Lifting Plan

Lifting Plan

Lifting Plan No:-01Project: - Al KHEESA PROJECT DN 071Date: - -- Contractor: - CGC jv SACYR1. Equipment:-

What Type:- 2. Time: - 6:00 Am to 6:00 pm From: - --to Brief Description Of Lifting Operation: - Hoisting up the ---unloading of cement pipes. (Please Descript what activity will going to do)

3. Name of appointed Person from Contractor:- Mr. John Godstime4. List means of identification (i.e. what clothing or color helmet etc will identify them from other site workers.

Vest- Florescent Green Safety helmet- GREEN.

5. Description of Loads:-

a. Weight- Max weight of load shall be 80% of SWL.

b. Characteristics- Miscellaneous types of materials, equipment

c. Method of lifting- Using web belt sling and shackle.

d. Center of gravity- Align with crane hook.

e. Lifting point or method of sling- To be determined by lifting supervisor.

6. Lifting Equipment or appliance to be used:-

a. Make / Model: - boom crane 19370b. Maximum capacity 25 T c. Main Boom Length- 10 Md. Maximum Radius- 3 Me. Safe Working Load- 25 T7. Proximity Hazards:-

a. Overhead Power Lines- None

b. Underground Tunnels- None

c. Airports- None

d. Other Strictures- None

e. Underground Services- None

f. Other Carnages -None

g. Others (specify)-NA

8. Ground conditions & Appropriate Controls:-Ground area is level and compacted Hardcore, concrete slab

Steel plate supports to be used for the outrigger base

Outrigger is fully extended

Width of access area is adequate to allow passenger of crane including full extended outriggers.

9. Are Temp Workers involved in the lift.

Described- 4 workers for support the lifting team10. What demarcation will be used:-

a. Is the area an exclusion zone- Yes.

b. What barriers and signage- Isolate area with warning tape or orange plastic net and warring signages. (Danger, Keep Out Signage)11. Control of load (tag lines etc)

Use of Tag line.

12. Crane Rigging requirement (ground condition)-

Stable and level ground

outrigger base.

13. Access/Egress (Lifting Equipment-vehicles etc.)

14. Wind speed( what is maximum wind speed for safe lifting, how is it recorded)- 25Knots(as per QCS 2010)15. Is lifting Open or blind? Describe of method of signaling/dogging-(Specify the number of signalers to be used.)One signalman is to be used. Communication is by hand signals, Visual contact between operator and signalman is maintained. Whatever visibility is not possible. Communication between operator and signalman shall be by radio.

16. Communication? (What means)

Communication between operator and signalman by hand signals and by radio.

17. Have appropriate CGC JV SACYR and crane operator checklist been completed.-

Yes.

18. Crane Operator Appointed Person (Contractor) Review & Date.

Signature-

Date-

19. Approved by CGC JV SACYR HSE Officer.

Signature-

Date-

The lifting plan is to be used no matter the type of lift; standard lifts may need to be reviewed weekly to ensure nothing has changed. Should the lifting operation come under scrutiny the lifting plan is evidence of addressing all aspect pertaining to the planning of the operation. If lifts are to be repetitive (standard) type then the one lifting plan can be put in place and remain as long as no significant changes have taken place. However as stated preciously it must be reviewed weekly by contractors appointed person.

Note: - For all the Lifting operation must prepare lifting plan to submit HSE Dept. before commencement. And attach together Lifting permit.

WORK AREA: ZONE

DEPT.Originator / ( ( HSE Manager /

Name: Mr. John GodstimeEng.Enrique Fjardo

Date :

Signature :