BoQ for Construction of Yudhiri Bailey Bridge - mowhs.gov.bt · PDF fileto be used for the...

17
Name of work : Construction of Yudhiri Bridge DDR 180 ft span and 3.277 mtrs Carriage way Location : On Trashigang - Phongmey Gewog Center Road Regional Office, Department of Roads, Trashigang SN Type of work Total Cost (Nu) 1 Method of Measurement and Site Installation 2 Earthwork 3 PCC, RCC, Formworks and Other Involved Works 4 Bailey bridge superstructure 5 RCC wall along river bank 6 approach road, B/wall & Drain Total Cost Amount in Words: Ngultrums Signature of the Bidder: ____________________________________ Name of Bidder: ________________________________________________ Summary of Cost Page 1

Transcript of BoQ for Construction of Yudhiri Bailey Bridge - mowhs.gov.bt · PDF fileto be used for the...

Name of work : Construction of Yudhiri Bridge DDR 180 ft span and 3.277 mtrs Carriage way

Location : On Trashigang - Phongmey Gewog Center RoadRegional Office, Department of Roads, Trashigang

SN Type of work Total Cost (Nu)

1 Method of Measurement and Site Installation

2 Earthwork

3 PCC, RCC, Formworks and Other Involved Works

4 Bailey bridge superstructure

5 RCC wall along river bank

6 approach road, B/wall & Drain

Total Cost

Amount in Words: Ngultrums

Signature of the Bidder: ____________________________________

Name of Bidder: ________________________________________________

Summary of Cost

Page 1

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

1 1001 Method of Measurement:

2 1001.1 Description:

The descriptions identify the work covered by

the respective items, but the exact nature and

extent of the work is to be ascertained from the

Drawings & Specifications.

3 1001.2 Quantities

4

The quantities shall be computed net using

dimensions from the drawing, unless directed

otherwise by the client's site engineer. No

allowance shall be made for bulking, shrinkage

or waste. No other type, terms or regulation for

computing the quantities will be used and

accepted. For any kind of work and item, the net

dimension will be used for computing the

quantities. Quantities may be rounded up or

down where appropriate. Fractional quantities

are not generally necessary and should not be

given to more than two places of decimals.

5 1001.3 Unit of measurement

6The following units of measurement and

abbreviations shall be used.

7

Unit & Abbreviation:

Millimetre = mm

Metre = m

Square millimetre = mm²

Square metre = m²

Cubic metre = m³

Kilogramme = kg

Tonne = t

Sum = sum

Number = No.

Hour = hr.

8 1002Site Installation: (facilities, tools, plant,

equipment etc)

9 1002.1

For all items, the relevant enclosed drawings

are an integral part of this bill of quantities. The

contractor shall prepare and submit site

installation plan for strict implementation at

site.

Type of Work: 1000 - Method of Measurement and Site Installation

SN Code Description of item Unit Quantity

Site Installation Page: 1 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of Work: 1000 - Method of Measurement and Site Installation

SN Code Description of item Unit Quantity

10 1002.2

The contractor shall be deemed to have fully

acquainted himself with the full nature of work,

the location and character of the site and means

of access to the site including any traffic

restrictions imposed.

11 1002.3

All tools and plants described and mentioned in

the various chapters shall be included either in

the site installation costs or in the item rates. No

additional costs will be paid.

12 1002.4

Infrastructure at bridge site, access roads,

contractor's yard, construction site, laborers camp

and so forth.

13 1002.5

All necessary accommodations like stores,

workshops, etc. required for proper execution of

works shall be provided, built, maintained and

removed by the contractor at his own cost and

within the working time period. The following

points are important to be fulfilled:

14a) all necessary safety measures and efforts to

avoid accidents and damages to the property.

15

b) sufficient labour camp with properly

maintained sanitary facilities, drinking water and

supply of electricity (if available).

16c) proper waste management at site and labour

camp.

17d) construction materials to be deposited and

stored well under shed.

18

e) a temporary drainage system at the site. The

contractor shall build no infrastructure without

prior approval by the client. The client shall

inspect the contractor's site infrastructure and

give instructions. These instructions are binding

and shall be strictly implemented by the

contractor.

19

f) The contractor shall make his own connections

for water and electricity supply and energy, if

any, and pay for it.

20

g) The Contractor cannot use the facilities like

telephone, fax, photocopies, etc. of the Client.

The contractor has to set up his own equipments.

Site Installation Page: 2 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of Work: 1000 - Method of Measurement and Site Installation

SN Code Description of item Unit Quantity

21

h) After completion of the works, the contractor

shall clear away and remove from the site all

tools and plants, surplus materials, rubbish,

garbage, temporary constructions, and temporary

work of every kind and leave the whole site clean

and to satisfaction of the client. The site area of

the camp, storage area, access road and so forth

shall be rebuilt and brought into the same shape,

state and condition as before starting the work.

The contractor is not allowed to dispose anything

into the river.

22

i) Clearance of the site shall be done as per the

instructions of the client. Clearings may have to

be done during construction period and at the end

of the phased construction tasks. The final

clearance shall be done within 2 (two) weeks,

after the certificate of completion is issued.

23 1003 Material & protection

24 1003.1

The contractor shall build sufficient stores, so

that all materials can be stored without being

exposed to rain and hot sun. All the construction

materials, particulalry cement and steel have to

be put under proper shed.

25 1004 Tools and plant

26 1004.1

The contractor shall supply and provide all

materials, plants, equipment, spare parts and

whatsoever to execute the works in accordance

with the contract.

27 1004.2

The contractor shall provide sufficient spare

parts and equipment to execute work without

delay. The tools, materials and plants shall be in

good working condition to erect all temporary

structures and scaffolding at site. The client

reserves the right to stop on-going work in case

tools and plants are not meeting the requirement

and /or are in unsafe condition.

28 1004.3

The mixing of concrete shall be done in a

concrete mixer and shall be compacted using

mechanical concrete vibrators.

Site Installation Page: 3 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of Work: 1000 - Method of Measurement and Site Installation

SN Code Description of item Unit Quantity

The contractor shall be required to carryout tests

on the materials like agregate, sand etc. that are

to be used for the bridge constrcution. Mix

design and trial mixes will have to be carried out

and tested prior to laying the concrete. Concrete

samples in form of cubes shall be taken from

different batches during the pouring of the

concrete and the cubes have to be tested for

strength. The contractor can either choose to

have the testing facilities set up at the

construction site or get the tests done from a

reputable laboratory. The contractor has to bear

the expenses for all the tests that are required for

building the bridge to the specifications

stipulated in the drawings, BoQ, technical

specification and other documents of the

contract.

29 1005 Various

It is understood that all the above costs are

included in the site installation . By signing the

contract, the contractor confirms that all efforts

and costs to fulfill the tasks listed above as a part

of site installation are included in the rates. The

mode of payment for the site installation shall be

as follows:-

a 80% after the site installation is complete

b

20% after the site is restored to its initial shape

and condition or as per the instruction of

Client/site engineer

LS 1.00Total costs for complete site installation

Site Installation Page: 4 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Excavation work

30 2001

The contractor shall be deemed to have made

himself fully acquainted with the full nature &

complexity of the work, the location and

character of the site and means of access to the

site.

31 2002

The rates and work descriptions have to include

all activities and all costs necessary to complete

the work. The erecting, use and dismantling of

necessary working platforms, scaffolding and

related structures have to be included in the

rates. Construction of coffer dams, guide bunds,

sheet piles etc. if required for diversion of the

river in order to get the working space or to

control seepage during excavation shall also be

included in the rates. The relevant drawings are

an integral part of these tender documents. The

contractor has to study all drawings in detail. By

submitting the tender, the contractor is

declaring that he has understood the drawings

and all the works involved and is prepared to

complete all construction work in a competent

manner. Only the highest degree of accuracy

and quality will be accepted.

Type of works: 2000 Earth work

SN Code Description of item Unit Quantity

Earthwork Page: 1 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of works: 2000 Earth work

SN Code Description of item Unit Quantity

32 2003

The Contractor confirms also to be fully aware

of the soil condition. He agrees not to ask for

additional payments due to changed soil

conditions.The word "soil" in this context refers

to all types of soil, earth, rock, stone, sand,

boulders, gneiss, clay, gravels, mica schist and

so on. In other words, the rate quoted for the

soil excavation shall apply for all the excavation

materials; soil, earth, rock - hard and/or soft,

requiring or not requiring blasting. Irrespective

of the type of excavation material, the

contractor shall be paid at the same rate - the

rate quoted by the contractor for 'soil'

excavation. Therefore, while submitting the

rates, the contractor has to estimate the

proportion of various materials (soil, ordinary

rock, hard rock) in the excavation depending on

the site condition and quote accordingly. The

fact that some of the excavation works will be at

the river side, in the river and below the water

level will also not justify any increase in the

costs. It is important that the contractor does

careful study of the site condition prior to

submitting the tender.

33 2004

The excavation shall be paid as Solid Volume.

Solid volume is the volume of excavation

calculated directly from the foundation

dimensions of the structure without

allowance for bulking, shrinkage, wastage,

working space, slope cutting etc. But the

contractor has to be aware of the fact that the

soil cannot be dug vertically and that additional

excavations would be required for getting the

working space around the foundations, slope

cutting etc. and the contractor has to account for

these additional quantities while setting rates

for the excavation works.

Earthwork Page: 2 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of works: 2000 Earth work

SN Code Description of item Unit Quantity

34 2005

Excavation in ordinary/hard rock for

foundations of abutments . Here excavation

means soil and rock cutting up to the level

shown in the drawing. Controlled balsting

would be permitted. The volume of soil

excavation is calculated as solid volume as

per drawings but the contractor has to

consider the fact that it maynot be possible to

excavate the foundation vertically for deeper

foundations and should therefore keep

provisions for slope cutting, working space

etc. in the rates including dewatering by

bailing out or pumping out water. The

loading, offloading and transportation has to be

included in the rate. The quantity is for both

banks.

m³ 1720.00

35 2006

Rock anchoring works: The work involves

drilling of minimum 34 mm diameter drill

holes, placing of the reinforcement (as per

design) in the hole and packing it with rich

cement motar 1:1. The reinforcement has to be

placed centrally in the hole so that the cement

motar fill the gap uniformly around the

reinforcement bar. The depth of the drill holes

are shown in the drawing. The reinforement

shall be paid seperately. All other efforts and

expenses required for completing the task shall

be included in the rates.

m 303.88

36 2007

Backfilling around and behind the foundations,

abutments & return walls. Handling, loading,

offloading, transportation, watering and all

necessary works shall be included in the rate.

The back filling shall be done as per the

instruction of site engineer and in layers not

more than 300mm thick and compacted well

with earth rammer or compactor. The

Client's site engineer will strictly supervise this

to make sure that full compaction is achieved.

The quantity of backfilling is only upto the end

of abutments at both the banks.

m³ 1120.00

Earthwork Page: 3 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of works: 2000 Earth work

SN Code Description of item Unit Quantity

37 2008

Providing and laying coarse gravel (filter

layer) behind the Abutments as per drawing.

Thickness d=60 cm for left abutment & d=50

cm for right abutment. The filter material to

be used have to be approved by the client.

Handling, loading, offloading, transportation

and all necessary work shall be included in the

rate.

m³ 32.46

38 2009

Providing and laying coarse gravel (filter

layer) behind the RC retaining wall as per

drawing. Thickness d=40 cm is provided. The

filter material to be used have to be approved by

the client. Handling, loading, offloading,

transportation and all necessary work shall be

included in the rate. The quantity is only for one

RC retaining wall.

m³ 16.80

Total Cost 2: Earthwork

Earthwork Page: 4 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

39 3001

The reinforced concrete works shall be carried

out strictly as per the stipulations in the

Technical Specification. The reinforced

concrete works may be under or above the

water level. The bidders have to study the site

condition and the design drawings carefully

and if necessary account for the dewatering

works using water pumps or any other means

including providing of temporary protection

works such as coffer dam, sheet pile etc. to

divert the river and/or control seepage for

laying the concrete works under water. It is

understood that the bidders' price for the

concrete works include, besides others,

possible expenses for river diversion,

cofferdam/sheet pile/guide bunds, dewatering

works etc. The rates shall include all the

efforts required to fulfill the task.

Abutments

40 3002

Providing & Laying of Lean Concrete 10 cm

thick in M10 underneath foundation slab as

shown in the drawing . The side of the lean

concrete can be inclined upto 15 degress and

therefore no formwork is necessary. The rate

has to include all works and materials to fulfill

the task including curing of the concrete.

m³ 4.90

41 3003

Providing & Laying of Lean Concrete 10 cm

thick in M10 underneath foundation slab of

RC retaining wall, RRM wing wall and also

caping for RRM walls as shown in the

drawing . The side of the lean concrete can be

inclined upto 15 degress and therefore no

formwork is necessary. The rate has to

include all works and materials to fulfill the

task including curing of the concrete.

m³ 9.78

Type of

works:

3000. Reinforced Concrete, Plain Cement Concrete, Formworks and Other

Involved Works

SN Code Description of item Unit Quantity

RC & other works Page: 1 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of

works:

3000. Reinforced Concrete, Plain Cement Concrete, Formworks and Other

Involved Works

SN Code Description of item Unit Quantity

42 3004

Providing & laying of Reinforced Cement

Concrete M25, for foundation slab of the

abutments as per drawing and specification.

All works and materials to complete the task

including curing of the concrete has to be

included in the rate.Formwork and

reinforcement will be paid separately.

m³ 41.40

43 3005

Providing & laying of Reinforced Cement

Concrete M25 for the abutment walls

(Stem) and dirt walls as per drawing and

specification. The surfaces may be vertical

and/or inclined. All works and materials to

complete the task including curing of the

concrete have to be included in the

rate.Formwork and reinforcement will be paid

separately.

m³ 74.94

44 3006

Providing & laying of Reinforced Cement

Concrete M20, for foundation slab of the

RC retaining wall as per drawing and

specification. All works and materials to

complete the task including curing of the

concrete has to be included in the

rate.Formwork and reinforcement will be paid

separately. The quantity mentioned here is

only for one wall.

m³ 13.30

45 3007

Providing & laying of Reinforced Cement

Concrete M20 for the vertical wall (stem) of

the RC retaining wall as per drawing and

specification. The surfaces may be vertical

and/or inclined. All works and materials to

complete the task including curing of the

concrete have to be included in the

rate.Formwork and reinforcement will be paid

separately. The quantity mentioned here is

only for one wall.

m³ 27.30

RC & other works Page: 2 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of

works:

3000. Reinforced Concrete, Plain Cement Concrete, Formworks and Other

Involved Works

SN Code Description of item Unit Quantity

46 3008

Proving and Fixing Formwork including all

temporary or permanent forms required for

forming the concrete of the shape, dimensions

and surface finish as shown in the drawings.

The rate shall include all props, staging,

centering, scaffolding and temporary

construction required for their support to

provide the structure true to shape as shown on

the drawing and removal of the form work

after the time specified in the specifications or

as directed by the Engineer/Client. The

formwork shall impact a smooth and even

finish on the concrete surface.

47 3008.1

Providing and fixing vertical formwork for the

foundation slab of the abutments as shown in

the drawing.

m² 35.40

48 3008.2

Providing and fixing vertical form work for the

abutment wall (stem) up to the bearing level

of the bridge (all sides) and also all sides of

dirt walls.

m² 169.08

49 3008.3

Providing and fixing vertical formwork for the

foundation slab of the RC retaining wall as

shown in the drawing. The quantity is only for

one wall.

m² 10.80

50 3008.4

Providing and fixing vertical form work for the

vertical wall (stem) up to the bearing (all

sides) and all sides. The quantity is only for

one wall.

m² 91.85

51 3009

Reinforcement steel in accordance with

drawings, including cutting, bending, hooking

by machine/manual, tying in position

including GI binding wire, spacers, laps,

chairs, cover blocks, placing into formwok

and fixation, all complete. Reference will be

made to the reinforcement list for calculating

the weight of the reinforcement for which the

contractor is eligible for payment. The

contractor will not be paid for any wastage.

The contractor has to consider and include

wastage into his pricing of the unit rates.

RC & other works Page: 3 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of

works:

3000. Reinforced Concrete, Plain Cement Concrete, Formworks and Other

Involved Works

SN Code Description of item Unit Quantity

52 3009.1

Bend-up bars with hooks and any kind of

bends, Diameter 10 - 32 mm. All efforts and

costs to be included to fullfil the task. The

quantity is for Abutments & dirt walls.

kg 10,744.93

53 3010

Providing, laying & fixing of HDPE pipes for

weep holes as per drawings - diameter = 11cm,

slope = 1 in 20. This quantity is for abutment

walls.

m 18.84

54 3011

Providing and laying dry stone wall in G.I

wire mesh 4mm (8 SWG) - double knotted

mesh ….100mm, including supplying and

weaving of mesh complete. The gabion wall

has to to be built using flat and elongated

stones. River boulders are strictly not

permitted to be used. The stones inside the

gabion wire mesh have to be built in form of

a dry wall so that the wall is stable on its

own even within the wire mesh. As

mentioned in the drawing, the quantity here

may change as per the requirment at the site.

m³ 77.40

55 3012

Providing & laying of Random Rubble

Masonry (Including parapets) in CM 1:4 for

the wing walls. As mentioned in the drawing,

the quantity of RRM wing wall may vary from

what is given in this BoQ as per requirement at

the site. The rate should include the delivery of

boulders/stones.

m³ 305.65

Total cost 3: Plain & Reinforced Cement

Concrete, formworks and other works

involved

RC & other works Page: 4 of 4

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount(Nu) (Nu)

56 4001

Transportation of Bailey bridge

superstructure (complete sets) from the Central Store, Regional Office, DoR, Phuentsholing to the bridge site.

T 94.50

57 4002Launching of Bailey bridge with following specification;

LS 1.00

a Span: 180 feet

b Construction: DDR

c Deck type: Steel

- Total Cost 4: Bailey Bridge & other involved works

Type of Works: 4000. Bailey Bridge and Other Involved Works

SN Code Description of item Unit Quantity

Bailey Bridge transportation Page: 1 of 1

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

58 5001

Excavation in foundation trenches for the

construction of RCC wall along the river bank,

including dressing and ramming, disposal of

surplus soil. The selected material for the

backfilling may stack along the bank- All

kinds of soil and rock.

m3 1800

59 5002

The reinforced concrete works shall be carried

out strictly as per the stipulations in the

Technical Specification. The reinforced

concrete works may be under or above the

water level. The bidders have to study the site

condition and the design drawings carefully

and if necessary account for the dewatering

works using water pumps or any other means

including providing of temporary protection

works such as coffer dam, sheet pile etc. to

divert the river and/or control seepage for

laying the concrete works under water. It is

understood that the bidders' price for the

concrete works include, besides others,

possible expenses for river diversion,

cofferdam/sheet pile/guide bunds, dewatering

works etc. The rates shall include all the

efforts required to fulfill the task.

60 5003

Providing & Laying position the Plain

Cement concrete of M10 (1:3:6)-40mm

aggregate. The rate has to include all works

and materials to fulfill the task including

curing of the concrete. The cost of centering

and shuttering will be paid separately

m³ 45.00

61 5004

Providing & laying of Reinforced Cement

Concrete M25 (1:1:2 (1 cement : 1 sand : 2

graded crushed rock 20 mm nominal size))

as per drawing and specification. All works

and materials to complete the task including

curing of the concrete has to be included in the

rate.Formwork and reinforcement will be paid

separately.

m³ 435.00

Type of

works:5000.RCC wall along the river bank

SN Code Description of item Unit Quantity

RCC Wall Page: 1 of 2

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

Type of

works:5000.RCC wall along the river bank

SN Code Description of item Unit Quantity

62 5005

Proving and Fixing Formwork including all

temporary or permanent forms required for

forming the concrete of the shape, dimensions

and surface finish as shown in the drawings.

The rate shall include all props, staging,

centering, scaffolding and temporary

construction required for their support to

provide the structure true to shape as shown on

the drawing and removal of the form work

after the time specified in the specifications or

as directed by the Engineer/Client. The

formwork shall impact a smooth and even

finish on the concrete surface.

63 5006

Providing & fixing centering and shuttering

(formwork) for PCC works as per the

specifications or as directed by the

Engineer/Client

m² 15.80

64 5007

Providing & fixing centering and shuttering

(formwork) For RCC as per the specifications

or as directed by the Engineer/Client

m² 986.80

65 5008

Providing & fixing, Thermo Mechanically

Treated (TMT) bars for R.C.C work including

cutting, bending, binding and placing in

position complete

kg 25,785.87

66 5009Providing,laying & fixing of HDPE pipes with

weep holes-diameter 90mm, slope 1 in 20. m 45.61

67 5010

Providing and laying hand packed stone soling

or filling with stones ( i.e filter materials

400mm)

m3 198.00

68 5011Back filling in layers < 200 mm using selected

excavated earth, ramming etc-complete.m

3 1,050.00

Total cost 5: RCC wall Along the River Bank

RCC Wall Page: 2 of 2

BoQ for Construction of Yudhiri Bailey Bridge

Rate Amount

Nu. Nu.

69 6001

Excavation of road formation/trace/box

cutting, with excavator including separate

deposition of soil, rocks and stones within

50m: All types of soil

m3 600

70 6002

Excavation of road formation/trace/box

cutting, with excavator including separate

deposition of soil, rocks and stones within

50m: All types of rock

m3 500.00

71 6003

Construction of Gabion wall as per drawings,

including excavation of foundations in all

types of soils, sides and backfilling, delivery

of materials, providing of geo textile at the

back face etc. Complete: Height up to 3.0m

m 30.00

72 6004

Construction of lined drain as per the standard

design drawing provided in the drawing

section including excavation, leveling,

formwork, curing, backfilling and disposal of

surplus excavated earth within 50 m lead.

m 100.00

Total cost 6 : Road, gabion & Drain

Type of

works:6000. Road, Gabion wall & Drain

SN Code Description of item Unit Quantity

App. road Page: 1 of 1