Board Update Measure BB
Project Short Falls Construc7on ac7vi7es Forecast of Change Orders Allowances for unknowns Design revisions in DSA Unallocated Budget for Technology
Service Related Short Falls Construc7on Management District Controls
Total Shor*alls Amounts by Sites
Sites Shor*alls Amount
Edison ($ 7,331,361.00)
John Adams ($ 2,569,443.00)
Lincoln ($ 227,864.00)
Olympic ($ 1,737,079.00)
SAMOHI ($10,530,350.00)
Data Center ($ 3,208,760.00)
Technology FF&E – SAMOHI, Olympic, Edison & Malibu
($2,397,552.00)
Management & Reimbursable ($2,477,426.00)
District Controls ($5,000,000.00)
Reserve Balance $3,860,992.00 Total Shor*alls ($31,618,843.00)
Edison AllocaBon/Budget: • Land Acquisi7on Budget: $4,515,400.00 • New school Budget (Pre-‐Construc7on): $34,000,000.00
Phase 1 : -‐Completed New 2 Story Elementary school,
27 Classrooms for K-‐5 New Library, Administra7ve Office, Cafeteria, Demoli7on Occupancy Jan 2014
Phase 2: -‐in Progress
Pre-‐School/ Bldg. w/2 Classrooms and Outdoor Learning Areas, Playfields PE Building, Courts, Parking, water rain Harves7ng system
CompleBon
Play Field Open: September 2015 Full Occupancy: November 2015
Edison Language Academy
Phase 2 In Progress: Play Field Grading, Rain water harves7ng area, and turf area
88%
6% 6% Expenditures
Forecast to Complete Project
Allowance: Unknown CO, Claims & Disputes
Edison Unallocated Budget/AddiBonal Scope: Temporary Housing Pre-‐school (Rogers) Temporary Housing Edison, DSA Legacy Closeout Classroom Technology FF&E, Temporary Playfields/Tent Structures, Enhancements for Exterior Safety, Guard Rails Planters, Gates Modifica7on, Screening, HVAC, BMS Controls, Fans/Solar Chimney/Heat Mi7ga7on, Environmental, Demoli7on, Soil, Air Mi7ga7on Acous7c Treatment, Irriga7on Revision, Relocate Roof Drains/ Hydronic Lines/U7lity Connec7on/Street Guher Eleva7ons, Bird Abatement Wire Total Project AllocaBon
Budget Expenditures Forecast to Complete the
Project Allowance: Unknown CO,
Claims & Disputes Remaining balance
$58,036,489.00 ** Project Budget was reduced by $3,066,574.00 for reducBon
of the program budget
$57,758,739.00 $3,609,111.00
$4,000,000.00 ($7,331,361.00)
2008 2009 2010 2011 2012 2013 2014 2015 2016
Original
Current
34 months
Document Construct 52 months DSA
Schedule:
Budget:
JAMs Projects AllocaBon: • Moderniza7on : Pre Construc7on Budget: $12,930,000.00 • Current Construc7on Budget: $17,542,352.00
Phase 1a & 1b: -‐Completed New Green Fringe and Relocatable Landscape Perimeter of Synthe7c Track Temporary Housing Admin and Classroom
Phase 2: -‐in Closeout
Replacement of 9 Classrooms Addi7on of Ahendance/Admin Moderniza7on of Art Room, Admin offices
CompleBon: Classrooms Occupancy: January 2013 Administra7on Occupancy: April 2013 Site Work Occupancy: August 2013 Closeout: April 2015
John Adams Middle School
JAMs Projects-‐Unallocated AddiBonal Scope DSA Legacy closeout Classroom technology FF&E Abatement of TSI Wrapped Pipe Upgrade Gas Line, Electrical Line, Soil Remedia7on, Added Waterproofing, Added Steel Plates, Addi7onal Structural Requirement, Added PA Speakers, Temporary Tent Structures Enhancements for Sun control, Earth tube PV/Fans Motors, BMS Controls, Solar Chimney/Heat Mi7ga7on, Hea7ng Elements, Structural , Termites, Environmental Mi7ga7on Demoli7on/Soil
90%
1% 9% Expenditure
Forecast to Complete Project
Allowance: Unknown CO,Claims & Disputes
Total Project AllocaBon Budget
Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$26,403,799.00 ** Project Budget was reduced by $1,001,600.00 for reducBon of
the program budget
$26,057,377.00 $415,865.00 $2,500,000.00 ($2,569,443.00)
2008 2009 2010 2011 2012 2013 2014 2015
Original
Current
Schedule:
3 Phases -‐ 35 months DSA
Document Ph. III – Construct & Closeout 50mo DSA
Budget:
Lincoln Projects AllocaBon: • Moderniza7on : Pre Construc7on Budget: $17,524,000.00 • Current Construc7on Budget: $22,201,494.00
Phase 1a & 1b: Complete Site u7li7es and Relocatable Moderniza7on 4 classrooms, 2 science labs & prep
Phase 2: Closeout
2 story facility housing new Library, reading rooms, chorus room, book rooms, community spaces 6 standard classrooms, 2 science labs & prep Restrooms, outdoor performance area
CompleBon Occupancy: January 2015 Closeout: May 2015
Lincoln Middle School
Lincoln Projects-‐Unallocated AddiBonal Scope DSA Legacy closeout Classroom technology FF&E Abatement of TSI Wrapped Pipe Upgrade Gas Line, Electrical Line, Soil Remedia7on, Termite, safety rails, gates Building Demo Waste Removal & Recycling Traffic Control Permits Fireproofing Scope of Work Mobiliza7on due to DSA Stop Work No7ce DSA Requirement to add Structural Steel Plates & Welding Relocate Underground Gas Lines
99%
1% Expenditure
Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Total Project AllocaBon Budget
Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$31,868,648.00 ** Project Budget was
reduced by $1,455,383.00 for reducBon of the program budget
$31,796,512.00 $300,000.00 ($227,864.00)
2008 2009 2010 2011 2012 2013 2014 2015
Original
Phase I:
Phase II:
Schedule:
17 months DSA
Documents 10 mo. DSA
Documents Construc7on 28 mo. DSA
Olympic AllocaBon/Budget: • Moderniza7on (Pre Construc7on Budget): $5,011,000.00 • Current Construc7on Budget: $5,437,845.00
DemoliBon Relocatables: Complete Removed 5 Relocatables
Landscape: Complete Recapturing Green Space for New Turf Field & New Trees
ModernizaBon: Hold Pending Environmental 15 rooms, Including 7 Classrooms, New Music
Classroom Modernize Library, Computer Lab, & Science Room Schedule
Construc7on start: December 2013 Stopped: Fire Alarm January 2014 Construc7on resume: June 2015 Occupancy: January 2017
Olympic High School
Olympic Unallocated/AddiBonal Scope: DSA Legacy Closeout Classroom Technology FF&E Environmental Supplemental Work
34%
66%
Expenditure
Forecast to Complete
Allowance: Unknown CO, Claims & Disputes
Total Project AllocaBon Budget
Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$8,487,095.00 ** Project Budget was
reduced by $436,869.00 for reducBon of the program
budget
$3,524,174.00 $6,700,000.00 ($1,737,079.00)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Original
Current DSA 18 months 30 months
14 months 10 months
Schedule:
Budget:
SAMOHI Projects AllocaBon: • New Construc7on : Pre Construc7on Budget: $62,350,000.00 • Current Construc7on Budget: $57,515,920.00
Phase 1: Main Science /Technology Bldg.: Commissioning 15 Science Labs, 18 Classrooms , Computer Lab 2 Special Educa7on Classrooms
Auto Shop Administra7ve Offices
Phase 2: Site Improvements, Sobball Field, Parking, ConstrucBon Site U7li7es, Parking, Sokball Field
CompleBon Phase I – Building Occupancy: June 2015 Phase II – Sokball Field Occupancy: April 2016 Phase II – Parking Occupancy: July 2016
Santa Monica High School
Samohi Projects-‐Unallocated AddiBonal Scope Campus Wide Transformer Campus Wide Electrical Pathway Tennis Court Retaining Wall New ADA Olympic Path of Travel Parking Rental Impacts Assistant DSA Inspec7on, Specialty Inspec7on Reduced Work Hours, Traffic Logis7cs Mul7ple Mobiliza7ons, Redesign to Preserve Science Move Management, DSA Legacy Closeout, Addi7onal Signage Classroom Technology FF&E Environmental supplemental work
47%
47%
1% 5% Alloca7on Budget
Expenditure
Forecast to Complete
Allowances for Claims & Disputes
Total Project AllocaBon Budget Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$82,494,834.00 ** Project Budget was reduced by $6,031,079.00 for reducBon of
the program budget
$79,765,184.00 $5,360,000.00 $7,900,000.00 ($10,530,350.00)
2008 2009 2010 2011 2012 2013 2014 2015 2016
Original
Current
41 months DSA
Documents Construc7on 58 months DSA
Schedule:
Budget:
Technology/Data Center Projects AllocaBon: • New Construc7on Pre Construc7on Budget: $10,925,000.00 • Smart Board $ 114,235.00 • Current Construc7on Budget: $10,600,550.00
Phase 1-‐3: District Wide Technology Upgrade-‐Complete
District Wide Wireless, LAN, Telephone, IT Upgrades and Classroom Prototype Educa7onal Technology Standards for Limited Classrooms Data Center: District office IT –in Progress/ConstrucBon
Hard Drive Storage, Processors, Racks, and Server Support Provided and Installed; Infrastructure and Current IT Equipment to Support Measure ES Technology Pending DSA Review for Current Updates
Schedule:
Commencement: March 2015 Occupancy – IT Equipment Transi7on: August 2015 Comple7on of Accessory Requirement: December 2015
Technology – Data Center
Data Center Projects-‐Unallocated AddiBonal Scope Redesign for Unforeseen Structural and Electrical Required Scope, Back Up Generator, Upgraded A/C Handling Units, ADA path of Travel, Fire Alarm Upgrades, Move Management
76%
24%
Expenditure
Forecast to Complete the Project
Allowance Unknown CO,Claims & Disputes
Total Project AllocaBon Budget
Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$12,940,112.00 ** Project Budget was
reduced by $167,110.00 for reducBon of the program
budget
$12,314,685.00 $3,834,187.00 ($3,208,760.00)
2008 2009 2010 2011 2012 2013 2014 2015
Original
Current 10 months
10 months
6 6 4
40 Months DSA DSA
Schedule:
Budget:
Board Update Measure BB
Service related Short Falls Construc7on Management District Controls
Management & Reimbursable Services Program/Project Management ConstrucBon Management
Parsons California Construc7on Managers (CCM)
Program Budgets/Category Constructability
Design Managers Joint Discipline Reviews
Planning/Site Liaisons On Site/ Logis7cs
Architects/Consultants Contractor Management
CEQA Move Management/ FF&E
Scheduling/Phasing Procurement/Bids
Document Control Construc7on Consultants
Program Controls Construc7on Controls
Commissioning
Environmental
Management & Reimbursable Services On Site/ LogisBcs acBve : Contractor Management: ConstrucBon Consultants ConstrucBon Controls: Commissioning Environmental
Edison; Samohi phase 1/2
On/site/Logis7cs Closeout: JAMS, Lincoln,
Move Management/ FF&E Edison; Samohi
On/site/Logis7cs Close-‐out: Move Management/ FF&E: Construc7on Consultants Construc7on Controls Commissioning Environmental
Olympic, Malibu, Webster
Total CM Budget Expenditures Forecast to Complete Projects 18 month
Remaining balance
$20,829,913 $19,402,467.82 $3,904,872.24 ($2,477,426.06)
District Controls District AllocaBon Prorated for BB
March 2015 to June 2018
Change Order review $450,000.00
SMMUSD Staff $1,792,000.00
District Consultants $1,740,000.00
Document Controls $290,000.00
Office Supplies $10,570.00
Office Opera7ons/Equipment $140,000.00
Legal-‐general $450,000.00
Audit $67,200.00
Adver7sement $30,500.00
Web $29,693.00
Total $5,000,000.00
Board Update Measure BB
Pending Projects Malibu High school Webster
Malibu AllocaBon/Budget: • Moderniza7on (Pre Construc7on Budget): $33,458,000.00 • Current Pre Construc7on Budget: $33,313,556.00
Phase 1 Fire Alarm: Complete Campus Wide Fire Alarm Upgrade
Phase 2 Water Main: Complete
Water District 29 Fire flow capacity main upgraded and replaced Phase 3 Soil RemediaBon: Complete
Soil removal as required by the Soil Removal Ac7on Work plan of 2009
Phase 4 ModernizaBon/New ConstrucBon/Parking Lot
New library, 2 Computer labs, 3 Science labs 4 General classrooms, Add 2 classroom and
Modernize 10 classrooms in Building E, and a new IT room. Commencement: Pending Coastal Review
Malibu High School
Malibu Unallocated/AddiBonal Scope : DSA Legacy closeout Classroom technology FF&E Environmental supplemental work 36%
64%
Expenditure
Forecast to Complete
Allowances for Unknown CO. Claims & Disputes
Total Project AllocaBon Budget
Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$49,344,243.00 ** Project Budget was
reduced by $3,275,414.00 for reducBon of the program budget
$17,882,862.00 $31,461,000.00 $381.00
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Original
Current DSA & Coastal Commission 38 months – 4th Phase 30 months
4 Phases
Schedule:
Budget:
Webster Projects AllocaBon: • New Construc7on Pre Construc7on Budget: $940,000.00 • Current Construc7on Budget: $1,520,000.00
Phase 1: Fire Alarm-‐Complete Campus Wide Fire Alarm Replacement
Phase 2: Site Improvements, Fencing Parking, Complete/Hold Security Fencing and Gates at Perimeter and Rear Areas Parking, Drop Off, and New ADA Pathways are on hold for Redesign and Scoping
Projected CompleBon Resume Parking: December 2015 Comple7on: December 2016
Webster Elementary School
Webster Projects-‐Unallocated AddiBonal Scope Redesign of Lower Parking Lot for ADA Path of Travel; Repair of County Culvert/Storm Drain; Sep7c Design Studies
57%
43%
Expenditure
Forecast to Complete the Project
Allowance: Unknown CO,Claims & Disputes
Total Project AllocaBon Budget
Expenditures Forecast to Complete the Project
Allowance: Unknown CO, Claims & Disputes
Remaining balance
$2,573,271.00 ** Project Budget was
reduced by $144,792.00 for reducBon of the program
budget
$1,476,068.00 $1,097,000.00 203.00
2008 2009 2010 2011 2012 2013 2014 2015 2016
Original
Current
Schedule:
8
Documents 8 months DSA
Budget:
Completed School Projects