Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED...

74
1 North Bristol NHS Trust INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1

Transcript of Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED...

Page 1: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

1

North Bristol NHS Trust

INTEGRATED PERFORMANCE REPORT

August 2015 (presenting July 2015 data)

V1

Page 2: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

2

Executive Summary

July 2015

Access – During July the Trust achieved the 4 hour A&E target with performance at 96.2% this is the second month in a row in line with the planned trajectory. For the RTT backlog NBT exceeded its trajectory for 2015/16 RTT incomplete performance 3,891 vs. a target of 4,216. The specialities of T&O, Spinal, General Surgery, Neurosurgery, and Neurology make up 74% of the overall backlog and each have demand and capacity plans in place to improve the position going forward to support the trajectories. The Trust achieved 99.16% diagnostics within 6 weeks achieving the target ahead of the planned trajectory. The final position of cancer targets in June showed the Trust had delivered on 3 of the 8 cancer waiting targets. The 2 week wait target was met in May but failed in June partially due to national problems with a new e-referral system which are now fixed. The un-validated July position currently has the Trust passing 4 of the 8 key targets though a pass is anticipated for the 2 week target once full validation is complete. Safety – For the safety thermometer Harm Free Care performance of 95.4% exceeded the target of 94%. For HCAI the year to date 32 reported cases is significantly higher than the Trust target, and during July the Trust is investigating the first hospital acquired MRSA since September 2013. Patient Experience – at the end of July overdue complaints has reduced to 15, the lowest position for 15 months. Workforce - From 1st April to 30th July 479.7 WTE staff have been recruited against the internal 571 WTE target. Additional recruitment actions including increased induction frequency are planned from August. Sickness at 4.2% has reduced in the last month. Finance - For the year to date the Trust is £5.4m adverse to plan with the primary drivers being lower than planned elective income of £2.5m, unidentified savings of £0.6m, pay overspends of £2.1m, and a small non-pay overspend.

Page 3: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

3

Key / Notes

Unless noted on each graph, all

data shown is for period up to,

and including, 31st July 2015.

All data included is correct at the

time of publication. Please note

that subsequent validation by

clinical teams can alter scores

retrospectively.

All target lines:

All improvement trajectories:

DASHBOARD KEY:

Perf worsened & below target

Perf worsened, but above target

Perf worsened, no target

Perf improved but below target

Perf improved & above target

Perf improved, no target

Perf stayed same, below target

Perf stayed same , above target

Perf stayed same , no target

Contents

CQC Domain / Report Section

Sponsor/s Page Number

Responsiveness Director of Operations & Medical Director

4

Safety & Effectiveness Medical Director, Director of Nursing, & Director of Facilities

24

Safe Staffing Director of Nursing 27

Caring Director of Nursing 47

Well Led Director of People & Organisation Health and Medical Director

55

Finance Director of Finance 67

Regulatory View Chief Executive 73

Annual Calendar n/a 76

Directorate/Group Abbreviation Glossary CCS Core Clinical Services CEO Chief Executive Clin Gov Clinical Governance IM&T Information Management Med Medicine MSK Musculoskeletal

Non Cons Non-Consultant Ops Operations Renal Renal Transplant & Outpatients Surg Surgery W&Ch Women’s & Children’s

Page 4: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

4 RESPONSIVENESS SRO Kate Hannam Director of Operations

Section Summary

Improvements & Actions

July’s 4 hour A&E performance was 96.2% against a target of 95% and has therefore exceeded the planned trajectory and the national standard for the second

month in a row. Attendances were 7,195 overall vs. a 2014/15 average of 7,114, non-elective admissions were 4554 overall vs. a 2014/15 average of 3759. The

Urgent Care Recovery Plan (UCRP) and its four work streams detail the actions by both the Trust and partners to continue to perform against the 4hr standard.

The NBT Internal Flow Priorities include:

Impact of Better Board Rounds project and the SAFER checklist, supported by ward level metrics and dashboards – 0.5 day length of stay reduction across

medical wards

Minimising delays for internal services; therapies, pharmacy, transport, deep cleans etc.

Improved implementation of Criteria Led discharge

Reconfiguration of the AAU to an Acute Medical Unit by 1st July, followed by implementation of an acute frail elderly unit in September

Revision of the Ambulatory Emergency Care model (AEC)

Expansion of Discharge to Assess, reduction in bed days associated with complex (DToC) patients building on the system’s capacity & demand model for

the external resource required (POC, placements etc.) to deliver a step change in the number of patients on the LHPD and hence improve 4hr sustainability

due to the targeted reduction in bed occupancy.

The Trust exceeded its trajectory for 2015/16 RTT incomplete performance 3864 vs. a target of 4216. The following specialties make up the majority of the

incomplete backlog; T&O & Spines (42%), General Surgery (14%), Neurosurgery (9%), Neurology (9%) and hence are the main focus for RTT recovery plans.

We continue to perform above our spinal Orthopaedic trajectory for patients waiting over 52 weeks for treatment (clearance January 2016), the Adult Epilepsy

Surgery Programme (AESP) 52 week breaches for July were 49 (planned clearance January 2017). Sub specialty IMAS modelling is to be undertaken in

Neurosciences in August to provide a revised 52 week forecast for non Epilepsy Patients given the imbalance in in-patient capacity (especially for craniotomy

and Neuro Surgical spinal work).

ED Breach Trends

The principle reason for breaches in July was bed availability (37%), followed by waits for ED assessment (24%). Since the reconfiguration of the AMU Medicine

for the first time in a year is meeting the BNSSG target of less than 20% of expected patients being diverted to ED. Breaches were spread more evenly

throughout the week in comparison to previous months, but the drop in weekend discharge numbers mean Monday’s FLOW issues on Sunday and into

Monday’s. The total number of medically fit for discharge days was 4488, equating to 145 occupied beds across the month. This is a reduction of by 26% from

January 2015.

Areas of Concern

The system continues to monitor the effectiveness of all actions being undertaken, with weekly and daily reviews. The main risks identified to the Urgent Care

Recovery Plan are as follows:

UCRP Risk 4: Lack of community capacity and/ or scope to provide Discharge to Assess pathways to reduce the size of the LHPD. Bristol DtA comes on line as

of 20th July 2015, but the SG launch is not anticipated until at least October.

UCRP Risk 5: Appropriate nursing and therapies staffing within NBT to enable flow given vacancy rates and hot spots such as AMU

UCRP Risk 6: LoS reductions and bed occupancy targets in the bed model are not met leading to performance issues

UCRP Risk 7: Temporary closure of Elgar beds for refurbishment for 12 weeks from July 2015, Bristol mitigation plan to be met by DtA roll out, SG plan reliant on

existing capacity and hence more high risk. The Trust is seeking to combat this through improvements in its own LOS and use of escalation capacity

Page 5: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

5

Access Standard

July 2015 Most recent quarter’s

performance (Quarter 1 Apr -

June) against national

target

Quarterly Trend (Q4 vs Q1)

Against national target

Against NBT

Trajectory

Trend from last month

Performance to be

achieved by… (as per trajectory)

Emergency Attendances – waits under 4 hour standard vs total attendances (95% target)

Achieving 84.4%(Q4) to 91.1% (Q1)

Referral to Treatment - % incomplete pathways <18 weeks (92% target)

Not met in 15-16

84.4% (Q4) to 86.1% (Q1)

Referral to Treatment - % within 18 weeks of GP referral for non-admitted patients (95% target)

Feb 2016 91.1% (Q4) to 93.3% (Q1)

Referral to Treatment - % within 18 weeks of GP referral for admitted patients (90% target)

Not met in 15-16

80.6% (Q4) to 80.3% (Q1)

Trust wide Referral to Treatment Backlog

Not met in 15-16

4141 (Q4) to 3869(Q1)

Cancelled Operations – same day - non-clinical reasons (0.8% target)

Oct 2015 1.83% (Q4) to 1.33% (Q1)

Cancelled Operations – 28 day re-booking breach (0 target)

Aug 2015 15 (Q4) to 7(Q1)

Responsiveness

Summary Dashboard Board Sponsors Director of Operations

Please note: Subsequent validation by clinical teams can alter scores retrospectively. Data is correct at time of publication.

96.2%

94.2% 91.3%

81.6%

1.3%

6 2

1.0%

4216

95.0%

81.6%

86.5%

3891

84.9%

Page 6: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

6 Responsiveness

Urgent Care Board Sponsor Director of Operations

Commentary

Overall July’s performance against

the 4 hour target was 96.2% with

waits for ED assessment being the

main cause of breaches.

The actions in the URCP aim to

reduce overall bed occupancy to

allow the trusts to better cope with

variation in ED attendances and

admissions throughout the week.

In July breaches were spread

more evenly across the week than

in previous months. Monday’s

remain a concern following the

reduced emergency discharge

levels across Saturday and

Sunday.

Page 7: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

7 Responsiveness

Urgent Care Admission Rates Board Sponsor Director of Operations

Commentary

Performance on Ambulance

turnaround times (15 minutes to

offload) has significantly improved

this year in comparison to 2014/15.

However, a change in national

performance reporting has meant

the 10% tolerance has been

eradicated and we are re-casting

internal trajectories against a zero

tolerance to 15 minute handover

delays.

Emergency admission numbers

across the last 5 months have

remained largely static. Bed

occupancy for July was 89.6%

Patient numbers in the ED corridor

have fallen to pre winter levels and

the average time spent per patient

is at it lowest level since June

2014. Driving down this indicator

is a key focus of the ED Quality

improvement plan. Key

developments include modification

of the consultant led rapid

assessment model, double triage,

remodelling of AEC and the overall

UCRP to improve flow.

Page 8: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

8 Responsiveness

Length of Stay Board Sponsor Director of Operations

Commentary

The number of patients with

Length of Stay over 14 days has

remained largely static over the

last 6 months. Weekly reviews by

senior nursing staff of all patients

over 10 days is underway.

BNSSG commissioned modelling

of complex discharges C&D

reinforced URCP plans to reduce

overall leaving hospital patient

database numbers, in light of the

disproportionate impact this

patient cohort has on occupied

bed days. The main cause of

MFFD delayed days remains wait

for assessment.

The system’s agreed approach is

expansion of Discharge to assess

pathways (Bristol went live on 20th

July 2015, SG not planned until at

least October 2015).

For the month of July the total

number of medically fit for

discharge days has reduced by

26% from January peaks

Page 9: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

9 Responsiveness

Discharges / Transfers Board Sponsor Director of Operations

Commentary

Delayed transfers of care

(monitored via the Leaving

Hospital Patient Database), in

particular, due to waits for social

work assessment remain above

nationally accepted levels (3.5%

target).

An independent review of the

classification of DTOCs across

Bristol was undertaken in April –

and it has been agreed in principle

at a system’s level to move to a

new recording system in October

at the same time as the launch of

Discharge to Assess pathways and

an Integrated Discharge Team.

.

Delayed Transfers - in month total COO22 035

Page 10: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

10 Responsiveness

Length of Stay Board Sponsor Director of Operations

Commentary

Elective remains below the Dr.

Foster expected level.

Non-elective length of stay remains

above target level and hence is the

main focus of NBT’s patient flow

projects, particularly in relation to

rehab patients and those requiring

input from health and social care

partners.

LOS targets have been agreed by

directorates and factored into the

overall Bed model. Progress vs.

target is being monitored via

monthly Directorate Performance

Reviews. Medicine’s LOS was 5.1

(including 0 day LOS) overall in

July, their lowest level since the

move to Brunel.

Page 11: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

11 Responsiveness

Emergency Department Dashboard Board Sponsor Director of Operations

Time to initial assessment and time to treatment data is undergoing

further validation and is expected to worsen once fully cleansed.

Page 12: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

12 Responsiveness

Patient Flow Work stream Board Sponsor Director of Operations

Commentary

The number of patients with Length

of Stay over 14 day has shown a

slight increase in July. Bristol CCG’s

and Bristol LA Discharge to Assess

pathways launched as of 20th July

2015 with new HomeCare package

providers coming on line in mid

August. The impact on performance

will be monitored through LOS KPIs

and the total number of MFFD days.

SG D2A roll out at scale will not

occur until October 2015. In the

mean time there has been step

change take up in the SG Sirona

D2A pathway one, where we are

regularly achieving maximum

discharges daily.

AEC project will be re-launched 13th

August 2015 and will aim to improve

the percentage of patients going

home within 2 midnights (presently

static). Project meetings have now

been held for Pharmacy and

Transport with planned outcomes to

improve discharge processes.

Complex Acute Unit go live delayed

by a month (until 1St September)

due to nursing workforce issues .

However, the reconfiguration of

short stay care of the elderly beds to

32A (CAU) has happened by

default, as a direct impact of the

AMU go live on 1st July.

Percentage discharge pre 12pm Emergency patients discharged within 2 midnights

COO25 001

COO25 002

Page 13: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

13 Responsiveness

Referral to Treatment All Specialties Board Sponsor Director of Operations

Commentary

Following the planned re-fresh of

RTT trajectories in Q1, the forecast

backlog position has changed from

2,759 to 3,896 by 31st March 2016.

Overall there was no change to 16

out of 26 specialties including T&O

(including spines 42% of the

backlog as of June 2015).

However, there were small

changes in 4 specialities (<50

patients) and significant

deterioration in 6 specialties:

Neurology, Neurosurgery,

Neuropsychiatry, Renal, Urology

and Gastroenterology.

For July, all bar two specialties

(Endocrine and Clinical

immunology) met the revised

backlog numbers.

The Trust will return to NADM

compliance in Qtr 4 of 15/16, but

will not meet the ADM or

incomplete target in year due to

the size of the T&O &

Neurosciences over 18 weeks

back log.

.

Page 14: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

14 Responsiveness

Referral to Treatment Specialty Level & 52 week waits Board Sponsor Director of Operations

Commentary

There were 278 patients waiting

over 52 weeks for treatment

(incompletes) at the end of July –

214 in spinal surgery, 15 in

neurosurgery and 49 in neurology

(AESP). The spinal position

continues to be favorable to the

trajectory (clearance by the end of

Jan 2016). The AESP 52 week

clearance is not until January

2017.

The diagnostic target was met in

July at 99.16%. Echocardiography

has exceeded its recovery

trajectory (December 2015) at

100%. At a Trust level we are not

expecting sustained delivery of the

target until December 2015.

Further Diagnostic IMAS modelling

is underway in all modalities. As

predicted the CT position did not

met the 99% standard (97.77%);

cystoscopy narrowly missed

98.74% due to 2 patient breaches

COO 040 999

Diagnostics 6 week wait

(Orange = Improvement Trajectory)

DOO058 999

Page 15: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

15 Responsiveness

Cancelled Operations Board Sponsor Director of Operations

Commentary

July’s rate of cancelled surgery on

the day was above trajectory

(1.3% vs. 1%) – the majority of

which was due to a lack of theatre

time. Specialties are attempting to

schedule sessions according to

average minutes per procedure to

reduce lost time and overruns.

Mediroom turnover and downtime

between cases continues to be a

focus; the Theatres Board is to

oversee a Mediroom Efficiency

Improvement plan.

There were 6 patients who were

unable to have their operation

rebooked within 28 days in June.

This equates to lost income of

approximately £30k.

2 urgent patients had their

operations cancelled for a 2nd time

for which detailed review for

accuracy is underway.

COO0010 999

Cancelled operations 28 day re-booking breach

(Orange = Improvement Trajectory

Target is 0)

COO08 003

Cancelled Operations (Orange = Performance Trajectory)

COO007 002

Number of urgent operations cancelled

for the second time (target is 0)

Page 16: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

16

Standard

June 15 July 2015 Q1 Performance

(Apr – Jun 15) against

National Target

Quarterly Trend – Q4 vs Q1 (un-validated

position)

Final June 15 position

Against National Target July 15

Against NBT

Trajectory

Trend from last

month

Patients seen within 2 weeks of an urgent GP referral (93% target)

92.5% (Q4) to 92.2% (Q1)

Patients with breast symptoms seen by specialist within 2 weeks

(93% target)

n/a 96.1% (Q4) to 99%(Q1)

Patients receiving first treatment within 31 days of cancer diagnosis

(96% target) 95.2% (Q4) to 89.1% (Q1)

Patients waiting less than 31 days for subsequent surgery (94%

target) n/a 93.0%(Q4) to 90.8% (Q1)

Patients waiting less than 31 days for subsequent drug treatment

(98% target)

n/a

100% (Q4) to 100% (Q1)

Patients receiving first treatment within 62 days of urgent GP

referral (85% target) 84.6% Q4) to 77.4%(Q1)

Patients treated 62 days of screening (90% target) n/a 90.7% (Q4) to 91.8%(Q1)

Patients treated within 62 days of consultant upgrades (90% target)

n/a

84.9% (Q4) to 83.8% (Q1)

Responsiveness

Cancer Summary Dashboard Board Sponsor Medical Director

Please note: Validation is still on-going for July figures.

92.5%

100% 100%

98.0%

90.9%

77.9%

100%

89.1%

93.8%

90.5%

93.1%

76.4%

91.4%

75.6%

88.0%

88.0%

Page 17: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

17 Responsiveness

Cancer Board Sponsor Medical Director

Commentary

The final position of cancer targets

in June showed the Trust had

delivered on 3 of the 8 cancer

waiting targets. The 2WW target

was met in May but failed in June

partially due to national problems

with a new e-referral system.

There was also a larger than

anticipated increase in skin cancer

referral. A pass position is

anticipated in July following

resolution of the e-referral issue.

Performance on the 62 day

pathway has deteriorated in Q1

15/16. This is predominantly due to

problems in the Urology pathway

which is receiving increased focus

from the management team.

In June the 2 week wait breast

referral target has been met, so too

has the 31 day subsequent drugs

treatment target and the

consultant upgrade target.

.

COO16 004

COO013 009

COO15 005

Page 18: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

18 Responsiveness

Cancer Board Sponsor Medical Director

Commentary

The national deadline for validated

July data is 4 September and the

team internally are working

towards this. The ‘unvalidated’

position currently has the Trust

failing 4 of the 8 key targets though

a pass in anticipated for the 2WW

once full validation is complete.

In addition to work on the urology

pathways the lung and upper GI

pathways have been mapped

between NBT and UHBristol to try

to address delays. Clinical

discussions are also occurring to

map the pathway for gynaecology

patients to attempt to expedite this

pathway across the Trusts.

Page 19: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

19 Responsiveness

Cancer Board Sponsor Medical Director

Commentary

All patients on a cancer pathway

are actively tracked by the cancer

services team using detailed

Patient Tracking Lists and potential

delays to pathways are escalated

to directorate teams and clinical

colleagues.

If a patient breaches a cancer

waiting times treatment target the

pathway for the patient is reviewed

to identify the reason for the

breach (which is recorded on the

cancer register) and the clinical

team are asked to comment on

any potential risk this delay has

had on the patient care or potential

outcomes. Actions, risks or

queries are actioned as

appropriate within the directorate

or the wider cancer services team.

The table illustrates the timeframe

patients on a 62 day pathway were

treated in and further internal

analysis of all the patients that wait

beyond 62 days is conducted post

validation.

Referral to Treatment 62 Day PTL: Number of patients treated within the specified period including tertiary referrals (irrespective of when referral received)

Number of patients Number of Days

No. of Patients Treated in the Period

Mean Wait

Max Wait With-in 31

32 -38

39 - 48

49 - 62

63 - 76

77 - 90

91 - 104

After 104

Breast 38.5 47 100 6.0 3.0 12.0 13.0 3.0 1.0 0.5 0.0

Colorectal 8.5 55 86 0.5 1.0 0.0 5.0 1.0 1.0 0.0 0.0

Gynaecology 3.5 57 79 0.0 0.0 0.0 3.0 0.0 0.5 0.0 0.0

Haematology 5.0 75 106 1.0 0.0 0.0 1.0 1.0 0.0 1.5 0.5

Lung 9.5 76 215 1.0 0.0 2.0 3.0 1.0 1.0 0.0 1.5

Other 0.5 54 54 0.0 0.0 0.0 0.5 0.0 0.0 0.0 0.0

Sarcoma 1.0 27 27 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Skin 32.0 30 61 17.5 4.0 8.5 2.0 0.0 0.0 0.0 0.0

Upper GI 3.5 63 115 0.0 0.0 1.5 1.0 0.5 0.0 0.0 0.5

Urology 25.5 91 249 2.5 0.5 4.0 2.0 3.5 0.5 4.0 8.5

TOTAL - Excluding

Breast Symptomatic 127.5 57 249 29.5 8.5 28.0 30.5 10.0 4.0 6.0 11.0

Page 20: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

20 Responsiveness

Cancer Board Sponsor Medical Director

The table illustrates the timeframe

patients on from their decision to

treat date until the date of actual

treatment.

Decision to Treat to Treatment 31Day PTL: Number of patients treated within the specified period including tertiary referrals (irrespective of when referral received)

Number of Patients Number of Days

No. of Patients Treated in the Period

% of patients treated who are Urgent GP referrals

No of patients treated who are Urgent GP referrals

Mean Wait

Max Wait

Within 31

32 -38 39 - 48

49 - 62

63 - 76

77 - 90

Brain 11 0 0 5 27 11 0 0 0 0 0

Breast 68 48.53 33 18 35 60 8 0 0 0 0

Colorectal 21 33.33 7 9 31 21 0 0 0 0 0

Gynaecology 1 0 0 20 20 1 0 0 0 0 0

Haematology 17 29.41 5 3 15 17 0 0 0 0 0

Lung 4 100 4 0 0 4 0 0 0 0 0

Sarcoma 4 50 2 33 65 2 1 0 0 1 0

Skin 55 58.18 32 15 31 55 0 0 0 0 0

Upper GI 2 50 1 15 30 2 0 0 0 0 0

Urology 76 42.11 32 26 119 50 3 5 7 7 0

TOTAL 259 44.79 116 17 119 223 12 5 7 8 0

Page 21: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

21 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

21 Responsiveness

Outpatients Work stream Board sponsor Medical Director

Booking & Clinic Utilisation has

remained static. 3 specialties have

undertaken their review of

appropriate clinics to remove HOT

clinics and drop in clinics. All

specialties are undertaking this

clinic review.

DNA Rates: The DNA rate for

Jun-15 has been validated to an

accurate position of 9.1% against

a target of 5%. Further work is

required to accurately record non

attendance when the patient has

called in advance to inform us that

they can not attend. Clinics with a

high DNA rate are being targeted

if they are yet to use the reminder

service.

Page 22: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

22 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

22 Responsiveness

Outpatients Work stream Board sponsor Medical Director

Commentary

Outpatient attendances are up

6.2% from those in 2014/15.

After a strong June

performance attendances in

July were below SLA.

OP procedures are above SLA

and actual activity from last

year

Page 23: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

23 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

23 Responsiveness Theatres Work stream Board Sponsor Director of Operations

Commentary .

Commentary Cases per day and session utilisation along are based on SLA and RTT recovery plans. Of concern, elective CPD has dropped by 2 per day since June and in list utilisation has dropped by 1% in month. Contributing factors include: • NEL demand above SLA levels

impacting elective throughput General Surgery : 14.4% Neurosurgery: 2.3% Plastic Surgery: 0.9% T&O: 18.6% Urology: 21.4% Gynaecology: 37.6% On the day cancellation rates are above plan (1.3% vs. target 1%). 90% of same day cancellations categorised as List Overran are due to non Theatre reasons (complications or late changes). • Consultant annual leave and lower

than expected cross cover rates (Target of 98% cross cover) and case mix changes on those lists that did run

• WLI requests in July dropped by 10% (40 down to 36) Acceptance levels are consistent at 50% of those sessions requested. Urology are the primary requestor for these lists in both July and YTD.

CC staffing trajectory remains on plan with only 2 patients cancelled due to staffing (one consultant and one nurse related both due to sickness on the day) Directorate recovery plans (co-agreed with the Theatres team) are to be presented at the September Theatres Board.

DOST 01 002

DOST 01 001

DOST 01 003

Page 24: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

24

QUALITY PATIENT SAFETY & EFFECTIVENESS SRO Chris Burton Medical Director & Sue Jones Director of Nursing

Section Summary

Improvements & Actions

Medicines management remains good with reducing missed doses

Efforts continue to ensure compliance with VTE, the current focus being on timely return of medical records.

Harm free care was the best in month for 12 months and above the national average at 95.4%

Trends

HSMR stable and better than benchmark

Outpatient effectiveness is improved compared to 12 months ago but below requirement

The dementia CQUIN is now being consistently achieved

Areas of Concern

The rate of incident reporting per 1,000 bed days has been decreasing, actions are in place to improve

reporting with a focus on the importance of learning from low harm and near miss incidents with a new safety

newsletter as well as improving feedback to staff who have reported to close the loop.

Concerns regarding C-diff numbers and one MRSA bacteraemia in month

Cleaning and standards of infection prevention and control have been the focus for the month, with all Matrons

undertaking Saving Lives No8 Audits and working together with facilities managers at the joint cleaning group.

Page 25: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

25 XXXX

XXXXX Board Sponsor XXXX

25

Patient Safety Dashboard

Safety

Summary Dashboard Board Sponsors Director of Nursing & Medical Director

Please note: Subsequent validation by clinical teams can alter scores retrospectively. Data correct at time of publication.

Standard (target)

July 2015 Most recent quarter’s

performance (quarter 1 Apr – June 15 against national target

Quarterly Trend (Q4 vs Q1) Performance

against national target / contract

Against NBT Trajectory

Trend from last month

Performance to be achieved by..

(as per trajectory)

Never Event Occurrence by month (0 target) n/a

Managed via Quality

Committee 1 event (in Q4) to 1 event (in Q1)

Safety Thermometer – overall compliance (94% internal target, 92% external target)

n/a Achieving 92.6% (in Q4) to 93.8% (in Q1)

Malnutrition Screening (90%) June 2015 81.4% in (Q4) to 86.9% (in Q1)

Hand Hygiene Compliance (95%) n/a

Managed via Infection Control

96.1% (in Q4) to 95% (in Q1)

MRSA (0 per month trajectory) n/a Achieving 0 cases in 2014/15

C-Difficile (<5 per month) n/a

Achieving quarterly

14 cases (in Q4) to 21 cases (in Q1)

MSSA (<1.5 per month) n/a Achieving 5 cases (in Q4) to 5 cases (in Q1)

Venous Thromboembolism Screening (95%) one month in arrears

n/a Managed via Thrombosis Committee

94.6% (in Q4) to 94.1% (in Q1 to date)

Dementia (find/assess/refer CQUIN) (90%) one month in arrears

n/a Achieving 92.6% (in Q4) to 91.8%(in Q1)

86.5%

94.5%

96.8%

95.4%

1

1

94.7%

9

5

Page 26: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

26 Safe Staffing

Nursing Workforce Ward Early Warning Trigger Tool (QUESTT) Board Sponsor Director of Nursing

Commentary

QUESTT is RAG rated with wards

scoring 12 and above recorded as Red.

6 wards have not completed in July 2015

These areas are being reviewed by the

Heads of Nursing and Matrons to ensure

any concerns are reviewed and monthly

submission occurs.

2 wards flagged ‘red’ with a score of 12

and 13

Gate 7A

Reason for an increase in score to 12

relates to the ward having 2 or more

complaints this month. This is in addition

to vacancy rates of RN’s, sickness rates

and unfilled shifts .

Action taken: The complaints were not

formal but related to patient discharges

and the learning and action required

from these are being disseminated .

Recruitment has taken place to fill the 5

RN vacancies with 3 RN’s start dates

planned in the next 3 months .

Gate 8A

Reason for trigger of 13 : New ward

sister in post, numbers of vacancies,

unfilled shifts, sickness and 2 or more

formal complaints in month

Action taken: Interim Ward Sister

demonstrating strong leadership, RN and

HCA vacancies covered by staff moved

from Elgar house closure and additional

recruitment fully underway to ensure in

place prior to Elgar house reopening.

Complaints being investigated and

responded to promptly.

Page 27: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

27 Safe Staffing

Nursing Workforce Board Sponsor Director of Nursing

This month has remained static following

the expected drop in fill rates last month

with the new staffing establishments in

place. This is expected to improve over

the next 2 months with the intensive

recruitment which has taken place.

Red flagged areas for July with less than

80% fill rate are:

NICU: The unit fill rates are improving

with the only shift flagging being CA fill

rate on night duty. The unit continues to

use RN/RM where needed to ensure the

unit is safe. This is visible in the RN fill

rate being over 100%

Percy Phillips: The change to the

template for this unit came into place on

the 22nd June. A recruitment plan is in

place which includes students about to

qualify, as staff are not yet in post bank

staff are requested . When these bank

shifts are not filled, staff are moved from

within the unit for short periods as

required, based on a risk assessment of

all the areas by a senior midwife

coordinator.

Mendip Ward: This month the postnatal

ward and birth suite have been reported

separately, with this the figures have

shown a drop in fill rate on the day shift

RM and the night shift CA. The Matron

for the area is happy that the staffing

levels are safe on the unit and that staff

are moved around the service as

required based on the risk assessment

of the areas as assessed by a senior

midwife coordinator. In order to maintain

safe staffing the birth suite is closed if

necessary. The birth suite closure

occurred on 12 occasions this month.

The numbers of hours Registered Nurses (RN) and Care Assistants (CA), planned and actual, on both day and night shifts are collated manually by each gate/ department every month. This data is uploaded on UNIFY for NHS Choices and also on our Website showing overall trust position and each individual gate level. Further commentary for these areas and the breakdown for each of the ward areas are available now on the external webpage.

June Data 2015 Day shift Night Shift

RN/Midwife Fill rate % CA Fill rate % RN/Midwife Fill rate CA Fill rate

Cossham 94.7% 93.8% 96.8% 100.0%

Riverside Unit 98.8% 100.9% 100.0% 100.0%

Southmead 94.7% 121.4% 97.8% 135.5%

Page 28: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

28 Safe Staffing Acuity & Dependency

Board Sponsor Director of Nursing

Guidance from NICE and from NHS

England have clearly stated that safe

staffing is not just about numbers it is

also about the acuity and

dependency (A&D) of patients..

Since March 2015 all inpatient wards

excluding Midwifery have been

recording patient A&D twice a day

using the SafeCare Module on

Health Roster.

This month is the third month of A&D

reporting. The first graph shows the

compliance with using the tool at

directorate level. The second

provides the actual hours of care

required based on the Shelford tool

in relation to the planned rostered

hours on the inpatient units. The pie

chart gives the patient A&D types at

a trust wide level.

The data shows that the actual hours

rostered are greater than the

required hours. With the current

vacancies and fill rates this is

unlikely to be the case. This is

evident in all directorates with the

exception of W&C which show that

the required hours of care is greater

than the planned. It is however noted

that this is one of the least compliant

areas for data input. This is being

reviewed with the Heads of Nurses

and at the E rostering Operational

group. It is believed that the

accuracy of this data will continue to

improve as additional staff are

trained to use the SafeCare module.

Required Hours of Care V Actual Nursing Hours Rostered

Page 29: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

29 Safe Staffing

Maternity Board Sponsor Director of Nursing

Commentary This report provides information

about midwifery staffing and will

track for the board, the occasions

when Delivery Suite is unable to take

new admissions and why.

The Midwife to birth ratio has

remained at 1:32 for the third month.

This reflects the improved sickness

levels for the maternity unit and

ongoing recruitment to funded

establishment.

The improved staffing has also

reflected in the number of times the

Delivery Suite has closed. Since Oct

2014 (when 10 WTE midwives were

employed) and June 2015 (when

11wte were added to the

establishment) the trend has

remained persistently low in

comparison to prior to Oct 2014

A rolling programme of recruitment

was introduced in April 2015 and this

is helping to ensure staff are

employed in a more timely way and

includes recruiting to the new

11WTE more midwives over the next

few months. Full establishment is

expected by October 2015

Acuity and number of midwives

required is monitored for delivery

suite 4 hourly during the 24 hour

period (The Birthrate plus acuity

tool).

Midwife to Birth Ratio

Nov 14

Dec 14

Jan 15

Feb 15

Mar 15

Apr 15

May 15

Jun 15

Jul-15

1:37 1:39 1:37 1:35 1:35 1:34 1:32 1:32 1:32

DON51 999

DON53 999

No beds on wards

13%

DON52 999

Page 30: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

30 Quality Patient Safety

Additional Safety Measures Board Sponsor Director of Nursing

Serious incidents

Eight Serious incidents were reported in

July 2015:

• 3 x Falls

• 2 x Pressure Ulcers Grade 3

• 2 x Maternal deaths

• 1 x Wrong site surgery Never Event

Falls: 1 x fractured NOF, 2 x Sub Dural

Haemorrhage

Maternal Deaths

1. Patient transferred from Yeovil

following collapse with a cerebral bleed.

Yeovil NHS Trust leading on the SI

investigation.

2. A homicide under police investigation.

Never Event

A wrong level spinal procedure, the third

of this type since 2010 the last being

within the last 12 months. Immediate

action awareness raising neurosurgery,

theatres and radiology, RCA is in

progress.

Serious Incident Rate July: An increase in SI’s since June but

similar to July 2014. This reflects in the

rate of 0.275 per 1000 bed days, 0.1

above last month demonstrating a

number slightly over median range for

the Trust. Directorate figures remain

largely unchanged over the last 12

months.

Incident Reporting Overall incident reporting continues to

decrease across the Trust,. An increase

in reporting is desirable to demonstrate a

pro-active approach to patient safety in

line with comparative Trusts. Actions

aligned to the CQC action plan are in

progress to improve reporting, including

better sharing of improvements made in

response to incident reports and a new

patient safety newsletter.

Page 31: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

31 Quality Patient Safety

Additional Safety Measures Board Sponsor Director of Nursing

Patient Safety

Facilities Medical Devices

New Alerts 1 0 2

Closed Alerts 1 0 2

Open alerts (within target date)

0 1 1

Breaches of Alert target

0 0 0

Commentary Incident reporting deadlines

One SI investigation has breached the

deadline, within the Surgery Directorate.

This is now due for submission on 14

August.

Top Types of SI’s over 12 months Falls and Pressure Ulcers are the most

prevalent Serious incident types

Other SI’s include:

12 hour trolley breach 1

Delay treating deteriorating patient 2

Incorrect Test Results 2

Infection Control 1

Line insertion 1

Lost to Follow Up 2

Retained Foreign Object 1

Surgical complication 2

Unexpected Admission to NICU 1

Unintended Damage to Organ 1

Actual impact

Minor incidents have increased in July

and rated highest against moderate

incidents which have plateaued. The

clinical risk team review all moderate,

severe and catastrophic actual impact

incidents on a daily basis. There has

been a significant drop in negligible

incidents indicating an area where

further encouragement to report is

required.

The new Patient Safety Newsletter to be

issued later this month will provide

thematic feedback on actions taken

following incidents reported and more

targeted reporting of incident reporting

rates is also being developed with

directorates.

CAS Alerts

Alerts are compliant within deadlines

4

8

11

7

11

3

10

7

3 1

6 6

1

2

1

1

0

2

4

6

8

10

12

Number of Serious Incidents Closed and Open Breaching Deadlines: Aug 2014 - Jul 2015

by Date Reported to STEIS

Closed Open Breaching Deadlines

DON030 01

Data Reporting basis

The data is based on the date a serious incident is

reported to STEIS. Serious incidents are open to being

downgraded if the resulting investigation concludes the

incident did not directly harm the patient i.e. Trolley

breaches. This may mean changes are seen when

compared to data contained within prior months’ reports.

Page 32: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

32 Safety

Harm Free Care (Catheter on-going care Falls Pressure Ulcers VTE) Board Sponsor Director of Nursing

Commentary

Harm Free Care

The trusts ‘harm free’ rate in July is

95.44% against the national average

rate of 93.9%, representing the

highest in-month achievement for at

least 12 months.

The highest harm incidence was

Pressure Ulcers with 3% which is a 2%

drop from the previous month.

Overall Falls The falls rate was lower in July, 6.36 per

1000 bed days representing 186 falls,

compared to a rate of 6.62 in June.

However, there were 3 Serious Injury

falls in July in the Medicine Directorate

with 2 resulting in death. These incidents

are currently being fully investigated to

understand the root cause, take

appropriate action and share learning.

A newly appointed Falls Nurse will start

work on training front-line staff shortly,

this initiative was part of a successful bid

for improvement resources with Sign Up

to Safety. The Falls Nurse will also

support the embedding of the Falls

Bundle on the wards.

Page 33: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

33 Safety

Harm Free Care Board Sponsor Director of Nursing

Pressure Ulcers Pressure ulcer incidence for July has

increased slightly to a rate of 8.41 per

10,000 bed days.

The Trust reported no grade 4 pressure

ulcers, sustaining the year to date

internal trajectory of zero cases. There

were two Trust reported grade 3

pressure ulcers; one occurring beneath a

lower leg cast within the Surgical

Directorate and one to a patient’s

sacrum within Neurosciences. A full

investigation is in progress for each

case.

There were 22 Trust reported grade 2

pressure ulcers, sustaining the rate from

the previous month. Programmes of

training and prevention awareness

continue across the Trust to achieve a

10% reduction in Trust attributable

pressure ulcers in 2015/16 as part of the

‘Sign Up to Safety’ campaign.

VTE (one month in arrears) The trust has to report fails for April /

May / June despite all three months

being on a trajectory to pass once the

coding of outstanding notes catches up.

The delay in notes being received by

coding remains a key factor. There are 3

main actions that will address this as part

of the broader notes management action

plan, which involve additional

administrators at the hospital gates,

quicker typing turnaround and reduction

in temporary folders.

DON55

999

Page 34: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

34 Safety

Additional Safety Measures Board Sponsor Director of Nursing

Commentary

Cardiac Arrest Calls The rolling mean of cardiac arrest calls is

0.67 per 1000 discharges (0.38 for July,

6 confirmed calls), which remains well

below the national average rate of 1.9

per 1000 discharges (which is

recalculated quarterly). There is a 25%

reduction in the number of cardiac

arrests compared to April – July last

year. There continues to be a reduction

in numbers year on year.

Dementia The current figures confirm continuing

compliance with CQUIN requirements,

which reflect the ongoing good quality of

patient review and referral. The dementia

trainer has been instrumental in

maintaining the levels achieved to

support completion of the daily audit.

Catheter Compliance Catheter care is audited using the

national ‘saving lives’ audit tool, which

measures 10 different components.

Total compliance in July was 88.8%

increasing from 85%, against national

benchmark of 95%.

Deeper analysis of the overall

compliance scores has confirmed that

catheter care delivery shows high levels

of compliance (above 90%) but the

issues pulling down the overall score

relates to the Daily Documentation of the

need for the catheter and recording that

the catheter bag has been correctly

changed. Catheter care record keeping

has been the focus of Safety

Thermometer day on 15th July

.

.

Page 35: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

35 Safety

Additional Safety Measures Board Sponsor Director of Nursing

Commentary

WHO Checklist Reported compliance with checklist in

July has dropped marginally to 96.70%,

however the rolling 12 month compliance

has improved to 96.05%.

The headline figure (blue line) covers 2

out of the 3 checklist questions being

responded to correctly. This usually

indicates (from prior audits) a lack of

evidence, rather than non completion

and is followed up and then corrected if

warranted. The red line tracks all 3

questions being completed. The gap

between the two should close over time

upon follow up of exceptions with clinical

teams.

Main directorate breakdowns are;

• Gynaecology 98.25%.

• Surgery 98.05%

• Musculo-Skeletal 97.80%,

• Neurosciences 97.50%

Nutrition Trustwide compliance for July was

85.5% which reduced from last month’s

compliance of 89.5%, (target 90%).

The daily list of patients admitted the

previous day who has not had their

nutrition risk assessment continues to be

reviewed by the ward sisters which then

enables ward nurses to ensure

assessment is achieved within the 48

hours.

.

WHO Checklist Compliance

(Orange = Stretch Target)

Page 36: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

36 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

36 Safety

Medicines Management: Medicine Reconciliation & Missed Doses Board Sponsor Medical Director

Commentary

Medicines Reconciliation and Missed

Doses data is available one month in

arrears.

Missed Doses

Results for June show further

improvement. The aim is to return to

13/14 performance.

Medicines Reconciliation

Meds rec on admission continues to

meet the Trust standard. The NBT

work continues to set the national

standard and is being presented as

an exemplar of good practice

internationally.

The work was shortlisted for the

Patient Safety Awards (July 2015)

and the Pharmaceutical Care

AWARDS (June 2015) and has now

been shortlisted for

“I love my Pharmacist” Award run by

the Royal Pharmaceutical Society..

Work is now starting on looking at

Meds Rec on discharge and this will

be linked with work undertaken with

the WEAHSN.

Page 37: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

37 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

37 Safety

Medicines Management: Medicines Related Incidents Board Sponsor Medical Director

Commentary

The Medication Safety Officer (MSO)

is Pharmacist Jane Smith. NBT has

a multidisciplinary “Medication Safety

Subgroup” to review all drug related

incidents from eAIMS. There is feed

back to reporters and managers to

improve accuracy of reports. Data is

shared via a dashboard through the

Medicines Governance Group.

Major incidents

No incidents were reported in June

2015 as “major”.

Themes / Types / NPSA alerts

The most common causes of

incidents are shown and reflect the

past year. The NPSA alert category

– shows incidents related to any

NPSA / PSA alerts issued by NHS

England.

There has been a decrease in all

reporting in the Trust during June

2015.

Actual Impact Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15

Near Miss/Insignificant 101 84 94 68 103 46 72 72 69 70 82 63

Minor/Moderate 8 11 7 10 16 29 31 31 36 43 24 24

Major/Catastrophic 0 1 2 0 0 0 1 0 0 0 0 0

Total 109 96 103 78 119 75 104 103 105 113 106 87

Incidents involving high risk drugs MD13 999

Themes

July 14 – June 15 MD16 999

NPSA Alerts

July 14 – June15

MD15 999

Type of Medication Error

July 14 - June 15

MD14 999

Page 38: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

38 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

38 Safety

Infection Control Board Sponsor Medical Director

Commentary

MRSA

One MRSA bacteraemia trajectory

case reported in July 2015. A full

investigation is in progress, (early

findings identified risk factors of high

risk patient already colonised with

MRSA on admission).

C. Difficile

9 Trust responsible cases for July. 7

in Medicine,1 in Neuro and 1 in

Surgery.

Year to date 32 reported cases

which is significantly higher than the

Trust target. Work continues with

commissioners to consider whether

lapses of care contributed to

development of each case and this

will be shown in future reports. The

TDA visited clinical areas in July

providing valuable feedback

concerning systems / processes and

practical issues where improvements

are to be made. Clinical and facilities

teams are concentrating on

improving cleanliness.

MSSA

5 Trust responsible cases for July. 1

each for Surgery and Medicine and 3

in Neurosurgery. Root Cause

Analysis is in place for each case.

Year to date 10 Trust reported cases

against an internally set target for

2015/16 of 18 cases. Improvement is

focusing on the practice for the

management of indwelling devices.

Page 39: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

39 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

39 Safety

Infection Control Board Sponsor Medical Director

Pseudomonas

The Trust has reported a higher than

usual reported incidence of

Pseudomonas aeruginosa in the

Intensive Care Unit. An incident

group is progressing relevant

actions. Early indicators are that

disinfection of water outlets has been

successful. Water testing continues,

alongside monitoring of practice

issues and cleaning standards.

Further mitigations are being

considered. Ongoing testing of

augmented care areas in line with

DH guidance has commenced.

National and Regional

benchmarks

Rates of MRSA in NBT compare

favourably with national and regional

benchmarks.

Rates of C.difficile are below the

national benchmark in latest

available data but that does not

include the more recent increased

rates reported above.

Hand Hygiene

The Trust Hand Hygiene compliance

is within the Trust standard. Control

of Infection Committee meeting

continues to focus on ensuring

sustainable performance of hand

hygiene.

Page 40: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

40 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

40 Safety - Sterile Services Department – Theatre Tray Set Production activity

and Non-Conformance Rates Board Sponsor – Director of Facilities

Commentary

The monitoring of sterile services is

regulated via our Notified Body

(British Standards Institute).

Production – At 12,784 tray sets

this is the most productive month

that Sterile Services has experienced

since the start of the year. Although

steadily rising since January the

production figures did plateau during

May and June. However during the

month of July the number of tray sets

produced rose by 370. Additional

agency technicians were employed

to meet this activity demand. Washer

capacity within the Quadrant unit

was also stretched but managed.

Non-conformances – These figures

continue to fluctuate a little in specific

areas. This month has seen a small

rise in ‘missing’ instruments.

Although both theatres and SSD are

working hard to understand and

resolve this issue. The possible

‘double’ reporting of the same

‘missing’ instrument may explain the

elevated figure. Torn wrap has also

risen slightly on the previous month

46 to 59. This again is being

monitored via theatre stores. On a

positive note, both ‘contaminated’

tray sets and ‘tracking issues’ have

fallen for the third successive month,

despite the upturn in tray set

production.

.

Reasons for Non-Conformance

July 2015

% Kit Numbers

Other i.e. locked set 99.92% 19

Missing item 99.67% 60

Torn wrap 99.58% 59

Contaminated 99.76% 14

Missing tape 99.88% 21

Wrong item 99.93% 16

Checklist issues 100.00% 0

Extra 99.94% 11

Wet 99.95% 1

Damaged 99.97% 3

Assembly 99.99% 1

Tracking issue 99.91% 6

Labels 100.00% 1

Sterility 99.97% 0

Turn round 100.00% 0

DOFA 5 999

DOFA 7 999

SSD Non-Conformance DOFA 4 999

Page 41: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

41 XXXX

XXXXX Board Sponsor XXXX

41

Board Sponsor: Director of Facilities

Facilities Management Cleaning performance against the 49 Elements of The National Specifications for Cleanliness in the NHS

Commentary

Cleaning performance targets

have dropped significantly this

month, especially within the Very

High and High risk areas. The

audit team are working hard to

ensure that these areas are

checked correctly and this may be

the cause of the drop in scores.

We continue to monitor and react

to the high demand that is put onto

the service each month, driven by

patient flow and the high demand

for infectious cleans (Deep

Cleans).

Activities to address improvement:

• FM recruitment is underway

which will ensure that we have

the appropriate consistent

resource in place to meet

demand.

• 50% of the new audit team is in

place. The other half of the

team has been sourced and are

due to start with us later this

month.

• FM are currently reviewing all

training, following a new training managers’ appointment

Very High Risk Areas Includes: Wards, ICU, Theatres, NICU, AAU, ED, RDU etc.

High Risk Areas Includes: Wards, Inpatient & Outpatient Therapies, Neuro OPD, Cardiac/respiratory OPD, Imaging Services etc.

Significant Areas Includes: Audiology, Plaster rooms, Cotswold OPD, Sherston OPD etc.

Low Risk Areas Includes: Brecon unit, Christopher Hancock, Data Centre, Seminar Rooms, Office Areas, L&R (non-lab areas) etc.

• North Bristol Trust have increased the NHS 49 elements to 52

• 36 of these elements are managed by Soft FM i.e. Domestics Services and Estates

• 13 of the elements are managed by Nursing only and 3 are jointly managed by Nursing & Domestic Services

Page 42: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

42 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

42 Effectiveness

Mortality Board Sponsor Medical Director

Commentary

Standardised mortality remains low

at NBT as shown by measures of

HSMR and SHMI. We continue to

track raw mortality as an early

marker of progress.

The Dr Foster analysis of HSMR by

day of admission does not show

excess mortality in NBT at

weekends.

Page 43: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

43 Research and Innovation Board Sponsor Director of Strategy & Transformation

Commentary

Weighted Recruitment is currently

on target. Approximately 48% of

the weighted recruitment is from 1

large maternity trial. In order to

minimise the risk caused by relying

on one study R&I is seeking other

studies to help support an

ambitious recruitment target.

NBT has a large number of active

research studies. R&I is

undertaking a wide ranging data

review. It is likely the number of

active studies will decrease as we

identify and close studies which

have finished.

NBT continue to perform well in

recruiting the first patient to trials

within 70 days of a research

application. 87.5% of our trials

meet this target.

Performance of our commercial

trials recruiting to time and target

continues to decrease (down to

50% in Q1) as the impact MOVE

had on patient recruitment

continues to be reflected in our

rolling 12 month report. A plan is in

place to improve performance over

15/16

Patient recruitment (weighted): The target (red line) equates to the total predicted number of patients to be recruited to each study as agreed by the Principal Investigator. The target in the table relates to that agreed with the Clinical Research Network. The NIHR portfolio of studies comprises three bands; 1,2 and 3, relating to increasing complexity. These are weighted in the ratio of 1:3:14 respectively. Weighted recruitment informs the funding allocation from the regional research network. First patient first visit (FPFV): A NIHR target of 70 days from receipt of a valid application for R&D approval to the first patient being recruited. It applies to trials only that were open to recruitment in the preceding 12 months. This target has been introduced to improve efficiency in setting up and recruiting patients to studies. Data is reported quarterly to the Department of Health. Recruitment to time and target (RTT): The recruitment target for a study is determined by the Principle Investigator as the total number of patients they will recruit to the study for the specified time that the study is open to recruitment. It applies to commercial studies only that were open to recruitment for the preceding 12 months. Data is reported to the Department of Health quarterly. Active: Active at any time during the reporting period NIHR: National Institute of Health Research R&D approval: This is a process to confirm a study can be delivered safely and successfully and must be issued by the NHS organisation before patient recruitment can commence.

Indicator TOTAL

2013-14

Total 2014-15 Q1 2015-16

Target (where appropriate)

Non-commercial studies active - ALL (No.) 346 426 450 N/A

Non-commercial studies active - NIHR Portfolio only (No.) 149 215 232 N/A

NIHR Programme Grants for Applied Research led by NBT active (No.) 4 3 3 3

Other NIHR grants led by NBT active (No.) 10 10 10 6

Commercial studies active - ALL (No.) 34 57 60 N/A

Commercial studies active - NIHR Portfolio only (No.) 23 39 35 N/A

Patients weighted cumulative recruitment - NIHR Portfolio only (No.) 23,544 16,535 5,408 31,000

Total grant income administered by NBT - NIHR Grants only (£million) 14 14.6 14.6 N/A

Initiating research - First patient first visit (trials only) - % met target n/a 85.3 87.5* not yet defined Delivering research - recruitment to time and target (commercial only) - % met target n/a 55.3 50 not yet defined

* Data as submitted to Department of Health, but subject to change depending on data verification by DH

Cumulative Weighted recruitment

0

5000

10000

15000

20000

25000

30000

35000

Ap

ril

May

Jun

e

July

Au

gust

Sep

tem

ber

Oct

obe

r

No

vem

ber

Dec

em

ber

Janu

ary

Feb

ruar

y

Mar

ch

Target

Actual

Page 44: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

Research and Innovation Board Sponsor Director of Strategy & Transformation

NBT is leading weighted recruitment within the WoE CRN. We have recruited more patients (unweighted) in Q1 this year than during Q1 in 2014/15 (479 patients versus 281). New governance arrangements have been put in place with RIG reporting quarterly to Trust Management Team. Key points:

•NBT Research and Innovation groups were restructured following approval at TMT in June 2015. A new internal-facing NBT Research and Innovation Group (RIG) was established which formally reports to TMT. •The purpose of the RIG is to maintain oversight of the implementation of the Trust research and innovation agendas as set out in the Board-approved Research and Innovation Strategies (2012-16). •Terms of reference were approved. It was agreed that clinical directorates would be asked to identify at least two representatives from their active research staff and expectations of representatives will be included in the invitation. •Research support funding allocations: Research support funding from the Clinical Research Network has been reduced to NBT due to poor recruitment across the region, despite NBT achieving its target recruitment. Any opportunities to increase recruitment to NBT and collaboratively with other organisations within our network as a whole are therefore encouraged. •Research Capability Funding call (to fund time to prepare grant applications): It was agreed this would move from a bi-annual call to an open call, accepting applications at any time. •Springboard (small research grants scheme) panel/Chair: A revised membership of the awarding panel was approved, and Dr Nick Maskell was appointed as Chair. •Increasing research financial transparency: It has been agreed with Finance that research costs for core clinical support services (pathology, pharmacy, radiology) and other providing support for research will be identified within the respective directorate budget. Support for this approach from RIG was unanimous.

The official launch of the NBT Science Quarter was held on the 20th May to coincide with International Clinical Trials day.

•117 people registered for the day which included public members, a mixture of Foundation Trust Members, research participants, research lay panel members. Representatives from the networks were also in attendance.

•As well as a poster arena there were a number of interactive activities and tours of the Clinical Research Centre, Pathology and the University of Bristol laboratories.

•We received an impressive amount of media activity. Dr Rebecca Smith was invited to speak on Radio Bristol about the launch. David Gibbs, Pathology Manager was interviewed on Radio Bristol and showcased the services that the new Pathology services provide.

•Social media was a hive of activity with over 10k accounts reached and over 51K impressions. 50 tweets with 23 contributors- Bristol Health Partners were the top contributor with 7 tweets and 2 retweets earning us 32k impressions

R&I is leading the way the way on nurse revalidation for research nurses across the regional network. The Research Matron will be assisting the wider NBT working group on this to share learning on some of the national projects she has been involved in.

Page 45: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

45 XXXX

XXXXX Board Sponsor XXXX

45

QUALITY PATIENT EXPERIENCE SRO Sue Jones Director of Nursing

Section Summary

Improvements & Actions

The improvement in complaints management give a July month end position of 15 overdue, the

lowest for 15 months.

All directorates are currently using their FFT narrative feedback for the last 6 months and their

national patient survey results to write an action plan.

Trends

FFT top ward performer was 28B (Medicine) with a response rate of 36%, 100% would

recommend and a net promoter score of 94. Neurosciences continue to ensure they use FFT

well with a 35% response rate across all of their wards.

Areas of Concern

The response rate for FFT in the Emergency Department has fallen below the standard again, the

video technology failed in month and this did not help ensuring patients are routinely directed to

complete a response. With this now fixed a renewed effort is required. For the team there have

been a number of positive responses praising reception staff and reflecting improvements in

reception

Page 46: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

46

Caring Board Sponsor Director of Nursing

Commentary

Support for Carers

Referrals have increased steadily from

March 2015 with June being particularly

high following a stall in the atrium and Vu

for carers week. Many more self referrals

are occurring due to a banner in atrium

and information in Carers News.

Some of the main issues for carers this

month were around End of Life,

bereavement and transition for patients

going into a nursing home. Carers

struggled with grief and the gap left

following the end of their caring

role. Most carers felt that the hospital’s

handling around end of life care was very

supportive and ‘without fault’.

Quarterly figures.

These are up from last quarter due to

more advertising, carers week and

beginning of the stroke café.

Carers issues were mainly around

decisions for discharge and

communication with the ward. Very few

young/child carers are being identified on

the wards. The Carers Support Centre

plans an awareness raising

campaign/seminar around young carers

in early 2016.

A new member of Staff Judy Gowenlock

joined the team in July.

Use of the carers support scheme is

increasing in the hospital with more

wards accessing the service.

Carers referrals received by location

Carers referrals received by referral

method

Total number of carers referrals received

Page 47: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

47 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

47 Caring

Friends & Family Test Trustwide Position Board Sponsor Director of Nursing

The Net Promoter Score (NPS) whilst no longer a national requirement is still measured to provide greater granularity of patient experience. Inpatients • 95% would recommend • 2% would not recommend • The Net Promoter Score is 72 • Response rate has fallen to 26%. To ensure

delivery of completed cards to the provider courier collection has been implemented in August 2015 (cost neutral).

• The Trust is ranked 116/170 nationally for % recommend and 79/170 for response rate (June 2015).

Emergency Department • 94% of patients would recommend, this is an

improving trend over the last year which if underpinned with an improved response rate would be more reliable.

• 2% would not recommend • The Net Promoter Score is 76. • Response rate has fallen again to 5% and

needs to be addressed within the department.

• The Trust is ranked 47/141 trusts for % recommend and 110/141 for would not recommend (June 2015).

Maternity – Overall • 99% of patients would recommend. • The Net Promoter Score is 74 • The response rate has been addressed since

last month 16%. Out Patient & Day Case • 92% of patients would recommend • 4% would not recommend • The Net Promoter Score is 66 • 100% would recommend at Cossham, Gate 5

and Ante Natal Clinic. • Gate 24 - 16% of patients would not

recommend. • Gate 36 – 7% of patients would not

recommend The results at these two gates need to be explored and addressed. MRI at Gate 18 are developing a performance monitoring board and starting to participate in FFT. .

NBT % Patients would recommend National % Patients would recommend NBT % patients would not rec ……… National Response Rate NBT Response Rate National % Patients would not recommend Response Rate Target

Page 48: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

48 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

48 Caring

Friends & Family Test Directorate Responses and Scores Board Sponsor Director of Nursing

Medicine

• 93% would recommend, 3% would not.

• Net promoter score = 63

• Response rate 31%

• NBT FFT Ward Top Performer 28B with

100% would recommend, NPS 94 and

response rate of 36%

MSK

• 95% would recommend, 0% would not.

• Net promoter score = 65

• Response rate 25%

• High performer in MSK is 26A with 95%

recommend, NPS 63 and response rate

of 38%.

Neurosciences

• 95% would recommend, 2% would not.

• Net promoter score = 81

• Response rate 41%

• High performer in Neurosciences is 6B

with 92% would recommend, NPS 86 and

response rate of 37%.

• All wards in Neurosciences have a

response rate of >35%

Surgery

• 97% would recommend, 0.5% would not.

• Net promoter score 78

• Response rate 25%

• High performer in Surgery is 33A with

98% would recommend, NPS 74 and

response rate of 41%

Directorates have been provided with their

FFT comments analysis (the last six

quarters) in addition to General Medicine,

General Surgery and MSK being given

individual Directorate reports for the National

Inpatient Survey 2014 to determine their

patient experience action plans.

.

NBT % Patients would recommend NBT % patients would not recommend Response Rate Target NBT Response Rate

Page 49: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

49 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

49 Caring

Friends & Family Test Directorate/Dept. Responses and Scores Board Sponsor Director of Nursing

Renal

• 100% of patients would recommend.

• Net promoter score = 67

• Response rate = 5%

The NPS has dropped 27 points and the

response rate 12% points since last month

and requires attention.

Women & Children’s

There were no responses from Cotswold

Ward where survey cards were posted but not

received. In order to address this the cards

will no longer be posted but will be sent by

courier to the provider of our FFT. Low

responses rate for maternity last month has

been addressed..

Maternity – Ante Natal

• 98% of patients would recommend, 2%

would not.

• Net promoter score = 69

• Response rate 9%.

• Nationally % would recommend - NBT is

ranked 97/135 trusts (June 2015)

Maternity – Delivery

• 99% of patients would recommend, 0%

would not.

• Net promoter score = 79

• Response rate 20%

• Nationally % would recommend - NBT is

ranked 91/135 trusts (June 2015).

Maternity – Post Natal – Inpatient

• 98% of patients would recommend, 0%

would not

• Net promoter score = 64

• Response rate 20%

• Nationally % would recommend – NBT is

ranked 83/135 (June 2015)

Maternity – Post Natal – Community

• 100% of patients would recommend, 0%

would not

• Net promoter score = 80

• Response rate 17%

• Nationally % would recommend - NBT is

ranked 45/135 (June 2015)

NBT % Patients would recommend NBT % patients would not recommend Response Rate Target NBT Response Rate

Response Rate Delivery/Post Community Response Rate Post Inpatient/Antenatal _ _ _ _ Response Rate Target % Not recommend Post Inpatient/Antenatal

% Patients would recommend Post Inpatient/ Antenatal % Patients would recommend Delivery/ Post Community % Not recommend Delivery/Post Community

Page 50: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

50 Caring

Complaints & Concerns Board Sponsor Director of Nursing

Commentary

The number of complaints received fell in

July, but concerns increased maintaining

the broad annual pattern of previous

years. Activity levels continue to settle

back towards the pre-hospital move

levels.

The total number of overdue complaints

at the end of July reduced to 15, the

lowest month end level for over 4 years.

Of these just one case related to Quarter

1. This and 9 others sat within the

Medicine Directorate, with a further 3 in

Surgery and 2 more with MSK.

Of these outstanding cases 5 were

cleared in early August with no new

complaints falling overdue. There

continues to be a concerted push to

achieve zero overdue complaints at each

month end and ongoing work to support

directorates in achieving good quality

and timely complaint investigations and

responses.

Enquiry numbers (806) saw an increase

in July but activity was still well below the

peak of last year post the Brunel move,

and numbers remain closer to the levels

seen after the problems with the

introduction of Cerner and before the

move to the Brunel Building last year.

Page 51: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

51 Caring

Complaints & Concerns Board Sponsor Director of Nursing

Commentary

The top 3 categories of complaint for

July, continue to reflect the ongoing

trend; Communication, Clinical care

and Delays and Cancellations. In

particular communication concerns

saw an increase reflecting the

reporting of lower level issues.

Work on the directorate toolkit is

continuing with ACT visiting

directorates to provide support and

identify and share good practice..

The Toolkit is now in first draft.

All written responses continue to be

fed back to the directorates to inform

style and good practice in

responding to complainants.

The new Patient Experience

feedback forms available in the

Brunel Atrium have proved a useful

additional source of feedback and

account for some of the increase

seen in the concerns recorded for

July.

Page 52: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

52 Caring

Complaints & Concerns Board Sponsor Director of Nursing

Commentary

1 new case was reported for

investigation by the PHSO in July.

No investigations were concluded or

draft reports issued by the PHSO last

month – 8 cases remain under

consideration by the Ombudsman.

* Detailed in a draft report and yet to be confirmed.

If all avenues for complaint resolution have been exhausted and the complainant is still dissatisfied with the Trust’s

response, the complaint has the right to take their complaint to the PHSO. Cases can take many months from ‘new’

to ‘decision’ which means the volumes shown above represent differing time periods and will not therefore ‘add up’

within any given period.

Page 53: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

53 XXXX

XXXXX Board Sponsor XXXX

53

Well Led SRO Anne Robson Director of People & Organisation Health

Section Summary

Improvements & Actions

The Trust was awarded Excellence Centre status for the work we do in our National Skills Academy for Health, providing high quality training and

development to our NHS support workforce.

Almost 300 new junior doctors joined the Trust This includes 54 foundation year one doctors who have recently qualified and are just embarking on their

medical careers.

The number of live vacancies with Human Resources has slightly increased from 543.85 wte (end of June) to 546.26 wte (end of July), which reflected an

increase in funded establishment due to business cases being approved. A trajectory is now in place for each staff group to reduce vacancy levels.

During July 250.26 wte offers were made and 145.19 wte accepted.

Quarter 2 Friends & Family Test went live

Preparations are being made for the National Staff Attitude Survey in Q3.

For the first time in several months, compliance in Fire training has been achieved. There is concern however that maintaining compliance with all

statutory and mandatory topics will be difficult over the summer holiday period with the additional requirement to undertake Lorenzo training.

Trends

There is an improving position in statutory and mandatory training, including the additional 3 topics added earlier this year.

Sickness absence remains above Trust target. A set of monthly targets through to March 2016 have been introduced and will be featured in Directorate

reporting.

Areas of Concern

Sickness Absence remains a concern. Work is continuing to develop a toolkit to deal with stress and anxiety which now represents the majority of long

term sickness absence cases being managed in the Trust. Resources available internally and externally are being collated. This will be looked at in

conjunction with the Trust’s Wellbeing Plan i.e. preventative measures as well as supporting staff who are off sick and affected by stress/anxiety.

Agency usage increased during July. An action plan with a trajectory aimed at reducing spend is being collated between HR, Finance and Nursing. The

trajectory is currently in development and will be tested for nursing in August and will appear in the next IPR.

Following a drop last month, turnover has increased again, this is coupled with a slight drop in the numbers recruited (which may be the effect of the

summer period when recruitment levels are generally down).

Page 54: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

54 XXXX

XXXXX Board Sponsor XXXX

54

Standard

(target)

July 2015

Most recent

quarter’s average

performance

(Q1 Apr – Jun 15)

Quarterly Trend (Q4 vs Q1) Performance

against national

target / contract

Trend from last

month

Turnover

(voluntary/perm staff)

10.2%

9.68% 10.4% (in Q4) to 9.68%(in Q1)

Trustwide Sickness

Absence (target 3.8% -

in month June 15

figure shown)

4.3% 5.1% (in Q4) to 4.3% (in Q1)

Long Term Sickness

Absence % pro rata

(One month in arrears)

2.7%

3.0%

3.0% (in Q4) to 2.76% (in Q1)

Short Term Sickness

Absence % pro rata

(One month in arrears)

1.5%

1.6% 2.2% (in Q4) to 1.6% (in Q1)

WTE Bank (usage)

495.57

469.0 502.1 (in Q4) to 469.0 (in Q1)

WTE Agency (usage)

253.9

213.0 236.7 (in Q4) to 213.0(in Q1)

Mandatory Training

Compliance (Target

85%) (one month in

arrears)

87.5% 86.3% (in Q4) to 87.5% (in Q1)

Well Led Summary Dashboard Board Sponsor Director of People & Organisation Health

88.9%

4.2%

Page 55: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

55 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

55 Well Led

Key Workforce Indicators Board Sponsor Director of People & Organisation Health

Turnover

Included: permanent staff who have

resigned voluntarily & fixed term staff

who left before the end of their

contract.

Excluded: bank workers, locums,

junior doctors, service transfers,

expected end of fixed term contracts,

retirements, dismissals,

redundancies, and internal

movements/transfers.

Following a reduction, over the past

couple of months, Trust turnover

levels have increased to 10.2%,

based on an increase over June in

the number of voluntary

resignations.

There were total of 106 staff who left

NBT in July (for all listed reasons) of

those staff who left voluntarily (80

people), the most recorded reasons

for leaving were:

• Relocation

• Work-life balance

Reasons for leaving will continue to

be analysed at both Trust and

Directorate level.

Work is underway to improve and

raise awareness the Trust’s

attraction and retention material.

Turnover from Voluntary Resignations

Period % Turnover

Aug 14 – July 15 10.2%

July 14 – June 15 8.75%

June 14 – May 15 9.90%

May 14 – Apr 15 10.4%

Apr 14 – Mar 15 10.5%

Mar 14 – Feb 15 10.4%

Feb 14 – Jan 15 10.5%

Jan 14 – Dec 14 10.3%

Dec 13 – Nov 14 10.1%

Nov 13- Oct 14 10.1%

Oct 13- Sept 14 9.8%

Sep 13 - Aug 14 9.9%

DOHR01 999

Page 56: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

56 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

56 Well Led

Recruitment Board Sponsor Director of People & Organisation Health

Recruitment • Recruiting to 546.3 wte vacancies.

Overall

• For July 250.4 wte offers made and

145.2 wte have been appointed to

posts .

• From 1st April to 30th July 479.7 wte

staff have been recruited against the

571 wte target. This leaves a deficit

of 91.3 wte. The main reason for this

is due to the 3 weekly induction cycle

which has reduced the number of

new staff who can start. This is being

addressed and starter numbers will

be up during August as a result of

two corporate inductions and medical

induction.

Registered Nurses

• Small decrease in the RN vacancy

levels during July which was

influenced by a the agreement of a

new business case agreeing to 12

new RN’s for ICU.

• Nurse Recruitment Open Day took

place on 24th July with 23 RN’s

offered.

• First tranche of the summer cohort of

Spanish nurses arrived in July.

• Starters : Aug – Oct = 184.46 wte

• Starters: Pipeline – 127.06 wte

Non-Registered Nursing

• Starters : Aug - Oct = 39.2 wte

• Starter: Pipeline – 56.10 wte

• Increased weekly assessment activity

ongoing, however, struggling with

candidate attendance over the

summer period.

Internal Recruitment

• The recruitment team now measuring

NBT staff applying for internal

vacancies and during July processed

42.93 wte internal recruitments in

addition to the above workload.

July 2015 Vacancies

Staff Group WTE

Registered Nurses 179.19

Non-Registered Nurses 106.15

Medical and Dental 31.0

Allied Health Professionals

23.9

Other (e.g Admin & Clerical)

126.28

FM 79.74

DOHR 12 999 Trust wide Vacancy Rate (Orange = Trajectory)

Page 57: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

57 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

57 Well Led

Sickness Absence Board Sponsor Director of People & Organisation Health

Sickness Absence

Sickness absence levels remain

above 3.8% and the in month target

for June.

Work is continuing to implement the

sickness action plan which includes:

• Reviewing the Sickness Policy

and User Guide

• Reviewing and agreeing the SLA

with Occupational Health

• Implementing local absence

targets for Directorates

In addition, a toolkit is being

developed for managers to prevent

and manage stress.

An update will be provided to the

September Workforce Committee.

Reasons for absence

91% of sickness cases logged with

Ask HR are long term cases. The

majority of these cases continue to

be attributed to stress and anxiety,

followed by musculo skeletal

conditions. 19 cases are being

managed under stages 2 & 3 of the

short term sickness absence

procedure, an increase of 5 on last

month.

Note : sickness absence trajectory has

been calculated using seasonal adjusted

averages over the last 3 years aiming for

target of 3.8% by March 16..

DOHR09 056

Page 58: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

58 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

58 Well Led

Pay Board Sponsor Director of People & Organisation Health

Bank and Agency

July 2015 has been the 2nd highest

usage period in the last 12 months,

which was expected due to seasonal

pressures (ie summer holiday

period) and vacancy levels which are

now starting to reduce.

Bank fill has continued to be steady

and has adapted to the increasing

demands, which shows the impact of

recruitment initiatives.

The last weekend of July showed no

agency shifts for healthcare support

workers, although non-framework

usage continues to be at an all time

high for registered nurses.

A number of actions from the Task

and Finish group are being put in

place to enable a reduction in the

use of non-framework agencies.

There is a slight discrepancy in the

charts (increasing agency usage but

decreasing spend) due to a

retrospective adjustment made for an

error in last month’s figures.

Pay Expenditure

As the graph shows, bank pay has

increased whilst substantive and

agency pay have reduced slightly.

Page 59: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

59 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

59 Well Led

Mandatory Training Board Sponsor Director of People & Organisation Health

Mandatory Training Mandatory training throughout June

remained steady.

It is anticipated that with the beginning of

Lorenzo training and summer breaks will

impact upon compliance rates between

July and October. Directorates have

been asked to ensure compliance rates

are maintained. This will be managed

through Directorate Performance

Management meetings.

The new Training Needs Analysis will be

launched early September along with the

move to the electronic passport. This

will ensure individual passport

information is up to date at all times.

All staff groups now receive automated

reminders of when a mandatory topic is

about to expire. This should increase

awareness amongst some groups who

were previously difficult to reach.

iCARE From the 1st April, iCARE training is

business as usual. This means that

iCARE training is solely at induction.

Changes in there number of staff who

have had iCARE training reflects the

number of staff attending induction in the

month

(Note : with effect from January 2015

the mandatory training data will only

include those topics which are

exceptions (e.g. not meeting, and

sustaining, 85% compliance target).

(Note : with effect from January 2015

the mandatory training data will only

include those topics which are

exceptions (e.g. not meeting, and

sustaining, 85% compliance target).

Page 60: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

60 XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

60 Well Led

Mandatory Training Board Sponsor Director of People & Organisation Health

Mandatory Training

The additional three top tier topics

continue to make steady progress

towards compliance.

New e-learning has either already

been introduced or is being

developed for these three topics

alongside all other existing modules.

These will not be linked to

incremental progression until April

2016.

Appraisal Completion – non-

medical staff

The chart shows the appraisal

completion rate against plan as at

end of July (for non-medical staff

only). The appraisal system

changed in April 2015 and the

change has meant that staff should

have an appraisal 6-8 weeks before

their incremental date.

Directorates have been asked to

implement action plans to improve

completion rates e.g. 90%.

Non Med appraisal chart to be added here

Non medical Appraisals – July 15

Page 61: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

61 Well Led

Medical Workforce Board Sponsor Medical Director

Commentary

The medical appraisal chart shows

the compliance with the

requirement for all doctors to have

not exceeded 15 months since

their last appraisal.

The small number of individuals

missing this deadline are targeted

by directorate appraisal leads as

necessary.

Clinical Fellows on short term fixed

contracts may have difficulty

keeping up to date with appraisal

dates. The revalidation support

manager is supporting these

doctors to ensure that they meet

the GMC requirement.

Page 62: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

62 Safe Staffing

Nursing Workforce Board Sponsor Director of Nursing

Commentary

Nursing spend on the inpatient

wards has increased again this

month associated with increased

temporary staffing usage of 4%

over last month. The WTE per bed

is now in excess of the funded

level by 10%. This is of concern

as all funded establishments have

been reviewed as part of the 15

/16 Budget setting process. The

increase is due to high levels of

absence in month and the

numbers of patients requiring

‘Enhanced care’. This is being

triangulated against the Safe care

(acuity/dependency) electronic

tool which is now being completed

twice daily on all wards.

The ‘Enhanced care’ policy and

implementation plan is being

refreshed following testing in the

Medicine Directorate.

Recruitment to vacancies with

associated reductions in premium

cost agency usage and control of

sickness absence remain the key

financial challenges for nursing.

The Nursing and Midwifery

workforce group is focusing on

gaining assurance on managing

vacancies, agency reduction and

adherence to sickness policies.

Ratio of Registered : Unregistered Ward Nurses (Target 60:40)

Mar

14

Ap

r 1

4

May

14

Jun

e 1

4

July

14

Au

g-1

4

Sep

-14

Oct

-14

No

v-1

4

De

c-1

4

Jan

-15

Feb

-15

Mar

-1

5

Ap

r-1

5

May

-15

Jun

e-1

5

July

-15

57:43 57:43 59:41 58:42 57:43 56:44 57:43 58:42 58:42 58:42 58:42 58:42 59:41 57:43 57:43 56:44 55:45

Page 63: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

63 Well Led

Care Quality Commission Action Plan Delivery Progress Board Sponsor Director of Nursing

Commentary

• There were 75 actions set by CQC

(status at 30/4/15) is shown in first

table.

• NBT’s Action Plan set out 192 total

actions to deliver the above,

summarised within the 2nd table.

65% have been completed, a further

19% are ‘on track.’

• Evidence is being validated for all

actions falling due by each of the bi-

monthly CQC Operational Delivery

Group meetings.

Compliance Action (CA) Progress Priority focus is to ensure delivery of the

CAs and Enforcement Action.

• An update against the ED

Enforcement Action is provided on

the following page.

• Two CAs are now completed (nos. 2

& 8).

• CAs 6, 7, 9 and 10 are on track as

planned.

• CAs 1, 3 & 4 – are now overdue

(previously flagged as a ‘risk of

delay’).

‘Must do’ exceptions (red) are listed on

the following page.

Total NBT actions required to deliver CQC Actions specified above Actions TOTAL %

Total actions completed 124 65

‘Green’ Actions (on track) 36 19

Potential Delay/ Insufficient evidence 3 2

Overdue 29 15

CQC Enforcement and Compliance Actions Status n=75 (Actions set by CQC)

Must Should Must Should Must Should Must Should Must Should

Patient Flow

Enforcement Action: Warning Notice 16th December 2014. Care and wel fare of

people who use services .

Compliance Action 1: Care and wel fare of people who use services . (#1A – 6)

31/07/2015 9 0 4 0 2 0 0 0 3 0

Patient Flow Other Actions (#7-11) 31/12/2015 2 3 1 1 1 2 0 0 0 0

Patient SafetyCompliance Action 2: Assess ing and monitoring the qual i ty of service

providers . (#12-16)Completed 3 2 3 2 0 0 0 0 0 0

Patient SafetyCompliance Action 3: Safeguarding people who use services from abuse.

(#17-18)31/07/2015 1 1 1 0 0 0 0 0 0 1

Patient Safety Compliance Action 4: Management of medicines . (#19-22) 01/07/2015 1 3 0 0 0 0 0 0 1 3

Patient SafetyCompliance Action 5: Care and wel fare of people who use services

(Records). (#23-27)31/12/2015 2 3 0 0 1 2 1 1 0 0

Patient Safety Compliance Action 6: Safety, ava i labi l i ty and sui tabi l i ty of equipment. (#28) 30/09/2015 1 0 0 0 1 0 0 0 0 0

Patient Safety Compliance Action 7: Cleanl iness and Infection Control . (#29-32) 30/11/2015 3 1 2 1 1 0 0 0 0 0

Patient Safety Compliance Action 8: Safety and sui tabi l i ty of premises (HITU speci fic). (#33) Completed 1 0 1 0 0 0 0 0 0 0

Patient Safety Other Actions (#34-39) 30/11/2015 1 5 1 4 0 1 0 0 0 0

Patient Experience Other Actions (#40-52) 31/10/2015 1 12 1 9 0 2 0 0 0 1

Staffing Levels,

Wellbeing &

Engagement

Compliance Action 9: Staffing. (# 53-63) 31/12/2015 5 6 2 4 3 2 0 0 0 0

TrainingCompliance Action 9: Staffing.

Compliance Action 10: Supporting s taff. (#64-72)01/10/2015 4 5 1 3 2 1 1 0 0 1

34 41 17 24 11 10 2 1 4 6

OverdueRegulationTheme

No. of Actions Completed On track Potential DelayFinal Action

Date

Page 64: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

64 Well Led

Care Quality Commission Action Plan Delivery Exceptions Board Sponsor Director of Nursing

Commentary

The four overdue ‘Must Do’ actions are

reported in the table opposite.

Revised action dates are proposed and

will be further reviewed and discussed

with the CQC prior to the next Board

review in September 2015.

There are also 2 ‘Must Do’ actions that

are deemed to be at risk (potential

delay),

• 24. Ensure that all patients’ medical

records are available when the

patient is being seen and reliance on

temporary records is reduced to a

minimum.

• 66. Enable and facilitate emergency

department staff to undertake

mandatory and essential clinical

training and professional training and

development.

ED Warning Notice – Actions • Quality Dashboard – updated and

data quality checks included as part

of standard reporting

• Nursing Documentation audits

undertaken within ED & AEC and

reported via online tool with real time

feedback.

• Weekly review of Quality Dashboard

including time-based metrics at Acute

Flow Group.

• CCG walk-round review of

Emergency Zone provided positive

feedback in many areas, including

the functioning of the AMU. Patient

flow in AEC noted as the area of

current focus

• Next Risk Summit date set by NHS

England for 9 October 2015.

Ref Action Lead(s) Action

Date

Issues / Revised Action Revised

Date

1C Ensuring that the

discharges of medical

and surgical patients

are always planned

effectively to avoid

delaying discharge

when medically fit to

leave.

Head of

Transformation

– Patient Flow

& Discharge

31/07/15 Significant work undertaken in line with

Urgent Care programme. Critical

components are;

1. Discharge Lounge utilisation - w.e.f.

17/8/15 all patient transport is mandated via

the DL, which will improve its use by

wards/specialties.

2. Discharge documentation in Lorenzo -

action date 31/10/2015

3. Discharge to Assess pathways rollout -

31/10/2015

4. Integrated Discharge Service Go Live -

31/10/2015.

Impact & achievement of the compliance

action set for 31/10/2015.

31/10/15

3.1 Mental Health Liaison

in ED

CD/ED

Consultant

30/04/15 Plan agreed, delays with AWP post now

resolved and interview date set for

22/10/2015. In meantime arrangements to

ensure patients receive safe care whilst

awaiting mental health assessments are in

place. Further details to be provided at

September update.

24/09/15

5.1/2 Care for patients in

AEC & future use

CD/ED

Consultant

31/05/15 Nursing Assessments and documentation

fully in place and audits underway to

confirm, outcomes included in ED Quality

Dashboard.

Task and finish group leading

improvements in AEC against national

standards including agreement of patient

pathways suitable for AEC.

31/08/15

(review &

close when

AEC use

finalised)

19.1 Ensure that all

medicines are stored

safely and

appropriately and

records relating to

administration are

accurate.

Deputy

DoN/Medicines

Management

Lead

01/07/15

The Medicines Governance Group has

overseen and agreed the storage approach

in Brunel - ensuring that sufficient

temperature controls, physical storage and

operational practicalities are in place. An

order has been placed for additional metal

cabinets and arrangements being

negotiated with Carillion for installation but

delayed beyond original planned date.

31/10/15

Page 65: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

65 FINANCE

SRO Catherine Phillips Director of Finance

Section Summary

Summary For the year to date the Trust is £5.4m adverse to plan • The primary drivers for the adverse to plan were lower than planned elective income of £2.5m and

unidentified savings of £0.7m together with pay overspends of £2.1m coupled with a small non-pay overspend.

• The cash balance is £16.7m, which includes £27.8m of the revolving working capital facility drawn down from the Department of Health.

• Capital expenditure totals £7.1m which is £5.0m below the plan for the year to date. • The Trust is rated red by the Trust Development Authority (TDA) as a result of the planned and forecast

deficit. Areas of concern • Elective inpatient performance continues to be lower than plan. It is essential that activity levels continue to

increase to planned levels as soon as possible to meet plan as well as a mitigation plan to recover underperformance

• Pay expenditure was £2.1m overspent for the year, primarily reflecting a combination of above plan use of agency and bank.

• Non Pay expenditure was £1.0m overspent for the Year, reflecting unrealised cost savings (£0.7m).

Actions • Continue the improvement in elective activity to planned levels and develop recovery plan. • Enhanced management of agency expenditure linked to recruitment to of vacancies within establishment.

Enhanced controls on the use of non framework agency usage. • Continue to monitor and manage cash on a daily basis to minimise the requirement for external cash

support.

Page 66: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

66

Commentary

Assurances

The financial position for June

shows a deficit of £17.0m

compared with a planned budget

deficit of £11.6m. This represents

an adverse position to plan of

£5.4m for the year to date.

Key Issues

Contract income is £2.5m

adverse to plan. This was driven

by lower than planned elective

activity, primarily within Trauma

and Orthopaedics and Spinal

Surgery.

Unrealised cost savings from as

yet unidentified or pipeline

schemes was the primary driver

the overspend on non pay.

Actions Planned

Improvement in theatre

throughput and productivity

through recruitment to vacant

posts and improvement in

session utilisation.

Closer management of nurse

establishment to ensure that

rosters are managed to agreed

levels and minimising and

removing high cost agency costs.

Finance

Statement of Comprehensive Income Board Sponsor Director of Finance

In month

variance (Adv)/

Fav

Budget £m Actual £m

Variation from

budget (Adv) /

Fav £m

£m

Income

Contract Income 156.1 153.6 (2.5) (1.0)

Other operating income 26.2 26.3 0.1 0.1

Donations income for capital acquisitions 0.0 0.6 0.6 0.0

Total Income 182.3 180.5 (1.8) (0.9)

Expenditure

Pay (115.8) (117.9) (2.1) (1.0)

Non-Pay (59.1) (59.9) (0.8) (0.1)

Total Expenditure (174.9) (177.8) (2.9) (1.1)

Earnings before Interest & depreciation 7.4 2.7 (4.7) (2.0)

1.50%

Depreciation & Amortisation (7.2) (7.4) (0.2) (0.1)

Non PFI Interest receivable 0.0 0.0 0.0 0.0

Non PFI Interest payable (0.5) (0.6) (0.1) 0.0

PFI Interest (11.0) (11.0) 0.0 0.0

PDC Dividend (0.3) (0.3) 0.0 0.0

Impairment 0.0 0.0 0.0 0.0

Retained Surplus / (Deficit) for accounting

purposes(11.6) (16.6) (5.0) (2.1)

Add back items excluded for NHS

accountability

IFRIC 12 Adjustment 0.0 0.0 0.0 0.0

Donations income for capital acquisitions 0.0 (0.6) (0.6) 0.0

Depreciation of donated assets 0.0 0.2 0.2 0.1

Impairment 0.0 0.0 0.0 0.0

Adjusted Surplus / (Deficit) for NHS

accountability(11.6) (17.0) (5.4) (2.0)

Position as at 31 July 2015

Page 67: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

67

Commentary

Assurances The new interim revolving working capital support facility has been accessed and the Trust has received £27.8m to date. Concerns & Gaps Better Payment Practice Code (BPPC) is below the required 95% with 81% of payments made within 30 days.

Actions Planned

Effective daily cash monitoring to

ensure the Trust is able to stay

within the cash limits set under

the revolving working capital

facility.

Payment improvement plan being

implemented with shared service

provider to improve BPPC

Finance

Statement of Financial Position Board Sponsor Director of Finance

31 March 2015

Actual £m

31 July 2015

Plan £m

31 July 2015

Actual £m

Variance above

/ (below) plan

£m

30 June

2015

Actual £m

Non current assets

508.3 Property, Plant and Equipment 514.1 509.0 (5.1) 510.4

0.4 Intangible Assets 0.4 0.3 (0.1) 0.4

508.8 Total non-current assets 514.5 509.3 (5.2) 510.8

Current Assets

7.9 Inventories 7.9 8.2 0.3 8.6

15.8 Trade & other Receivables NHS 15.8 13.1 (2.7) 12.9

25.2 Trade & other non-receivables Non-NHS 18.0 28.2 10.2 27.8

1.0 Cash and Cash equivalents 2.9 16.7 13.8 17.6

50.0 Total Current Assets 44.7 66.2 21.6 66.9

31.7 Non-current assets held for sale 31.2 31.2 0.0 31.2

590.5 Total Assets 590.4 606.8 16.4 608.9

Current liabilities (< 1 year)

7.5 Trade & other payables – NHS 7.5 6.4 (1.1) 8.6

76.9 Trade & other payables – Non-NHS 66.7 85.0 18.2 80.2

1.4 Borrowings 1.4 29.2 27.8 29.2

10.5 PFI l iability (current) 10.5 10.5 0.0 10.5

96.3 Total current liabilities 86.1 131.1 45.0 128.5

(14.5) Net current assets / (liabilities) (41.5) (64.8) (23.4) (61.6)

494.2 Total Assets less current liabilities 504.3 475.7 (28.6) 480.4

7.4 Trade payables and deferred income 7.0 7.7 0.7 7.1

416.1 PFI l iability 412.9 412.9 (0.0) 413.7

19.5 Borrowings 19.5 19.5 0.0 19.5

51.2 Total Net Assets 64.8 35.6 (29.3) 40.1

Capital and Reserves

241.3 Public dividend capital 265.6 241.3 (24.3) 241.3

(242.2) Income & Expenditure reserve (269.6) (269.6) 0.0 (269.6)

(27.4) Income & Expenditure account – current year (11.6) (16.6) (5.0) (12.1)

79.5 Revaluation reserve 80.4 80.4 (0.0) 80.4

51.2 Total Capital and Reserves 64.8 35.6 (29.3) 40.1

Page 68: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

68

Commentary

Assurances

The Trust has secured assurance

from the TDA that it will make

sufficient cash available to meet

its obligations, subject to the

implementation of the Financial

Sustainability Plan.

Concerns & Gaps

The Trust has a red rating on the

TDA risk assessment criteria as a

result of the actual deficit for

2014/15. This will continue into

2015/16.

The risk rating against Monitor’s

Continuity of Service rating is the

lowest score of 1.

Finance

Financial Risk Ratings Board Sponsor Director of Finance

Page 69: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

69

Commentary

Assurances

The Trust’s cash balance is

presently £16.7m. The new

interim revolving working capital

support facility has been

accessed and the Trust has

received £27.8m cash support to

date..

Planned capital expenditure for

the year is £30.5m. £7.1m spend

year to date is £5.0m below plan.

Actions Planned

Application to the Independent

Trust Financing Facility (ITFF) for

permanent cash support during

2015.

Finance Rolling Cash Flow Forecast, In Year Surplus, & Capital Programme Expenditure Board Sponsor Director of Finance

Page 70: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

Commentary

XXXX

XXXXX

XXXX

70

Commentary

Assurances

Savings review meetings are in

place to ensure in year

implementation and development

of future years plans.

Concerns & Gaps

The first graph shows the in-year

over delivery of £3.0m against the

target of £29.2m, including pipeline

schemes.

The second graph shows the

monthly profile of the total savings

throughout the year with savings

higher than the monthly target from

September compensating for the

early months.

There remains a level of

unidentified recurrent savings

which needs to be identified. There

is a recurrent shortfall of £2.4m

compared to the recurrent target of

£41.2m, Overall recurring shortfall

is £5.9m.

Actions Planned

Continued development of the

savings programme coupled with

focus on delivery.

Finance

Savings Board Sponsor Director of Finance

0

5

10

15

20

25

30

35

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

£m

Month

Trust 2015/16Annual CRES Position (In Year)

Pipeline

Red

Amber

Green

Target

Page 71: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

XXXX

XXXXX Board Sponsor XXXX

71 REGULATORY VIEW

Overall Commentary Board Sponsor Chief Executive Officer

Regulatory Area Jan 15

Feb 15

Mar 15

Apr 15

May 15

Jun 15

Jul 15

Finance Risk Rating (FRR)

Red

Red

Red Red Red Red

Board non-compliance statements

1 1 1 1 1 1 1

Prov. Licence non-compliance statements

0 0 0 0 0 0 0

CQC Inspections RI RI RI RI RI RI RI

CQC reports history (all sites)

Summary

The Governance Risk Rating (GRR) for ED 4 hour performance continues to be a challenge through 2015/16, Actions to improve and sustain this standard are set out earlier

in this report. A recovery plan is in place for RTT (please see Key Operational Standards section for commentary). Cancer figures are undergoing final validation therefore,

whilst indicative, the figures presented are not necessarily reflective of the Trust’s finalised position. However, the indicative position shows that we passed 5 of 8 of the

Cancer targets. Any subsequent updates will be flagged next month.

We are scoring ourselves against the TDA Accountability Framework (AF) 2014-15. This requires that we use the performance indicator methodologies & thresholds provided

to calculate scores for Quality and Delivery (an overall score based upon a subset of individual scores for each of the CQC domains of Caring, Effective, Responsive, Safe,

Well-Led) and a Finance Risk Assessment based upon in year financial delivery & Monitor’s Risk Assessment Framework. Details are provided over the following 2 pages.

Board compliance statements – number 4 (going concern) and number 10 (ongoing plans to comply with targets) warrant continued board consideration in light of the financial

budgets for 2015-16 and ongoing performance challenges as outlined within this IPR. The Trust is committed to tackling these challenges and revised recovery trajectories

have been submitted to the TDA as outlined elsewhere in this report and are scrutinised on an ongoing basis through the monthly Integrated Delivery Meetings.

Location Standards Met

Report date

Overall Requires Improvement

Feb-15

Child and adolescent mental health wards (Riverside)

Good Feb-15

Specialist community mental health services for children and young people

Requires Improvement

Feb-15

Community health services for children, young people and families

Outstanding Feb-15

Southmead Hospital Requires Improvement

Feb-15

Cossham Hospital Good Feb-15

Frenchay Hospital Requires Improvement

Feb-15

Page 72: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

72 XXXX

XXXXX Board Sponsor XXXX

72 Regulatory View

Monitor Provider Licence Compliance Statements at July 2015 Board Sponsor Chief Executive Officer

Ref Criteria Comp (Y/N)

Comments where non compliant or at risk of non-compliance

G4

Fit and proper persons as

Governors and Directors (also

applicable to those performing

equivalent or similar functions)

Yes Existing processes sufficient. New requirements have been discussed and processes are being put in place

to ensure compliance with the new regulations.

G7 Registration with the Care

Quality Commission Yes CQC registration is in place. No outstanding non-compliance actions with CQC. The Trust is scheduled for

inspection by the CQC in early November 2014.

G8 Patient eligibility and

selection criteria Yes Trust Board has considered the assurances in place and considers them sufficient.

P1

Recording of information Yes A range of measures and controls are in place to provide internal assurance on data quality. Further

developments to pull this together into an overall assurance framework are planned through strengthened

Information Governance Assurance Group.

P2

Provision of information Yes Information provision to Monitor not yet required as an aspirant FT. However in preparation for this the Trust

undertakes to comply with future Monitor requirements.

P3 Assurance report on

submissions to Monitor Yes Assurance reports not as yet required by Monitor since NBT is not yet a Foundation Trust. However, once

applicable this will be ensured. Scrutiny & oversight of assurance reports will be provided by Trust's Audit

Committee as currently for reports of this nature.

P4

Compliance with the National Tariff Yes NBT complies with national tariff prices. Scrutiny by CCGs, LAT and NTDA provides external assurance

that tariff is being applied correctly.

P5

Constructive engagement

concerning local tariff

modifications

Yes Trust Board has considered the assurances in place and considers them sufficient.

C1 The right of patients to make

choices Yes Trust Board has considered the assurances in place and considers them sufficient.

C2

Competition oversight Yes Trust Board has considered the assurances in place and considers them sufficient.

IC1

Provision of integrated care Yes Range of engagement internally and externally. No indication of any actions being taken detrimental to care

integration for the delivery of Licence objectives.

Self-assessed, for submission to NTDA

Ref Criteria Comp (Y/N)

Comments where non compliant or at risk of non-compliance

G4

Fit and proper persons as

Governors and Directors (also

applicable to those performing

equivalent or similar functions)

Yes Existing processes sufficient. All Executive and Non-Executive Directors have completed a self assessment

and no issues have been identified. A Fit and Proper Person Policy is being developed for approval in

September 2015.

G5 Having regard to monitor

Guidance Yes The Trust Board has regard to Monitor guidance where this is applicable

G7 Registration with the Care

Quality Commission Yes CQC registration is in place. The Trust received a rating of Requires Improvement from its inspection in

November 2014. A number of compliance actions were identified which are being addressed through an

action Plan. The Trust Board receives regular updates on the progress of the action plan through the IPR.

G8 Patient eligibility and

selection criteria Yes Trust Board has considered the assurances in place and considers them sufficient.

P1

Recording of information Yes A range of measures and controls are in place to provide internal assurance on data quality. Further

developments to pull this together into an overall assurance framework are planned through strengthened

Information Governance Assurance Group.

P2

Provision of information Yes Information provision to Monitor not yet required as an aspirant FT. However in preparation for this the Trust

undertakes to comply with future Monitor requirements.

P3 Assurance report on

submissions to Monitor Yes Assurance reports not as yet required by Monitor since NBT is not yet a Foundation Trust. However, once

applicable this will be ensured. Scrutiny & oversight of assurance reports will be provided by Trust's Audit

Committee as currently for reports of this nature.

P4

Compliance with the National Tariff Yes NBT complies with national tariff prices. Scrutiny by CCGs, LAT and NTDA provides external assurance

that tariff is being applied correctly.

P5

Constructive engagement

concerning local tariff

modifications

Yes Trust Board has considered the assurances in place and considers them sufficient.

C1 The right of patients to make

choices Yes Trust Board has considered the assurances in place and considers them sufficient.

C2

Competition oversight Yes Trust Board has considered the assurances in place and considers them sufficient.

IC1

Provision of integrated care Yes Range of engagement internally and externally. No indication of any actions being taken detrimental to care

integration for the delivery of Licence objectives.

Page 73: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

73 XXXX

XXXXX Board Sponsor XXXX

73

No. Criteria Comp (Y/N)

No. Criteria

Comp (Y/N)

1

The Board is satisfied that, to the best of its knowledge and using its

own processes and having had regard to the TDA’s oversight model

(supported by Care Quality Commission information, its own

information on serious incidents, patterns of complaints, and

including any further metrics it chooses to adopt), the trust has, and

will keep in place, effective arrangements for the purpose of

monitoring and continually improving the quality of healthcare

provided to its patients.

Yes 8

The necessary planning, performance management and corporate and

clinical risk management processes and mitigation plans are in place to

deliver the annual operating plan, including that all audit committee

recommendations accepted by the board are implemented satisfactorily. Yes

2 The board is satisfied that plans in place are sufficient to ensure on

going compliance with the Care Quality Commission’s registration

requirements.

Yes 9

An Annual Governance Statement is in place, and the trust is compliant

with the risk management and assurance framework requirements that

support the Statement pursuant to the most up to date guidance from HM

Treasury (www.hm-treasury.gov.uk).

Yes

3 The board is satisfied that processes and procedures are in place to

ensure all medical practitioners providing care on behalf of the trust

have met the relevant registration and revalidation requirements.

Yes 10

The board is satisfied that plans in place are sufficient to ensure ongoing

compliance with all existing targets (after the application of thresholds) as

set out in the relevant GRR; and a commitment to comply with all known

targets going forwards.

No

4 The board is satisfied that the trust shall at all times remain a going

concern, as defined by the most up to date accounting standards in

force from time to time.

Yes 11

The trust has achieved a minimum of Level 2 performance against the

requirements of the Information Governance Toolkit. Yes

5 The board will ensure that the trust remains at all times compliant

with regard to the NHS Constitution.

Yes 12

The board will ensure that the trust will at all times operate effectively.

This includes maintaining its register of interests, ensuring that there are

no material conflicts of interest in the board of directors; and that all board

positions are filled, or plans are in place to fill any vacancies.

Yes

6

All current key risks have been identified (raised either internally or

by external audit and assessment bodies) and addressed – or there

are appropriate action plans in place to address the issues – in a

timely manner

Yes 13

The board is satisfied that all executive and non-executive directors have

the appropriate qualifications, experience and skills to discharge their

functions effectively, including setting strategy, monitoring and managing

performance and risks, and ensuring management capacity and

capability.

Yes

7 The board has considered all likely future risks and has reviewed

appropriate evidence regarding the level of severity, likelihood of it

occurring and the plans for mitigation of these risks.

Yes 14

The board is satisfied that: the management team has the capacity,

capability and experience necessary to deliver the annual operating plan;

and the management structure in place is adequate to deliver the annual

operating plan. Yes

Regulatory View

Board Compliance Statements at July 2015 Board Sponsor Chief Executive Officer

Self-assessed, for submission to NTDA

Page 74: Board Report (Integrated Performance Report) - August 2015 Report (Integrated... · INTEGRATED PERFORMANCE REPORT August 2015 (presenting July 2015 data) V1 . XXXX XXXXX Board Sponsor

74 XXXX

XXXXX Board Sponsor XXXX

74 IPR / Board Additional Reporting Schedule 2015 Board Sponsor All Executive Directors

74

Measures & Reports overseen by Trust Board which fall outside monthly IPR reporting January February March

• Other qualitative aspects of patient experience report • External Reporting – Coroners Report • Flu Vaccination Rates – added to IPR cycle • Cancelled Operations – reasons for cancellations – added

to IPR cycle • Non Medical Appraisals – last month for reporting for

year • Tariff – NBT V Dr Foster removed whilst data queries

raised with Dr Foster • Compliments – moved from monthly to quarterly cycle

• IPR Measure: Research & Innovation • Periodic IPR Measure: Clinical Audits • Facilities cleaning schedule • Sterile Services • Pay bill chart – to be revised

• Safeguarding Adults & Children • Medical Notes – added to IPR cycle • Length of Stay – page to be developed • Delayed Transfers – page to be developed

April May June

• Other qualitative aspects of patient experience report • Clinical Audit • Additional Patient Flow KPIs • Theatre Productivity KPIs • Outpatients KPIs

• IPR Measure: Research & Innovation • Complaints – monthly trends • Carers Report – quarterly • Expanded Medicines Management section • Staff Survey Results • Vacancy Reporting • CQC action plan & progress

• Clinical Legal claims/inquests (6 monthly) • Clinical Audit • Acuity & Dependency

July August September

• Other qualitative aspects of patient experience report • Staff Survey Results • CQUINs

• IPR Measure: Research & Innovation (page 43) • Carers Report – quarterly (page 46) • IPR Measure: Non Medical Appraisals (page 60)

October November December

• Safe Staffing – 6 monthly report • Clinical Audit • CQUINs

• IPR Measure: Research & Innovation • Clinical Legal claims/inquests (6 monthly) • Carers Report – quarterly

• Clinical Audit