  • Best Practices for

    Design and Construction

    of MSE Walls

    Robert A. Gladstone, P.E.

    Executive Director

    Association for Mechanically Stabilized Earth

    Geotechnical Consultant Workshop

    Ohio Department of Transportation

    June 7, 2017

  • Best Practices for Design and Construction

    of MSE Walls

    NOT a Best Geotechnical Practice

  • Best Practices for Design and Construction

    of MSE Walls

    Common MSE Wall Systems

    Segmental Blocks, Steel

    or Geosynthetic

    Reinforcements

    Welded Wire Facings, Steel

    or Geosynthetic

    Reinforcements

    Precast Facing Panels,

    Steel or Geosynthetic

    Reinforcements

  • Best Practices for Design and Construction

    of MSE Walls

    Design Roles and Responsibilities

    • MSE Designer

    • Civil / Structural

    • Geotech• Owner

    Service Life Requirements

    Aesthetic Requirements

    Acceptable Wall Types

    Global Stability

    Bearing Capacity

    Settlement

    Acceptable Wall Types

    Internal Stability

    Detailed facing and

    reinforcement design

    Construction drawings

    Site Grading

    Wall Location

    DRAINAGE DESIGN

    Acceptable Wall Types

    Loading

  • Best Practices for Design and Construction

    of MSE Walls

    Design Responsibility

    • Internal Stability – MSE wall system supplier

    • Simple check of sliding and overturning

    • Determine eccentricity and applied bearing pressure

    • Check reinforcement pullout and rupture

    • Design of wall system components

    • External Stability – Owner or Consultant

    • Owner proposing to build the structure in the specified location

    • Therefore, owner is responsible for investigating feasibility

    • Includes: global stability, bearing capacity, settlement analysis

  • Best Practices for Design and Construction

    of MSE Walls

    Global Stability

  • Best Practices for Design and Construction

    of MSE Walls

    Options for Bearing Capacity and Settlement

  • Best Practices for Design and Construction

    of MSE Walls

    Specify Requirements in

    Contract Drawings

  • Best Practices for Design and Construction

    of MSE Walls

    Contract Specifications

  • Best Practices for Design and Construction

    of MSE Walls

    Contract Drawings

  • Best Practices for Design and Construction

    of MSE Walls

    Design Parameters

    • Design usually based on assumed parameters

    • These parameters are actually a good choice:

    • 34o is maximum value permitted by AASHTO without test data

    • 34o is approximately the mobilized shear that will develop

    • 34o has been assumed in design for 4 decades

    * Foundation soil design parameters

    should be clearly defined in the contract documents

    Soil Type Unit WeightFriction

    Angle

    Select Granular fill 125 pcf 34°

    Retained Fill 125 pcf 30°

    Foundation Soil * ----- 30° *

  • Best Practices for Design and Construction

    of MSE Walls

    Coherent Gravity Design

    W

    Sliding Resistance

    Vertical Pressure

    E

    Facing

    Reinforced Soil

  • Best Practices for Design and

    Construction of MSE Walls

    Meyerhof Bearing Pressure Distribution

    V = e=

    V = BEARING PRESSURE

    V = SUM OF VERTICAL LOADS

    L = REINFORCING STRIP LENGTH

    e = ECCENTRICITY OF STRUCTURE

    DUE TO APPLIED LOADS

    MC = SUM OF MOMENTS ABOUT

    CENTER LINE DUE TO APPLIED

    LOADS

    V

    L - 2e

    MC

    V

  • Best Practices for Design and Construction

    of MSE Walls

    Characteristics of the

    Coherent Gravity Method

  • Best Practices for Design and Construction

    of MSE Walls

    Fabrication / QC and QA

  • Best Practices for Design and Construction

    of MSE Walls

    Pre-Construction Meeting

    • Attendance

    • MSE wall Rep, Resident Engineer, Inspector, Wall Foreman and Crew

    • Presentation by MSE wall Rep

    • Detailed MSE wall construction procedures

    • Compaction of backfill and installation of soil reinforcements

    • Project specific details – drainage structures, obstructions, etc

    • Inspection

    • What to look for, what will be required

    • General discussion

    • Discuss what's important to: Resident, Inspector, Contractor

  • Best Practices for Design and Construction

    of MSE Walls

    MSE Wall Construction

  • Best Practices for Design and Construction

    of MSE Walls

    Duties of MSE Wall Rep

    • On site for start up of wall construction – 2 to 3 Days

    • Instruct on installation of MSE wall components

    • Instruct on backfilling within the MSE wall volume

    • Answer questions of contractor and inspector

    • MSE wall rep is NOT the Inspector

    • The MSE wall Rep is employed by the Contractor

  • Best Practices for Design and Construction

    of MSE Walls

    Construction Inspection

    Minimum 95%

    Standard Proctor

    Density Required

    CONSIDER:

    NHI training course # 132080:

    Inspection of Mechanically Stabilized

    Earth Walls and Reinforced Soil Slopes

  • Best Practices for Design and Construction

    of MSE Walls

    Backfill Selection is Critical

    Clay backfill =

    poor friction and

    drainage

    Good friction

    and drainage

    come from

    granular

    backfill

  • Best Practices for Design and Construction

    of MSE Walls

    Backfill Materials

    Granular Fill

    Expanded Shale

    Crushed Stone

    LWFC Fill

  • Best Practices for Design and Construction

    of MSE Walls

    Granular Backfill for MSE Walls

    • Gradation limits per AASHTO

    • Some states use different gradation limits and/or reduce fines

    • FHWA allowed up to 25% fines in the early 1980s

    • Backfills often exceeded this limit, up to 35% fines

    • Facing panel alignment was difficult to achieve

    • FHWA and AASHTO returned to 15% limit on fines

    U.S. Sieve Size Percent Passing

    4” 100

    3” 75-100

    #200 0-15

  • Best Practices for Design and Construction

    of MSE Walls

    Flat Plate Tamper

    within 3 ft. of Wall Face

    Compaction is Important

    Minimum 95%

    Standard Proctor

    Density Required

    Large Roller Stay 3 ft. Away

  • Best Practices for Design and Construction

    of MSE Walls

    Installation of Soil Reinforcements

  • Best Practices for Design and Construction

    of MSE Walls

    Reinforcement Connections are Critical

  • Best Practices for Design and

    Construction of MSE Walls

    Accommodating Differential Settlement

    Perpendicular to the Face of Wall

    2" Typical for

    Normal

    Construction

    4" to 6" if

    expect large

    settlement

  • Best Practices for Design and Construction

    of MSE Walls

    Critical Bottom of Wall Details

    • Adequate Foundation Soils

    • Embedment

    • Underdrain

  • Best Practices for Design and Construction

    of MSE Walls

    Drainage Within MSE Walls

  • Best Practices for Design and Construction

    of MSE Walls

    Angles Shift Reinforcements

    at Inlets and Manholes

  • Best Practices for Design and Construction

    of MSE Walls

    Pipes Behind Walls

  • Best Practices for Design and Construction

    of MSE Walls

    Precast Traffic Barrier Design

    4’-6”

    Important: Coping Lip Required

  • Best Practices for Design and Construction

    of MSE Walls

    Membrane

    with

    Traffic

    Barrier

  • Best Practices for Design and Construction

    of MSE Walls

    Locate Guiderail Posts - Skew Reinforcements

  • Best Practices for Design and Construction

    of MSE Walls

    Membrane with Guiderail Posts

  • Best Practices for Design and Construction

    of MSE Walls

    Precast Coping Detail

  • Best Practices for Design and Construction

    of MSE Walls

    There was a Reason for This!

    • MSE Designer

    • Civil / Structural

    • Geotech• Owner

    Service Life Requirements

    Aesthetic Requirements

    Acceptable Wall Types

    Global Stability

    Bearing Capacity

    Settlement

    Acceptable Wall Types

    Internal Stability

    Detailed facing and

    reinforcement design

    Construction drawings

    Site Grading

    Wall Location

    DRAINAGE DESIGN

    Acceptable Wall Types

    Loading

  • Best Practices for Design and Construction

    of MSE Walls

    Implementing Best Practices

    Produces

    Beautiful Long-Performing Structures

    That Reason Is …

  • Best Practices for Design and Construction

    of MSE Walls

    Some of Ohio's Best

    I-90 Cleveland

    (2015)

    In Great

    Condition!

    (1984 – 33 yrs)

    I-75 Dayton

    (Wright

    Brothers)

  • Best Practices for Design and Construction

    of MSE Walls

    Thanks for Listening