in individuals with progressive neuro-degenerativedisorders living within or in close proximity to theproposed project. Cape Vincent's zoning law providesguidance for evaluating the impacts of shadow flicker: Theapplicant shall conduct a study on potential shadowflicker. The study shall identify locations where shadowflicker may be caused by wind turbines and the expecteddurations of the flicker at these locations. For

    residences, the zone for predicting shadow coverage shallinclude the area within a 100-foot radius of the center ofthe residence. The study shall identify areas where shadowflicker may interfere with residences or highways anddetail measures that will be taken to mitigate or eliminatesuch interference. The universal software used to predictshadow flicker impacts calculates shadow effects based onturbines within 1,000 meters of a receptor and a receptorof 1 square meter placed 1.5 meters above ground. Theuniversal standard of shadow impact used by consultants is30 hrs/yr/receptor. Given that most residents of Cape

    Vincent do not hover around a one square meter window, butoccupy a far greater living space that includes areaoutside the home itself, the WindPro model should consideran alternative analysis that includes turbines within 2,000meters of a receptor and assuming that each receptor is 5 mwide by 10 m long.

    7. FIRE PROTECTION & EMERGENCY RESPONSE BP should provide aFire Protection/Emergency Response Plan: A fire protectionand emergency response plan, created in consultation withthe fire department(s) having jurisdiction over theproposed industrial wind project shall address coordination

    with local emergency/fire protection providers during anyconstruction or operation phase emergency, hazard, or otherevent.

    8. COST OF FACILITIES Article 10 rules (Exhibit 14) requirethat detailed financial data should accompany any requestfor an application. For example, such information may berelevant to the required consideration of alternatives, thereasonableness of local laws, or whether the proposed

    4

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    5/22

    Town of Cape Vincent Review January 20, 2013

    facility is in the public interest. BP has been extremelyreluctant to provide any information, let alone relevant,important financial assumptions. As stated in the rules,

    the Town underscores this requirement of the rules.9. STRAY VOLTAGE - The applicant shall provide epidemiological

    evidence that stray voltage generated by the turbine modelselected and transmission components do not pose adverserisks to the nervous and immune systems of residents livingwithin or in close proximity to the project. Similarly,the applicant must be able to rule out the possibility thatstray voltage or electromagnetic fields generated by theturbines or transmission components will not adverselyeffect the function of pacemakers or similar implanteddevices intended to regulate human organ functions. The

    applicant shall also provide evidence that stray voltagegenerated by the turbine model and transmission componentsshall not adversely affect milk production in dairy cowsand goats in farms within or in close proximity to theproject. Further, Cape Vincent zoning law requires anassessment, pre- and post-installation, of possible strayvoltage problems on the site and neighboring propertieswithin one (1) mile of the project boundary to show whatproperties need upgraded wiring and grounding. Theapplicant/operator is responsible for assessment and anycorrection required.

    2. Involved Agency SEQRA Reviews of BP and Acciona ProjectsSubmitted to Cape Vincent Planning Board 2007-2009

    1. KARST GEOGRAPHY - Conducting a comprehensive assessment ofthe karst geology in the Town of Cape Vincent was probablythe most egregious lapse in oversight by the Lead Agencyduring the SEQRA review of the BP and Acciona projectproposals. The Town's engineering consultant recommendedat the time that the applicants include an evaluation of

    the bedrock geology, in particular the karst geology. Theystated, This work is critical to maintain suitablefoundations for future turbines, as well as to protect andmaintain any regional geological and hydrogeologicconditions of the karst geology. Regrettably, the karstassessment was never completed, but it nevertheless shouldbe a part of BP's list of issues that require study duringthe application phase of Article 10.

    5

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    6/22

    Town of Cape Vincent Review January 20, 2013

    (a) BERNIER CARR ASSOCIATES TOWN CONSULTANT 6/28/07 SLWFReview - We recommend that the applicant, St. LawrenceWind, include an evaluation of the bedrock geology in

    their definition as well as the Environmental ImpactAnalysis. This work is critical to maintain suitablefoundations for future turbines, as well as to protectand maintain any regional geological and hydrogeologicconditions of the karst geology. Our challenge duringthe SEQRA review is to identify the potential impactswhich will limit tower locations within sensitive areasof the karst geology.

    (b) USFWS 6/15/07 SLWF Review Karst landscapes aretypified by underground drainages, caverns, and on thesurface shallow, linear patterns of vegetation. The

    dissolution cracks, caves and caverns provide heretoforeunknown hibernacula for bats and that these areas shouldbe avoided.

    (c) NYSDEC 2/29/08 CVWPP Review DEC recommends that amore complete discussion of karst features be included inthe SDEIS. The location of bedrock fractures andsinkholes should be shown relative to proposed projectactivities. Where carbonate rocks are exposed at landsurface, solution features create karst topography,characterized by little surface drainage as well as bysinkholes, blind valleys and sinking streams. Because

    water enters the carbonate rocks rapidly throughsinkholes and other large openings, any contaminants inthe water can rapidly enter and spread through theaquifers. In addition, a detailed construction plan needsto be developed to incorporate stringent containment ofconstruction materials, particularly concrete slurry.This would include such practices as the use ofwatertight forms, silt/storm-water fencing, controlledconcrete truck washout areas, and covered storage ofequipment and construction chemicals. Engineeringspecifications to describe these proposed practices need

    to be detailed in this plan.(d) NYSDEC 6/15/07 SLWF Review DEC recommends that a

    plan be prepared that specifies procedures for conductingdetailed subsurface investigations at turbine sitelocations and other project components that may interfacewith limestone/karst features. The plan should specifyactions to be taken if karst features are identified orsuspected, including further investigation (e.g., dye

    6

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    7/22

    Town of Cape Vincent Review January 20, 2013

    testing), turbine relocation, determination of theeffects of blasting, or engineering constructioncontrols.

    (e) NYSDEC 5/29/09 SLWF Review - In comments on the DEISfor this project dated June 15, 2007, DEC recommendedthat a comprehensive survey of karst features beconducted in the project development area, and a plan beprepared that specifies procedures for conducting adetailed subsurvace investigations at turbine locationsand other project componsent that may itnerface withlimestone/karst features. DEC further recommended thatan environmental monitor qualified to work in karstenvrionment be on site for all pre-construction surveysand any construction activities that involve excavation

    to bedrock or are located in proximity to a known karstfeature. The SDEIS included an outline of proposedkarst investigations, but DEC recommends the studies becompleted prior to construction in order to assess theadequacy of proposed mitigation measures.

    (f) MENTOR, RUBIN & TRIVELPIECE 6/13/07 SLWF Review -TheDEIS provides to construction, a geo-technicalinvestigation would be performed to identify subsurfaceconditions necessary for engineering the final design ofthe Project. DEIS contains no technical investigation.

    (g) PRESSY & ASSOCIATES 5/29/07 SLWF Review Thepotential to impact receptors, e.g., domestic wells,springs etc., will be increased due to the presence ofkarst limestone bedrock across the project area and theneed to construct large concrete foundations.

    2. CUMULATIVE ANALYSIS All resources agencies recommended acomprehensive impact analysis on birds and bats from thepotential development of nearly 700 wind turbines withinour region. Furthermore, estimates of mortality (whichwere lacking in the BP SDEIS) should utilize the WolfeIsland Wind Farm experience and a time frame of at least 20

    years. In addition to quantifying turbine-induced avianand bat mortality there should also be some considerationfor displacement impacts from a regional build-out ofindustrial wind facilities.

    (a) USFWS 6/15/07 SLWF Review FWS recommends a cumulativeimpact analysis of other wind projects underconsideration which includes both BP and Acciona projectsas well as Horse Creek. The analysis should consider all

    7

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    8/22

    Town of Cape Vincent Review January 20, 2013

    potential projects and effects on avian and bat speciesover project lifespans of 20 years.

    (b) USFWS 3/19/08 CVWPP Review Other wind farm proposals

    added to the mix besides SLWF and CVWPP: Wolfe Island,Galloo Is. Roaring Brook, Maple Ridge for a total ofnearly 700 turbines in our region. A cumulative analysisshould consider this magnitude of turbine development inthe analysis.

    (c) NYSDEC R-6 4/17/07 SLWF Review - An overall concernfrom regional staff is the potential cumulative impactsof the numerous proposed wind power projects to belocated in the Lake Ontario/St. Lawrence River plains...The St. Lawrence Wind Energy Project is located in amajor flyway, important raptor wintering ground,important grassland bird nesting area (not only in NewYork state, but in Northeast America) and in closeproximity to a winter hibernaculum and dispersal area forboth federal and state-listed bat species. Since naturalresources know no boundaries, it is believed that thestudy area should be extended to include all of the lakeand river coastal areas for a clearer assessment of thepotential impacts.

    (d) NYSDEC 6/15/07 SLWF Review The SDEIS also needs toconsider a cumulative assessment of visual impacts ofthis project and the two other wind power projectsproposed in the general area, the BP proposal for theTowns of Cape Vincent and Lyme, and the PPM Atlanticproject in the Town of Clayton. Both of these projectshave formally submitted applications for review and dataare available sufficient to conduct a cumulative visualassessment.

    (e) NYSDEC 9/14/07 CVWPP Review - The cumulative impactanalysis should include consideration of impacts from allwind projects known to be under development or review inthe region, including St. Lawrence Wind Power Project in

    the Town of Cape Vincent, the Horse Creek Wind Project inthe Town of Clayton, and the Wolfe Island Wind PowerProject in Wolfe Island, Ontario. Specific resources ofprimary concern to DEC that warrant cumulative analysisare bird/bat/wildlife impacts (including impacts toendangered, threatened and special concern species),wetland/watershed impacts and visual/historic impacts.

    (f) PSC 02/28/08 BP - Project must be discussed in

    8

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    9/22

    Town of Cape Vincent Review January 20, 2013

    relation to neighboring project(s) and proposed projects.

    3. ALTERNATIVES ANALYSIS Alternative project layouts andarrangements in the Acciona FEIS and BP's SDEIS were

    woefully inadequate in relation to extensive comments madeby involved agencies under SEQRA. Aside from BP's proposedproject, which is incompatible with the Town of CapeVincent Comprehensive Plan and Zoning Law, BP shouldinclude for consideration a renewable energy developmentalternative that is compatible with the Town's plan andlaw. The analysis should also include alternative options(e.g., buried line) for the transmission line bisecting theTown of Lyme.

    (a) USFWS 6/15/07 SLWF Review The DEIS notes that thedeveloper has a range of turbine sizes underconsideration. The developer should be required to alsogive serious consideration to a range of alternativefacility arrangements to enable the advancing of aproject design that is responsive to the many significantresources of State interest in the project area.

    (b) USFWS 3/19/08 CVWPP Review No explanation is providedas to whether a smaller project is feasible. The DEISshould provide an explanation on the minimum number ofturbines needed to make a viable project. How canalternatives be considered without knowledge of windresources and avian concentrations within the projectfootprint.

    (c) NYSDEC 2/29/08 CVWPP Review "The lack of any detail inthe project scope precludes any meaningful discussion ofalternatives, as there is no project to comparealternatives to. SEQRA regulations state, Thedescription and evaluation of each alternative should beas a level of detail sufficient to permit a comparativeassessment of the alternatives discussed. The projectdescription in this DEIS fails to do this. Details toinclude in these evaluations should include the factors

    that led to the specific turbine layout for eachalternative, such as wind resource evaluation, turbinespacing and/or orientation, wind turbine model selection,site constraints (setback requirements, avoidance ofwetlands, landowner preference, etc.), access road andinterconnect design considerations, and avoidance ofidentified adverse environmental impacts (e.g.,archeological sites). The range of alternatives may alsoinclude, as appropriate, alternative sites, technology,

    9

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    10/22

    Town of Cape Vincent Review January 20, 2013

    scale or magnitude, design, timing, use, and types ofaction.

    (d) PSC 1/12/07 BP - Should include alternative scales

    and layouts to avoid significant impacts.(e) PSC 02/28/08 BP - DEIS does not provide alternatives

    that avoid or minimize environmental impacts to greatestextent practicable.

    (f) PSC 06/13/07 SLWF - The location of (transmissionline) facilities should be specified, and alternatives,including consideration of the costs and benefits ofunderground location for all or part of the line shouldbe addressed in the SDEIS. The alternatives analysisshould address routing alternatives for 115kV

    transmission line, including facility routes: within theabandon railroad ROW, adjacent to abandon railroad ROW,and other alternative locations. Consideration ofunderground placement should address at a minimum, thecrossing of the Chaumont River, any regulated wetlands orWildlife Management Areas, Important bird areas,locations visible from the Seaway Trail Scenic Byway,Historic Districts, and other locations as appropriate.

    (g) PSC 06/13/07 SLWF - The discussion of projectalternatives should consider project alternative reducedscale, and alternative layout and project arrangement,

    which would remove turbines from: the most prominentlocations near the Coastal Zone and Local WaterfrontRevitalization Areas, the Seaway Trail Scenic Byway,State Parks, Historic Properties listed or eligible forlisting on the State or National Register of HistoricPlaces, and other resources of recreational, scenic andaesthetic importance to the State, from designatedSignificant Coastal Habitat areas, Important Bird Areas,Wildlife Management Areas and NYS regulated wetlands.

    (h) PSC 06/13/07 SLWF - Alternative Scenarios thatshould be addressed include, at a minimum: Reducedproject footprint, Increase setbacks from shoreline areasand the Seaway Trail, Increase setbacks from visual andcultural resources, Increase setbacks from SignificantCoastal Fish and Wildlife Habitats, Increase setbacksfrom WMA and Important Bird Areas, AND Remove facilitiesfrom NRHP listed properties.

    (i) MENTOR, RUBIN & TRIVELPIECE 6/14/07 SLWF Review - TheDEIS should contain a meaningful discussion of

    10

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    11/22

    Town of Cape Vincent Review January 20, 2013

    alternatives and not just the conclusory assertions thatit presently contains. An Environmental Impact Statementmust contain a description and evaluation of the range

    od reasonable alternatives to the action that arefeasible, considering the objectives and capabilities ofthe sponsorat a level of detail sufficient to permit acomparative assessment of the alternatives discussed.NYCRR617.9(b)(5)(v) Significant further assessment ofalternatives is warranted.

    4. MULTIPLE YEARS ENVIRONMENTAL STUDY RECOMMENDED Althoughpast baseline studies of bird and bat populationsassociated with SEQRA efforts may appear extensive andcomplete, involved resource agencies considered the effortinadequate and recommended three years of study.

    Therefore, additional work is needed for nocturnal radarstudies (1 yr. spring & fall), raptor migration (1 yr.fall), breeding birds (2 yrs.), and winter raptor &waterfowl (1 yr.) studies.

    (a) USFWS LAND-BASED WIND ENERGY GUIDELINES - In order toestablish a trend in site use and conditions thatincorporates annual and seasonal variation inmeteorological conditions, biological factors, and othervariables, pre-construction studies need to occur overmultiple years. To address this need, and in light ofdevelopment timelines, three years of pre-construction

    studies may be appropriate in many circumstances.However, the level of risk and the question of datarequirements will be based on site sensitivity, affectedspecies, and the availability of data from othersources.

    (b) NYSDEC GUIDELINES CONDUCTING BIRD BAT STUDIES 8/09 - In particular, a proposal to site a wind energy projectin proximity to an Indiana bat hibernaculum (40 miles),wildlife concentration area (2 miles), along a coastline(5 miles), or on a prominent ridgeline may result in arecommendation to conduct expanded pre-constructionstudies. If a developer proposes to construct a windenergy project in or near one of the features orresources of concern identified in section 2(b), then twoto three years of pre-construction study may berecommended incorporating one or more expanded pre-construction studies to provide in-depth information onthe bird and bat resources of the site.

    (c) NYSDEC R-6 4/17/07 SLWF Review - This is only a one

    11

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    12/22

    Town of Cape Vincent Review January 20, 2013

    (1) year protocol and is too short based on the USFWSguidelines and the local knowledge of the migratory birdsand bats of the area. This plan should follow the USFWS

    guidelines of three (3) years as a minimum to establishpre-construction base line data. The single year ofdata on migrating raptors is also inadequate: The numberof points, amount of time (i.e. 60 minutes) per point,the number of days and duration of sampling period areall inadequate to capture the raptor (Migration) dataneeded to fully address potential impacts.

    (d) SAVE THE RIVER 2/29/08 Letter - The DEIS must includestudies of at least three years in duration to accountfor natural annual variability of bird and wildlifehabitat. Currently, the DEIS includes only one year of

    study and data collection.(e) MENTOR, RUBIN & TRIVELPIECE 6/13/07 SLWF Review - In

    addition, the proposed one-year avian and bat study isnot adequate to determine the value and usage of theProject area by wildlife. According to United States Fishand Wildlife Service a three year pre-construction studyshould be conducted to assess such impacts.

    (f) SMITH, ECOLOGIST 6/8/07 SLWF Review - At best thestudies to date must be considered pilot effortsrequiring 3-5 years of intense further studies of manygroups before any conclusions of value may be drawn..

    5. MIGRATION STUDIES In the Joint Comprehensive Plan for theTown and Village of Cape Vincent the avian migrationcorridor was recognized as one of the Town's most importantnatural resource assets. The spatial context and dynamicsof the avian migratory corridor through the Town of CapeVincent should be described in far greater detail (seebelow) than the one year of study conducted by BP in 2006-2007. More effort is required to document annual variationin numbers, specie composition, description of the spatialgradient within the corridor, and the vertical

    distribution of migrants over the project footprint (500 ftturbines are 100 ft higher than those previously consideredand therefore require a new assessment).

    (a) USFWS 3/19/08 CVWPP Review As we have indicatedbefore, starting the radar study in mi-April misses asubstantial portion of the spring avian migration andlikewise, ending the radar study on October 15 in thefall will underestimate the migration during that season,

    12

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    13/22

    Town of Cape Vincent Review January 20, 2013

    particularly some raptors and passerines and mostwaterfowl. Further, collecting data in only one year isinadequate.

    (b) USFWS 5/29/09 SLWF Review The close proximity ofturbines to these (grasslands etc.) habitats as well asLake Ontario and the St. Lawrence River are cause forgreat concern, because these habitats are known toattract waterfowl, waterbirds, and shorebirds to the areaduring the breeding and migratory periods.

    (c) USFWS 5/29/09 CVWPP Review - We find insufficient datawere collected at the project site to determine thespatial and temporal use of the project air space byflying animals. Our recommendation for wildlife studiesat wind projects generally specifies that the data shouldbe collected over multiple seasons and years to determineaverage annual conditions. Because of the variability inmigration and weather patterns, collecting data for 1year likely does not reflect typical wildlife use in theproject area. Therefore, we find insufficient datacurrently exists to adequately conduct a risk assessmentand predict wildlife mortality for this project.

    (d) ARTICLE 10 EXHIBIT 31 - Setbacks requirements wouldhave to be considered on a case by case basis by lookingat the purpose for their establishment and thecircumstances of a specific site or case. A setback mightbe unreasonable for the purposes of preventingconstruction encroachments but reasonable to protectmigratory flight-paths. [our emphasis]

    (e) NYSDEC 5/29/09 SLWF Review SDEIS suggests winterdensities were low and that the relative risks to thesespecies are very low. DEC staff, on the other hand,have documented high numbers. To overcome thisinconsistency in reporting between the DEC and theproject consultant, additional survey effort directedtowards the short-eared owl is recommended both pre-

    construction and post-construction, to be sure thisspecies' distribution and abundance is accuratelydocumented as a basis for future project evaluation andplanning efforts. It is also known that the projectarea lies within one of the most important raptorwintering grounds in New York State. A more thoroughanalysis of raptor migration within the project area isneeded to support the conclusions made in the SDEIS.It is clear from Table 3-11 that the numbers of birds

    13

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    14/22

    Town of Cape Vincent Review January 20, 2013

    per hour for Cape Vincent are not similar to the otherwind facilities, but higher than all of the other sites.

    (f) NYSDEC 12/31/04 Chautauqua Wind Farm Review (K.

    Kispert) - The eastern and southern shore of LakeOntario and the eastern shore of Lake Erie are documentedand well recognized migratory bird pathways, which areimportant within Eastern North America on a regionalscale, particularly during spring migration as birds movenorth.

    (g) PSC 2/28/08 CVWPP Review - A more thorough explanationof the nature of migration through the project area, andconsideration of potential impacts of the project onmigrating raptors is warranted.

    (h) SMITH, ECOLOGIST 6/8/07 SLWF Review - The fact noother waterfowl than Canada Goose and mallard wereidentified is of particular concern as it suggest atbest marginal competence of observers and inadequatesampling time.

    (i) AUDUBON 6/11/07 SLWF Review - We have concerns aboutdevelopment of wind power at sites that are knownmigratory corridors or provide habitat to at-riskspecies.

    (j) OLD BIRD, INC. 6/14/07 SLWF Review - Given that windturbines are tending to get larger and that this project,as with many wind projects, takes longer to be built thanprojected, bird/bat migration altitude information shouldbe provided at 25-m resolution up to 200 m above groundlevel. The West radar report, however, does not provideinformation on movements along the shoreline, and inlandareas of coverage are simply summed together to produce asingle passage rate for the whole radar survey area.

    (k) OLD BIRD, INC. 6/14/07 SLWF Review - The mostsignificant problems I find with the West Inc. radarstudy involve the location they chose to carry out theirradar study and their lack of analysis of migrationdensity dynamics within the radar study area. The St.Lawrence Wind project area is currently proposed to belocated within 800 m of the St. Lawrence River. Theradar study site is apparently only about 500 m from theshoreline, in fact outside the wind project area. Myinterpretation of the NYSDEC and USFWS comments is thatthe radar site would ideally be located 1500 m from theshoreline. West's placement of the radar unit

    14

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    15/22

    Town of Cape Vincent Review January 20, 2013

    approximately one kilometer closer to the shoreline thanhad apparently been recommended leads to the fact thatabout one third of the radar detection area was located

    over the St. Lawrence River and less than half of theirradar coverage was actually over the proposed windproject site.

    (l) OLD BIRD, INC. 6/14/07 SLWF Review - The question ofmigration corridor along the south shore of the St.Lawrence River is not addressed as was suggested it wouldbe in the study plan. What would be useful to see inevaluating potential impact to night migrants is a 500 mresolution representation of flying target density as onemoves away from the St. Lawrence River. In other words,what is the migration density within 500 m of the river?

    What is the migration density in the zone between 500 mand 1 km from the river? What is the migration densityin the zone between 1 km and 1.5 km from the river? Whatis the migration density in the zone between 1.5 km and2.0 km from the river? Such data can be obtained from aproperly designed marine radar study or with othermethodologies.

    6. WIND TURBINE OPERATIONAL MANAGEMENT As per therecommendations of the U.S. Fish & Wildlife Service BPshould provide an operational plan that includes theincrease in cut-in speed and the provision for shut down

    during the migration season as outlined below.(a) USFWS 6/15/07 SLWF Review If turbines will be

    located in blocks of grassland habitat, we recommend thatinformation be gathered on the displacement of grasslandnesting birds. To mitigate potential impacts to bats,turbines should not have a cut-in speed of less than 6m/s, and operation should be curtailed between July 15and September 15 for 5 hours after sunset.

    (b) USFWS 5/29/09 SLWF Review - Our previousrecommendation to mitigate potential impacts to bats was

    not included in the SDEIS. The project sponsor shouldcommit to adjusting turbine cut-in speeds during low windperiods to reduce bat fatalities. This is the periodwhen most bats are killed as documented by recentresearch, e.g., Arnett 2005. Cut-in speed should be 6m/s or more and operation should be curtailed for 5 hoursafter sunset from July 15 to September 15.

    (c) NYSDEC 5/29/09 CVWPP Review - The SDEIS should further

    15

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    16/22

    Town of Cape Vincent Review January 20, 2013

    state that based on the results of these studies,adjustments to the project's operational configurationand or time-table may be necessary to affect avoidance or

    minimization of the take of birds and bats, with listedspecies receiving the highest consideration.

    7. RISK ASSESSMENT Included in the assessments listed belowby the USFWS is avian mortality. As indicated inCumulative Analysis section above, projected avianmortality should use the mortality data coming from theWolfe Island Wind Power project located 2 miles north ofthe Village of Cape Vincent. Risk assessments should alsoinclude avian avoidance or displacement, i.e., those birdsand bats driven away from traditional habitats by theproposed industrial development.

    (a) USFWS 6/15/07 SLWF Review Typically, environmentalassessments of impacts on wildlife from wind projectsshould include a risk assessment. None was provided inthe DEIS. These assessments should consider populationabundance, distribution in the project airspace overmultiple years and seasons, avian avoidance, weatherimpacts as well as information on breeding, wintering andstopover habitat.

    (b) USFWS 3/19/08 CVWPP Review - Further, it appears thatthe site has high avian use as well but these resources

    were not fully considered in the f atal-flaw analysis .Based on the data collected so far, the Cape Vincent areahas high concentrations of waterfowl and waterbirds,migrating passerines and year round raptor use.

    8. LONG-TERM ENVIRONMENTAL MANAGEMENT PLAN Included in along-term management plan should be an adaptive managementcomponent that would outline steps and actions that wouldbe taken in response to potential adverse impacts that mayarise from project operations.

    (a) NYSDEC 6/15/07 SLWF Review The SDEIS should include aproject-wide long-term environmental management plan thatincorporates plans for restoration of environmentalimpacts during and following project construction(including grading, slope stabilization, re-planting withappropriate indigenous plant species, control ofinvasives, and restoration of disturbed habitats),environmental considerations to be included in theongoing maintenance of the facility (includingmaintenance and repair of roads and transmission

    16

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    17/22

    Town of Cape Vincent Review January 20, 2013

    corridors, a contingency plan to assess and minimizeenvironmental impacts during major repairs, andassessment and mitigation of environmental impacts during

    the decommissioning process. An adaptive managementcomponent is a necessary feature of an environmentalmanagement plan, to respond to environmental impacts thatarise during project operation (such as potential impactsto birds and bats, disturbance to Blanding's turtle nestsites).

    9. INADEQUATE ENVIRONMENTAL STUDIES - The following excerptfrom the Cape Vincent zoning law requires a developer shalltake to properly evaluate wildlife and other environmentalissues The scope of such assessment shall be developedin consultation with the New York State Department of

    Environmental Conservation and the United States Fish andWildlife Service and shall adhere to the USFWS Land-BasedWind Energy Guidelines, March 23, 2012 to assesssuitability of the site, and, if application is approved,outline post-Operational studies to assess impacts.

    (a) NYSDEC 2/29/08 CVWPP Review In order to adequatelyassess the potential impacts to the Project Area'sthreatened and endangered species, the Project needs tofully characterize seasonal use of the area by thesespecies. As submitted, the SDEIS is inadequate to allowa thorough evaluation of the potential impacts to these

    species. Regarding breeding bird surveys they state,Surveying during only one year and two days the entirebreeding season is far from adequate. Knowing that bothendangered and threatened grassland bird species have thepotential to nest in this area should have triggered amore thorough Breeding Bird Survey consisting of morethan one year of study.

    (b) USFWS 3/19/08 CVWPP Review BP stated that the avianand bat study protocols were approved by the Service. Wereviewed the study protocols and provided input to thesponsor (BP). We also provided recommendations to theTown of Cape Vincent. However, many of ourrecommendations have not been implemented, such asconducting surveys over multiple years to account forannual variation in weather and migration.

    (c) NYSDEC 5/29/09 SLWF SDEIS Review - In order toadequately assess the potential impacts to the projectarea's threatened and endangered species, the projectneeds to fully characterize seasonal use of the area by

    17

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    18/22

    Town of Cape Vincent Review January 20, 2013

    these species. As submitted, the SDEIS is inadequate toallow a thorough evaluation of the potential impacts tothese species.

    (d) MENTOR, RUBIN & TRIVELPIECE 6/13/07 SLWF Review - Basedon material omissions described below, we request thatthe Planning Board, as the Lead Agency under SEQRA,reject the DEIS, reconsider its previous determinationthat the DEIS is complete and adequate for public reviewand return the document to the Applicant for significantaddition and revision.

    10. INADEQUATE MAPPING & WETLANDS INFORMATION The reviewsbelow by involved agencies were very critical of pastattempts at depicting industrial wind project layouts dueto the lack of sufficient detail with the underlying maps.BP should use a map similar to that provided in the Town'scomprehensive plan that describes state and federalwetlands, archeological and historical resources, naturalheritage assets, and the migratory corridor to name a few.Moreover, project maps need better detail than what iscurrently available to allow landowners to locate theirproperty to better understand wind turbine setbacks fromtheir property lines and potential adverse environmentalimpacts.

    (a) PSC 02/28/08 BP - Project maps should include

    sensitive environmental features., e.g. wetlands, rareplants, coastal zone protections, cultural and historicalfeatures, as well as the project layout.

    (b) PSC 02/28/08 - DEIS does not have adequate mapping ofTX line and resources.

    (c) USFWS 3/19/08 CVWPP Review Lack of sufficientinformation to properly assess impacts on wetlands. Infact no estimates are provided. Without an understandingof wetlands extent, it is not possible to evaluate orprovide recommendations.

    (d) PSC 2/28/08 CVWPP Review - The representation of thewetlands...obscures relevant cover type information byuse of solid colors for Field Verified Wetland Area.The scale of the mapping included is too gross to enablediscernment of details. More detailed mapping withproject layout should be provided in a supplement.

    (e) PRESSY & ASSOCIATES 5/29/07 SLWF Review DEIS noteswetland impacts will be avoided if practicable... and

    18

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    19/22

    Town of Cape Vincent Review January 20, 2013

    where impacts could occur, if practicable, projectcomponents will be moved to avoid or minimize impacts towetlands. The proposed project, however, has placed

    many turbines adjacent to wetlands and streams.Therefore, the listed turbines should be moved oreliminated.

    (f) USFWS 3/19/08 CVWPP Review Without field surveys, thedescription of reptiles and amphibians may beunderestimated. Due to the abundant aquatic habitatfound in the area, these animals may represent animportant part of the ecosystem. Further, the discussionof affected mammals is inadequate, as no survey data orexisting information sources were provided.

    11. PROJECT BENEFIT The U.S. Fish & Wildlife Service makes avaluable point in their June 2007 review, that projectedbenefits should be derived from a realistic analysis andnot a sales brochure. For example, estimated electricenergy production from the project should be based onrealistic production figures rather than maximum ratedoutput which a project never delivers (capacity factor).Real world benefits are important understand in order toaccurately assess and weigh potential adverse impacts.

    (a) USFWS 6/15/07 SLWF Review FWS recommends an analysisof the environmental benefit from the project. Usingrealistic production data, e.g., capacity factor andseasonal production figures, and other generatingfacilities operating as backup and to meet demand duringintermittent wind periods, analyze the projected airquality benefits.

    (b) USFWS 3/19/08 CVWPP Review Reiterate comment abovefrom SLWF review. Project benefits cannot justify theunavoidable adverse impacts if all the adverse impactsare unknown or inadequately treated, and if projectbenefits are insufficiently documented.

    (c) OPRHP 05/28/08 SLWF - ..the project will have anADVERSE IMPACT on cultural resources.

    (d) SAVE THE RIVER 2/29/08 Letter - A cost-benefitanalysis of the project must be considered so thatdecision-makers have a thorough understanding of economicand environmental costs and benefits to the region.

    12. MITIGATING VISUAL IMPACTS A great deal of effortshould be expended in assessing the impact of industrial

    19

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    20/22

    Town of Cape Vincent Review January 20, 2013

    wind turbine placement within the sight planes around theTown's historical assets. Mitigation should includeremoving or moving turbines out of the line of sight.

    Moreover, traditional screening treatments should also beconsidered to minimize the visual impact of turbines onthese historic homes and structures. In addition, BPshould keep any planned development well away from theScenic Byway and Seaway Trail.

    (a) NYSDEC 6/15/07 SLWF Review DEC disagrees that thesetraditional treatments would be infeasible in allcases. DEC recommends that the visual setting of eachaffected significant resource in the project area andfive-mile visual impact area, including newly identifiedsignificant historic resources, be analyzed, and where

    feasible at specific impacted resources, directmitigation options such as screening or selective turbinere-location should be applied.

    (b) PSC 1/12/07 BP- Mitigation to include relocation,screening and reduced scale of project.

    (c) PSC 09/12/07 BP - Use scale reduction, avoidance ofimportant areas and increased setbacks to mitigate aswell as entire set if mitigation measures mentioned inDEC visual policy.

    (d) PSC 06/13/07 SLWF - The striking appearance of

    multiple turbines, with rotors turning, in the foregrounddistance zone from the Scenic Byway will have thepotential to distract drivers attention and carefulvehicle operation. The DEIS does not address in acomprehensive manner the relation of the Seaway TrailScenic Byway to the landscape and the various resourceswhich contribute to the corridor adjacent to the Trail.

    13. HISTORICAL & CULTURAL In addition to the concerns forhistoric and cultural resources outlined in Section 12,past reviews associated with the Town's SEQRA processrecommended warned that industrial wind turbine developmenthad a very substantial visual impact on historic andcultural resources. More attention has to be directed tominimizing these impacts.

    (a) PSC 06/13/07 SLWF - The DEIS indicates the locationof the Project substation on four acres near Swamp Road.The location indicated on the project facilities layoutmap is within or directly adjacent to the Warren WilsonHouse Historic District, which is listed on the National

    20

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    21/22

    Town of Cape Vincent Review January 20, 2013

    Register of Historic Places. This location presents apotential conflict with the Historic District, is likelyto adversely affect that District. Alternative locations

    should be explored...(b) PSC 06/13/07 SLWF - Adverse effects (turbines in

    view) on the Cape Vincent Village Broadway HistoricDistrict will conflict with Coastal Zone ManagementPolicies. Supplemental surveys should include allcomponent resources and landscapes within listed,eligible or potentially eligible historic properties ordistricts, as appropriate, to demonstrate the extent ofimpacts of the project on those resources. Thediscussion of Visual Resources and Community Characterdoes not adequately address the scale and scope of

    potential project impacts on the project area, theaffected community, or several resources of regional andstatewide significance.

    (c) MENTOR, RUBIN & TRIVELPIECE 6/13/07 SLWF Review -Determine how presence of each turbine affects eachbuilding that meets criteria for inclusion in theNational Historic Registry

    14. INVASIVE SPECIES PLAN In the recent past the Town hastried to control the invasive plant Swallowwort, but itstill remains a invasive that requires careful managementduring any construction period. An invasive plan should bedeveloped and approved by DEC staff prior to the onset ofany construction.

    (a) NYSDEC 6/15/07 SLWF Review DEC recommends that theSDEIS include an Invasive Species Control Plan (ISCP) tominimize the spread of invasive propagules throughout theproject development area, and particularly in regulatedwetland and stream areas.

    15. NATURAL HERITAGE VEGETATIVE LANDSCAPES Again adequatemapping is needed to document and highlight those areaswithin the Town and the proposed project footprint thathave important plant resources. These data are availablefrom the DEC's mapping section and should be included as anoverlay on any project layout mapping.

    (a) USFWS 6/15/07 SLWF Review Project area has manyunique plant habitats that are protected and others thatshould be avoided. SLWF DEIS makes no mention of theseareas and therefore when and where they should beavoided.

    21

  • 7/29/2019 BP Additional Impacts for Cape Vincent Wind Complex

    22/22

    Town of Cape Vincent Review January 20, 2013

    (b) USFWS 3/19/08 CVWPP Review Assessment conducted infall when most plants were unavailable and/or difficultto observe. Better assessment needed at an appropriate

    time.16. COASTAL ZONE CONSISTENCY REVIEW As suggested by the

    PSC a Coastal Zone Consistency Analysis should be completedand not ignored as was the case in the past.

    (a) PSC 06/13/07 SLWF - DPS informed the Lead Agency, byletter of December 8, 2006 that the Coastal ZoneConsistency Analysis must be presented for review by thePSC (Lead Agency did not require review in DEIS). TheSDEIS should include a complete Coastal Zone ConsistencyReview and should document and address the full range ofCoastal Policies as listed in 19 NYCRR $600.5.

    17. DECOMMISSIONING Towns of Cape Vincent and Lyme areuncertain as to who, other than the towns, haveresponsibility for ensuring that after the life of anyindustrial wind project has been completed that thecommunities are restored to their pre-development states.A plan should be provided to ensure that insolvency ofeither the project LLC or the State does not preclude ourtowns being made whole at the project's end-of-life.

    (a) DOS 5/26/09 Review - It may be useful to require aperformance bond or dedicated fund established to ensurethe complete decommissioning of the project.

    (b) MENTOR, RUBIN & TRIVELPIECE 6/13/07 SLWF Review - ThePlanning board must demand financial assurance to funddecommissioning of all of these towers, in the event thatthe Applicant is no longer financially viable refuses toproperly remove the facility.