BLUE LINE EXTENSION - DART.org · BLUE LINE EXTENSION South Oak Cliff Line Section ... Ledbetter...

19
BLUE LINE EXTENSION South Oak Cliff Line Section - 3 Public Meeting December 11, 2014

Transcript of BLUE LINE EXTENSION - DART.org · BLUE LINE EXTENSION South Oak Cliff Line Section ... Ledbetter...

BLUE LINE EXTENSION South Oak Cliff Line Section - 3

Public Meeting

December 11, 2014

Dawn Dorman Community Engagement

Representative

MEETING AGENDA Welcome

DART Update

Communication Tools

SOC- 3

Project Team

Project Status

Introduction of Construction Team

Project Update

Questions/Comments

3

DART TO DFW AIRPORT UPDATE

4

COMMUNICATION TOOLS

Temporary

NOTICE

Service Interruption

There will be a temporary interruption in service on Friday, July 31st between 10:00 a.m. and 11:00 a.m.

Call XXX-XXX-XXXX for questions.

Door Hangers:

Can be used for utility shut-offs or work that will affect a small area

Will be hung on individual doors

Internet:

www.DART.org Facebook Twitter

5

General Public Meetings

Home Owner’s Associations

Educational Institutions

Business Organizations

Face-to-Face

Community Meetings:

COMMUNICATION TOOLS

6

Reza Shirmanesh, P.E. DART Design and Construction

Project Manager

PROJECT TEAM Reza Shirmanesh – DART Project Manager

Steve Knobbe – Design Team Project Manager

Blue Alliance Partners a JV of HNTB and Dikita

Clayton Sorrells – SOCA Project Manager

South Oak Cliff Alliance a JV of Archer Western, Phillips May, and Robinson Industries

Dawn Dorman – Community Engagement Representative

8

PROJECT STATUS

Design Completed October 2014

Start General Construction November 2014

Service Plan December 2016

9

Clayton Sorrells Construction Team Project

Manager

PROJECT TEAM

11

Construction & Testing

Design

CURRENT WORKING SCHEDULE

12

PROJECT OVERVIEW

Clear and Grub work began October 2014

13

PROJECT OVERVIEW

First Drilled Shafts at 5-Mile Bridge began December 2014

14

Looking North Toward Ledbetter Station

WHAT TO EXPECT

MAJOR WORK ACTIVITIES OVER THE NEXT 90 DAYS:

Ledbetter Station Sidewalks and Underground Utilities

5-Mile Bridge Drilled Shafts

5-Mile Bridge Columns

Crouch Bridge Drilled Shafts

Pipe Installation between Five Mile and Crouch

Earthwork and Grading

15

WHAT TO EXPECT

PHASING AT LEDBETTER:

16

• Phase 1 – Blue

• Phase 2 – Red

• Phase 3 – Purple

• Phase 4 – Green

• Phase 5 - Yellow

SOCA Contact Information

Clayton Sorrells – SOCA Project Manager

Clifton Miller – Community Relations Manager

Hotline Number (877) 561 - 4445

17

CONTACTS

DART Community Engagement (214) 749-2598

[email protected]

www.DART.org

Dawn Dorman

18

Questions / Comments