Barranca Parkway Access Road
IRVINE VALLEY COLLEGE South Orange County Community College District
Bi-Weekly Progress Update
Through November 15, 2016
PROJECT STATUS:
• The irrigation controller was installed.
• The mow curb along both sides of the access road was placed.
• The asphalt patching was competed on Barranca.
• Potholing was complete at the Shadow Oaks entry to locate the existing utilities.
• Scheduled completion date: January 19, 2017. Project currently on schedule.
• Project is 70% complete overall.
Barranca Median Asphalt Patch Back
Mow Curb Placed Along Access Road
Irrigation Controller was installed
.
Upcoming Activities:
• Install planting material
• Install traffic signal foundations