BOE 3-4-15 bb Revised FINAL...

24
Board Update Measure BB Project Short Falls Construc7on ac7vi7es Forecast of Change Orders Allowances for unknowns Design revisions in DSA Unallocated Budget for Technology Service Related Short Falls Construc7on Management District Controls

Transcript of BOE 3-4-15 bb Revised FINAL...

Page 1: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Board  Update  Measure  BB  

Project  Short  Falls        Construc7on  ac7vi7es        Forecast  of  Change  Orders        Allowances  for  unknowns      Design  revisions  in  DSA        Unallocated  Budget  for  Technology  

Service  Related  Short  Falls        Construc7on  Management      District  Controls            

Page 2: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Total  Shor*alls  Amounts  by  Sites    

Sites   Shor*alls  Amount  

Edison   ($  7,331,361.00)  

John  Adams   ($  2,569,443.00)  

Lincoln   ($  227,864.00)    

Olympic   ($  1,737,079.00)  

SAMOHI   ($10,530,350.00)  

Data  Center   ($    3,208,760.00)  

Technology  FF&E  –  SAMOHI,  Olympic,  Edison  &  Malibu  

($2,397,552.00)  

Management  &  Reimbursable   ($2,477,426.00)  

District  Controls   ($5,000,000.00)  

Reserve    Balance   $3,860,992.00  Total  Shor*alls   ($31,618,843.00)  

Page 3: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Edison  AllocaBon/Budget:  •  Land  Acquisi7on  Budget:                              $4,515,400.00  •  New  school  Budget  (Pre-­‐Construc7on):    $34,000,000.00  

 Phase  1  :  -­‐Completed          New  2  Story    Elementary  school,    

 27  Classrooms  for  K-­‐5    New  Library,  Administra7ve  Office,      Cafeteria,    Demoli7on                      Occupancy  Jan  2014  

                         Phase  2:  -­‐in  Progress    

 Pre-­‐School/  Bldg.  w/2  Classrooms  and      Outdoor  Learning  Areas,  Playfields    PE  Building,  Courts,    Parking,  water  rain      Harves7ng  system  

                                                 CompleBon  

 Play  Field  Open:  September  2015                            Full  Occupancy:  November  2015  

Edison  Language  Academy  

Phase  2  In  Progress:      Play  Field    Grading,    Rain  water  harves7ng  area,  and  turf  area  

Page 4: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

             

88%  

6%   6%  Expenditures    

Forecast  to  Complete  Project  

Allowance:  Unknown  CO,  Claims  &  Disputes  

Edison  Unallocated  Budget/AddiBonal  Scope:    Temporary  Housing  Pre-­‐school  (Rogers)  Temporary  Housing  Edison,  DSA  Legacy  Closeout  Classroom  Technology  FF&E,  Temporary  Playfields/Tent  Structures,  Enhancements  for  Exterior  Safety,  Guard  Rails  Planters,  Gates  Modifica7on,  Screening,    HVAC,  BMS  Controls,  Fans/Solar  Chimney/Heat  Mi7ga7on,  Environmental,  Demoli7on,  Soil,  Air  Mi7ga7on  Acous7c  Treatment,  Irriga7on  Revision,  Relocate  Roof  Drains/  Hydronic  Lines/U7lity  Connec7on/Street  Guher  Eleva7ons,  Bird  Abatement  Wire         Total  Project  AllocaBon  

Budget  Expenditures     Forecast    to  Complete  the  

Project  Allowance:  Unknown  CO,    

Claims  &  Disputes  Remaining  balance  

$58,036,489.00      **  Project  Budget  was  reduced  by  $3,066,574.00  for  reducBon  

of  the  program  budget  

$57,758,739.00   $3,609,111.00      

$4,000,000.00   ($7,331,361.00)  

2008   2009   2010   2011   2012   2013   2014   2015   2016  

Original    

Current  

34  months  

Document   Construct  52  months  DSA  

Schedule:    

Budget:    

Page 5: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

JAMs  Projects  AllocaBon:  •  Moderniza7on  :  Pre  Construc7on  Budget:  $12,930,000.00  •  Current  Construc7on  Budget:                                                $17,542,352.00  

Phase  1a  &  1b:  -­‐Completed        New  Green  Fringe  and  Relocatable    Landscape  Perimeter  of  Synthe7c  Track    Temporary  Housing  Admin  and  Classroom  

                         Phase  2:  -­‐in  Closeout  

 Replacement  of  9  Classrooms    Addi7on  of  Ahendance/Admin    Moderniza7on  of  Art  Room,  Admin  offices  

                           CompleBon:                                                Classrooms  Occupancy:  January  2013                                                Administra7on  Occupancy:  April  2013                                                Site  Work  Occupancy:  August  2013                                                Closeout:  April  2015  

John  Adams  Middle  School  

Page 6: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

JAMs  Projects-­‐Unallocated  AddiBonal  Scope    DSA  Legacy  closeout  Classroom  technology  FF&E  Abatement  of  TSI  Wrapped  Pipe  Upgrade  Gas  Line,  Electrical  Line,  Soil  Remedia7on,    Added  Waterproofing,  Added  Steel  Plates,  Addi7onal  Structural  Requirement,  Added  PA  Speakers,                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            Temporary  Tent  Structures  Enhancements  for  Sun  control,    Earth  tube      PV/Fans  Motors,  BMS  Controls,    Solar    Chimney/Heat  Mi7ga7on,  Hea7ng  Elements,  Structural  ,  Termites,  Environmental  Mi7ga7on  Demoli7on/Soil  

90%  

1%   9%   Expenditure  

Forecast  to  Complete  Project  

Allowance:  Unknown  CO,Claims  &  Disputes  

Total  Project  AllocaBon  Budget  

Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$26,403,799.00      **  Project  Budget  was  reduced  by  $1,001,600.00  for  reducBon  of  

the  program  budget  

$26,057,377.00   $415,865.00   $2,500,000.00   ($2,569,443.00)  

2008   2009   2010   2011   2012   2013   2014   2015  

Original    

Current  

Schedule:  

3  Phases  -­‐  35  months  DSA  

Document   Ph.  III  –  Construct  &  Closeout  50mo  DSA  

Budget:    

Page 7: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

 Lincoln    Projects  AllocaBon:  •  Moderniza7on  :  Pre  Construc7on  Budget:  $17,524,000.00  •  Current  Construc7on  Budget:                                $22,201,494.00  

Phase  1a  &  1b:    Complete      Site  u7li7es  and  Relocatable    Moderniza7on  4  classrooms,  2  science  labs  &  prep  

                       Phase  2:  Closeout  

 2  story  facility  housing  new  Library,  reading  rooms,    chorus  room,  book  rooms,  community  spaces    6  standard  classrooms,  2    science  labs  &  prep      Restrooms,  outdoor  performance  area  

                       CompleBon                                                Occupancy:  January  2015                                                Closeout:  May  2015  

   

Lincoln  Middle  School  

Page 8: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Lincoln  Projects-­‐Unallocated  AddiBonal  Scope      DSA  Legacy  closeout  Classroom  technology  FF&E  Abatement  of  TSI  Wrapped  Pipe  Upgrade  Gas  Line,  Electrical  Line,  Soil  Remedia7on,    Termite,  safety  rails,  gates  Building  Demo  Waste  Removal  &  Recycling  Traffic  Control  Permits  Fireproofing  Scope  of  Work  Mobiliza7on  due  to  DSA  Stop  Work  No7ce  DSA  Requirement  to  add  Structural  Steel  Plates  &    Welding  Relocate  Underground  Gas  Lines  

99%  

1%   Expenditure  

Forecast  to  Complete  the  Project  

Allowance:  Unknown  CO,  Claims  &  Disputes  

Total  Project  AllocaBon  Budget  

Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$31,868,648.00      **  Project  Budget  was  

reduced  by  $1,455,383.00  for  reducBon  of  the  program  budget  

$31,796,512.00   $300,000.00     ($227,864.00)  

2008   2009   2010   2011   2012   2013   2014   2015  

Original    

Phase  I:  

Phase  II:  

Schedule:    

17  months  DSA  

Documents   10  mo.  DSA  

Documents   Construc7on  28  mo.  DSA  

Page 9: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Olympic  AllocaBon/Budget:  •  Moderniza7on  (Pre  Construc7on  Budget):        $5,011,000.00  •  Current  Construc7on  Budget:                                                      $5,437,845.00    

DemoliBon  Relocatables:    Complete      Removed  5  Relocatables    

                     Landscape:  Complete    Recapturing  Green  Space  for  New  Turf  Field  &  New    Trees  

                     ModernizaBon:  Hold  Pending  Environmental      15  rooms,  Including  7  Classrooms,  New  Music    

                                             Classroom  Modernize  Library,  Computer  Lab,  &                                                  Science  Room                          Schedule  

 Construc7on  start:    December  2013    Stopped:    Fire  Alarm  January  2014    Construc7on  resume:  June  2015    Occupancy:  January  2017  

 

   

Olympic  High  School  

Page 10: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Olympic  Unallocated/AddiBonal  Scope:    DSA  Legacy  Closeout  Classroom  Technology  FF&E  Environmental  Supplemental  Work  

34%  

66%  

Expenditure  

Forecast  to  Complete  

Allowance:  Unknown  CO,  Claims  &  Disputes  

Total  Project  AllocaBon  Budget  

Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$8,487,095.00      **  Project  Budget  was  

reduced  by  $436,869.00  for  reducBon  of  the  program  

budget  

$3,524,174.00   $6,700,000.00   ($1,737,079.00)  

2008   2009   2010   2011   2012   2013   2014   2015   2016   2017  

Original    

Current   DSA   18  months  30  months  

14  months   10  months  

Schedule:    

Budget:  

Page 11: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

SAMOHI  Projects  AllocaBon:  •  New  Construc7on  :  Pre  Construc7on  Budget:  $62,350,000.00  •  Current  Construc7on  Budget:      $57,515,920.00  

Phase  1:  Main  Science  /Technology  Bldg.:  Commissioning        15  Science  Labs,  18  Classrooms  ,  Computer  Lab    2  Special  Educa7on  Classrooms  

   Auto  Shop    Administra7ve  Offices      

                     Phase  2:  Site  Improvements,  Sobball  Field,  Parking,  ConstrucBon  Site  U7li7es,  Parking,  Sokball  Field  

                       CompleBon                                                Phase  I  –  Building  Occupancy:  June  2015                                                Phase  II  –  Sokball  Field  Occupancy:  April  2016                                                Phase  II  –  Parking  Occupancy:  July  2016    

Santa  Monica  High  School  

Page 12: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Samohi  Projects-­‐Unallocated  AddiBonal  Scope      Campus  Wide  Transformer  Campus  Wide  Electrical  Pathway    Tennis  Court  Retaining  Wall  New  ADA  Olympic  Path  of  Travel  Parking  Rental  Impacts  Assistant  DSA  Inspec7on,  Specialty  Inspec7on    Reduced  Work  Hours,  Traffic  Logis7cs  Mul7ple  Mobiliza7ons,  Redesign  to  Preserve  Science  Move  Management,  DSA  Legacy  Closeout,  Addi7onal  Signage  Classroom  Technology  FF&E  Environmental  supplemental  work  

47%  

47%  

1%   5%   Alloca7on  Budget  

Expenditure  

Forecast  to  Complete  

Allowances  for  Claims  &  Disputes  

Total  Project  AllocaBon  Budget   Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$82,494,834.00      **  Project  Budget  was  reduced  by  $6,031,079.00  for  reducBon  of  

the  program  budget  

$79,765,184.00   $5,360,000.00   $7,900,000.00   ($10,530,350.00)  

2008   2009   2010   2011   2012   2013   2014   2015   2016  

Original    

Current  

41  months  DSA  

Documents   Construc7on  58  months  DSA  

Schedule:    

Budget:  

Page 13: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Technology/Data  Center  Projects  AllocaBon:  •  New  Construc7on    Pre  Construc7on  Budget:                $10,925,000.00  •  Smart  Board                                                                                                      $            114,235.00  •  Current  Construc7on  Budget:                                                                      $10,600,550.00

                     Phase  1-­‐3:  District  Wide  Technology  Upgrade-­‐Complete  

 District  Wide  Wireless,  LAN,  Telephone,  IT  Upgrades                                                  and    Classroom  Prototype  Educa7onal  Technology                                                  Standards  for  Limited  Classrooms                      Data  Center:  District  office  IT  –in  Progress/ConstrucBon    

 Hard  Drive  Storage,  Processors,  Racks,  and  Server  Support    Provided  and  Installed;    Infrastructure  and  Current  IT    Equipment  to  Support  Measure  ES  Technology  Pending  DSA    Review  for  Current  Updates  

                                               Schedule:  

 Commencement:  March  2015                                                Occupancy  –  IT  Equipment  Transi7on:  August  2015                                                  Comple7on  of  Accessory  Requirement:  December  2015  

   

   

Technology  –  Data  Center  

Page 14: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Data  Center  Projects-­‐Unallocated  AddiBonal  Scope      Redesign  for  Unforeseen  Structural  and  Electrical  Required      Scope,  Back  Up  Generator,  Upgraded  A/C  Handling  Units,    ADA  path  of  Travel,  Fire  Alarm  Upgrades,  Move  Management  

76%  

24%  

Expenditure  

Forecast  to  Complete  the  Project  

Allowance  Unknown  CO,Claims  &  Disputes  

Total  Project  AllocaBon  Budget  

Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$12,940,112.00      **  Project  Budget  was  

reduced  by  $167,110.00  for  reducBon  of  the  program  

budget  

$12,314,685.00   $3,834,187.00   ($3,208,760.00)  

2008   2009   2010   2011   2012   2013   2014   2015  

Original    

Current   10  months  

10  months  

6   6   4  

40  Months  DSA   DSA  

Schedule:    

Budget:  

Page 15: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Board  Update  Measure  BB  

Service  related  Short  Falls        Construc7on  Management      District  Controls            

Page 16: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

   

   

Management  &  Reimbursable  Services  Program/Project  Management   ConstrucBon  Management  

Parsons   California  Construc7on  Managers  (CCM)  

Program  Budgets/Category   Constructability  

Design  Managers   Joint  Discipline  Reviews  

Planning/Site  Liaisons   On  Site/  Logis7cs  

Architects/Consultants     Contractor  Management  

CEQA   Move  Management/  FF&E  

Scheduling/Phasing   Procurement/Bids  

Document  Control   Construc7on  Consultants  

Program  Controls   Construc7on  Controls  

Commissioning    

Environmental    

Page 17: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

   

   

Management  &  Reimbursable  Services  On  Site/  LogisBcs  acBve  :  Contractor  Management:  ConstrucBon  Consultants  ConstrucBon  Controls:  Commissioning  Environmental  

Edison;    Samohi  phase  1/2  

On/site/Logis7cs  Closeout:   JAMS,  Lincoln,    

Move  Management/  FF&E   Edison;    Samohi    

On/site/Logis7cs  Close-­‐out:  Move  Management/  FF&E:  Construc7on  Consultants  Construc7on  Controls  Commissioning  Environmental      

Olympic,    Malibu,  Webster    

Total  CM  Budget   Expenditures     Forecast    to  Complete  Projects    18  month  

Remaining  balance  

$20,829,913   $19,402,467.82   $3,904,872.24     ($2,477,426.06)  

Page 18: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

   

   

District  Controls    District  AllocaBon   Prorated    for  BB      

March  2015  to  June  2018  

Change  Order  review   $450,000.00  

SMMUSD  Staff   $1,792,000.00  

District  Consultants   $1,740,000.00  

Document  Controls     $290,000.00  

Office  Supplies   $10,570.00  

Office  Opera7ons/Equipment   $140,000.00  

Legal-­‐general   $450,000.00  

Audit   $67,200.00  

Adver7sement   $30,500.00  

Web   $29,693.00  

                                                     Total     $5,000,000.00  

Page 19: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Board  Update  Measure  BB  

Pending  Projects      Malibu  High  school    Webster  

Page 20: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

 Malibu  AllocaBon/Budget:  •  Moderniza7on    (Pre  Construc7on  Budget):              $33,458,000.00  •  Current  Pre  Construc7on  Budget:                                                $33,313,556.00    

Phase  1  Fire  Alarm:    Complete      Campus  Wide  Fire  Alarm  Upgrade  

                       Phase  2  Water  Main:  Complete  

 Water  District  29  Fire  flow  capacity                                                  main  upgraded  and    replaced                            Phase  3  Soil  RemediaBon:  Complete  

 Soil  removal  as  required  by  the  Soil                                                  Removal  Ac7on    Work  plan  of  2009  

                           Phase  4  ModernizaBon/New  ConstrucBon/Parking  Lot    

 New  library,  2  Computer  labs,  3  Science  labs    4  General  classrooms,  Add  2  classroom  and    

                                             Modernize  10  classrooms  in  Building  E,    and                                                  a  new  IT  room.      Commencement:  Pending  Coastal  Review  

   

   

Malibu  High  School  

Page 21: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Malibu  Unallocated/AddiBonal  Scope  :    DSA  Legacy  closeout  Classroom  technology  FF&E  Environmental  supplemental  work   36%  

64%  

Expenditure  

Forecast  to  Complete  

Allowances  for  Unknown  CO.  Claims  &  Disputes  

Total  Project  AllocaBon  Budget  

Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$49,344,243.00      **  Project  Budget  was  

reduced  by  $3,275,414.00  for  reducBon  of  the  program  budget  

$17,882,862.00   $31,461,000.00     $381.00    

2008   2009   2010   2011   2012   2013   2014   2015   2016   2017   2018  

Original    

Current   DSA  &  Coastal  Commission     38  months  –  4th  Phase  30  months  

4  Phases  

Schedule:    

Budget:  

Page 22: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Webster  Projects  AllocaBon:  •  New  Construc7on    Pre  Construc7on  Budget:          $940,000.00  •  Current  Construc7on  Budget:      $1,520,000.00    

Phase  1:  Fire  Alarm-­‐Complete    Campus  Wide  Fire  Alarm  Replacement      

                     Phase  2:  Site  Improvements,  Fencing  Parking,  Complete/Hold  Security  Fencing  and  Gates  at  Perimeter  and  Rear  Areas    Parking,  Drop  Off,  and  New  ADA  Pathways  are  on  hold  for    Redesign  and  Scoping  

                       Projected  CompleBon                                                Resume  Parking:  December  2015                                                Comple7on:  December  2016  

Webster  Elementary  School  

Page 23: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Webster  Projects-­‐Unallocated  AddiBonal  Scope      Redesign  of  Lower  Parking  Lot  for  ADA  Path  of  Travel;  Repair  of  County  Culvert/Storm  Drain;  Sep7c  Design  Studies  

57%  

43%  

Expenditure  

Forecast  to  Complete  the  Project  

Allowance:  Unknown  CO,Claims  &  Disputes  

Total  Project  AllocaBon  Budget  

Expenditures     Forecast    to  Complete  the  Project  

Allowance:  Unknown  CO,    Claims  &  Disputes  

Remaining  balance  

$2,573,271.00      **  Project  Budget  was  

reduced  by  $144,792.00  for  reducBon  of  the  program  

budget  

$1,476,068.00   $1,097,000.00   203.00    

2008   2009   2010   2011   2012   2013   2014   2015   2016  

Original    

Current  

Schedule:    

8  

Documents   8  months  DSA  

Budget:  

Page 24: BOE 3-4-15 bb Revised FINAL 01fip.smmusd.org/CitizensOversight/handouts/BOE030415BB.pdfTotal&Shor*alls&Amounts&by&Sites& & Sites Shor*alls&Amount& Edison ($7,331,361.00) John&Adams&

Completed  School  Projects