BASIC CONCEPTS AND PROCESSES OF ROAD AND BRIDGES

Transcript of BasicConcepts&ProcessesOfRoadAndBridgeMaintenance

Maintenance Methods

BASIC CONCEPTS and PROCESSin MAINTENANCE MANAGEMENT

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYSCordillera Administrative RegionMAINTENANCE MANAGEMENT SYSTEMMAINTENANCE MANAGEMENT SYSTEMThe Management System provides a framework for making informed decisions about highway maintenance.

1216717183845141323121069112221201924252627282915PlanningSchedulingDirectingReportingControl

MAINTENANCE MANAGEMENT SYSTEMPLANNING

It provides direct relationship between Programmed Work and Budgeted Costs and bases for meaningful comparisons of Planned Work with Actual Performance.

It also determine which activities will be performed during the year and how much of which activity will be performed.

10 Steps in the Preparation of Annual Maintenance Work Program/Performance BudgetSTARTENDUPDATE MAINTENANCE FEATURES INVENTORYIDENTIFICATION AND PRIORITIZATION OF MAINTENANCE NEEDS UPDATE UNIT COST OF LABOR, MATERIALS & EQUIPMENTPREPARE DISTRICT ANNUAL MAINT. WORK PROGRAM/PERFORMANCE BUDGETCOMPUTE MAINTENANCE BUDGET ALLOCATION UPDATE PLANNING VALUESFORWARD DISTRICT AWMP/PB TO REGIONAL OFFICES FORWARD REGIONAL AMWP/PB TO BOM FORWARD REGIONAL AMWP/PB TO CENTRALOFFICE FOR APPROVAL RETURN APPROVED AMWP/PB REGIONAL OFFICES66ANNUAL MAINTENANCE WORK PROGRAMStep 1: UPDATE MAINTENANCE FEATURES INVENTORYResponsible: District Maintenance EngineerDME/MPP prepare the worksheet for the inventoryAnnual updating is doneOnly inventories with changes shall be recordedPrepare Summary

(Tad 5.1)(Tad 5.2)7ANNUAL MAINTENANCE WORK PROGRAM

TAD/R 5.2SHEET:AS OF DATE:PREPARED BY:APPROVED BY:DISTRICT:INVENTORY ITEM:123456789101112131415161718192021222324DISTRICT ROAD NAMECL KMCL KMCL KMCL KMLN KMLN KMLN KMSHO. KMDITCH KMNO.NO.NO.NO.NO.NO.LM.LM.LM.LM.LM.NO.LM.NO.LM.TOTALREGION:MAINTENANCE FEATURE INVENTORY SUMMARYTOTALCONCRETE DECKSWIDTH OF WATERWAYSUNPAVEDBITUMINOUSCONCRETEBITUMINOUSCONCRETETOTALTOTALGUARDRAILSSTEELCONCRETEBAILEYTIMBERLENGTHUNPAVED SHOULDERDITCHDROP INLETS CATCHCROSS/LATERALE-3ROADSPAVEMENTBRIDGESBOX CULVERTROADSIDE STRUCTUREFERRIESTRAFFIC SIGNS ETC.Philippine Highway Maintenance Management ManualStep 2: IDENTIFICATION AND PRIORITIZATION OF MAINTENANCE NEEDSResponsible: District Maintenance EngineerConduct routine inspection at least twice a monthDetermine maintenance needs including observations and complaint from the publicEstimate the maintenance activity that needs to be performed11ANNUAL MAINTENANCE WORK PROGRAMOUTPUTS and WORK CATEGORIESWork Category Number/Name10 Pavement Maintenance11 RegravellingBridge and Structure Maintenance15 Shoulder Maintenance16 Drainage Maintenance17 Vegetation Control18 Traffic Services MaintenanceOutputCarriagewayMaintenance

Roadside Maintenance

ACTIVITY STANDARD13

Step 3: UPDATE UNIT COST OF LABOR, MATERIALS & EQUIPMENTResponsible: Regional Office/Dist. Maintenance EngineerAverage Daily Labor Cost

Standard Unit Cost of Equipment

Standard Unit Cost of Materials22ANNUAL MAINTENANCE WORK PROGRAMMAINTENANCE EQUIPMENT LISTFOR PLANNING VALUES

MAINTENANCE MATERIAL LISTFOR PLANNING VALUES

Labor CostLabor Crewday Cost

Performance Budget Workday Standard Cost

Step 4: UPDATE PLANNING VALUESResponsible: BOM StaffMaterials Standard Material Crewday Cost Unit Cost

Equipment Unit CostEquipment Crewday Cost

25ANNUAL MAINTENANCE WORK PROGRAM26

CY - 2014 LABOR CREWDAY COSTCY - 2014 MATERIAL CREWDAY COSTACTRES.NO.FACT.UNIT COSTCOSTUNIT COSTCOST10211/21SURFACE COURSECU.M.1864.008641,023.001,02312/22BASE COURSECU.M.8900.007,2001,371.0010,9688,06411,99110311/21SURFACE COURSECU.M.20864.0017,2801,023.0020,46012/22BASE COURSECU.M.60900.0054,0001,371.0082,26071,280102,72011130HOT MIXCU.M.0.39,450.002,8359,506.002,85231COLD MIXCU.M.2.710,885.0029,3908,148.0022,00032EMULSIFIED ASPHALTLITER6067.004,02063.003,78036,24528,63111210/20CRUSHED AGGREGATECU.M.0.5900.004501,413.0070713/23UNCRUSHED AGGREGATECU.M.1.6918.001,4691,151.001,84214/24FINE AGGREGATESCU.M.1.4496.006941,249.001,74933PENETRATION ASPHALTLITER40046.0018,40051.0020,40021,01324,69711314/24FINE AGGREGATESCU.M.1496.004961,249.001,24932EMULSIFIED ASPHALTLITER15067.0010,05063.009,45010,54610,69911430HOT MIXCU.M.0.29,450.001,8909,506.001,90131COLD MIXCU.M.1.810,885.0019,5938,148.0014,66632EMULSIFIED ASPHALTLITER4067.002,68063.002,52033PENETRATION ASPHALTLITER26646.0012,23651.0013,56610/20CRUSHED AGGREGATECU.M.1.7900.001,5301,413.002,40213/23UNCRUSHED AGGREGATECU.M.1.2918.001,1021,151.001,38114/24FINE AGGREGATESCU.M.1.2496.005951,249.001,49939,62637,93612130HOT MIXCU.M.0.39,450.002,8359,506.002,85231COLD MIXCU.M.1.510,885.0016,3288,148.0012,22232EMULSIFIED ASPHALTLITER3067.002,01063.001,89033PENETRATION ASPHALTLITER20046.009,20051.0010,20010/20CRUSHED AGGREGATECU.M.0.1900.00901,413.0014113/23UNCRUSHED AGGREGATECU.M.0.7918.006431,151.0080614/24FINE AGGREGATESCU.M.0.75496.003721,249.0093731,47729,048REGION XIDESCRIPTIONUNITREGION XIII28

29

CY - 2014 EQUIPMENT CREWDAY COST30

31

32

10Compute Regional/District Allocation based on EMK

10% of the Total District Allocation

5% for the Maintenance of the Newly Converted National Roads

5% for Immediate Response Fund

Step 5: COMPUTE MAINTENANCE BUDGET ALLOCATIONResponsible: BOM Staff33ANNUAL MAINTENANCE WORK PROGRAMCompute standard cost per activity

Make a summary

Total Work Program Cost should not exceed the District AllocationStep 6: PREPARE DISTRICT AMWP/PERFORMANCE BUDGETResponsible: Regional/District Maintenance Engineer34ANNUAL MAINTENANCE WORK PROGRAM REGION: ____________CY 201_ ANNUAL MAINTENANCE WORK PROGRAM AND PERFORMANCE BUDGET - ROADS AND BRIDGES (TOTAL) Sheet 1 of 3 PREPARED BY: SUBMITTED BY: APPROVED: Regional Maintenance Engineer Regional Director Undersecretary for Technical Services DATE: DATE: DATE: NO. ACTIVITY NAME WORKCTRL CTGRY FEATURE INVENTORY QTY. STD. PLANNED WORK AVE DLY PROD CREW DAYS REQ'D CREW SIZE MANDAYS REQ'D PERFORMANCE BUDGET (PESOS) QTY. UNIT LABOR EQUIPMENT MATERIALS CONTRACTUAL & OTHER EXP. TOTAL (1)(2)(3)(4)(5)(6)(7)(8)(9)(10)(11)(12)(13)(14)(15)(16)(17) 4x6 7/9 10x11 13+14+15+16 CARRIAGEWAY MAINTENANCE Work Category No. 10 Pavement Maintenance 111 Premix Patching Bituminuos Pavements un-ltd L-km 3.631 cu.m 308.50112 Penetrating Patching Bituminuous Pavements ltd. L-km. cu.m 3.5080113 Sealing Bituminuous Pavements ltd. L-km 44.554 ltrs. 150070114 Replacement of Bituminuous Pavements Var. L-km 4.948 sq.m. 80080121 Patching Concrete Pavements un-ltd L-km 0.552 cu.m. 3070122 Crack & Joints Sealing of Concrete Pavements ltd L-km 28.366 ltrs. 130060123 Replacement of Concrete Pavement var L-km 0.201 sq. m. 5090101 Manual Repair of Unpaved Road Surfaces ltd Cl-km CL-m 70040102 Manual Patching of Unpaved Road Surfaces un-ltd CL-km. cu.m 10060103 Machine Patching of Unpaved Road Surfaces un-ltd CL-km. CL-m 80050104 Machine Grading of Unpaved Road Surfaces ltd. CL-km CL-km 303.50171 Temporary Patching var CL-km 22.073 CL-m 90040401 Initial Response to Emergencies Roadways unltd. CL-km. 1.544 M-day 6060 41x Emergency Project Proj. CL-km. 0.197 Proj. 0.400503 Indirect Cost Work of Expenses Var. % Budget 0.0044040504 Other Work of Expenses Var. % Budget 0.0044.504.50509 Foreman Supervision Ltd. crewdays 0.538 Proj. 2.5020 Total - Work Category 10 00Step 7: FORWARD DISTRICT AMWP/PB TO REGIONAL OFFICESResponsible: District EngineerStep 8: FORWARD REGIONAL AMWP/PB TO BOMResponsible: Regional Maintenance EngineerStep 9: FORWARD REGIONAL AMWP/PB TO CENTRAL OFFICE FOR APPROVALResponsible: BOMStep 10: RETURN APPROVED AMWP/PB TO REGIONAL OFFICESResponsible: BOM36ANNUAL MAINTENANCE WORK PROGRAMPlanningSchedulingDirectingReportingControl

MAINTENANCE MANAGEMENT SYSTEMSCHEDULING

Timely execution of the maintenance activities

DISTRICT MAINTENANCE ENGINEER (DME)Responsible for scheduling and the immediate rectification of the noted defects taking note of the response time allowed for each defect.

DISTRICT MAINTENANCE ENGINEER (DME)Responsible for Scheduling

Immediate Rectification of the noted defects

Response Time

DO 13 series 2011TAD 5.3NUMBER OF WORKMENDAYS IN PERIODSUBTOTAL MAN-DAYS AVAIL.EST. MAN-DAYS LEAVETOTAL MAN-DAYS AVAIL.SEMIMONTHLY SCHEDULE DEPATRMENT OF PUBLIC WORKS AND HIGHWAYS HIGHWAY MAINTENANCESCHEDULED BY:DISTRICT/CITYAREASCHEDULING PERIODAPPROVED BY:X=-=FROMTOACT. NO.ACTIVITY NAMENO. OF WORK DAYS SCHEDULEDCREW SIZEMAN DAYS SCHED.DATES SCHEDULEDEQUIPMENT TO BE ASSIGNEDMATERIALS TO BE ASSIGNEDSUPERVISING FOREMANREMARKSR/S NO.ROAD NAME/KMS.QUINCENAL/SEMIMONTHLY SCHEDULES40Department of Public Works and HighwaysDAILY ROAD INSPECTION REPORTDate: _____________Stationing/Station Limits/LandmarkCodesDefects/DeficienciesEstimated Quantity and Unit of MeasureRegion: ____________District : ___________________________Submitted by:______________________________ Maintenance Point Person41

SCHEDULINGIt is composed of the following:

Identification of maintenance needs

Preparation of quincenal schedule

Work assignment

ForemanDistrict Maintenance EngineerMaintenance CrewOperatorWork AssignmentSCHEDULINGInstruction Written/VerbalUNDERSTANDWho? What? Where? When? How? & How WellUNDERSTANDWho? What? Where? When? How? & How WellUNDERSTANDWho? What? Where? When? How? & How WellForemanDistrict Maintenance EngineerMaintenance CrewOperatorSCHEDULINGSCHEDULINGWhat an Area Engineer/MPP Should know:

Activity number and name

Work Location

The names of the crew members

The equipment to be used

The materials to be used

Accomplishments units

Any special instruction

ACTIVITY CARD

Improvement of Quality Managementfor Highway and Bridge Constructionand Maintenance, Phase II

POCKETBOOKONROUTINE MAINTENANCE

(Final Draft)SEPTEMBER 2013

Department of Public Works and HighwaysJapan International Cooperation AgencyCheckpointFor manual patching of potholes, surfacing materials are taken from side ditches or high spots of the road.When there is water ponding, remove water prior to filling of surface materials.When Telford base is observed, remove boulders or oversized aggregates and fill surface with required materials.Filling pothole

Repair of pothole using surfacing material which is taken from side ditches.

2) Material not to be usedMaterials containing tree and plant pieces are inappropriate and should be disposed properly.

Photographs9PurposeTo eliminate hazardous conditions, to provide smooth and well-drained surfaces.Procedure Act. No.101 Repair without new materials1. Reshape ditches.Reclaim suitable materials from ditches and sides. Unsuitable waste materials should be disposed to designated areas.Cut high areas.Blend materials from high areas with reclaimed materials.Fill low areas and compact.Reshape surrounding surface or dig outlet channels through high areas of surface, if needed, to allow water to drain.

Act. No.102 Patching with new materialsRestore shape of road surface.Place material in layers to facilitate compaction.Compact each layer.Shape surrounding surface or dig outlet channels through high areas of surface, if needed, to allow water to drain to the ditch.Check cross-section, profile and drainage. Rework if needed.

1-1 MANUAL REPAIR OF UNPAVED ROAD SURFACESRelated Activity Standard No. 101, 1028PlanningSchedulingDirectingReportingControl

DIRECTINGConsists of actions necessary to produce acceptable work results after work assignment has received from the supervising foreman.The most important line of communication is that from the engineer to the foreman and the instructions are communicated clearly and accurately to the person supervising the actual work

DIRECTINGWORK METHODFOREMANCREW MATERIALS EQUIPMENTDECISION OTHER PERTINENT INFODAILY PRODUCTION RANGEACTIVITY STANDARDDIRECTING SpecificationConstruction MethodFOREMANCrewMaterialsEquipmentDECISION Unanticipated events on siteWork Quantity per dayRangePersonDescriptionPurposeACTIVITY STANDARDDPWH - HIGHWAY MAINTENANCEREVISION DATE: SEPTEMBER 2014ACTIVITY NO.: 101 MANUAL REPAIR OF UNPAVED ROAD SURFACESDESCRIPTION: Use this activity for correcting minor surface erosion, ruts, corrugations, potholes and other minor defects without adding new materials. Reclaiming surface materials and short ditching at adjacent sections are included.PURPOSE:To provide smooth, well-drained surface. Reclaiming surface materials and providing functional ditches are secondary purposes.APPROVING AUTHORITY: District EngineerWORK CONTROL CATEGORY: LimitedSCHEDULE:When defects affect traffic speed or the structure of the road and when there are isolated spots on short sections.CREWWORK METHODLaborers1.Place safety devices at designated areas.2.Reshape and reclaim suitable materials from ditches andEQUIPMENT / TOOLSsides.1Wheelbarrow3.Clean the defective areas and remove unsuitable 1Hand Tampermaterials to a depth where good base material exist andVarious Hand Toolsreplace with suitable materials. Safety Devices4.Blend the reclaimed suitable materials and sprinkle withPersonal Protective Equipment water if directed, in order to attain a favorable moisture content. If necessary, additional filler is blended by mixing on the roadway.CONT: ACTIVITY STANDARDCONT: ACTIVITY STANDARDMATERIALS

None

5. WORK METHODThe materials are spread in layers of not more than 10cm. and compacted thoroughly. Any depressions orirregularities should be corrected and compacted.Measure/record the repaired section.6.Remove safety devices.7.Report to the Area-In-Charge the corrective actions undertaken.

DAILY PRODUCTION RANGEcenterline meters (full width)centerline meters (partial width)NOTES:(1)If the primary purpose is ditching, use Activity No. 141 or 199.(2)Use Activity No. 199 for subgrade repair (soft spots).(3)Limited - indicates 2nd priority, the activity should be performed approximately in the quantity planned.PlanningSchedulingDirectingReportingControl

REPORTINGAct as the source of information and data upon which control of all components of the system dependsCY 2015 STATUS REPORT ON MAINTENANCE OF NATIONAL ROADS AND BRIDGESFor the Month of March 2015Regional SummarySource of Fund : GAA - 101Mode of Implementation : By AdministrationCATEGORYActivities undetakenCost% of AccomplishmentExpenditures (Php)%Remarks(per Work Category)This PeriodPrev. monthTotalThis PeriodPrev. monthTotalTotal vs. AWP123456 = (4+5)7 = (3 x 4)8 = (3 x 5)9 = (7+8)101110Pavement Maintenance###########5.94%14.27%20.21%########### - ##########9.32%101Manual Repair of Unpaved Road Surfaces 1,071,360.00 10.30%19.63%29.93% 187,786.06 187,786.06 17.53%On-going102Manual Patching of Unpaved Road Surfaces 1,426,544.00 4.95%13.60%18.55% 105,657.57 105,657.57 7.41%- do -103Machine Patching of Unpaved Road Surfaces 3,350,412.00 10.21%12.07%22.28% 525,924.16 525,924.16 15.70%- do -104Machine Grading of Unpaved road Surfaces 6,392,298.00 6.44%17.22%23.67% 977,153.69 977,153.69 15.29%- do -111Premix Patching Bituminous Pavements 18,046,826.00 4.64%11.91%16.55% 1,030,869.50 1,030,869.50 5.71%- do -112Penetrating Patching Bituminous Pavements 10,168,224.00 7.07%14.06%21.13% 931,391.46 931,391.46 9.16%- do -113Sealing Bituminous Pavements 2,397,952.00 5.61%11.39%17.00% 206,834.65 206,834.65 8.63%- do -114Replacement of Bituminous Pavements 272,815.00 0.00%0.00% - - - do -121Patching Concrete Pavements 11,261,676.00 5.67%10.74%16.41% 808,885.07 808,885.07 7.18%On-going122Crack & Joints Sealing of Concrete 9,092,944.00 7.65%14.60%22.25% 746,412.86 746,412.86 8.21%- do -123Replacement of Concrete Pavements 1,696,696.00 2.98%0.00%2.98% 50,614.92 50,614.92 2.98%- do -171Temporary Patching 1,609,104.00 11.49%25.75%37.24% 312,981.85 312,981.85 19.45%On-going401Initial Response to Emergencies Roadways 6,039,306.00 4.16%19.69%23.84% 580,667.34 580,667.34 9.61%- do -41xEmergency Projects - - - 503Indirect Cost Work of Expenses 28,988,160.00 6.78%20.38%27.17% 3,245,969.88 3,245,969.88 11.20%On-going504Other Work or Expenses 8,367,840.00 6.62%15.72%22.34% 1,204,131.63 1,204,131.63 14.39%- do -509Foreman Supervision 29,092,608.00 6.73%17.49%24.22% 3,270,005.48 3,270,005.48 11.24%- do -510Unproductive Time 2,184,840.00 7.67%11.19%18.87% 235,218.17 235,218.17 10.77%- do -71xSpecial Maintenance (Resealing Bituminous Pavement) 10,914,278.00 2.29%0.00%2.29% 250,000.00 250,000.00 2.29%- do -62x(a)Resealing of Bituminous Concrete Pavement (Mechanized) 1,390,000.00 0.00%0.00%0.00% - - 66xSelective Replacement of Portland Cement Concrete Pavement 3,613,748.00 0.00%0.00%0.00% - - 11Regravelling 45,371,938.00 9.05%1.39%10.44% 2,772,141.00 - 2,772,141.00 6.11%61xResurfacing of Unpaved Roadways 25,500,000.00 9.29%2.06%11.36% 2,767,890.00 2,767,890.00 10.85%On-going63xRegravelling of Unpaved Shoulder 19,871,938.00 8.74%0.52%9.26% 4,251.00 4,251.00 0.02%- do -Department of Public Works and HighwaysDAILY ROAD INSPECTION REPORTDate: _____________Stationing/Station Limits/LandmarkCodesDefects/DeficienciesEstimated Quantity and Unit of MeasureRegion: ____________District : ___________________________Submitted by:______________________________ Maintenance Point Person58HIGHWAY MAINTENANCE ACTIVITY CARDPREPARED BY:APPROVED BY:TAD 2.2DISTRICT/CITYAS OF DATE ACTIVITY DATA SUMMARYACTIVITYREPORT PERIODWorkdaysAccomplishmentWork UnitMan-DaysStandard CostNo.NameLABOREQUIPMENTMATERIALSTOTALWork Category No. 10: Pavement MaintenanceTHIS MONTHTO DATE102Spot Replacement Unpd. Roadway SurfaceTHIS MONTHTO DATE104Reshaping Unpaved RoadwaysTHIS MONTHTO DATE105Regrading Unpd. RoadwaysTHIS MONTHTO DATE109Other Unpaved Roadways Surface MaintenanceTHIS MONTHTO DATEWhy Reporting of work is needed:Review work performanceEvaluate progress toward program activitiesGuide corrective action needed to improve work performanceProvide information for advance planningTo maintain factual records REPORTINGA Reporting System should: 1. Provide a source of document that records:Type of workDate & work locationResponsible of work directing and reportingType and quantity of resource useQuantity of work accomplishmentFiled by Activity and date for easy retrieval2. Provide a simple format for summarizing data3. Provide reports of data summaries4. Provide performance reports based on analysis of summarized dataPlanningSchedulingDirectingReportingControl

CONTROLEnsuring the maintenance work done as nearly as possible to plans and standards and that it is carried out with the financial constraints

Operational control is continuous. To ensure intelligent decisions about scheduling, directing and reporting.System controlusually occurs annually to correct system procedures, policies, plans and standards.CONTROLCONTROLMethod/Procedures:

Work performance and management actions are compared with plans and standards.

Significant deviations are identified.

Significant deviations are investigated to determine when they occurred.

The most appropriate corrective actions are identified.

The corrective actions are implemented.

The corrective actions are followed up to ensure that they are effective.

End of PresentationTHANK YOU!Sheet1REPAIR AND MAINTENANCE ACTIVITIESFOR ROADS AND BRIDGESActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsCARRIAGEWAY MAINTENANCEWork Category No. 10 - Pavement Maintenance101Manual Repair ofLimitedcenterline metersUnpaved Roadcenterline kilomters ofUnpaved RoadrepairedSurfacesunpaved roadsSurfaces102Manual Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced103Machine Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced104Machine GradingLimitedcenterlineUnpavede Roadcenterline kilometers ofUnpaved Roadkilometers gradedSurfacesunpaved roadsSurfacesCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance111Premix PatchingUnlimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspremix placedPavementsbituminous roads112Penetration PatchingLimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspatching aggregatePavementsbituminous roadsplaced113SealingLimitedliters of sealerBituminouslane kilometers ofBituminous Pavementsmaterial placedPavementsbituminous roads114Replacement ofVariablesquare metersBituminouslane kilometers ofBituminous PavementsreplacedPavementsbituminous roadsCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance121Patching ConcreteUnlimitedcubic meters ofConcretelane kilometers ofPavementsmaterials placedPavementsconcrete roads122Crack and JointLimitedliters of asphaltConcretelane kilometers ofSealing of Concretematerial placedPavementsconcrete roadsPavements123Replaclement ofVariablesquare metersConcretelane kilometers ofConcrete PavementsreplacedPavementsconcrete roads171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roads401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 11 - Regravelling61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 12 - Bridge and Structure Maintenance151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterways402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -BridgesActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsROADSIDE MAINTENANCEWork Category No. 15 - Shoulder Maintenance131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 16 - Drainage Maintenance141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept Bridges203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 17 - Vegetation Control201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roads209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 18 - Traffic Services Maintenance301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsUNPAVED SHOULDERS131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersDRAINAGE141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.BRIDGES151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterwaysFERRIES161Ferry ServiceLimitedhours of ferry operationNonenumber of ferriesTEMPORARY REPAIRS171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roadsOTHER MAINTENANCE AND REPAIRS199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept BridgesGROUP 200 - - -ROADSIDE FEATURES201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roadsand Ditch Slopes203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsGROUP 300 - - - TRAFFIC SERVICES301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsGROUP 400 - - - EMERGENCY WORK401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -Bridges41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsGROUP 500 - - - SUPERVISION, SUPPORT AND OVERHEAD501Production ofUnlimitedcubic meters ofNonelane kilometers ofBituminous Premixpremix producedpaved roads502Other MaterialLimitedman-daysNonecenterline kilometers ofProduction andall roadsHandling503Indirect Cost, WorkVariableman-daysNonepercent of budgetor Expense504Other Work or ExpenseVariableman-daysNonepercent of budget509Foreman SupervisionLimitedman-daysNonecrewdays plannedwithout full-time foreman510Unproductive TimeVariablenumber of scheduledNonetotal planned crewdaysor assigned crewdaysnot performedGROUP 600 - - - PERIODIC MAINTENANCE (PROJECT)61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roads62XResealingBituminous SurfaceMethod AProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roadsMethod BProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roads63XResurfacing UnpavedShouldersMethod AProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shouldersMethod BProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shoulders64XReplacing TimberProjectLinear meters ofBridges with Timberlinear meter of bridgesDecksbridge re-deckedDeckswith timber decks66XSeclectedProjectsquare metersConcrete Pavementslane kilometers ofReplacement ofconcrete pavementConcrete Pavement65XBridge RepaintingProjectnumber of bridgesBridges with Steelnumber of bridges withcompletely paintedMemberssteel members69XPeriodProjectman-daysNonecenterline kilometers ofMaintenance Supportall roadsGROUP 700 M - - - PREVENTIVE MAINTENANCE71XSpecial MaintenanceProjectprojects completedAll Featurescenterline kilometes ofall roadsRepair & Maint. Activities for National Rds. And Bridges/Budget-FY-2011/Dell

Sheet2

Sheet3

Sheet1REPAIR AND MAINTENANCE ACTIVITIESFOR ROADS AND BRIDGESActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsCARRIAGEWAY MAINTENANCEWork Category No. 10 - Pavement Maintenance101Manual Repair ofLimitedcenterline metersUnpaved Roadcenterline kilomters ofUnpaved RoadrepairedSurfacesunpaved roadsSurfaces102Manual Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced103Machine Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced104Machine GradingLimitedcenterlineUnpavede Roadcenterline kilometers ofUnpaved Roadkilometers gradedSurfacesunpaved roadsSurfacesCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance111Premix PatchingUnlimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspremix placedPavementsbituminous roads112Penetration PatchingLimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspatching aggregatePavementsbituminous roadsplaced113SealingLimitedliters of sealerBituminouslane kilometers ofBituminous Pavementsmaterial placedPavementsbituminous roads114Replacement ofVariablesquare metersBituminouslane kilometers ofBituminous PavementsreplacedPavementsbituminous roadsCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance121Patching ConcreteUnlimitedcubic meters ofConcretelane kilometers ofPavementsmaterials placedPavementsconcrete roads122Crack and JointLimitedliters of asphaltConcretelane kilometers ofSealing of Concretematerial placedPavementsconcrete roadsPavements123Replaclement ofVariablesquare metersConcretelane kilometers ofConcrete PavementsreplacedPavementsconcrete roads171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roads401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 11 - Regravelling61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 12 - Bridge and Structure Maintenance151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterways402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -BridgesActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsROADSIDE MAINTENANCEWork Category No. 15 - Shoulder Maintenance131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 16 - Drainage Maintenance141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept Bridges203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 17 - Vegetation Control201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roads209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 18 - Traffic Services Maintenance301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsUNPAVED SHOULDERS131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersDRAINAGE141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.BRIDGES151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterwaysFERRIES161Ferry ServiceLimitedhours of ferry operationNonenumber of ferriesTEMPORARY REPAIRS171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roadsOTHER MAINTENANCE AND REPAIRS199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept BridgesGROUP 200 - - -ROADSIDE FEATURES201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roadsand Ditch Slopes203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsGROUP 300 - - - TRAFFIC SERVICES301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsGROUP 400 - - - EMERGENCY WORK401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -Bridges41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsGROUP 500 - - - SUPERVISION, SUPPORT AND OVERHEAD501Production ofUnlimitedcubic meters ofNonelane kilometers ofBituminous Premixpremix producedpaved roads502Other MaterialLimitedman-daysNonecenterline kilometers ofProduction andall roadsHandling503Indirect Cost, WorkVariableman-daysNonepercent of budgetor Expense504Other Work or ExpenseVariableman-daysNonepercent of budget509Foreman SupervisionLimitedman-daysNonecrewdays plannedwithout full-time foreman510Unproductive TimeVariablenumber of scheduledNonetotal planned crewdaysor assigned crewdaysnot performedGROUP 600 - - - PERIODIC MAINTENANCE (PROJECT)61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roads62XResealingBituminous SurfaceMethod AProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roadsMethod BProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roads63XResurfacing UnpavedShouldersMethod AProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shouldersMethod BProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shoulders64XReplacing TimberProjectLinear meters ofBridges with Timberlinear meter of bridgesDecksbridge re-deckedDeckswith timber decks66XSeclectedProjectsquare metersConcrete Pavementslane kilometers ofReplacement ofconcrete pavementConcrete Pavement65XBridge RepaintingProjectnumber of bridgesBridges with Steelnumber of bridges withcompletely paintedMemberssteel members69XPeriodProjectman-daysNonecenterline kilometers ofMaintenance Supportall roadsGROUP 700 M - - - PREVENTIVE MAINTENANCE71XSpecial MaintenanceProjectprojects completedAll Featurescenterline kilometes ofall roadsRepair & Maint. Activities for National Rds. And Bridges/Budget-FY-2011/Dell

Sheet2

Sheet3

Sheet1REPAIR AND MAINTENANCE ACTIVITIESFOR ROADS AND BRIDGESActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsCARRIAGEWAY MAINTENANCEWork Category No. 10 - Pavement Maintenance101Manual Repair ofLimitedcenterline metersUnpaved Roadcenterline kilomters ofUnpaved RoadrepairedSurfacesunpaved roadsSurfaces102Manual Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced103Machine Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced104Machine GradingLimitedcenterlineUnpavede Roadcenterline kilometers ofUnpaved Roadkilometers gradedSurfacesunpaved roadsSurfacesCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance111Premix PatchingUnlimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspremix placedPavementsbituminous roads112Penetration PatchingLimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspatching aggregatePavementsbituminous roadsplaced113SealingLimitedliters of sealerBituminouslane kilometers ofBituminous Pavementsmaterial placedPavementsbituminous roads114Replacement ofVariablesquare metersBituminouslane kilometers ofBituminous PavementsreplacedPavementsbituminous roadsCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance121Patching ConcreteUnlimitedcubic meters ofConcretelane kilometers ofPavementsmaterials placedPavementsconcrete roads122Crack and JointLimitedliters of asphaltConcretelane kilometers ofSealing of Concretematerial placedPavementsconcrete roadsPavements123Replaclement ofVariablesquare metersConcretelane kilometers ofConcrete PavementsreplacedPavementsconcrete roads171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roads401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 11 - Regravelling61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 12 - Bridge and Structure Maintenance151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterways402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -BridgesActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsROADSIDE MAINTENANCEWork Category No. 15 - Shoulder Maintenance131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 16 - Drainage Maintenance141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept Bridges203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 17 - Vegetation Control201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roads209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 18 - Traffic Services Maintenance301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsUNPAVED SHOULDERS131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersDRAINAGE141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.BRIDGES151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterwaysFERRIES161Ferry ServiceLimitedhours of ferry operationNonenumber of ferriesTEMPORARY REPAIRS171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roadsOTHER MAINTENANCE AND REPAIRS199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept BridgesGROUP 200 - - -ROADSIDE FEATURES201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roadsand Ditch Slopes203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsGROUP 300 - - - TRAFFIC SERVICES301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsGROUP 400 - - - EMERGENCY WORK401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -Bridges41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsGROUP 500 - - - SUPERVISION, SUPPORT AND OVERHEAD501Production ofUnlimitedcubic meters ofNonelane kilometers ofBituminous Premixpremix producedpaved roads502Other MaterialLimitedman-daysNonecenterline kilometers ofProduction andall roadsHandling503Indirect Cost, WorkVariableman-daysNonepercent of budgetor Expense504Other Work or ExpenseVariableman-daysNonepercent of budget509Foreman SupervisionLimitedman-daysNonecrewdays plannedwithout full-time foreman510Unproductive TimeVariablenumber of scheduledNonetotal planned crewdaysor assigned crewdaysnot performedGROUP 600 - - - PERIODIC MAINTENANCE (PROJECT)61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roads62XResealingBituminous SurfaceMethod AProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roadsMethod BProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roads63XResurfacing UnpavedShouldersMethod AProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shouldersMethod BProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shoulders64XReplacing TimberProjectLinear meters ofBridges with Timberlinear meter of bridgesDecksbridge re-deckedDeckswith timber decks66XSeclectedProjectsquare metersConcrete Pavementslane kilometers ofReplacement ofconcrete pavementConcrete Pavement65XBridge RepaintingProjectnumber of bridgesBridges with Steelnumber of bridges withcompletely paintedMemberssteel members69XPeriodProjectman-daysNonecenterline kilometers ofMaintenance Supportall roadsGROUP 700 M - - - PREVENTIVE MAINTENANCE71XSpecial MaintenanceProjectprojects completedAll Featurescenterline kilometes ofall roadsRepair & Maint. Activities for National Rds. And Bridges/Budget-FY-2011/Dell

Sheet2

Sheet3

Sheet1REPAIR AND MAINTENANCE ACTIVITIESFOR ROADS AND BRIDGESActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsCARRIAGEWAY MAINTENANCEWork Category No. 10 - Pavement Maintenance101Manual Repair ofLimitedcenterline metersUnpaved Roadcenterline kilomters ofUnpaved RoadrepairedSurfacesunpaved roadsSurfaces102Manual Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced103Machine Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced104Machine GradingLimitedcenterlineUnpavede Roadcenterline kilometers ofUnpaved Roadkilometers gradedSurfacesunpaved roadsSurfacesCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance111Premix PatchingUnlimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspremix placedPavementsbituminous roads112Penetration PatchingLimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspatching aggregatePavementsbituminous roadsplaced113SealingLimitedliters of sealerBituminouslane kilometers ofBituminous Pavementsmaterial placedPavementsbituminous roads114Replacement ofVariablesquare metersBituminouslane kilometers ofBituminous PavementsreplacedPavementsbituminous roadsCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance121Patching ConcreteUnlimitedcubic meters ofConcretelane kilometers ofPavementsmaterials placedPavementsconcrete roads122Crack and JointLimitedliters of asphaltConcretelane kilometers ofSealing of Concretematerial placedPavementsconcrete roadsPavements123Replaclement ofVariablesquare metersConcretelane kilometers ofConcrete PavementsreplacedPavementsconcrete roads171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roads401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 11 - Regravelling61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 12 - Bridge and Structure Maintenance151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterways402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -BridgesActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsROADSIDE MAINTENANCEWork Category No. 15 - Shoulder Maintenance131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 16 - Drainage Maintenance141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept Bridges203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 17 - Vegetation Control201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roads209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 18 - Traffic Services Maintenance301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsUNPAVED SHOULDERS131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersDRAINAGE141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.BRIDGES151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterwaysFERRIES161Ferry ServiceLimitedhours of ferry operationNonenumber of ferriesTEMPORARY REPAIRS171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roadsOTHER MAINTENANCE AND REPAIRS199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept BridgesGROUP 200 - - -ROADSIDE FEATURES201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roadsand Ditch Slopes203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsGROUP 300 - - - TRAFFIC SERVICES301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsGROUP 400 - - - EMERGENCY WORK401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -Bridges41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsGROUP 500 - - - SUPERVISION, SUPPORT AND OVERHEAD501Production ofUnlimitedcubic meters ofNonelane kilometers ofBituminous Premixpremix producedpaved roads502Other MaterialLimitedman-daysNonecenterline kilometers ofProduction andall roadsHandling503Indirect Cost, WorkVariableman-daysNonepercent of budgetor Expense504Other Work or ExpenseVariableman-daysNonepercent of budget509Foreman SupervisionLimitedman-daysNonecrewdays plannedwithout full-time foreman510Unproductive TimeVariablenumber of scheduledNonetotal planned crewdaysor assigned crewdaysnot performedGROUP 600 - - - PERIODIC MAINTENANCE (PROJECT)61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roads62XResealingBituminous SurfaceMethod AProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roadsMethod BProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roads63XResurfacing UnpavedShouldersMethod AProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shouldersMethod BProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shoulders64XReplacing TimberProjectLinear meters ofBridges with Timberlinear meter of bridgesDecksbridge re-deckedDeckswith timber decks66XSeclectedProjectsquare metersConcrete Pavementslane kilometers ofReplacement ofconcrete pavementConcrete Pavement65XBridge RepaintingProjectnumber of bridgesBridges with Steelnumber of bridges withcompletely paintedMemberssteel members69XPeriodProjectman-daysNonecenterline kilometers ofMaintenance Supportall roadsGROUP 700 M - - - PREVENTIVE MAINTENANCE71XSpecial MaintenanceProjectprojects completedAll Featurescenterline kilometes ofall roadsRepair & Maint. Activities for National Rds. And Bridges/Budget-FY-2011/Dell

Sheet2

Sheet3

Sheet1REPAIR AND MAINTENANCE ACTIVITIESFOR ROADS AND BRIDGESActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsCARRIAGEWAY MAINTENANCEWork Category No. 10 - Pavement Maintenance101Manual Repair ofLimitedcenterline metersUnpaved Roadcenterline kilomters ofUnpaved RoadrepairedSurfacesunpaved roadsSurfaces102Manual Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced103Machine Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced104Machine GradingLimitedcenterlineUnpavede Roadcenterline kilometers ofUnpaved Roadkilometers gradedSurfacesunpaved roadsSurfacesCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance111Premix PatchingUnlimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspremix placedPavementsbituminous roads112Penetration PatchingLimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspatching aggregatePavementsbituminous roadsplaced113SealingLimitedliters of sealerBituminouslane kilometers ofBituminous Pavementsmaterial placedPavementsbituminous roads114Replacement ofVariablesquare metersBituminouslane kilometers ofBituminous PavementsreplacedPavementsbituminous roadsCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance121Patching ConcreteUnlimitedcubic meters ofConcretelane kilometers ofPavementsmaterials placedPavementsconcrete roads122Crack and JointLimitedliters of asphaltConcretelane kilometers ofSealing of Concretematerial placedPavementsconcrete roadsPavements123Replaclement ofVariablesquare metersConcretelane kilometers ofConcrete PavementsreplacedPavementsconcrete roads171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roads401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 11 - Regravelling61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 12 - Bridge and Structure Maintenance151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterways402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -BridgesActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsROADSIDE MAINTENANCEWork Category No. 15 - Shoulder Maintenance131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 16 - Drainage Maintenance141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept Bridges203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 17 - Vegetation Control201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roads209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 18 - Traffic Services Maintenance301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsUNPAVED SHOULDERS131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersDRAINAGE141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.BRIDGES151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterwaysFERRIES161Ferry ServiceLimitedhours of ferry operationNonenumber of ferriesTEMPORARY REPAIRS171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roadsOTHER MAINTENANCE AND REPAIRS199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept BridgesGROUP 200 - - -ROADSIDE FEATURES201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roadsand Ditch Slopes203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsGROUP 300 - - - TRAFFIC SERVICES301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsGROUP 400 - - - EMERGENCY WORK401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -Bridges41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsGROUP 500 - - - SUPERVISION, SUPPORT AND OVERHEAD501Production ofUnlimitedcubic meters ofNonelane kilometers ofBituminous Premixpremix producedpaved roads502Other MaterialLimitedman-daysNonecenterline kilometers ofProduction andall roadsHandling503Indirect Cost, WorkVariableman-daysNonepercent of budgetor Expense504Other Work or ExpenseVariableman-daysNonepercent of budget509Foreman SupervisionLimitedman-daysNonecrewdays plannedwithout full-time foreman510Unproductive TimeVariablenumber of scheduledNonetotal planned crewdaysor assigned crewdaysnot performedGROUP 600 - - - PERIODIC MAINTENANCE (PROJECT)61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roads62XResealingBituminous SurfaceMethod AProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roadsMethod BProjectlane meters resealedBituminous Pavementslane kilometers ofbituminous roads63XResurfacing UnpavedShouldersMethod AProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shouldersMethod BProjectshoulder kilometersUnpaved Shouldersshoulder kilometers ofresurfacedunpaved shoulders64XReplacing TimberProjectLinear meters ofBridges with Timberlinear meter of bridgesDecksbridge re-deckedDeckswith timber decks66XSeclectedProjectsquare metersConcrete Pavementslane kilometers ofReplacement ofconcrete pavementConcrete Pavement65XBridge RepaintingProjectnumber of bridgesBridges with Steelnumber of bridges withcompletely paintedMemberssteel members69XPeriodProjectman-daysNonecenterline kilometers ofMaintenance Supportall roadsGROUP 700 M - - - PREVENTIVE MAINTENANCE71XSpecial MaintenanceProjectprojects completedAll Featurescenterline kilometes ofall roadsRepair & Maint. Activities for National Rds. And Bridges/Budget-FY-2011/Dell

Sheet2

Sheet3

Sheet1REPAIR AND MAINTENANCE ACTIVITIESFOR ROADS AND BRIDGESActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsCARRIAGEWAY MAINTENANCEWork Category No. 10 - Pavement Maintenance101Manual Repair ofLimitedcenterline metersUnpaved Roadcenterline kilomters ofUnpaved RoadrepairedSurfacesunpaved roadsSurfaces102Manual Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced103Machine Patching ofUnlimitedcubic meters ofUnpavede Roadcenterline kilometers ofUnpaved Roadpatching materialSurfacesunpaved roadsSurfacesplaced104Machine GradingLimitedcenterlineUnpavede Roadcenterline kilometers ofUnpaved Roadkilometers gradedSurfacesunpaved roadsSurfacesCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance111Premix PatchingUnlimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspremix placedPavementsbituminous roads112Penetration PatchingLimitedcubic meters ofBituminouslane kilometers ofBituminous Pavementspatching aggregatePavementsbituminous roadsplaced113SealingLimitedliters of sealerBituminouslane kilometers ofBituminous Pavementsmaterial placedPavementsbituminous roads114Replacement ofVariablesquare metersBituminouslane kilometers ofBituminous PavementsreplacedPavementsbituminous roadsCont'.ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 10 - Pavement Maintenance121Patching ConcreteUnlimitedcubic meters ofConcretelane kilometers ofPavementsmaterials placedPavementsconcrete roads122Crack and JointLimitedliters of asphaltConcretelane kilometers ofSealing of Concretematerial placedPavementsconcrete roadsPavements123Replaclement ofVariablesquare metersConcretelane kilometers ofConcrete PavementsreplacedPavementsconcrete roads171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roads401Initial Response toUnlimitedman-daysAll features,centerline kilometers ofEmergencies - - -except Bridgesall roadsRoads41XEmergency ProjectsProjectprojects completedAll Featurescenterline kilometers ofall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 11 - Regravelling61XResurfacing UnpavedProjectcenterlineUnpaved Roadcenterline kilometers ofRoadwaysKilometers resurfacedSurfaceunpaved roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 12 - Bridge and Structure Maintenance151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterways402Initial Response toUnlimitedman-daysAll Bridgesnumber of all bridgesEmergencies - - -BridgesActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsROADSIDE MAINTENANCEWork Category No. 15 - Shoulder Maintenance131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 16 - Drainage Maintenance141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept Bridges203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)ActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 17 - Vegetation Control201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roads209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsActivityActivity NameWork ControlWork UnitsMaintenanceInventoryNumberCategoryFeatureUnitsWork Category No. 18 - Traffic Services Maintenance301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic ServicesVariableman-daysAll Traffic Controlcenterline kilometers ofDevicesall roadsUNPAVED SHOULDERS131Manual Repair ofLimitedshoulder metersUnpavedunpaved shoulderUnpaved ShouldersrepairedShoulderskilometers132Manual Patching ofUnlimitedcubic meters ofUnpavedunpaved shoulderUnpaved Shoulderspatching materialsShoulderskilometersplaced133Machine Grading ofLimitedshoulder kilometersUnpavedunpaved shoulderUnpaved ShouldersgradedShoulderskilometersDRAINAGE141Manual Ditch CleaningUnlimitedlinear meters ofDrainage Ditcheskilometers lined orditch cleanedunlined ditches142Manual Inlet/OutletUnlimitednumber of inletsMinor Drainageinlets/outlets of cross-Cleaningand outlets cleanedStructures (culvertdrainage, catch basins,(including catchinlets and outlets,drop inlets, manholesbasins, manhole)catch basins, etc.)143Culvert Line CleaningLimitednumber of linesCulvert Linesnumber of cross-drainagecleanedand lateral lines144Repair and/orVariablenumber ofMinor Drainagecross-drainage culvertsReplacement of Minorstructures repairedStructures(pipe and box), catchDrainage Structuresor replacedbasins, drop inlets,manhole.BRIDGES151Cleaning BridgesLimitedlinear meters cleanedAll Bridgeslinear meters of allbridges152Patching ConcreteUnlimitedsquare meters ofConcrete Bridgelinear meters ofDecksdeck patchedDecksconcrete decks153Repairs to concreteLimitednumber of bridgesConcrete Bridgeslinear meters ofBridgesrepairedconcrete bridges154Repairs to SteelLimitednumber of bridgesSteel Bridgeslinear meters ofBridgesrepaired(including compositestealbridges)155Repairs to BaileyLimitednumber of bridgesBailey Bridgeslinear meters ofBridgesrepairedbailey bridges156Repairs to TimberLimitednumber of bridgesTimber Bridgeslinear meters ofBridgesrepairedtimber bridges157Clearing BridgeUnlimitednumber of waterwaysBridge withlinear meters of bridgeWaterwaysclearedWaterwayswith waterwaysFERRIES161Ferry ServiceLimitedhours of ferry operationNonenumber of ferriesTEMPORARY REPAIRS171Temporary PatchingVariablelimits of patching inAll Roads andcenterline kilometers ofcenterline metersShouldersall roadsOTHER MAINTENANCE AND REPAIRS199Other Maintenance toVariableman-daysAll Roads andcenterline kilometersRoad and RelatedRelated Features,of all roadsFeaturesexcept BridgesGROUP 200 - - -ROADSIDE FEATURES201Vegetation ControlVariablepassmeters ofRoadside withcenterline kilometers ofroadside mowed orMowable Vegetationall roadscleared202Erosion Repair andLimitedcubic meters ofBackslopes of Cuts,centerline kilometers ofControl on Roadsidesmaterial placedForeslopes of Fillsall roadsand Ditch Slopes203Repair to MajorLimitednumber ofMajor Roadsidenumber of majorRoadside Structuresstructure repairedStructuresroadside features(rip-rapped slopes,sea walls, retainingwalls, etc.)209Other RoadsideVariableman-daysAll Roadsidecenterline kilometers ofMaintenanceFeaturesall roadsGROUP 300 - - - TRAFFIC SERVICES301Sign MaintenanceUnlimitednumber of unitsSign Units (signnumber of sign untismaintainedinstallations, markersdelineators, etc.)302Centerlineline and LaneLimitedline kilometersCenterline andlane kilometers ofLine RepaintingrepaintedLane linespaved roads303Guardrail MaintenanceUnlimitedlinear meters ofGuardrailslinear meters ofguardrail maintainedguardrails304Sight DistanceUnlimitedpassmeters ofRoadside withcenterline kilometers ofMowing and Clearingroadside mowed orMowable Vegetationall roadscleared309Other Traffic S