Botwsana - MIC Grant to Support PEEPA in Improving …€¦ · · 2014-07-02CEO Chief Executive...
Transcript of Botwsana - MIC Grant to Support PEEPA in Improving …€¦ · · 2014-07-02CEO Chief Executive...
AFRICAN DEVELOPMENT BANK
PROJECT : MIC GRANT TO SUPPORT PEEPA IN IMPROVING PRIVATE
SECTOR PARTICIPATION IN THE DELIVERY OF PUBLIC
INFRASTRUCTURE AND SERVICES
COUNTRY : REPUBLIC OF BOTSWANA - Public Enterprises Evaluation and
Privatization Agency (PEEPA)
------------------------------------------------------------------------------------------------------------
APPRAISAL REPORT
Date: June 2010
Appraisal Team
Team Leader:
Team Members:
Sector Manager:
Sector Director:
Regional Director:
Christian Lim, Senior Private Sector Development Specialist,
OSGE.2
Carlos Mollinedo, Senior Macro Economist, OSGE.2
Achraf Tarsim, Economist Consultant, OSGE.2
Marlène Kanga, OSGE.2
Gabriel Negatu, OSGE
Abdirahman Beileh, ORSA
Peer Reviewers
Kate Tench, Technical Advisor, OSGE
Melanie Xuereb-De-Prunele, Senior Country Economist, ORSB
Abayomi Babalola, Transport Engineer, OPSM.3
i
TABLE OF CONTENTS
LIST OF TABLES………………………………………………………………………....……ii
LIST OF ANNEXES………………………………………………………………………..…..ii
CURRENCY…………………………………………………………...................................... ii
GOVERNMENT FISCAL YEAR……………………………………………………….…… . ii
LIST OF ABBREVIATIONS AND ACRONYM……………………………………………...iii
RESULTS BASE LOGICAL FRAMEWORK……………………………………………… iv
EXECUTIVE SUMMARY ........................................................................................................ 1
1. INTRODUCTION .............................................................................................................. 2
2. PRIVATIZATION IN THE GOVERNMENT‟S AGENDA.............................................. 2
3. PEEPA‟s KEY FEATURES ............................................................................................... 3
3.1. LEGAL AND INSTITUTIONAL FRAMEWORK ....................................................................... 3
3.2. GOVERNANCE AND ORGANIZATION ................................................................................. 4
3.3. ACHIEVEMENTS AND PEEPA‟S BUSINESS PLAN ............................................................... 4
3.4. PRELIMINARY SKILLS AUDIT ............................................................................................ 6
4. PROJECT DESCRIPTION ................................................................................................. 6
4.1. PROJECT OBJECTIVE ......................................................................................................... 6
4.2. STRATEGIC ALIGNMENT ................................................................................................... 7
4.3. PROJECT JUSTIFICATION ................................................................................................... 7
4.4. INPUT AND ACTIVITIES ..................................................................................................... 8
4.5. RISKS AND MITIGATION MEASURES ................................................................................. 9
5. COST AND FINANCIAL PLAN ..................................................................................... 10
6. PROCUREMENT ............................................................................................................. 11
6.1. PROCUREMENT ARRANGEMENTS ................................................................................... 11
6.2. PROCUREMENT PLAN ..................................................................................................... 11
7. FINANCIAL MANAGEMENT ....................................................................................... 12
7.1. DISBURSEMENTS ............................................................................................................ 12
7.2. FINANCIAL REPORTING ARRANGEMENTS ....................................................................... 12
7.3. LETTER OF AGREEMENT ................................................................................................. 12
8. IMPLEMENTATION ....................................................................................................... 12
8.1. EXECUTING AGENCY ...................................................................................................... 12
8.2. REPORTING AND SUPERVISION ....................................................................................... 13
8.3. INDICATIVE WORK PLAN ................................................................................................ 13
9. CONCLUSION AND RECOMMENDATION ................................................................ 14
9.1. CONCLUSION .................................................................................................................. 14
9.2. RECOMMENDATION ........................................................................................................ 14
ANNEXES……………………………………………………….……………………………15
ii
LIST OF TABLES
Table 1 Cost estimate and financing plan
Table 2 Work plan
LISTE OF ANNEXES
Annex 1 Government‟s MIC grant request
Annex 2 MIC grant request form
Annex 3 Terms of Reference (1)
Annex 4 Terms of Reference (2)
Annex 5 Terms of Reference (3)
Annex 6
Annex 7
Detailed work plan (indicative)
PEEPA Organizational Structure
Annex 8 Preliminary skills audit (summary)
Annex 9 Preliminary skills audit (detailed table)
Annex 10 Project procurement arrangements
Annex 11 Privatization transactions‟ status
Annex 12 Botswana ADB active portfolio
Annex 13 Botswana Country Profile
Annex 14 Map of Botswana
CURRENCY
Currency Equivalents
(June, 2010)
1 UA = 10.36 BWP
1 UA = 1.47 USD
1 US$ = 7.03 BWP
GOVERNMENT FISCAL YEAR
April 1- March 31
iii
LIST OF ABBREVIATIONS AND ACRONYM
AfDB / ADF African Development Bank / African Development Fund
BIUST Botswana International University of Science and Technology
BPC Botswana Power Corporation
BPL Botswana Pty Limited
BTC Botswana Telecommunications Corporation
BWP Botswana Pula
CEO Chief Executive Officer
CSP Country Strategy Paper
CTO Central Transport Organization
EDSL Economic Diversification Support Loan
GDP Gross Domestic Product
GECL Legal Department of the African Development Bank
GEMVAS Government Employee Motor Vehicle Advance Scheme
GoB Government of Botswana
GLIF Residential Property Advance Scheme
ICB International Competitive Bidding
MEWT Ministries of Environment, Wildlife and Tourism
MIC Middle Income Country
NDB National Development Bank
NCP National Competitive Bidding
NDP National Development Plan 10
OSGE Governance, Economic and Financial Reforms Department of AfDB
PEEPA Public Enterprises Evaluation and Privatization Agency
PPADA Public Procurement Assets and Disposal
PPP Public-Private Partnerships
TOR Terms of Reference
UA Unit of Account
iv
RESULTS BASED LOGICAL FRAMEWORK
HIERARCHY OF
OBJECTIVES EXPECTED RESULTS
REACH/
BENEFICIARIES
PERFORMANCE INDICATORS,
SOURCE, PERIODICITY
INDICATIVE TARGETS
AND TIME FRAME RISKS, MITIGATION MEASURES
GOAL:
Diversify economy
through private
sector involvement
in delivery of
public
infrastructure and
services
IMPACT:
Botswana successfully
implements its privatization
agenda
Government of
Botswana
Domestic
entrepreneurs and
investors
Users of public
services
Timely completion of
implementation of projects in the
Privatization Master Plan (currently
being updated)
Source: PEEPA
70% of transactions are
completed according to
schedule (to be updated with
the new Privatization Master
Plan)
Risk:
Opposition from Line Ministries, public
enterprises and services departments
Weakness of high level political support to
implement transactions.
Mitigation:
The recent financial crisis has highlighted the
need to accelerate privatization to achieve
sustainable fiscal position
PEEPA undertakes policy dialogue on
importance of privatization and awareness
raising on benefits of privatization to
Botswana‟s economy primarily to policy
makers and relevant stakeholders involved in
decision making
OBJECTIVES:
Build capacity in
PEEPA
OUTCOMES:
Two private sector
participation transactions
strategies completed
Privatization skills
strengthened
Future transactions lead to
citizen participation
All Ministries that
have privatization
projects
PEEPA
Domestic
entrepreneurs and
investors
Privatization strategy for BPC
approved and maintenance of
Government building transaction
completed
Domestic entrepreneurs take part in
the consortium of the winning
company
Domestic entrepreneurs provide
services to the winning company
Domestic savings are invested in
project implementation
Private sector participation
strategy for BPC approved by
December 2011
Private sector participation in
maintenance of Government
buildings completed by March
2012
Yes or No1
Yes or No
Yes or No
Risk:
Weakness of high level political support to
implement transactions
Mitigation:
High level of political support has been
expressed for these transactions, including in
the concerned line Ministries. The recent
financial crisis has highlighted the need to
accelerate privatization to achieve sustainable
fiscal position. Partners, which are heavily
investing in the power sector, also support
these reforms.
Policy dialogue on importance of privatization
and awareness raising on benefits to relevant
ministries and public enterprises will be
conducted with the support of the Consultants.
1 It is impossible to determine an acceptable level of citizen participation, because it is highly industry and country dependent. This indicator is therefore a Yes/No indicator.
v
HIERARCHY OF
OBJECTIVES EXPECTED RESULTS
REACH/
BENEFICIARIES
PERFORMANCE INDICATORS,
SOURCE, PERIODICITY
INDICATIVE TARGETS
AND TIME FRAME RISKS, MITIGATION MEASURES
INPUTS
UA 450,000 for
advisory and
training services to
prepare two private
sector participation
transactions
UA 60,000
Consulting services
to develop a citizen
empowerment
framework and
guidelines for
privatization
transactions
UA 122,000 for the
secondment of staff
to an experienced
sister privatization
agency
UA „000
AfDB 600
PEEPA 32
Total 632
OUTPUTS
A. Strategy document for
private sector participation in
BPC
B. Strategy and tender
documents for private sector
participation in the
maintenance of government
buildings including, hospitals,
and schools
C. On-the-job training on the
development and
implementation of divestiture
and concession transactions,
tendering, evaluation and
negotiation of offers and the
regulation and monitoring of
post privatization transactions
D. Citizen empowerment
policy in privatization
PEEPA
Ministry of Minerals,
Energy and Water
Resources
Ministry of
Infrastructure,
Science and
Technology and
DBES
Ministry of Health
Ministry of
Education and Skills
Development
Completion of the two privatization
transaction strategy
Completion of tender documents for
securing private sector service
providers for the maintenance of
government buildings
Number of man / hours of in-class
training
Completion of training manuals
Completion of citizen empowerment
Framework
Source: PEEPA
Strategy documentation ready
by March 2011
Tender documentation ready by
March 2011
At least 480 man/hours trained
by 2012
Framework documentation
ready by March 2011
Citizen empowerment
framework completed by 2012
Risk:
Transaction Consultants do not dedicate
enough resources to training
Information available on assets and services
for privatization are insufficient
Mitigation:
The ToRs explicitly describe training as a key
deliverable and payment is also based on
performance on this dimension
Available data is provided to prospective
consultants during the selection process and
the contract make them responsible for
obtaining missing information necessary to
complete the assignment, provided that the
Government provides reasonable access to
existing information
1
EXECUTIVE SUMMARY
1. The Government of Botswana wishes to further advance the implementation of its
privatization program, a key component of its diversification agenda. Economic
diversification has been a central objective of Botswana‟s development policy, in recognition of
the excessive dependence of Botswana‟s economy on diamonds. In 2009, the African
Development Bank supported this objective by providing a US$ 1.5bn Economic Diversification
Support Loan (EDSL). The loan supported reforms designed in particular to promote “the
development of a vibrant private sector including privatization” (component one).
2. The objective of the proposed project is to build capacity in the Public Enterprises
Evaluation and Privatization Agency (PEEPA). PEEPA is mandated to take the leadership in
the implementation of the privatization program. The project is an important complement to the
privatization-related reforms included in the EDSL.
3. The project includes the following activities: (i) Preparing options analyses and tender
documents for two privatization transactions; (ii) providing on-the-job training based on these
two transactions; (iii) improving practical skills of PEEPA staff through secondment to
experienced sister institutions; (iv) producing a policy for Citizen Economic Empowerment in
privatization projects. The project focuses on on-the-job training on actual transactions, to
complement the overall adequate academic qualifications of PEEPA staff. It will be implemented
during the period 2010-2012.
4. The project will contribute to accelerating the implementation of the privatization
program by building practical privatization skills and through the demonstration effect of
delivering two high priority transactions. The Citizen Economic Empowerment Policy will also
make a major contribution to improving economic opportunities for domestic businesses and
investors.
2
1. INTRODUCTION
1.1 The Government of Botswana wishes to accelerate the implementation of its
Privatization Program which ranks high on its diversification agenda. The future success of
the economy is linked to Botswana‟s ability to diversify the economy and develop new engines
of growth beyond diamond mining and the public sector, which still represent together about
50% of GDP; public spending represents about 40% of GDP (one of the largest in Africa), and
employment by the government and its paratsatals reaches 47%. As such, privatization has been
identified as one of the reforms necessary to transform the Botswana economy from a public
sector-led economy to a private sector-led economy. The Government‟s privatization policy aims
at transferring commercially viable activities to the private sector, thus reducing its financial and
administrative burden, improving service delivery, facilitating citizen empowerment and
encouraging investment, entrepreneurship and job creation.
1.2 The Public Enterprises Evaluation and Privatization Agency (PEEPA), as an
advisor and in charge of the implementation of privatizations, plays a central role in the
execution of the Privatization Program. PEEPA serves as an advisor and executive agency for
all Ministries involved in the privatization program. However, given the short history of
privatization in Botswana, most PEEPA staff has limited experience in privatization.
1.3 The objective of the proposed project is to build capacity in PEEPA through
transaction support, training and assistance in preparing a citizen empowerment policy.
The project will provide advisory services to develop a strategy for private sector participation in
the incumbent power company and in the maintenance of Government buildings, hospitals and
schools. The technical assistance will come with provision of on the job training, and
secondment training. It will also include a citizen economic participation policy for future
transactions.
Box 1: Defining Privatization, Divestiture and PPP Privatization is defined in the Privatization Policy for Botswana, Government paper No. 1 of 2000. It is understood
in its broadest sense, as it includes, not only the transfer of ownership of public enterprises to private buyers but also
“all measures and policies aimed at strengthening the role of the private sector in the economy”. In practice and for
the purpose of this project, privatization is defined as all the methods for private participation in the provision of
public goods and services, including the divestiture of assets and operations of public enterprises, the
commercialization and / or contracting out of public services, and private sector provision of infrastructure and
services through Public-Private Partnerships (PPP). In order to avoid confusion, in this document, the full transfer
of ownership of assets and provision of services from the public to the private sector is referred to by “divestiture”
rather than “privatization”. Privatization is used in its broad sense only. Similarly, “PPP” is used in a narrow
meaning, to describe the provision of green field infrastructure and associated services by a private sponsor.
2. PRIVATIZATION IN THE GOVERNMENT’S AGENDA
2.1 The Privatization Policy for Botswana, launched in 2000, is a key component of the
broader economic diversification policy. The economic diversification strategy, in line with
Vision 2016 and the National Development Plan 10 (2010-2016), aims at achieving sustainable
3
development, transforming the economy from a public-sector driven to a private-sector led
market one, and promoting an environment that supports non-mining private sector development
initiatives.
2.2 The Government’s key objectives for establishing a privatization program include:
Achieving much needed efficiencies in delivery of public services;
Relieving the Government of the financial and administrative burden of undertaking
and maintaining a constantly expanding network of services and investments in
infrastructure;
Reduce the size of the public sector, creating space for private sector to be involved in
driving the growth of the economy and stimulating entrepreneurship;
Attracting FDI and technology transfer;
Broadening and deepening the capital market through providing investment
opportunities in privatized companies.
3. PEEPA’s KEY FEATURES
3.1. LEGAL AND INSTITUTIONAL FRAMEWORK
3.1.1 The founding framework for the Privatization Program is the Privatization Policy
for Botswana of 2000 with the key objective of the Policy being to improve efficiency and
productivity in the delivery of public infrastructure and services through increased involvement
of the private sector. The Public Enterprises Evaluation and Privatization Agency (PEEPA) was
established in 2001 as an autonomous agency of Government, to advice on all aspects of
privatization and commercialization.
3.1.2 Among other things, PEEPA mandate is to advise on policy formulation, strategies
and implementation plans that facilitate private sector involvement in public sector
functions. It does so by undertaking sectoral, public services and enterprise studies and assisting
sector ministries and Government departments in delivering approved privatization transactions.
The other responsibilities of PEEPA include monitoring the performance of parastatals and their
Boards as well as assisting with the appointment of their board members.
3.1.3 Legislatively, there is no overarching law for privatization activities in Botswana
and any legal requirements are handled on a case by case basis. Transactions involving the
sale or disposal of shares or assets, or activities involving the procurement of goods and services
to facilitate transactions are implemented in accordance with the Public Procurement of Assets
and Disposal (PPADA) of Botswana.
3.1.4 Implementation of the Policy is guided by the Privatization Master Plan of 2005
which indicates those public enterprises and services suitable for privatization and those that
require to be restructured prior to consideration for privatization, as well as an action plan, the
processes to be followed and the roles and responsibilities of relevant parties that would be
involved in the processes. At that time, comprehensive divestiture and outsourcing manuals were
4
developed. The privatization agenda was reinforced in 2009 through the adoption of the PPP
Policy and Implementation Framework (Presidential Directive 18-B, 2009) that created a PPP
unit within the MFDP to promote PPP initiatives, in close coordination with PEEPA.
3.1.5 In November 2008, in addition to its original advisory mandate mentioned above,
PEEPA was mandated by an executive decision to take leadership in the implementation of
the privatization program. Cabinet has recently endorsed this decision. PEEPA becomes the
single point of accountability for the overall privatization program and can now drive the
privatization process. However, approval of the critical stages of the transaction process, mainly
for each transaction the privatization strategy, the bidding documents and the selection of the
private partner - still remain with the Cabinet.
3.2. GOVERNANCE AND ORGANIZATION
3.2.1 PEEPA is established as a Company Limited by Guarantee with the Government of
the Republic of Botswana as the sole shareholder. The Board is established and governed by
the Memorandum and Articles of Association of PEEPA and the Companies Act. The PEEPA
Board comprises of 9 members appointed by the Minister of Finance and Development Planning
and have a tenure of four years, renewable for another period of four years. The Ministry of
Finance and Development Planning, being the parent ministry, is automatically represented on
the Board to ensure continuity. Other members are drawn mainly from the private sector.
3.2.2 The Chief Executive Officer (CEO), who is not a member of the Board, is appointed
by the Board, subsequent to the approval of the Minister of Finance and Cabinet. Operational, the CEO is supported by a Deputy CEO and the staff members fall under two
categories, namely under the core departments and the support services as outlined in Annex 6.
Under the core departments, the (i) Restructuring and Privatization Department deals with
advising on the transfer of ownership or management of public enterprises to the private sector
through various methods such as divestiture, leasing and management contracts, and PPPs, (ii)
the Outsourcing Department deals with the transfer of non-core services currently being handled
by Government to the private sector and (iii) the Performance Monitoring Department which
deals with monitoring the performance of public entities and their boards.
3.2.3 PEEPA is committed to best corporate governance principles and practices and has
developed a comprehensive Corporate Governance Framework to enhance organizational
performance. The Framework consists of a Performance Contract (Shareholder Compact), a
Board Charter and a Board Evaluation/Appraisal System, among other elements, and is being
considered by the Ministry of Finance and Development Planning.
3.3. ACHIEVEMENTS AND PEEPA’S BUSINESS PLAN
3.3.1 To date, the achievements under the program surround the outsourcing/contracting
out of public services as well as implementation of a few PPP projects. With respect to
divestiture, key achievements involve the development of transaction strategies for the airlines
company, the incumbent telecommunication company, the National Development Bank and the
Government ranch. Implementation is placed with the line Ministries.
5
3.3.2 Though milder methods of privatization, such as PPPs and outsourcing of services
have been achieved, key challenges remain to divestiture, as evidenced by the absence of
completed divestiture since the approval of the privatization policy in 2000. These challenges
include the following:
- Though political will is significant2, economic incentives have so far not been in favor of
divestiture, as the Government could still benefit for at least 15 years from substantial
diamond revenues which allow it to finance and bail out if necessary the companies
targeted for divestiture;
- The institutional framework centralized the advisory support with PEEPA, while
decentralizing implementation of transactions to line ministries, which in some cases can
weaken the incentive to implement the privatizations;
- There has been a lack of clarity in the initial design of the projects, which led to
difficulties in negotiations that could not be overcome;
- More communication is needed at a political level to identify the impacts of the
divestitures and reach agreement on acceptable mitigation measures;
- The strategic choice of target companies was not always optimal. For instance, Air
Botswana, being a national flag carrier, was in this regard a difficult company to
privatize.
3.3.3 Economic incentives have become more favorable since the financial crisis, as the
subsequent slump in diamond prices has highlighted the fragility of diamond revenues. This has concretely resulted in a reduction of the funding of Government agencies and public
enterprises, and created a renewed momentum for privatization, including divestiture.
3.3.4 As explained above, PEEPA’s mandate has been revised to enable it to take
leadership in the implementation of the privatization program. Though the decisions at the
critical stages of the transaction process still remain with the Cabinet, PEEPA is now empowered
to drive the technical preparation of the transactions.
3.3.5 This project will enhance the capacity to identify upfront critical constraints, and
manage them including through better communication.
3.3.6 PEEPA is developing a Priority Privatization Program for NDP 10, which will
update the current Privatization Master Plan and take into account the past experiences in
identifying public enterprises to be divested in priority. This Priority Program should further
enhance the delivery of privatization by attaining agreement and commitment of key
stakeholders to this Program and will form the basis for measuring PEEPA‟s performance.
PEEPA‟s 2010/11 Business Plan will therefore be based on this priority privatization program.
2 Beyond declarations of intention, this is demonstrated by the fact that the privatization of Air Botswana was
approved three times by the Cabinet, after a relatively short preparation time of two years on average. Each time
however, the transaction was canceled for various reasons, which included unfavorable market conditions due to the
9/11 attacks, pulling out of the preferred bidder at the last minute because of changes in the strategy of the buyer,
disagreement on politically sensitive aspects of the business plan proposed by the buyer, such as the removal of the
national flag.
6
3.4. PRELIMINARY SKILLS AUDIT
3.4.1 PEEPA has 33 staff. This includes 8 persons at management / senior level, 7 analysts
and 18 from corporate services, including finance and administration. The preliminary skills
audit (Annexes 7 and 8) provides a detailed breakdown.
3.4.2 Privatization experiences are scarce in Botswana, which has prompted PEEPA to
largely rely so far on various forms of international expertise. This is the result of
privatization being a relatively new public sector reform initiative in Botswana. A number of
PEEPA staff are international long term consultants. International Consultants are also recruited
on a transaction basis. As a result, PEEPA has been operating under a project management
approach with a minimal core staff group that procures and supervises consultants or sector
experts that offer advisory support and expertise. The core skills and competencies that have
hitherto been required in PEEPA have therefore evolved around project management, financial
analysis, procurement, negotiations and communication and advocacy skills.
3.4.3 PEEPA has now taken the strategic option to reduce the number of consultants
being used on assignments and carry-out more of the work in-house. This is expected to
bring the following benefits: cost reduction, increased flexibility, and improved quality control of
consultants, improved contribution of PEEPA in the stakeholder dialogue. The success of this
strategy hinges on PEEPA enhancing the technical capacity of its staff, in particular on business
case assessments and business valuation.
3.4.4 The preliminary skills audit indicates that PEEPA’s skills base would be best
enhanced through on-the-job training on real privatization cases and through
secondments. Indeed, on the one hand, the educational background of PEEPA staff seems
adequate. All managers hold an advanced business degree and all analysts hold Bachelor‟s
degree in a relevant field, mostly economics, business and finance. In addition, the total of prior
years of experience working in parastatals is substantial, with 9 years on average at management
level and 3 at analyst level. However, on the other hand experience of privatization structuring
and analysis prior to joining PEEPA is very limited.
4. PROJECT DESCRIPTION
4.1. PROJECT OBJECTIVE
4.1.1 The overall objective of the project is to build capacity in PEEPA to support the
implementation of the Government’s agenda for private participation in the delivery of
public services. Specific activities include: (i) Preparing two privatization transactions; (ii)
providing on-the-job training based on these two transactions; (iii) improving technical skills of
PEEPA staff through practical training including a secondment program to advanced sister
institutions in other countries; (iv) completing a policy for citizen economic empowerment in
privatization projects, to ensure that privatization translates into actual opportunities for domestic
businesses and investors.
7
4.2. STRATEGIC ALIGNMENT
4.2.1 The proposed technical assistance program:
Aligns with the objectives of the MIC Trust Fund. It fits fit into two of the priority
activities identified in the Revised Guidelines for the Administration and Utilization of
the Technical Assistance Fund for Middle Income Countries (ADB/BD/WP/2005/90),
namely: (i) capacity building and institutional building and (ii) promotion of the
private sector.
Serves to implement pillar I of the Bank’s Country Strategy Paper 2009-2013,
which consists in “supporting actions to expand private sector investment”. In
particular, the CSP indicates that the Bank will “influence policy reforms that focus on
promoting privatization and private-public partnerships”.
Deepens the EDSL reform program, under the component one “Promoting the
private sector as the mainstray of economic growth”. In particular, the reforms in this
component aim to promote “the development of a vibrant private sector including
privatization”.
4.3. PROJECT JUSTIFICATION
4.3.1 The proposed technical assistance will:
Support Botswana’s objective of diversification of the economy through private
sector development as stated in the National Development Plan 10 and the
Privatization Policy (Government Paper No. 1 of 2000 and Presidential directive
2009). The two transactions supported have been identified as priorities in the
Privatization Master Plan. In addition, one of the key concerns raised about the
privatizations completed so far is that they have not resulted in significant
opportunities for citizen participation. The Citizen Economic Empowerment Policy
will set out clear principles and strategies to achieve so.
Provide essential privatization skills to PEEPA through on-the-job learning on
real cases. PEEPA staff will have the opportunity to learn and apply privatization
frameworks and methodologies. In particular, PEEPA will be better equipped to
address the technical, social and political challenges to privatization.
Promote and enhance awareness of privatization and PPPs. If successfully
completed, the two transactions supported by this project, by their demonstration
effect, will help catalyze future transactions. In addition, the implementation of the
above mentioned projects will create an opportunity for PEEPA to engage more with
various stakeholders. It is hoped that the projects will stimulate general policy
dialogue as well as awareness raising on the importance and benefits of privatization
to Botswana‟s economy primarily to policy makers and relevant stakeholders involved
in decision making. The dialogue process and the transparent implementation and
delivery of the projects would help enhance trust between PEEPA and key
stakeholders.
Support the implementation of the privatization component of the reform
program of the EDSL.
8
4.4. INPUT AND ACTIVITIES
4.4.1 Activities are to be completed by three consulting firms and through a secondment plan
prepared and implemented by PEEPA.
COMPONENT A: STRATEGY FOR PRIVATE SECTOR PARTICIPATION IN BPC AND TRAINING
4.4.2 Consulting Firm A will be recruited to prepare a strategy for the involvement of the
private sector in the operations and service provision by BPC to improve efficiency and
productivity in power provision and to provide training. Because the transaction is complex
and the approval of the strategy involves extensive consultations, it is expected that the actual
tender could take place 8 months or more after the proposition of the strategy. The tender
documents are therefore not included in this project. The preparation of the strategy will involve
a thorough due diligence, a market analysis, a valuation, an assessment of investor interest, as
needed recommendations for restructuring and reforms at the company level and at the
environment level, an analysis of options for private sector involvement including a
recommendation, a roadmap for implementation of the strategy. It will also include consultations
with relevant stakeholders. The training component will aim at transferring to PEEPA the non-
sector specific skills needed to prepare strategies similar to that for BPC. It will cover all aspects
of the project cycle, from due diligence to options analysis and implementation plan
development. The method will be based on a mix of in-class training on the broad principles and
on-the-job training through direct participation of PEEPA staff in the key steps of the
assignment, with a view to apply on the development of the strategy for BPC and future project,
the knowledge acquired in class.
4.4.3 The terms of reference for Consulting Firm A are outlined in Annex IV and the key
deliverables are a report on a private sector participation strategy for BPC, and training
including training manuals.
COMPONENT B: PRIVATE SECTOR PARTICIPATION IN THE MAINTENANCE OF GOVERNMENT
BUILDINGS AND TRAINING
4.4.4 Consulting Firm B will be recruited to prepare a strategy and tender documents for
the involvement of private sector participation in the maintenance of government
buildings, schools and hospitals, and to provide training. Because this transaction is much
less complex than the BPC one (no impact on the core mandate of a line Ministry and fewer
models for risk sharing), it is expected that the strategy would be approved rapidly and that
tendering would take place a few months after the preparation of the strategy. The tender
documents are therefore part of the same assignment. It is anticipated that the privatization will
take the form of a concession, with significant upfront investment to rehabilitate the facilities.
Other options will also be considered as deemed necessary, such as for instance lease, or sale and
lease back. As for BPC, the assignment will involve a thorough due diligence, a market analysis,
a valuation, an assessment of investor and operator interest, as needed recommendations for
restructuring and reforms at the company level and at the environment level, an analysis of
options for private sector participation including a recommendation, and implementation plan. It
9
will also include consultations with relevant stakeholders. The training component will aim at
transferring to PEEPA the non-sector specific skills needed to prepare privatization strategies for
assets similar to this assignment. It will cover all aspects of the project cycle, from due diligence
to options analysis and to the recommendation of implementation plans. The method will be
based on a mix of in-class training on the broad principles and on-the-job training through direct
participation of PEEPA staff in the key steps of the assignment, with a view to apply on the
assets covered by the project the knowledge acquired in class.
4.4.5 The terms of reference of Consulting Firm B are outlined in Annex V and the key
deliverables will be the Strategy Options Report and Tender documents for the private
sector participation in the maintenance of government buildings, and training including
training manuals.
COMPONENT C: CITIZEN ECONOMIC EMPOWERMENT STRATEGY FRAMEWORK FOR
PRIVATIZATION
4.4.6 Consulting firm C will be recruited to develop a Citizen Economic Empowerment
strategy framework specific to privatization transaction, to guide the involvement of
citizens in such transactions. The CEE policy will lay out principles for providing opportunities
for domestic entrepreneurs and business arising from privatization, through amongst others
preferential participation in the privatized companies, and access to sourcing from privatized
companies. The policy will include targeting methods, conditions and guidelines to ensure that
economic benefits outweigh the costs of distortions resulting from market intervention.
4.4.7 The terms of reference for Consulting Firm C are in Annex VI and the key
deliverable is a Citizen Economic Empowerment Strategy for implementation.
COMPONENT D: SECONDMENT TO EXPERIENCED SISTER INSTITUTIONS
4.4.8 During two years, three staff will be seconded each year to experienced sister
privatization agencies in other countries, to gain first-hand exposure to the final stages of the
privatization process – bid evaluation and negotiation and the actual implementation
privatization – transfer of assets, monitoring and evaluation, regulation. The secondees will be
fully part of the teams in the host institution and directly carry out the tasks to be learnt, with
support from a mentor. PEEPA has been requested to propose a secondement program for its
staff by selecting fields of expertise to develop as well as a list of sister institutions with solid
experience in the privatization domain.
4.5. RISKS AND MITIGATION MEASURES
4.5.1 The key risks to achieving the Outcomes of the project and the mitigation measure
are outlined in the Logical Framework. Political support has so far been significant but has
mainly achieved the mild forms of privatization, and not divestitures which is the most
10
challenging type of privatization. However, recently, the budget deficit triggered by the financial
crisis has highlighted the unsustainable level of public expenditures and increased the incentive
for Government to accelerate privatization. The proposal will assist Government to accelerate
privatization, and addresses these risks through providing demonstration projects, and improving
transaction design and communication
5. COST AND FINANCIAL PLAN
5.1 The total cost of the plan is estimated at UA 632,000, financed from the MIC Trust Fund
and the Government of Botswana (GoB). It is broken down as follows:-
Table 2- Costing and Financing Plan
5.2. The cost estimate is based on an extrapolation from similar projects, including Botswana
Telecom Communication, Air Botswana and NDB.
11
6. PROCUREMENT
6.1. PROCUREMENT ARRANGEMENTS
6.1.1 The procurement in relation to the Bank‟s contribution will be undertaken in accordance
with the Bank Group's “Rules and Procedures for the Use of Consultants” (May 2008) using the
relevant Bank Standard Bidding Documents. Detailed information on the procurement
arrangement for the current project is reported in annex 9.
6.1.2 The procurement of consultancy firms will be undertaken on the basis of a short list of 6
firms prepared by the PEEPA in compliance with Bank‟s rules of procedures and approved by
the Bank. The letter of invitation, including the TORs will also be approved by the Bank before
communication to the short-listed consultants. The selection method shall be Quality and Cost-
Based Selection (QCBS) which takes into account the quality of the proposal and the cost of the
services in the selection of the successful firm. Cost as a factor of selection shall be used
judiciously. The relative weight to be given to the quality and cost shall be determined for each
case depending on the nature of the assignment. The selection process shall include the following
steps:
(a) preparation of the TOR;
(b) preparation of cost estimate and the budget;
(c) advertising requests for expression of interest;
(d) preparation of the short list of consultants;
(e) preparation and issuance of the RFP;
(f) receipt of proposals;
(g) evaluation of technical proposals: consideration of quality;
(h) public opening of financial proposals;
(i) evaluation of financial proposal;
(j) final evaluation of quality and cost; and
(k) negotiations and award of the contract to the selected firm.
6.1.3 The contribution of the Republic of Botswana covers per diem and flights for its own
staff. Audit of the project will be conducted by the firm auditing PEEPA at no additional cost.
The Bank Terms of Reference for audit will be used for the audit of the project. The procurement
in relation to the contributions of Botswana will be undertaken using the procurement rules in
place in PEEPA.
6.2. PROCUREMENT PLAN
6.2.1 As part of the preparation of the project the Recipient shall prepare and, before signature
of the Financing Agreement, furnish to the Bank for its approval, a Procurement Plan acceptable
to the Bank setting forth: (a) the particular contracts for the goods, works, and/or services
required to carry out the project during the initial period of at least 18 months; (b) the proposed
methods for procurement of such contracts that are permitted under the Financing Agreement,
and (c) the related Bank review procedures. The Recipient shall update the Procurement Plan
12
annually or as needed throughout the duration of the project. The Borrower shall implement the
Procurement Plan in the manner in which it has been granted the approval by the Bank.
7. FINANCIAL MANAGEMENT
7.1. DISBURSEMENTS
7.1.1 The disbursement of the MIC grant can be done using the following methods:
Special Account method
Direct Payment method
Reimbursement method
7.1.2 The Special Account method will be the preferred method when possible. However,
administrative and regulatory difficulties have been experienced in previous projects in
Botswana with, on the one hand, obtaining comfort letters from commercial banks and, on the
other hand, opening a special account with the Central Bank or the Treasury. Other methods of
payment will therefore be used as appropriate.
7.1.3 The direct payment method will be used when there is no constraint on the turnaround
time for payment. The reimbursement method can also be used for accelerated payment if
needed and PEEPA has the necessary liquidity.
7.1.4 All disbursements will subject to the Bank‟s disbursement rules, in particular the rules on
suspension of disbursements.
7.2. FINANCIAL REPORTING ARRANGEMENTS
7.2.1 PEEPA will maintain independent accounts for the activities financed by MIC Trust Fund
in accordance with sound international accounting practices. An annual audit will be submitted
to the Bank no later than 180 days after the end of the financial year.
7.3. LETTER OF AGREEMENT
7.3.1 Following the approval of the request by the Bank, the Bank‟s Legal Department (GECL)
will prepare a Letter of Agreement using the format provided in Annex 3 of the Guidelines for
Administration and utilization of the Technical Assistance Fund for MIC.
8. IMPLEMENTATION
8.1. EXECUTING AGENCY
8.1.1 The Public Enterprises Evaluation and Privatization Agency (PEEPA) will be the
executing agency for the project and the CEO of PEEPA will be the Project Coordinator and
will take overall responsibility for final outcome of the project. He will form a Project Team that
13
will be responsible for the implementation of project activities. The Project Team will include
senior staff from the operational departments. It will also include a staff from Finance and
Administration, responsible for administrating the procurement, disbursement and financial
management related to the project. The Project Team will be lead by a Project Team Leader from
the senior management of PEEPA.
8.2. REPORTING AND SUPERVISION
8.2.1 The Board of Directors of PEEPA will provide strategic guidance to the project, in
particular with regards to its links with other Government entities, national developments and the
industry. It will follow up the overall implementation of the project.
8.2.2 The project will be supervised for the African Development Bank by a Task Manager
appointed by the Governance, Economic and Financial Reforms Department (OSGE).
Consulting Firms will report to the Project Team Leader of PEEPA.
8.2.3 The CEO of PEEPA will be responsible for the reporting to the Board of PEEPA and to
the African Development Bank regarding progress of the project. The reports delivered by the
Consulting Firms and the secondees will be shared with the African Development Bank for Non
Objection.
8.2.4 In addition, supervisions will be undertaken by the African Development Bank at an
average frequence of 1.5 missions per year during the implementation of the project. They will
be concluded by an aide-memoire jointly prepared by the Project Coordinator and the Bank‟s
Task Manager, summarizing progress - measured against the logical framework, highlighting
key issues and setting out actions to be taken. An independent audit will be conducted at the end
of the project and a completion report will be prepared by PEEPA within 2 months after the
closing of the project.
8.3. INDICATIVE WORK PLAN
8.3.1 The project will be carried out within 30 months from the approval of the request for
financing to the MIC Trust Fund (see summary in table 2 below and detailed work plan in annex
6).
Table 2 – Work Plan
Activity
9 10 11 12
Project preparation (incl. procurement)
Privatization strategy for BPC and training
Privatization strategy and tendering documents for Government buildings and training
Policy for Citizen economic empowerment
Secondment of staff
2010 2011 2012
S1 S2 S3 S4
14
9. CONCLUSION AND RECOMMENDATION
9.1. CONCLUSION
9.1.1 Accelerating the implementation of Botswana’s Privatization Policy is critical to
diversify the economy by involving private sector participation. The successful
implementation of the Policy will boost the operations of the private sector while achieving the
objectives of improving efficiency in the delivery of services to the public, promoting both
domestic and foreign investment and the transfer of technology, assisting in deepening and
broadening the capital market, and enhancing citizen participation in the economy.
9.1.2 This project is designed to help PEEPA demonstrate results through delivering two
high priority privatizations, build core skills needed to accelerate the implementation of the
Privatization Policy. To achieve this, this project focuses on on-the-job training on actual
transactions, to complement the overall adequate academic qualifications of PEEPA staff.
9.1.3 Through the delivery of a Citizen Economic Empowerment Policy, the project will
also improve economic opportunities for Batswana in privatization projects. Future projects
will be designed to explicitly include this dimension so as to derive maximum benefits from
privatization for the domestic economy.
9.1.4 Finally, the project is an essential complement to the EDSL program, in that it
deepens one of its key components: “Promoting the private sector as the mainstray of economic
growth”. The reforms in this component aim to promote “the development of a vibrant private
sector including privatization”.
9.2. RECOMMENDATION
9.2.1 It is recommended that an amount not exceeding UA 600,000 be granted to PEEPA from
the resources of the MIC Trust Fund to undertake the project activities described hereto.
19
Annex 3 - TERMS OF REFERENCE (1) FOR
ADVISORY SERVICES FOR DEVELOPMENT OF A STRATEGY FOR
INVOLVING PRIVATE SECTOR PARTICIPATION IN BOTSWANA POWER
CORPORATION
AND PRIVATIZATION TRAINING
1 INTRODUCTION
1.1 The Ministry of Minerals Energy and Water Resources (MMEWR) of Botswana
to identify the possible options available for private sector involvement in the Botswana
Power Corporation (BPC). MMEWR has requested the Public Enterprises, Evaluation
and Privatization Agency (PEEPA), the Government‟s advisor on privatization, to carry
out the required diagnostic review.
1.2 The review will be undertaken in accordance with the objectives of the
Privatization Policy of Botswana (Government Paper No. 1 of 2000), which seeks to
improve the efficiency, productivity and competitiveness of the public sector and the
economy as a whole through enhancing the role of the private sector in the economy. The
other objective through this involvement will be to attract private investment and
technology to grow the energy sector and the economy as a whole.
1.3 The objectives of this assignment are to produce a private sector participation
strategy for BPC and deliver training based on the BPC case. In addition, PEEPA will use
this transaction as support for providing on-the-job training to PEEPA staff on core
privatization skills illustrated by the BPC case.
2 BACKGROUND
2.1 The Botswana Power Corporation (BPC) was established under the Botswana
Power Corporation (BPC) Act of 1970 to produce and supply electricity throughout
Botswana, in a commercial manner. Until the amendment of the Electricity Supply Act in
December 2007, BPC had monopoly over the provision of electricity in Botswana. The
Corporation‟s corporate objective is to facilitate sustainable and diversified development
of our country by rendering quality electrical energy services that are affordable, efficient,
safe and environmentally prudent.
2.2 BPC has a electricity generation capacity of 132MW from the coal fired
Morupule Power Station located in Palapye, 280km from Gaborone. Currently, the Power
Station contributes about 30% of the country‟s electricity requirements and it augments
the remaining 70% through imports from neighboring countries, mainly Eskom and the
Southern African Power Pool (SAPP).
20
2.3 BPC faces the challenge of ensuring that there will be adequate power supply
once its major supplier; Eskom reduces the power that it makes available to Botswana. In
addition, BPC faces challenges of attaining its commercial goals, due to low tariff rates, in
a bid to make Botswana competitive as an investment destination through the provision of
cost effective power supply.
2.4 BPC undertook a restructuring exercise, commencing in 2005, which resulted in
the unbundling of the previously vertically integrated organization into a structure of self
accounting Strategic Business Units (SBUs), to mitigate against the its challenges as well
as a step towards introducing private sector participation into BPC. The exercise was
completed in 2007. In addition, a feasibility study advising on the expansion of the Power
Station project to 1200MW was carried out in 2005 and the process to secure financing for
the project was subsequently pursued with the use of financial advisors. The project has
however, been scaled down to 600MW and is planned for completion in 2013. BPC‟s
current strategic agenda is focusing on securing power supply, financial recovery,
customer satisfaction and realizing the new SBU business model for the period 2008 to
2013.
2.5 Financially, BPC has consistently made operating losses for 3 consecutive years,
culminating with a loss of P86,8 million in 2007/8. It, however, has achieved net profit
during these years due to earnings from financial investments, which is not a sustainable
situation. Combined transmission and distribution losses are estimated at 12%, and every
1% is estimated at about P7 million loss. In addition, BPC sells electricity below the cost
of electricity imported which constitutes the bulk of power supplied to the local markets.
2.6 Other unfavorable factors include:-
a) The Increase in the cost of imports brought about by the depreciating of the Pula
against the Rand given that more than 80 percent of the national power requirements
are met through imports mainly from the Republic of South Africa.
b) Limited tariff increases due to the Government‟s quest to meet the diverse needs of
the economy.
c) A sharp increase by cost of imports especially of copper being a base metal and fuel
costs.
2.7 Under Botswana‟s Economic Diversification Strategy, the Ministry of Minerals
Energy and Water Resources has called for acceleration and expansion of utilities through
privatization or PPP of major infrastructure projects and that new power stations be built
and expansion of existing ones be carried out. In addition, there is a step towards
deregulation with MMEWR progressing the establishment of an Energy and Water
Regulator. This is in light of the various opportunities being considered in the energy
sector, including the following:-
a) Introduction of 250 MW Independent Power Producers (IPP) Projects to increase future
power supply
b) Provision of 80 MW Emergency Power Supply.
21
c) Establishment of the Westcor Project (Regional).
d) Implementation of a National Electricity Efficiency Campaign (NEEC)
2.8 Being cognizant that the Privatization Master Plan of 2005 envisaged that the
privatization of BPC should be considered after the restructuring of BPC into SBU‟s has
taken place, and given that the amendment the Energy Supply Act in 2007 now allows the
introduction of other independent power producers in the sector, MMEWR wishes to
consider possible opportunities for private sector participation in BPC, including through
various forms of privatization, that will enable it to operate and compete effectively in the
energy sector.
3 STRATEGIC OBJECTIVES
3.1 The Government strategic objectives for considering the involvement of the
private sector in BPC are:-
(i) Leveraging efficiency, increasing productivity and promoting
competitiveness through the involvement of private sectors service providers in
BPC,
(ii) Enhance the contribution of Electricity Supply Industry to the
economy by BPC serving as a catalyst and enabler to doing business in a cost
effective way and improve Botswana‟s competitiveness,
(iii) Reduce the Government‟s financial commitments and operational
involvement in undertaking and maintaining a constantly expanding energy
sector.
(iv) Enhanced investments in technology, machinery and equipment,
including modernization, in the generation, transmission, distribution and
customer service operations of BPC through innovation and cost effective
solutions
(v) Expanding the range of services and products as well as strengthening
of managerial capabilities.
4 OBJECTIVE OF THE ASSIGNMENT
4.1 The first objective of the assignment is to carry out a diagnostic study that will
assess possible opportunities and options and develop an optimal private sector
participation strategy through which the private sector can be involved in the operations of
and services provided by BPC to deliver on the Government‟s strategic options. This will
be done in line with the Privatization Policy of Botswana.
4.2 The second objective of this assignment is to provide training to PEEPA on core
privatization skills, using BPC‟s case as a support for both in-class and on-the-job
training.
22
5 SCOPE OF WORK
5.1 The scope of work for the Advisor regarding the first objective will include
carrying out a diagnostic study that will inform the possible strategy for private sector
participation in BPC and will include, but not limited to:-
5.1.1 Carrying out as due diligence review of the Electricity Supply Industry
and business of BPC, including reviews on the:-
(i) legal and regulatory aspects covering the existing laws,
regulations, policies and processes governing the Electricity Supply
Industry and BPC,
(ii) technical, condition of assets and investment aspects of BPC
(iii) operations, production capacities, products and services as well as
the institutional structures and employment status, and the environment
within which BPC operates,
(iv) financial position and performance of BPC
5.1.2 Carrying out a full market analysis, which will include demand forecasting
and competitor analysis, and an assessment of the level of investor interest in
BPC.
5.1.3 Carrying out an asset and business valuation of BPC, using whatever
techniques are appropriate for the Electricity Supply Industry.
5.1.4 From the above, identify and assess available possible options for private
sector involvement in BPC and structured value propositions of a possible private
sector participation strategy. In addition, advise on and recommend, if
necessary:-
(i) Any restructuring activities for BPC that would be necessary to
prepare it for the proposed private sector participation strategy,
(ii) reforms (legislative, regulatory, institutional, etc) that will allow
for the optimal realization of private sector participation opportunities in
BPC, using the recommended strategy,
(iii) human resource issues and recommend necessary measures that
need to be put in place to minimize negative impact on workers,
(iv) other obstacles to the prescribed private sector participation
options/strategy.
5.1.5 The Advisor will present a draft private sector participation strategy for
BPC and facilitate a stakeholder consultation workshop to be organized by the
Government of Botswana.
5.2 The training component will cover all aspects of the project cycle, from due
diligence to options analysis and to the recommendation of implementation plans for
23
privatization transactions. In order to keep the focus on principles that can be generalized
from the BPC case, the training will focus on privatization in the infrastructure sector, in
particular divestiture, outsourcing, leasing and concessions.
5.2.1 The target group of the training will be the Management Team and
analysts, which comprises 15 persons. A preliminary skills audit is attached to
allow the Consultant to prepare a detailed training plan, to be submitted with the
offer.
5.2.2 The method, to be detailed by the Advisor, will be based on a mix of in-
class training on the principles, processes and project management, and on-the-job
training through direct participation of PEEPA staff in the key steps of the
transaction, with a view to apply on BPC and future projects, the knowledge
acquired in class. It is not expected that the Consultant will produce
comprehensive educational material for the training. However, the training could
rely on books available, which would be provided as part of the services. In
addition, the consultant is expected to produce a training manual comprising the
necessary case study material, presentations and exercises.
5.2.3 The training will be concluded by an examination, personal feedback to
each participant, and an overall feedback to the CEO of PEEPA. A training report
will summarize the outcomes of the training and recommend an action plan to
further build the skills base of PEEPA staff.
6 DELIVERABLES AND TIMEFRAME
6.1 The Advisor will commence by submitting an Inception Report which will
include, amongst other things, a detailed work plan for the strategy assignment and
envisaged training activities, and findings from initial stakeholder consultations.
6.2 The assignment will take a period of 18 weeks. The deliverables and an
indicative timetable is as follows:
Deliverables Time frame
From signature
Inception Report 2 weeks
Training manual 2 weeks
Due Diligence Report 10 weeks
Asset and Business Valuation Report 10 weeks
Draft Private Sector Participation Strategy for BPC 12 weeks
Stakeholder Workshop 15 weeks
Final Privatization strategy for BPC 18 weeks
Specific training activities From week 3 to15
Training report 18 weeks
24
6.3 The timetable may be modified subject to the approval of PEEPA and MMEWR
to cater for exigencies which might be identified by the PEEPA, the Advisor or MMEWR
during the assignment
7 COMPETENCY AND EXPERTISE REQUIREMENTS
7.1 The Advisor should be capable of undertaking the assignment. In assessing the
capability of the Advisor, consideration will be given to whether:-
7.1.1 the Advisor has the resources to carry out the assignment on a timely
basis.
7.1.2 the Advisor has the relevant professional expertise and experience to carry
out the assignment, including the experience of the individual consultants of
having carried out similar assignments before and the Advisor‟s performance in
connection with those assignments.
7.2 The Advisor shall propose a sufficient team that is appropriately qualified with
relevant experience for the project to ensure quality and completion within schedule. The
Diagnostic Review requires multidisciplinary analysis. Therefore, the Advisor must
endeavor to provide the range of expertise needs to address these issues. The composition
of key disciplines for the team required for the study are summarized below, with more
details in the ITT, Clause 10.5:
NATURE OF EXPERTISE MINIMUM QUALIFICATION/EXPERIENCE
1 Power Sector Economist –
team leader
Bachelor‟s degree in relevant economics
discipline.
15 years of post-qualification experience leading
transactions and with particular experience
advising on the structuring and implementation
of private sector participation strategies in, or
privatization or concessioning of electricity
companies.
2 Electricity Operations
specialist
Bachelor‟s degree in relevant discipline.
15 years of post-qualification experience in the
operations of electricity companies and with
particular experience advising on the
privatization or private sector participation
strategies for electricity companies
3 Financial/costing expert Master‟s degree in relevant finance discipline
10 years of post qualification experience in
costing and analyzing power sector projects, as
well as carrying out financial and business
valuations.
4 Electricity Engineering Expert Bachelor‟s degree in electrical or relevant
engineering discipline .
10 years of post-qualification experience
advising on power sector projects
5 Legal expert Bachelor‟s degree in Law.
25
7.3 The consultant is free to suggest alternatives for consideration by the Client. In
addition, the Advisor is encouraged to associate with local citizen firms and/or Batswana
by way of joint venture or sub-contracting arrangements.
8 REPORTING REQUIREMENTS
8.1 The Advisor will report to the Chief Executive Officer of PEEPA as the principal
representative on this assignment and will work closely with the staff of PEEPA, the
Ministry of Minerals, Energy and Water Resources and BPC. The Chief Executive Officer
of PEEPA will serve as the principal contact for the Advisor and through whom the
Advisor will receive all necessary approvals. A Reference Committee, comprising of key
stakeholders will be established by PEEPA, as a consultative forum, to review and
monitor deliverables of the assignment.
8.2 All reports, including any advisory documents submitted to the Client by the
Advisor will be in hard copy (5 copies) as well as in soft copy on CD ROMs (5 copies).
9 TENDER SUBMISSION
9.1 A tender submission shall comprise of two separate proposals, a “technical
proposal” and a “financial proposal” which shall be submitted in separate envelopes
clearly marked as specified in Section 3 Instruction to Tender. The technical proposal
shall include only the technical requirements responding to the terms of reference and
should not include any financial information relating to the price of the assignment.
9.2 The financial proposal should provide the expected total cost of the assignment
being the aggregate of the proposed fixed fee, reimbursable expenses and a proposed
success fee.
9.3 The financial proposals may be denominated in the Botswana Pula, South African
Rand or United States Dollar, however, the contracted sum will be converted into
Botswana Pula at the prevailing Pula exchange rate (mid-rate) at the tender submission
closing date for assessment purposes (Source of exchange rate will be the Bank of
Botswana).
10 years of post-qualification experience with
experience advising on energy sector projects
and privatization or private sector participation
projects in the energy sector.
6 Human Resources and
Organization Development
Specialist
Master‟s degree in Human Resources
Management/Organization Development or
relevant discipline. 10 years of post-qualification
experience in human resources restructuring,
development and change management.
26
10 CONFIDENTIALITY
10.1 The Advisor, its sub-contractors and personnel or either of them shall not either
during the term or after the termination of or expiration of this assignment, disclose any
proprietary or confidential information relating to the services, as well as the operations of
PEEPA, MMEWR and BPC and the Botswana Government, without PEEPA‟s prior
written consent.
11 PROPRIETARY INTERESTS
11.1 Proprietary interests on all materials and documents prepared by the Advisor
under this assignment shall become and remain the property of PEEPA and the
Government and cannot be used without PEEPA‟s prior approval.
27
Annex 4 - TERMS OF REFERENCE (2) FOR
PRIVATE SECTOR PARTICIPATION IN PROVISION OF MAINTENANCE
SERVICES TO GOVERNMENT BUILDINGS
1. BACKGROUND
1.1 The Department of Building and Engineering Services (DBES), under the Ministry of
Transport and Communications is charged on the development and maintenance of all
Government buildings. An exercise carried out in 2008 found Government had a total
number of 2,299 buildings (Tables 1 and 2).
Table 1: Government building by location
Central Region 430 (18.7%)
Gaborone Region 1,032 (44.9%)
North Region 314 (13.7%)
North West Region 134 (5.8%)
South Central Region 68 (3.0%)
South Region 321 (14.0%)
Total 2,299 (100%)
Source: DBES, 2008
Table 2: Government building by type
Residential 1,520 (66.1%)
Offices 499 (21.7%)
Schools 50 (2.2%)
Hospitals 34 (1.5%)
Police Station 29 (1.3%)
Colleges / Universities 27 (1.2%)
Other Types 140 (5.2%)
Total 2,299 (100%)
Source: DBES, 2008
1.2 Although hospitals (1.5%), schools (2.2%) and colleges/universities (1.2%) constituted a
small percentage of the overall figure, their maintenance requirements need substantial
budgets to support the size of the buildings and sophistication of technology involved
which supports business / public services.
1.3 The industry norm is that the average life cycle of a building is 25 years. After this a
revamp of the building is required to address refurbishment of structure and replacement
of hard service infrastructure. Buildings in the Central Region were found to have as
average 29 years old and as a result were viewed to be more problematic in terms of
condition of hard services. While this indicated a majority of the recorded buildings were
28
at an “established” stage and fast approaching or already at a stage where major repairs
and refurbishments are required to address maintenance and up keep, it was noticed that
one fifth of the buildings were 25 years or older. Maintenance regimes and plans are very
reactive and did not address future life cycle maintenance management. Also notice was
that in some regions that hard service infrastructure within 7 years and younger (“newer”)
are in a very poor - very bad state of repair. Also in other limited cases Secondary
Schools buildings had been vandalized and in a dilapidated state totally unfit for
occupation or use.
1.4 Maintenance, of which 89.4% is provided in-house by DBES staff, is budgeted at head
office for the annual cycle and is based on escalating the budget from the previous year
by an economic indicator and therefore falls short of addressing current maintenance
requirements, backlog of maintenance from previous cycles and emergency maintenance
contingencies. Maintenance is seen as non-core and therefore is seldom seen as an
important aspect when budgeting and forecasting. In addition, infrastructure is not
unattended to despite numerous requests from users due logistical and resourcing issues
and a lack of urgency to respond to calls or prioritize these maintenance requests.
1.5 As a result of limited cyclical maintenance, exacerbated by insufficient budgetary
allocations, limited human resources capacity at DBES and in-availability of spares and
training to repair sophisticated and specialised infrastructure equipment, a majority of
Government buildings have lacked civil maintenance and in some, conditions have
deteriorated to critical levels. Vandalism and abuse of structures has rendered many
buildings unsuitable for occupation and no measures are in place to curb such abuse.
DBES is in urgent need to improve and accelerate maintenance of Government buildings
to ensure it offers promptly reliable infrastructure accommodation. It requires to develop
and implement a more cost effective and efficient maintenance delivery methods,
involving private sector service providers, that will ensure infrastructure sustainability, as
a way of improving service delivery..
2. OBJECTIVE
2.1 The purpose of the assignment is to procure transaction advisory services to advise on
how best to structure Government buildings‟ maintenance delivery services and on the
selection of the private sector service provider to deliver suitable infrastructure
accommodation. Specific objectives of the assignment are to:
i) develop the most suitable and cost method that will support DBES in delivery of
maintenance services.
ii) procure a private sector service provider to deliver the maintenance in the most
efficient manner.
iii) Provide capacity build staff to project manage the structuring, development and
monitoring of private sector services delivery projects.
29
2.2 The assignment will be carried out in accordance with the Government of Botswana‟s
Privatization Policy which seeks to improve the efficiency, productivity and
competitiveness in delivery public sector infrastructure and services through the
involvement of the private sector.
3. TASKS
3.1. The Transaction Advisor will be required to:-
3.1.1. Undertake a comprehensive feasibility study or business case assessment and
recommend the most efficient and cost effective solution for delivery of the
maintenance services. This will include a project due diligence, a solutions
options analysis that takes into consideration technical, legal and financial issues
associated with project, an assessment of the availability and capabilities of the
private sector to deliver, relevant business valuations and NPVs including
development of a public sector comparator, and development of optimal private
sector delivery solution/option.
3.1.2. Undertake a risk assessment of all risk associated with the project, their
quantification and how the risks should be allocated to the parties that will best
manage/mitigate them.
3.1.3. Based on the above, develop a suitable delivery structure for the recommended
maintenance delivery option including innovative operational efficiencies that
may realistically be expected of the private sector party, the risk allocation,
project cost, payment and penalty mechanism. All assumptions must be clearly
stated.
3.1.4. Prepare a Project Implementation Plan
3.1.5. Prepare bidding documents including, amongst others, the scope of requisite
output specifications and expected service delivery standards, compliance
requirement, payment mechanism and a penalty deduction system and PPP or any
other contract to be signed for delivery of the project and relevant service level
agreements. The will be developed in accordance the Public Procurement and
Asset Disposal Board regulations.
3.1.6. Administer bidding process including preparation of a data room, arrange
necessary structured pre-bidding conferences and meetings, manage bidder
clarification and feedback, and manage evaluation process
3.1.7. Facilitate contract negotiations (commercial and legal), award and signing, and
financial closure
3.1.8. Develop Contract Management, Communication and Stakeholder Relationship
Plans and facilitate monitoring of project.
30
3.2. The Transaction Advisor will be required to develop and implement a training plan that
covers all technical and management aspects of the assignment, to ensure capacity
building of staff within PEEPA and DBES, to enable these entities acquire skills that can
adequately structure, monitor and manage similar future assignments
4. DELIVERABLES AND DURATION OF THE ASSIGNMENT
4.1. The Advisor will commence by submitting an Inception Report which will include,
amongst other things, a detailed work plan for the strategy assignment and envisaged
training activities, and findings from initial stakeholder consultations. The deliverables
will include the following:-
(i) An Inception Report,
(ii) Training Manual
(iii) A Feasibility Study and Risk Assessment Report on Government Building
Maintenance
(iv) Maintenance Delivery Options Report and Implementation Plan
(v) An Tender Documents and Relevant contracts,
(vi) Reports on of Pre-qualification, Bidding and Negotiation processes
(vii) Contract Management, Communication and Stakeholder Relationship Plans
(viii) Contract Completion Report
4.2. The assignment will take a period of 6 months. The indicative timetable for submission
of the deliverables by the Advisor is as follows:-
Deliverables Time frame
From signature
Inception Report 2 weeks
Training manual 2 weeks
Feasibility Study and Risk Assessment Reports 10 weeks
Options Report and Implementation Plan 12 weeks
Stakeholder Workshop 14 weeks
Tender documents and Contracts 20 weeks
Prequalification Report 26 weeks
Bidding Process Report 38 weeks
Negotiations Report 44 weeks
Contract Management, Communication and Stakeholder
Relationship Plans
48 weeks
Specific training activities From week 3 to48
Contract Completion and Training reports 52 weeks
31
4.3. The timetable may be modified subject to the approval of PEEPA and DBES to cater for
exigencies which might be identified by the PEEPA, the Advisor or the Ministry during
the assignment
5. COMPETENCY AND EXPERTISE
5.1. The Transaction Advisor should comprise a team, managed by a single Lead Advisor
who should have relevant experiences of leading a similar assignment.
5.1.1. The skills and experience required in the transaction advisory team are as
follows:-
Engineering with project management qualification as well as relevant
project structuring and contract management expertise,
Financial analysis, with relevant corporate or project finance structuring
experience;
Engineering with specific in infrastructure management, maintenance and
monitoring,
Legal, with relevant experience in risk allocation, contract drafting and
negotiations.
5.1.2. The Lead Advisor will be held accountable, in terms of the Contract, for ensuring
project deliverables and the professional conduct and integrity of the team.
5.1.3. The Transaction Advisor is free to suggest alternatives for consideration by the
Client. In addition, the Advisor is encouraged to associate with local citizen firms
and/or Batswana by way of joint venture or sub-contracting arrangements.
6. REPORTING REQUIREMENTS
6.1. The Advisor will report to the Chief Executive Officer of PEEPA as the principal
representative on this assignment and will work closely with the staff of PEEPA, the
DBES and the Ministry of Transport and Communications. The Chief Executive Officer
of PEEPA will serve as the principal contact for the Advisor and through whom the
Advisor will receive all necessary approvals. A Reference Committee, comprising of key
stakeholders will be established by PEEPA, as a consultative forum, to review and
monitor deliverables of the assignment.
6.2. All reports, including any advisory documents submitted to the Client by the Advisor will
be in hard copy (5 copies) as well as in soft copy on CD ROMs (5 copies).
7. TENDER SUBMISSION
7.1. A tender submission shall comprise of two separate proposals, a “technical proposal” and
a “financial proposal” which shall be submitted in separate envelopes clearly marked as
specified in Section 3 Instruction to Tender. The technical proposal shall include only
32
the technical requirements responding to the terms of reference and should not include
any financial information relating to the price of the assignment.
7.2. The financial proposal should provide the expected total cost of the assignment being the
aggregate of the proposed fixed fee, reimbursable expenses and a proposed success fee.
7.3. The financial proposals may be denominated in the Botswana Pula, South African Rand
or United States Dollar, however, the contracted sum will be converted into Botswana
Pula at the prevailing Pula exchange rate (mid-rate) at the tender submission closing date
for assessment purposes (Source of exchange rate will be the Bank of Botswana).
8. CONFIDENTIALITY
8.1. The Advisor, its sub-contractors and personnel or either of them shall not either during
the term or after the termination of or expiration of this assignment, disclose any
proprietary or confidential information relating to the services, as well as the operations
of PEEPA, DBES, the Ministry of Transport and Communications and the Botswana
Government, without PEEPA‟s prior written consent.
9. PROPRIETARY INTERESTS
9.1. Proprietary interests on all materials and documents prepared by the Advisor under this
assignment shall become and remain the property of PEEPA and the Government and
cannot be used without PEEPA‟s prior approval.
33
Annex 5 - TERMS OF REFERENCE (3) FOR
CONSULTANCY SERVICE FOR THE FORMULATION OF A STRATEGY AND
POLICY TO ENHANCE CITIZEN ECONOMIC EMPOWERMENT THROUGH
PRIVATIZATION
1. BACKGROUND
1.1. One of the key objectives the Privatization Policy for Botswana (Government Paper no. 1 of
2000) is to promote the participation of citizens in the economy by increasing the opportunities
for Batswana to own productive assets arising from the privatization program. This is in line with
the Government‟s high level long term vision strategy (Vision 2016) through which it has
committed itself to finding “concrete strategies to ensure citizen empowerment and to maximize
the participation of citizen owned companies in the economy”.
1.2. The Privatization Policy for Botswana highlights the main measures that will be used to empower
citizens during the process of privatization. These include:
(i) Promoting share-holding by citizens in share offerings of public enterprises
(ii) Using pension and other funds (e.g. unit trusts) to buy shares for the benefit of
members, special access to shares by management and employees of privatised
entities
(iii) Provide special advice and assistance in organising employee and management
buy-outs.
(iv) Educating Batswana on how to empower themselves through training and
development of managerial and entrepreneurial skills.
1.3. To encourage citizen participation in share ownership, Government has already committed itself
to several policy initiatives which are set out in the Privatization Policy, for Botswana, including:
(i) The size of the share purchases required to participate in IPOs will be low enough
to attract as many citizen buyers as commercially feasible
(ii) The Government will set up an Investment Trust Fund to purchase a certain
percentage of shares of privatised enterprises on behalf of citizens
(iii) The Government will extend the Small, Medium and Micro Enterprises (SMME)
or its successor CEDA “credit scheme” to small citizen investors to facilitate
citizen ownership of privatised enterprises
(iv) The management buy-outs as means of transferring ownership to management and
employees will be encouraged
(v) Appropriate technical assistance and training arrangements will be provided to
management and employees for implementing buy-out transactions
(vi) Existing empowerment schemes will be reviewed and used to enable citizen
participation in ownership of shares of privatised entities
1.4. To ensure accelerated deal flow as well as for PEEPA effectively deliver on its mandate of
advising and leading implementation of transactions, there is need to, amongst other things,
develop a Citizen Economic Empowerment Strategy Framework that will identify new measures
and initiatives to guide empowerment within the ambit of the Privatization Policy, as well as
34
provide guidelines to guide the approach and manner of facilitating meaningful participation of
citizens in privatization transactions.
2. OVERALL OBJECTIVE
2.1. Develop a comprehensive citizen economic empowerment strategy and guidelines to be used and
applied during the privatization transaction process, which be carried out through the divestiture
of public entities and assets, public service contracting out initiatives as well as in the provision
of infrastructure and services by means of public private partnership methods.
3. SCOPE OF WORK
3.1. To ensure citizen participation of in privatization transactions on a sustainable basis, the Expert is
required, but not limited to:
(i) Review the existing policy environment for citizen economic empowerment
through privatization, identify and recommend changes to the current support
policies and measures as well as recommend new measures to achieve the
objectives of citizen empowerment as it relates to privatization.
(ii) Develop entrepreneurial development principals, methods and guidelines that will
result in successful citizen businesses and broaden the ownership base through
privatization. These should include empowerment mechanism for employees of
public enterprises that are to be privatised and staff of Government departments
whose services will be contracted out, such management and employee buy-outs,
ESOPs and participation of employees in public services which have/are to be
contracted out. The guidelines should include any prerequisites including capacity
initiatives that will be require that would be required to give effect to the
recommended methods.
(iii) Design investment vehicles that are attractive and affordable to the general public
to encourage wider participation by the public and broaden ownership of
companies by citizens. This will include review of the initiatives which are
highlighted in the Privatization Policy to encourage citizen participation and
empowerment.
(iv) Structure and recommend financing strategies for supporting empowerment
transactions following a review of the existing procurement requirements as well
as financing institutions and Government empowerment schemes and programs.
(v) Make recommendations on training, skills development and transfer programs for
the private sector, which may be deemed necessary to support privatization, as
well as a mentorship program that will be required to ensure the success of citizen
businesses after privatization. Identify opportunities for technical assistance to
finance training and workshop costs for capacity building of citizen investors.
(vi) Recommend necessary employee support programs and a social safety net to be
implemented during privatization.
(vii) Develop an advocacy for citizen economic empowerment that will strengthen
and/or integrate business associations and organisations as well as to build
capacity amongst communities and civil society structures
35
3.2. Based on the above the Expert will develop and present a draft strategy framework report laying
out the principals for providing opportunities for citizens and citizen entreprenuers and businesses
participation during privatization as well as conditions and guidelines to ensure that the economic
benefits outweigh the cost of distortion resulting from this market intervention.
4. DELIVERABLES AND TIMEFRAME
4.1. The Expert will commence by submitting an Inception Report which will include findings from
initial stakeholder consultations and detailed work plan for the strategy assignment. The
deliverables will include the following:-
(ix) An Inception Report,
(x) A Draft Citizen Economic Empowerment Report
(xi) A final Citizen Economic Empowerment Report
4.2. The assignment will take a period of 12 weeks. The indicative timetable for submission of the
deliverables by the Advisor is as follows:-
Deliverables Time frame
From signature
Inception Report 2 weeks
Draft Citizen Economic Empowerment Report 8 weeks
Stakeholder Workshop 10 weeks
Final Citizen Economic Empowerment Report 12 weeks
4.3. The timetable may be modified subject to the approval of PEEPA to cater for exigencies which
might be identified by the PEEPA and the Expert during the assignment
5. COMPETENCY AND EXPERTISE REQUIREMENTS
5.1. Masters degree is required, preferably in business administration or private sector development
with a minimum of ten years of relevant experience in formulating similar citizen empowerment
policies or strategies and guidelines, private sector review and analysis and private sector capacity
building. Experience in privatization and project management in the Africa region is an added
advantage.
6. REPORTING REQUIREMENTS
6.1. The Expert will report to the Chief Executive Officer of PEEPA as the principal representative on
this assignment and will work closely with the staff of PEEPA. The Chief Executive Officer of
PEEPA will serve as the principal contact for the Advisor and through whom the Advisor will
receive all necessary approvals. A Reference Committee, comprising of key stakeholders will be
established by PEEPA, as a consultative forum, to review and monitor deliverables of the
assignment.
36
6.2. All reports, including any advisory documents submitted to the Client by the Advisor will be in
hard copy (5 copies) as well as in soft copy on CD ROMs (5 copies).
7. TENDER SUBMISSION
7.1. A tender submission shall comprise of two separate proposals, a “technical proposal” and a
“financial proposal” which shall be submitted in separate envelopes clearly marked as specified
in Section 3 Instruction to Tender. The technical proposal shall include only the technical
requirements responding to the terms of reference and should not include any financial
information relating to the price of the assignment.
7.2. The financial proposal should provide the expected total cost of the assignment being the
aggregate of the proposed fixed fee, reimbursable expenses and a proposed success fee.
7.3. The financial proposals may be denominated in the Botswana Pula, South African Rand or United
States Dollar, however, the contracted sum will be converted into Botswana Pula at the prevailing
Pula exchange rate (mid-rate) at the tender submission closing date for assessment purposes
(Source of exchange rate will be the Bank of Botswana).
8. CONFIDENTIALITY
8.1. The Advisor, its sub-contractors and personnel or either of them shall not either during the term
or after the termination of or expiration of this assignment, disclose any proprietary or
confidential information relating to the services, as well as the operations of PEEPA and the
Botswana Government, without PEEPA‟s prior written consent.
9. PROPRIETARY INTERESTS
9.1. Proprietary interests on all materials and documents prepared by the Advisor under this
assignment shall become and remain the property of PEEPA and the Government and cannot be
used without PEEPA‟s prior approval.
37
Annex 6 – DETAILED WORK PLAN (INDICATIVE)
Activity Who
9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Project preparation (incl. procurement)
Submission to AfDB Board and Approval PEEPA / AfDB
Tendering for consulting firms A, B and C PEEPA
Final selection of consulting firms A, B and C PEEPA / AfDB
Privatization strategy for BPC and training
Inception report Consulting firm A
Due diligence and training Consulting firm A
Asset and Business Valuation and training Consulting firm A
Options analysis Consulting firm A
Stakeholder Workshop Consulting firm A
Final privatization strategy Consulting firm A
Training on due diligence and options analysis for infrastructure companies Consulting firm A
Privatization strategy and tendering documents for Government buildings, schools and hospitals and training
Inception report Consulting firm B
Due diligence and training Consulting firm B
Asset and Business Valuation and training Consulting firm B
Options analysis Consulting firm B
Stakeholder Workshop Consulting firm B
Final privatization strategy Consulting firm B
Evaluation of the strategy by Cabinet Govt Botswana
Preparation of tender documents Consulting firm B
Request for proposal Consulting firm B
Evaluation of offers Consulting firm B
Training on due diligence, options analysis, tendering for public buildings Consulting firm B
Policy for Citizen economic empowerment
Inception report Consulting firm C
Diagnostic Consulting firm C
Interim report Consulting firm C
Preparation of draft report and first draft law for citizen economic empowerment Consulting firm C
Consultative workshop Consulting firm C
Preparation of final report and final draft law for citizen economic empowerment Consulting firm C
Secondment of staff
Implementation of the secondment program PEEPA
2010 2011 2012
39
Annex 8 - Preliminary skills audit (Summary)
Preliminary skills audit - Summary
Years of
experience with
PEEPA
Total years of
experience in
the private
sector
Total years of
experience in
the public
sector
(excluding
PEEPA and
parastatal)
Total years of
experience in a
parastatal
(excluding
PEEPA)
Years of
experience in
Privatisation
outside
PEEPA[1]
Total years
of
experience
All inclusive
Management
Total years of experience 20 19 36 70 19
Average years of experience 3 2 5 9 2 18
Operations staff (excluding corporate services)
Total years of experience 11 24 0 19 1
Average years of experience 2 3 0 3 0 8
40
Annex 9 - Preliminary skills audit (Detailed Table) Department Highest degrees First Degree, diploma or
certificate
Years of
experience with
PEEPA
Total years of
experience in
the private
sector
Total years of
experience in
the public
sector
(excluding
PEEPA and
parastatal)
Total years of
experience in a
parastatal
(excluding
PEEPA)
Years of
experience in
Privatisation
outside
PEEPA[1]
1
Deputy CEO MBA B.Com (Accounting, Finance
& Mgt) 2.5 0 0 20 0
Core DepartmentsPrivatisation and
Restructuring
2 Manager MBA BCom (Finance) 8 6 13 6
3
Manager MBA Financial Mgt
Doctorate: Fin Dev, Fin
Structure & Economic
Growth
BA Economics & Stats
1.5 0 1 14 0
Performance Monitoring
4
Head, MSc Economics & Finance BA Economics; PGD
Economics 7 0 0 6 1
5
Manager BA Economics & Industrial
Psychology 1 1 0 15 2
Public Services Outsourcing
6 Head MBA BSc Physics 0.5 13 24 10
7
Manager MBA Business Finance &
Administrative Studies
BCom Accounting & Mgt
1 4.5 5 10
8
Manager MBA Supply Chain Mg) BCom; Graduate PGD
Purchasing & Supply 1 0 12
Analyst
9
Analyst 1 MCom Economics BCom (Honours) Economics;
BA Social Sciences (Econ &
Stats) 3 0 13 0
10
Analyst 2 BA Business Science (Finance
& Economics) 2.5 2 0 0
11
Analyst 3 ) BSc Finance (Economics &
Risk Mgt 0.5 3 0 1
12
Analyst 4 BBA Marketing ,PGD
Purchasing & Supply 1.5 4 0 1 0
13
Analyst 5 Masters Electronic &
Computer Engineering
BEng (Hons) Computer
Engineering; Prince2
Practitioner 1.5 5 0 0
14
Analyst 6 CIMA BCom Business Systems
Implementation & Electronic
Commerce Mgt 1 5 0 3
15
Analyst 7 Advanced Diploma in
Computers, Certificate in
Project Mgt & Business Mgt 1 5 0 1.5 0
Corporate Services
Departments
16 Manager, IT MBA BSc Computer Science 1.5 8 2 0
17
Database & Network
Administrator
Advanced Diploma
Computer Studies 1 6 0 0
18
Manager, Information
Resource Centre
Master s Library & Info
Studies
BA Humanities; PGD in
Library & Info Studies 6 1 11 0
19
Library & Records Officer Diploma in Library & Info
Studies 4 0 10 0
20
Manager, HR Masters Organizational &
Clinical Psychology
Bsc Psychology
2.5 2 2 5 0
21 HR Practitioner BA Humanities 0 1 2 0 0
22
Manager, Finance &
Administration
ACCA BCom Accounting
2 3 5 11 0
23
Assistant Manager, Finance
& Administration
CIMA AAT
2 1.5 1.5 0
24 Accounts Officer AAT 2 5 0 0
25
Principal Communications
Manager
Masters Mass
Communications
BA Social Work
0.5 2 5 11
26
Manager, Communications
& Public Education
BA in Visual Comms(Fine
Arts) 2 9 1
27 General Corporate Counsel Masters Law LLB 0 0.5 15 0.5 0
28 Administration Officer 0 0 7 0 1 4 0
29 Divisional Secretary1 Diploma in Secretarial 5 6 7 0
30 Divisional Secretary2 Diploma in Secretarial 4 9 0 0
31 Divisional Secretary3 Adv. Certificate Secretarial 1.5 0 17 0
32 Receptionist 0 0 2 8 0 0
33
Office
Assistant/Driver/Messenger
0 0
1.5 3 0 0
[1] Years experience in privatization, outsourcing or PPP outside of PEEPA (either on the private sector side, in projects and operations involving a privatized company, outsourcing or a PPP, or on the public side, for instance regulating a PPP or implementing a privatization)
41
Annex 10 - Project Procurement Arrangements
Project Categories
ICB NCB Other* Short List Non-Bank-
Funded
Total
1. Goods N/A N/A N/A N/A N/A N/A
2. Service Contracts N/A N/A N/A N/A N/A N/A
2.1 publications
3. Consulting Services N/A N/A N/A N/A N/A N/A
3.1 Studies and Engineering N/A N/A N/A N/A N/A N/A
3.2 Technical Assistance
Privatization strategy for BPC and training 260,000 260,000
Privatization strategy and tendering documents for
Government buildings, schools and hospitals and training
160,000 160,000
Policy for Citizen economic empowerment 60,000 60,000
Secondment of staff to an experienced sister privatization
agency 76,000 32,000
108,000
4. Training
5. Miscellaneous 44,000 44,000
TOTAL 0 0 120,000 480,000 32,000 632,000
* Other may be National Shopping, Direct Purchase.
Figures in italic are amounts financed by the Bank Group.
[ in UA]
42
Annex 11 - Privatization transactions’ status
TRANSACTIONS COMPLETED AT PEEPA LEVEL
Transactions Update
1. Privatization of Air
Botswana
Structuring of transaction and negotiations with a potential equity partner were
completed in June 2007, however, Government decided to recapitalize and
restructure the company first before further consideration of its privatization.
2. Botswana Vaccine
Institute
Process, which was intended to raise funding for the expansion of the vaccine
making facility, involved issuing of redeemable preference shares worth P50m; bond
issue of P70m; term debt of P15m, all of which was completed end of 2008
3. GEMVAS and
GLIF
Structuring and completion of transaction that offered the administration of
GEMVAS, an insurance scheme to the private sector was completed in December
2009.
4. Strategy For
National Development
Bank (NDB)
Development of privatization strategy that includes a transaction structure and
implementation plan to guide in the privatization of the National Development Bank
(NDB) was completed and submitted to Government for consideration in October
2009
5. Office
Accommodation for
Office of the
Ombudsman and Land
Tribunal
The PPP Project was completed by the private sector partner and handed over, for
Government use, in February 2008
TRANSACTIONS ON-GOING
Transactions Update
6. Privatization of
Botswana Telecom
Corporation (BTC)
A transaction structure has been approved in May 2010. Implementation timelines
envisage completion of transaction during 2011/12.
7. Privatization Of
Banyana Pty Limited
(BPL)
Government approved, in April 2009, the restructuring of BPL, which involves the
privatization, via leasing, of 97,000hectares of the Ranch to commercial farmers to
obtain value from the Ranch and BPL retaining 52,000hectares to operate its
ranching mandate. A feasibility assessment and development of leasing structures
were completed in March 2010, for Government consideration. Implementation is
envisaged to be completed during 2010/2011
8. Privatization of
Seed Production
Development of a strategy for the privatization of the seed production function in the
Department of Agricultural Research was completed in April 2010. Implementation
is envisaged to be completed during 2011/2012.
9. Serviced Office
Accommodation
for: Environment,
Wildlife &Tourism
and Lands &
Housing (MLH)
Transaction structuring and negotiations for the award of a concession to a private
sector service provider, was completed in December 2008. However, due to costs
concerns by Government, the project scope is being reviewed, for possible re-
negotiation or re-tendering.
10. Botswana
International
University Of
Science &
Technology
The project comprises of the design, financing and implementation of the best option
involving the private sector in the delivery of the BIUST campus infrastructure. The
tender process for securing a private sector service provider(s) is on-going and
financial closure is envisaged in the fourth quarter of 2010/11.
11. Outsourcing of the
Management of
Government Fleet
by Central
Transport
Organisation (CTO)
A diagnostic review to advise on the most cost effective and efficient option for the
provision of vehicle fleet management services to Government Ministries and its
departments, currently being provided by the Central Transport Organisation (CTO)
was completed in April 2008. Recommendations are being processed for
consideration by Government.
12. Outsourcing of Fuel
Operations for CTO
Vehicles
An assessment that will recommend an optimal solution for provision of fuel to
Government vehicles more efficiently is to be completed during 2010/11.
13. BMC Pre-
Feasibility Review.
A pre-feasibility review to advise on the readiness of BMC‟s privatization, is at an
advanced stage.
Source: PEEPA
43
Annex 12 - Botswana – African Development Bank active portfolio
Annex I: Ongoing Projects as at 31
March 2010
Pandamatenga Agirculture
Infrastructure Project ADB 2008 38.6
MIC capacity Building for the Ministry
of Agriculture MIC 2007 0.29
AWF-Watercontrol and Management
system AWF 2007 1.08
Economic Diversif ication Support
Loan ADB 2009 949.19
MIC-Corporate Governance Code MIC 2007 0.15
Institutional strengthening of local
authorities MIC 2008 0.28
Vision 2016 MIC 2008 0.25
Support for Education Quality MIC 2010 0.6
Kanzangula Bridge (Multinational) MIC 2007 0.6
Kanzangula Bridge (Multinational) IPPF 2006 1.45
Morupule"B" Pow er Transmission
Project ADB 2009 139.9
Solar Energy Project MIC 2009 0.6
Total 1,132.99
Project Title Window
Approved
Amount
(MillionUA)
Year
approved
44
Annex 13 - Botswana - Country Profile
Africa
Year Value
Social
Population, mid-year (millions) 2008 1.9 986 5523
Population growth (annual) (%) 2008 1.5 2.3 1.4
GNI per capita (Atlas method, US$) 2008 6,470 1,428 2,405
Urban population (% of total population) 2008 60.0 39.1 44.2
Life expectancy at birth (years) 2008 54.4 54.5 65.7
Infant mortality (per 1,000 live births) 2008 36.5 83.9 53.1
Child malnutrition (% of children under 5) 2004 5.9 130.2 80.8
Access to an improved water source (% of population) 2006 96.0 68.0 62.0
Illiteracy (% of population age 15+) 2007 82.9 38.0 21.0
Gross primary enrollment (% of school-age population)
Male 2005 107.5 101.7 112.0
Female 2005 106.0 92.1 103.0
Human Development Index 2007 0.694 0.514 0.679
Macroeconomic indicators 1990 2000 2006 2007 2008
GDP (US$ billions) 3.4 5.6 11.3 12.3 13.4
Real GDP Growth Rate (%) 5.5 4.1 5.1 4.4 2.8
Real Per Capita GDP Growth Rate (%) 2.5 2.3 3.7 2.9 1.3
Gross capital formation (% of GDP) 38.8 31.8 24.0 25.9 32.6
Gross national savings (% of GDP) 48.6 38.9 48.2 49.1 51.4
Inflation (%) 11.0 8.5 11.6 7.1 12.6
Growth of Money Supply, M2 (%) -14.0 1.4 67.4 31.2 21.1
Export Growth of Goods, volume (%) 11.4 2.3 2.5 5.0 -15.1
Import Growth of Goods, volume (%) -13.1 -8.1 -4.7 24.6 11.4
Terms of Trade (%) -29.8 -4.4 -2.9 0.2 -1.2
Debt Service (% of Exports of G&S) 11.6 18.5 16.8 16.6 7.2
Current Account (% of GDP) -0.5 9.7 17.2 14.3 7.0
Total external debt (% of GDP) 18.6 42.2 12.5 10.2 9.3
Average exchange rate (National Currency Per US $) 1.860 5.102 5.837 6.139 6.827
Reserves including gold (US$ millions) 3,331.5 6,318.2 7,992.4 9,789.7 9,118.6
Reserves (months of imports of goods & services) 20.1 32.6 27.7 26.3 19.4
STRUCTURE of the ECONOMY
By sector (% of GDP)
Agriculture 4.9 2.4 1.8 1.7 1.8
Industry 61.2 52.8 48.8 49.1 49.6
Manufacturing 5.2 4.4 3.3 3.2 3.2
Services 33.9 44.8 49.4 49.2 48.6
By sector (Annual growth rate)
Agriculture 3.6 -11.5 -1.2 1.1 1.1
Industry 0.3 10.8 -1.5 4.7 4.7
Manufacturing 4.8 3.5 -0.9 -0.9 -0.8
Services 15.9 4.5 7.5 5.9 4.2
Botswana
Botswana - Country Profile
Most Recent Year
Developing countries
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
2000
2001
2002
2003
2004
2005
2006
2007
2008
GNI Per Capita, Current US $
Botswana Africa
45 50 55
2000
2001
2002
2003
2004
2005
2006
2007
2008
Life Expectancy at Birth (Years)
0.0
1.0
2.0
3.04.0
5.0
6.0
7.08.0
9.010.0
2000
2001
2002
2003
2004
2005
2006
2007
2008
Real GDP Growth Rates, (%)
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
2000
2001
2002
2003
2004
2005
2006
2007
2008
CPI, Inflation, (%)