BAR RevA Resubmission - 24 Dec 2010
Transcript of BAR RevA Resubmission - 24 Dec 2010
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
1/402
07257/I2/G/R014A
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage Tunnel
Blasting Assessment Report for Intake I-2
December 2010
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
2/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
3/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
EXECUTIVE SUMMARY
The proposed works covered by this blast assessment include all drill and blast operations in
connection with the hard rock excavation of the lower sections of the Vortex Drop Shaft and the
Upper Man Access Shafts, the Upper and Lower connecting Man Access Adits, the Lower Man
Access Shaft, De-aeration Chamber and Main Adit at the Intake I-2, Lo Wai, Tsuen Wan.
Various types of sensitive receivers have been identified close to the proposed blasting areas with
some having a higher order of ranking than others. In particular there are slopes and the Ship
Temple () within the locality and identified as being in close proximity to the blastareas at the Intake I-2 location.
For any geotechnical features located within the influence of the blasting areas, stability analysishas been carried out to determine the safe vibration levels for such features. It has been
determined that any sensitive receivers subjected to a PPV less than 5mm/s will not require
detailed assessment unless preconstruction condition survey suggests the feature may be
unusually sensitive to blasting vibrations.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
4/402
CONTENTS
1.0 INTRODUCTION ................................................................................................................................... 1
1.1 Background ........................................................................................................................................ 1
1.2 Government Blasting Requirements .................................................................................................. 1
1.3 Scope of Report ................................................................................................................................. 2
1.4 Structure of Report ............................................................................................................................ 3
1.5 Report Limitation ................................................................................................................................ 3
1.6 Reference to Other Relevant Reports ............................................................................................... 3
2.0 PROPOSED BLASTING LOCATIONS ................................................................................................. 4
2.1 General .............................................................................................................................................. 4
2.2 INTAKE I-2 Area ................................................................................................................................ 4
3.0 TOPOGRAPHIC, GEOLOGIC AND HYDROGEOLOGIC STUDY ....................................................... 5
3.1 General .............................................................................................................................................. 5
3.2 Geology .............................................................................................................................................. 5
3.3 Published Geology ............................................................................................................................. 5
3.4 Previous Ground Investigations ......................................................................................................... 6
3.5 Groundwater ...................................................................................................................................... 6
3 6 Ph i l Sit C t i t 7
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
5/402
6.9 Natural Terrain Hillside and Boulders .............................................................................................. 20
6.10 Existing Buildings and Structures .................................................................................................... 20
6.11 Historical Buildings and Monuments ............................................................................................... 22
6.12 WSD Facilities ................................................................................................................................. 22
6.13 Utility Companies ............................................................................................................................. 23
6.14 Other Facilities ................................................................................................................................. 23
6.15 Controlling Sensitive Receivers ....................................................................................................... 24
7.0 CONSTRUCTION REQUIREMENTS .................................................................................................. 25
7.1 Proposed Blasting Areas ................................................................................................................. 25
7.2 Estimates and Quantities of Explosives Required ........................................................................... 25
7.3 Explosives Delivery .......................................................................................................................... 25
7.4 Tunnel Blasting operations .............................................................................................................. 25
7.4.1 Shafts at Intake I-2 ................................................................................................................... 267.4.2 As Constructed Air Vent Shaft ................................................................................................. 27
7.4.3 Pre-Constructed Main Tunnel .................................................................................................. 27
7.4.4 Tunnel Blasting Procedure ...................................................................................................... 27
8.0 BLASTING CONTAINMENT AND CONTROL MEASURES ............................................................. 30
8.1 Blast Restrictions and Control Levels .............................................................................................. 30
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
6/402
TABLES
Table 3.5: INTAKE I-2 WATERTABLE 7
Table 4.0: REFERENCE TO AS-CONSTRUCTED STRUCTURES 9
Table 5.2: TYPICAL CHARGE WEIGHT PER DELAY AGAINST DISTANCE ANDPPVC
11
Table 5.3a: CORRESPONDENCE WITH UTILITY COMPANIES 12
Table 5.3b: VIBRATION LIMITS AS DETERMINED BY UTILITY COMPANIES INHONG KONG
12
Table 5.4a: STRUCTURAL BEHAVIOUR SUBJECT TO AIRBORNE VIBRATION 14
Table 5.4b: TYPICAL CHARGE WEIGHT PER DELAY VERSUS DISTANCE ANDDBL
15
Table 6.5: PARTIAL FACTORS APPLIED TO LOADING AND MATERIALPARAMETERS
19
Table 6.8: SUMMARY TABLE OF AFFECTED MAN-MADE FEATURES NEARINTAKE I-2
20
Table 6.10: SUMMARY TABLE OF AFFECTED BUILDINGS AND STRUCTURES 22
Table 6.12: SUMMARY TABLE OF AFFECTED MAJOR WSD FACILITIES 23
Table 6.13: SUMMARY TABLE OF AFFECTED MAJOR UTILITIES 23
Table 6.14: SUMMARY TABLE OF OTHER AFFECTED FACILITIES 24
T bl 8 1 BLAST VIBRATION CONTROL PROCEDURE 30
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
7/402
APPENDICES
APPENDIX A OVERALL LAYOUT OF THE INTAKE I-2
APPENDIX B GEOLOGICAL SECTION OF INTAKE I-2
APPENDIX C REFERENCE DRAWINGS FOR INTAKE I-2
APPENDIX D ROCKHEAD AND GROUNDWATER CONTOURS PLAN
APPENDIX E INVENTORY OF EXISTING BUILDINGS
APPENDIX F DRAWINGS OF EXISTING UTILITIESAPPENDIX G TYPICAL BLAST PATTERNS
APPENDIX H ASSESSMENT OF AFFECTED MAN-MADE SLOPES AND RETAININGWALLS
APPENDIX I ASSESSMENT OF EXISTING FACILITIES
APPENDIX J EXPLOSIVE QUANTITIES AND DELIVERY SCHEDULE
APPENDIX K INSTRUMENTATION LAYOUT PLANAPPENDIX L PROPOSED PROTECTIVE MEASURES
APPENDIX M BOREHOLE LOCATION PLAN AND GROUNDWATER MONITORINGRECORDS
APPENDIX N REPORT FOR SOUND INSULATION MEASUREMENT TEST
APPENDIX O DOCUMENTARY RECORD OF PUBLIC CONSULTATION
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
8/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
1.0 INTRODUCTION
1.1 BACKGROUND
The Tsuen Wan Drainage Tunnel (TWDT) has been commissioned to improvethe flood protection level in the Tsuen Wan and Kwai Chung area by constructinga drainage tunnel system to intercept flow from upland catchments. The tunnelsystem will comprise:
an Intake Structure at the junction of Wo Yi Hop Road and Shing Mun Road(I-1);
an Intake Structure at Lo Wai (I-2);
an Intake Structure at Tso Kung Tam, about 350m off the southern side ofRoute Twisk (I-3);
an Outfall Structure at Yau Kom Tau underneath Castle Peak Road (O-1);
a 5.1km long, 6.5m diameter Main Tunnel with associated adit tunnelsconnected to the various intake structures.
Currently the excavation of the Intake at I-2 is being undertaken usingmechanical means which gives the geology of the area, slightly decomposedtuff, rates of excavation are consequently slow.
The current view of the contractor is that to maintain the constructionprogramme of Intake I-2 excavation will have to be completed using blastingmethods. However, given the locality of the site and the proximity of variouslocal structures, the purpose of this report is to assess the undertaking of
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
9/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Report (BAR) are contained in Geotechnical Engineering Office (GEO) Circular
No. 27.These blasting requirements are also noted and defined in PNAP 178 for thoseprivate projects that are under taken through the Buildings Department (BD)Ordinance.
1.3 SCOPE OF REPORT
This BAR refers to the portion of Works referred to in Section 1.1 above.
This BAR is prepared in order to determine the sensitive receivers within thevicinity of the pre-determined blast areas, the likely restrictions that they willimpose on blasting and appropriate control measures that should beimplemented in order to ensure blasting is carried out safely. This will then allowan evaluation of the feasibility of blasting.
An initial review of the various blast site constraints indicates that a maximumexplosive charge-weight of 0.2 kg / 0.33 kg per delay determined through designof blast pattern will allow normal excavation progress of the Intake I-2 Shafts and
Man Access Adits, and 0.4kg per delay for the De-aeration Chamber and MainAdit. Based on this maximum charge-weight and using the standard MinesDivision blast prediction formula, it has been calculated that the level of vibrationdue to blasting would have an attenuation of less than 5mm/s at a radial distanceof 30m from 0.33kg per delay blasting point or 34m from 0.4kg per delay blastingpoint. These values correspond with the vibration limit typically applied to historicbuildings, buildings in poor condition or of unknown design quality. It hastherefore been determined that any sensitive receivers subjected to less than
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
10/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
A 4m ID Man Access Shaft (Lower),
A 3.5m ID Man Access Adit (Upper), and
The commencement of blasting for 14m, from a depth of approximately 25mbelow ground level, within a single 4m ID Man Access Shaft (Upper) whichhas a total depth of approximately 39m.
The overall layout of Intake I-2 is shown in Drawing MCSJV/TW/I-2/2020102located in Appendix A.
The shafts and tunnels will be constructed within rock and it is anticipated thatthe excavation will be by drill and blast methods. This blasting assessmenttherefore has been prepared in accordance with GEO Circular No.27.
1.4 STRUCTURE OF REPORT
The Blasting Assessment Report (BAR) covers a small section of the Works atIntake I-2 that constitutes the tunnel alignment between Intake I-2 and the maintunnel alignment making reference to the various individual sensitive receivers
and local blasting issues within the area.This report contains general background information relevant to the wholealignment detailing the topographical, geological and hydrological setting.It alsodescribes the general blasting approach related to each blast area outlining theassociated blasting constraints for each of the blast areas as well as therequirements for supervision and inspection that will be adopted for the whole ofthe alignment blasting works.
1.5 REPORT LIMITATION
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
11/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
2.0 PROPOSED BLASTING LOCATIONS
2.1 GENERAL
The proposed works covered by this blast assessment include all drill and blastoperations in connection with the excavation in hard rock in the followingsections of the Works:
A single 5m ID and 5.84m OD Vortex Drop Shaft which has a total depth ofapproximately 30m,
A De-aeration Chamber of approximately 21m long by 9m wide by 13m high, A 3.5m ID and 4.24m OD Man Access Adit (Lower),
A 4m ID and 4.74m OD Man Access Shaft (Lower),
A 4.5m ID and 5.6m OD Main Adit,
A 3.5m ID and 4.24m OD Man Access Adit (Upper), and
A single 4m ID and 4.74m OD Man Access Shaft (Upper) which has a total
depth of approximately 39m.
A layout plan for each of these areas is shown in the accompanying drawing:MCSJV/TW/I-2/2020102 inclusive and geological sections of these areas areshown in MCSJV/TW/I-2/2020108 respectively. These drawings are located inAppendices A and B respectively.
2.2 INTAKE I-2 AREA
The proposed Main Tunnel extends from its eastern end in the Sheung Kwai
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
12/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
3.0 TOPOGRAPHIC, GEOLOGIC AND HYDROGEOLOGIC STUDY
3.1 GENERAL
The proposed Intake I-2 is located in a major stream course adjacent to Lo WaiRoad bridge crossing. There is extensive surface development at Lo Waiincluding the Yuen Yuen Home for The Aged to the northwest of the intake,Yuen Yuen Institute to the north and Hilltop Country Club to the northeast. Thetopography in section along the alignment is shown in geological sections underdrawing MCSJV/TW/I-2/2020108 and the inferred rockhead contour is shown in
drawing MCSJV/TW/I-2/2020109. These drawings are located in Appendices Band D respectively. The borehole information is included in Appendix M.
3.2 GEOLOGY
In accordance with the information presented in the Geotechnical BaselineReport (GBR), Intake I-2 will be excavated entirely within volcanic coarse ash tuffof the Yim Tin Tsai Formation. It is described as dense greenish grey to darkgrey, very fine to fine-to-medium grained crystalline rock.
The coarse ash tuff is generally strong to very strong (79 MPa to 374 MPa) andis highly abrasive. The rock joints are generally medium to widely-spaced andare predominantly sub-vertical. Low angle sheeting joints also occur, particularlytowards the ground surface. Joints and micro-fissures have complex jointspacing varying from very close to widely and occasionally very widely spaced.The joints are rough/planar to smooth/planar, with Fe/Mn staining or Ch/Qu/Cafill. There are typically 4 sets of joints (3 subvertical and 1 horizontal); some ENEbasalt dykes are likely.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
13/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
3.4 PREVIOUS GROUND INVESTIGATIONS
GIU Report No. 42632
This report comprises a Final Fieldwork Report for the ground investigation (GI)works of Feature No. 7SW-C/R86. The GI works consist of 3 drillholes (CH1 toCH3), 5 coreholes (CH4 to CH8) and a trial trench (TT1) which are located atapproximately 80m to 90m from the proposed Intake I-2. The drillholes revealedthat the underlying geology comprises a thin layer of Fill overlying Alluvium andDecomposed Tuff. Bedrock was encountered at about 4m below ground. The
groundwater monitoring records at CH3 indicated that the groundwater level is atabout 3.7m below ground (+87.40mPD).
GIU Report No. 46167
This report comprises a Final Fieldwork Report for the GI works of Feature No.7SW-A/R39. The GI works consist of 1 drillhole (BH1) and 2 trial pits (TP1 andTP2) which are located at approximately 60m from the proposed Intake I-2.Drillhole No. BH1 revealed that the underlying geology comprises a layer of Filloverlying Slightly Decomposed Tuff (SDT). Bedrock was encountered at about2.6m below ground. The groundwater monitoring records at BH1 indicated thatdry condition is occurred at about 3.5m below ground (+109.02mPD).
GIU Report No. 47059
This report comprises a Final Fieldwork Report for the GI works of Feature No.7SW-A/R39. The GI works consist of 4 coreholes (CH1 to CH4) which arelocated at approximately 60m from the proposed Intake I-2. The coreholesrevealed that the underlying geology comprises a layer of Fill overlying Slightly
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
14/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
monitoring records show significant variations in the highest monitored
groundwater levels (HMGWL) which vary between regolith layer and bedrockthroughout the tunnel alignment.
The GBR states the baseline conditions for groundwater levels are as follows:Except where stated otherwise, the watertable lies within 1 m of rockhead in thewet season, rising into the regolith to within 1 m of the ground surface duringrainstorms. Perennial artesian groundwater (1 m higher than the ground coverand higher during rainstorms) occurs across the Lo Wai valley adjacent to IntakeI-2.
From the recent groundwater monitoring data, the recorded highest and lowestgroundwater levels for relevant areas are presented in the table below.
Borehole No. Monitoring Period HighestGroundwater Level
(mPD)
Lowest GroundwaterLevel (mPD)
I2/BH511 Aug 2009
14 Aug 2010 105.16 103.71
I2/BH10A30 Sept 2008
16 Aug 2010102.41 99.86
I2/BH11A30 Sept 2008
18 Aug 2010105.71 98.10
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
15/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Various types of sensitive receivers have been identified close to the proposed
blasting areas with some having a higher order of ranking than others. Inparticular there are slopes and the Ship Temple () within the localityand identified as being in close proximity to the blast areas at the Intake I-2location.
However, as part of the Pre-condition and Structural Survey, the nearby buildingstructures have been identified as being either in close proximity to the alignmentor one of the designated blast areas. Reference is made to drawingMCSJV/TW/I-2/2020114 which highlights these structures locality and also theinventory of existing buildings. This information is located in Appendix E forreference.
3.7 EXISTING UTILITIES
In addition to the existing building structures, numerous existing utilities arelocated in the vicinity of the designated blasting area and the utilities undertakersinclude the following:
Drainage Service Department PCCW Ltd.
Water Supplies Department
Hong Kong & China Gas Ltd (Towngas)
CLP Power Hog Kong Ltd.
The location of the existing utilities in the vicinity of the different blast areas are
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
16/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
4.0 PROPOSED LAYOUTS OF THE SHAFTS AND ADIT CONNECTIONS
It is from the Upper Man Access Shaft and Vortex Drop Shaft that the drill andblast excavation of the Intake I-2 will start and the shafts will be the only meansof access and egress to men, material and plant until the connecting aditsintersect the De-aeration Chamber.
The shaft area is already established as other surface works have alreadycommenced and there have been some retaining measures undertaken tosupport the adjacent slopes and surrounding area.
Details of the as-constructed structures are included in Appendix C as listed inthe table below.
As-constructed Structures Reference Drawings
Noise Enclosure above Upper ManAccess Shaft
MCSJV/TW/I-2/2012090 to 2012094,2012101 and 2012209 to 2012212
Noise enclosure above Vortex DropShaft
MCSJV/TW/I-2/2012095 to 2012098and 2012100
Air Vent Shaft MCSJV/PW/I-2/2030025
Approach Channel DC/2001/12/SK/072, 0471 and 0459,MCL/4111CD/S/220 and 223,MCSJV/SK/I-2/2104067 and 2104068
Solider-pile Wall MCL/4111CD/G/209,DC2007/12/SK/0056, 0068, 0149, 0221,
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
17/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
5.0 BLASTING MECHANISM AND POSSIBLE DETRIMENTAL EFFECTS
5.1 GENERAL
The maximum charge weight that will be used during the Intake I-2 blastingworks was calculated based on the limited PPV of the sensitive receivers in thevicinity of the site and has been found to not exceed 0.2 kg / 0.33 kg per delayfor the Shafts and 0.4kg per delay for the Chamber and Main Adit. Whereverused these will enable a pull, that is blasted advance, of around 0.8m to 1.0m tobe gained for full face blasting. This rate of advance is deemed optimal when
consideration is made of the practicable constraints such as the excavation cycletimes taken for the development of the shaft, adit and de-aeration chamber. Themaximum charge weight table for Intake I-2 has been presented in drawingMCSJV/TW/I-2/2020116 in Appendix G. The results have been summarized andshown in drawing MCSJV/TW/I-2/2020117. And the typical blast pattern designsfor the shaft, adit and de-aeration chamber are also shown in Appendix G.
5.2 GROUND VIBRATION
It is observed that ground vibrations induced by blast stress wave have a peakvelocity that is related to the instantaneous charge weight and the distance fromthe blast source. A preliminary assessment of the ground vibrations likely toresult from blasting can be made using the formula as shown derived by theUnited States Bureau of Mines:
PPV = K (R/ W)-B
This formula has been adopted by the Mines Division of the Hong KongGovernment, which has monitored blasting vibrations in Hong Kong since 1965.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
18/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Allowable Charge Weight (kg/delay)
RadialDistancefromB
last(m)
Distance6.00 5.00 4.00 3.00 2.00 1.00 0.50 0.25 0.10
Predicted Peak Particle Velocity (PPV) (mm/sec)
120 5.6 5.0 4.4 3.7 2.9 1.9 1.2 0.8 0.5
100 7.0 6.2 5.4 4.6 3.6 2.3 1.5 1.0 0.6
90 7.9 7.1 6.2 5.2 4.1 2.7 1.7 1.1 0.7
80 9.2 8.2 7.2 6.0 4.7 3.1 2.0 1.3 0.8
70 10.8 9.6 8.4 7.1 5.5 3.6 2.4 1.6 0.965 11.8 10.6 9.2 7.7 6.0 4.0 2.6 1.7 1.0
60 13.0 11.6 10.2 8.5 6.7 4.4 2.9 1.9 1.1
55 14.5 12.9 11.3 9.5 7.4 4.8 3.2 2.1 1.2
50 16.2 14.5 12.7 10.6 8.3 5.4 3.6 2.3 1.3
45 18.5 16.5 14.4 12.1 9.5 6.2 4.1 2.7 1.5
40 21.3 19.1 16.7 14.0 10.9 7.2 4.7 3.1 1.8
35 25.1 22.5 19.6 16.5 12.8 8.4 5.5 3.6 2.1
30 30.3 27.1 23.7 19.9 15.5 10.2 6.7 4.4 2.525 37.9 33.9 29.6 24.8 19.4 12.7 8.3 5.4 3.1
20 49.7 44.5 38.8 32.6 25.4 16.7 10.9 7.2 4.1
15 70.6 63.2 55.1 46.2 36.1 23.7 15.5 10.2 5.8
10 115.8 103.6 90.4 75.8 59.2 38.8 25.4 16.7 9.5
5 269.7 241.3 210.6 176.7 138.0 90.4 59.2 38.8 22.2
Table 5.2 : Typical Charge weight per delay against Distance and PPVc
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
19/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Utility Request on Letter Ref. Reply on Letter Ref.
WSD
21 Jul 201007257/
339555
3 Aug 2010(3) in WSD/NTW486/70/125/2006 TJ(7)
Towngas 23 Jul 2010 UNE2010/03636/N
CLP - -*
DSD 6 Sept 2010(176918) in MS
9/DC2007/12/0/0PCCW 23 Jul 2010 OPS/NT/WKC/RW-605
Wharf T&T Ltd 30 Jul 2010 WTT/NT10//0680/KSW
HighwaysDepartment
- -*
Table 5.3a:Correspondence with Utility Companies
Note: * Allowable PPV based on ER Clause 4.4.4 (5). Extract of ER has been included inAppendix F.
Utility InstallationPPV(mm/sec)
Max Amplitude
WSD Water retaining structures / WaterTunnels
13 0.1mm
Water Mains / Other structures and pipes 25 0.2mm
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
20/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
assessment shall be prepared based on the acceptable vibration levels agreed
by the utilities operators.The Utilities affected by the project are located in Appendix F for reference.
5.4 AIR BLAST AND NOISE CRITERIA
Air-blasts and construction noise are the common description of air pressurewaves generated by explosive detonation and construction machinery.
The pressure waves can be described with time histories where amplitude is air
pressure. Construction noise is the audible, high frequency portion of thepressure wave. The lower frequency portion is the air-blast, which is not audible,but excites structures and buildings to produce noise through rattling windowsetc.
The pressure wave generated by an explosion also propagates through air,forming an airborne vibration in the form of concussion or air overpressure.Noise is the audible result of this pressure wave, with frequencies from 20 to20,000 Hz, while air blast lies in the inaudible range below 20 Hz.
Measurement of sound pressure is made in decibels (dB). The decibel scale islogarithmic and allows the compression of zero to one kPa into a range of about150 dB. An increase of 6 dB represents a doubling of the sound pressure and anincrease of about 3 dB occurs as a result of the sound doubling (for example 2machines instead of one). A noise level of about 100 dB is very loud, 140 dBpainfully loud and 180 dB will lead to irreversible hearing loss.
The human perception of sound, which is more sensitive to some frequenciesthan others, has led to the development of weighting scales to simulate the
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
21/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
SymptomsPeak Overpressure
kPa dB
Rattle of loose window sash against window frame 0.2 140
Failure of poorly mounted window pane 0.7 150
Damage to strongly mounted window pane 7 170
Cracking plaster > 7 > 170
Table 5.4a: Structural behaviour subject to airborne vibration.
Airblast is usually controlled by wind speed and direction, humidity, temperature,topography, type and amount of explosives used, depth of explosives buried,geology etc.
The US Bureau of Mines recommends the following safe levels for airblast (forevents exceeding 2 seconds duration):
135 dB when using a 0.1 Hz high pass linear measurement method, or
133 dB when using a 2 Hz high pass response, and
129 dB for a frequency range of 6 to 200 Hz
Noise from blasting is exempt from consideration under a Construction Noise
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
22/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
blasting operations and typical blasting times. The schematic temporary traffic
arrangement is enclosed in Appendix J for reference.The Mines Division target for air overpressure will be complied with and will bedetermined in dBL. At the time of writing this report, 120dBL is the Mines Divisiontarget for allowable air-overpressure.
Usually Mines Division applies this target for air blast for sites in Hong Kongalthough there is some flexibility on the limit dependent on the number ofcomplaints received.
The following analysis for the allowable air overpressure is based upon siteformation derived constant from various surface projects in Hong Kong. Theequation outlined below is one used by Mines Division to check the allowable airoverpressure close to the blast.
Air overpressure (dBL) = 170 24log10 [ D/W0.333
]
Table 5.4b presents the typical range of charge weights and predicted vibrationlevels using the Mines Division vibration constants.
This analysis is really only applicable to surface blasting although it can be usedtentatively when blasting is carried out in tunnel areas close to the portal or shaft.
Various air overpressure control measures should be proposed by the Contractorto suit his intended work programme and scheduling of the works.
Allowable Charge Weight (kg/delay)
Distance6.00 5.00 4.00 3.00 2.00 1.00 0.50 0.25 0.10
dBL
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
23/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
5.5 FUMES AND DUST
Fumes generated from the initiation of explosives can be easily alleviated withproper ventilation. The general philosophy includes:
ensuring adequate ventilation to dilute the fumes, and
ensuring adequate time after blasting before allowing access to the blastface.
5.6 FLYROCK
It is envisaged that flyrock is unlikely to be a problem for the works, as all theblasting will be underground and well below the ground level, and the blast holeswill be well-confined. In addition, a suitable blast face cover will be provided tocover the shaft during each blast. The typical blast face cover is shown inDrawings MCSJV/TW/I-2/2020119 and MCSJV/TW/I-2/2020120 in Appendix L.Flyrock containment measures will be included in Method Statement andsubmitted separately for approval by MD/GEO.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
24/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
6.0 OVERVIEW OF SENSITIVE RECEIVERS
6.1 GENERAL
Sensitive Receivers are anything that may be damaged by blast vibrations ornoise. The common sensitive receivers are structures such as buildings andbridges, man-made slopes and retaining walls, natural slopes, and services.Maximum allowable vibration limits have been allocated for these receivers andmaximum charge weights calculated accordingly.
The sensitive receivers, except for man-made slopes and retaining walls, within
a calculated radial distance of the areas to be blasted have been assessed todetermine the maximum allowable charge weight for any specific point along thetunnel. The limit of inspection has been based upon the 5mm/s contour from theassumed blast charge weight at tunnel level.
It must be noted that 5mm/s is much lower than the threshold level of damage tovarious structures and facilities which is normally over 50mm/sec or higher.However, the condition of the structures will be checked by preliminary visualinspection to ensure that they can tolerate the assessed allowable PPVs whichwill normally be defined as 15mm/sec for buildings or structure or as per theanalysed allowable PPVs for the slopes.
Geoguide 4 Section 5.7.1 states As a general guide, blast vibrations from sub-surface works are normally not potentially damaging at distances of more than50m and only exceptionally at distances of more than 100m. It is not clearlystated whether this is in plan distance or radial distance from the source.
With regards to the designated blast areas of Intake I-2, the blasting zone of
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
25/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
6.4 METHODOLOGY OF ANALYSIS OF CUT AND FILL SLOPES
The calculation of the allowable vibration limits of existing slopes were basedupon the critical peak particle velocity (PPVc) which was calculated using themethod set out in GEO Report 15. The PPVc for existing soil slope wascalculated from the following formulae:-
PPVc = Kc g/(Ka)
where Kc = the critical acceleration at which the slope has a factor ofsafety of 1.0 against failure for Category II/III features and 1.10
for Category I features (m/s-2)g = the acceleration due to gravity (m/s-2)
= the circular frequency of the ground motion (2f) (s-1)
Ka = the magnification factor
In order to obtain Kc, slope stability analyses were performed with varying valuesof Kc until a FOS of 1.0 was achieved. is dependent on the frequency of the
vibration, which typically ranges from 20-100Hz due to blasting. A frequency of30Hz was adopted, as recommended in GEO Report 15, in the assessment.
For an upgraded slope, the pseudo static factor of safety for the slope has beenadopted as 1.20 or as specified in the desk study information. Figures in GEOReport 15 would be used as reference to calculate these PPVc.
6.5 METHODOLOGY OF ANALYSIS OF RETAINING WALLS
The vibration limits of existing retaining walls are calculated in accordance with
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
26/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Loading / Material Parameters Partial Factors
Dead Load 1.0
Imposed Loads (storage, residential, etc) 1.0
Transient Loads considered as surcharge in HongKong (traffic, pedestrian loads, etc)
1.0
Water Pressure 1.0
tan where is angle of shear resistance includingbase friction angle (tan b)
1.1
Soil apparent cohesion, c 1.2
Table 6.5: Partial Factors applied to loading and material parameters
The critical PPV is then calculated from the formula shown above in section 6.4.6.6 DESK STUDY
A desk study search of all the various relevant existing man-made features hasbeen carried out. For any DH order features that had not completed upgradingworks, further assessment would be performed to determine whether the chargeweight might need to be reduced to minimize the vibration effect on the features.The desk study results of the adjacent man-made features are summarized and
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
27/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
performing adequately.
6.8 EXISTING MAN-MADE FEATURES
A detailed desk study search of all the various relevant existing man-madefeatures for this blasting assessment and a summary of the related data arecontained in Appendix H of this report. The relevant pseudo-static stabilityanalysis for the slope that lies close to the blasting influence zone is also outlinedin this BAR.
As also noted from the desk study results, some DH order slopes have not beenupgraded and they are identified to be outside the blasting influence zone.Hence, their impact to the charge weight is considered to be insignificant.
Where there is no records or where the slope has been served with a DH orderwe have analysed the different groundwater conditions of the slopes. It must benoted that there is significant conservatism in the analysis of the slopes. Wehave also carried out a visual inspection of the slopes and have identified thatthe slopes will be able to accommodate safely an allowable PPV of 5mm/sec.
The locations of the affected man made features are highlighted on the plan asshown in Appendix H. Only Feature No. 7SW-C/C1384 is found within theblasting influence zone and the allowable PPV is given in Table 6.8.
Feature No.Consequence-
to-LifeCategory
Feature Type Predicted PPV(mm/s)PPVc
(mm/s)
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
28/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Structure EBS Ref. No. Structural Form
Predicted ppv
(mm/s)
Allowable ppv
(mm/s)
Village House I2-001 Concrete Frame 1 10
Village House I2-002 Concrete Frame 2 15
Yuen Yuen Institute I2-003 Concrete Frame 1 15
Village House I2-004 Concrete Frame 1 15
Storage I2-005 Wooden Frame 2 15
Storage I2-006 Wooden Frame 2 15
Village House I2-007 Iron Sheet 2 15
Village House I2-008 Iron Sheet 2 15
Storage I2-009 Iron Sheet 3 15
Village House I2-010 Concrete Frame 2 15
Village House I2-011 Concrete Frame 2 15
Shrine I2-012 Concrete Frame 1 15
Village House I2-013 Concrete Frame 2 15
Village House I2-014 Concrete Frame 2 10
Village House I2-015 Concrete Frame 2 15
Grave I2-016 Stone 3 25
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
29/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Grave I2-035 Stone 1 25
Grave I2-036 Stone 2 25
Village House TWDT/S/019 Iron Sheet 3 15
Village House TWDT/S/020 Iron Sheet 2 15
Village House TWDT/S/021 Concrete Frame 2 15
Village House TWDT/S/023 Concrete Frame 4 15
Village HouseTWDT/S/024 Iron Sheet
3 15Lo Wai Road TWDT/S/026 Concrete Paved 5 25
Yuen Yuen Home for the Aged TWDT/S/027A Concrete Frame 3 15
Yuen Yuen Home for the Aged TWDT/S/027B Concrete Frame 3 15
Yuen Yuen Home for the Aged TWDT/S/027C Concrete Frame 2 15
Ship Temple TWDT/S/028 Concrete Frame 6 15
Western Monastery TWDT/S/029 Concrete Frame 3 15
Village House TWDT/S/036 Iron Sheet 4 15
Village House TWDT/S/037 Concrete Frame 2 15
Yuen Yuen Care & AttentionHome for the Aged
TWDT/S/040 Concrete Frame 2 15
Temple TWDT/S/080 Concrete Frame 3 15
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
30/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
WSD Facility Location Predicted ppv(mm/s)Allowable ppv
(mm/s)
100mm Fresh Watermain Along Lo Wai Road 5 25
Table 6.12: Summary Table of Affected Major WSD Facilities
To facilitate the surface construction works, the above fresh watermain has beentemporarily diverted by the Contractor as shown in drawings MCSJV/SK/I-
2/2103007 to 2103009 in Appendix C.6.13 UTILITY COMPANIES
Utility companies have numerous assets crossing and adjacent to the proposedIntake I-2. The services include gas pipes, electricity cables, telephone cables,cable television services, stormwater drains and sewage pipes.
The utilities present within the Intake I-2 blast area are fresh watermains, andtelecommunications ducts; all of which run parallel to Lo Wai Road on the
western side of the existing bridge and come closest to the proposed blastlocations at the access shaft. All utilities remain at least 10m away from theground level of drop shaft blast area.
Table 6.13 summarises the predicted and allowable PPV.
Utility Location Predicted ppv(mm/s)Allowable ppv
(mm/s)
300mm Drain Along Lo Wai Road 5 25
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
31/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Facility Predicted ppv
(mm/s)
Allowable ppv
(mm/s)As-constructed ELS System
(Sheet-pile at Upper Man Access Shaft)6.9 >25
As-constructed Air Vent Shaft 92.1 97
As-constructed Approach Channel 6.8 25
Table 6.14: Summary Table of Other Affected Facilities
The assessment for the above facilities is included in Appendix I for reference.
6.15 CONTROLLING SENSITIVE RECEIVERS
The analysis and assessment of the various sensitive receivers are outlined insection 6.2 ~ 6.14 above.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
32/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
7.0 CONSTRUCTION REQUIREMENTS
7.1 PROPOSED BLASTING AREAS
The proposed blast locations have been previously discussed in Section 2.0 ofthis report and include the following:
The commencement of blasting for 5m, from a depth of approximately 25mbelow ground level, within a single 5m ID Vortex Drop Shaft which has atotal depth of approximately 30m,
A De-aeration Chamber of approximately 21m long by 9m wide by 13m high, A 3.5m ID Man Access Adit (Lower),
A 4.5m ID Main Adit,
A 4m ID Man Access Shaft (Lower),
A 3.5m ID Man Access Adit (Upper), and
The commencement of blasting for 14m, from a depth of approximately 25m
below ground level, within a single 4m ID Man Access Shaft (Upper) whichhas a total depth of approximately 39m.
As mentioned in the scope of the report and sections 4.0 and 5.0, adetermination of the maximum charge-weight to be used to achieve acomparable advance given the construction constraints was determined basedon preliminary blast designs for the shafts, adits and tunnels. The maximumcharge weights determined were 0.2kg, 0.33kg or 0.4kg of explosive per delay.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
33/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
under the same road closure period of the day but not at the same time.
7.4.1 SHAFTS AT INTAKE I-2
Due to the proximity of the local sensitive receivers in the area, including theshaft sound barrier structure itself, low charge weights will have to be used tocomply with the restrictions on allowable PPVs at this location.
Setting up of adequate protective measures will also be required before anyblasting will be able to take place. Due to the location of the shaft, blasting mayhave to be sequential within the blast area as PPVs are restricted to the design
PPV contour due to the proximity of numerous sensitive receivers in the area.This will call for a lowering of the specified charge weights which in turn willdictate the rates of advance in the shaft.
At a predetermined distance, relaxation of the PPV restrictions will allow for fullproduction, i.e. maximum round length with maximum charge weight, as the aditswill then be advanced towards the de-aeration chamber.
As the blasting works approach holing, the advance rate will be reduced again
due to the local PPV limitations and will remain in force until breakthrough.7.4.2 AS-CONSTRUCTED AIR VENT SHAFT
The Air Vent Shaft connecting the De-aeration Chamber to the ground surfacehas already been constructed. The shaft is approximately 30m in depth and issteel lined. The blasting design of the chamber near the shaft is needed to bemodified in order to prevent the shaft from damaged.
The maximum allowable charge weight for the De-aeration Chamber has been
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
34/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
7.4.4 TUNNEL BLASTING PROCEDURE
(A) Ordering & Delivery of Explosives
To receive explosives from the Kowloon ExplosivesDepot (KED), the Contractor will submit required application for a RemovalPermit to the nominated explosives supplier. Once the order arrives at site, theShotfirer will unload the loading delivery truck and check the order and arrange
for the explosives to be conveying to the blasting face.
(B) Pre-drilling Works for Blasting Surfaces
Pre-drilling works of the blast holes in the shafts and adits will be performedusing a drilling rig and pneumatic rock drills.
(C) Transportation of Explosives down the Shaft using the 20Ton or 15TonGantry
Explosives cartridges will be placed, under the supervision of the Chief Shotfireron wooden boxes specially dedicated for the conveyance of explosives. All theboxes will be locked before conveyance down to blast area level. The firstoperation will be to convey the explosives boxes down the shaft under the
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
35/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
and reduce the chance of explosive being ejected out of the hole when the
charge is initiated. The stemming will also help to reduce the air overpressure(AOP) levels.
(E) Site Clearance and Evacuation Procedures
Based on the discussion and agreement with TMLG, temporary road closure, ifrequired, will be for carrying out when blasting works at Intake I-2 is required.
All personnel shall evacuate from the shaft and adit. For safer operation, whenthe blast of the Main Adit is within 10m from the Main Tunnel, the area of theMain Tunnel 20m from either side of the interception with the Main Adit will beevacuated.
Except the registered Shotfirer and his assistant, nobody is allowed to stay nextto the Shafts. An evacuation procedure shall be followed. For better protection tothe registered Shotfirer, the Shotfirer shall fire the shot next to the containerwhich is a standard steel-made container near the site entrance.
It is proposed to temporarily close Lo Wai Road and footpath in the vicinity ofshafts for each individual blast for circa 10 ~ 15 minute when blasts are fired.
(F) Covering of Blasting Works
ICE approved noise enclosure structure had been constructed at ground level
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
36/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Pedestrians and Public. The PRN will be advising the blasting time and location
as well as clearance areas in advance. The Gong Men and Sentries arepositioned to ensure that the public is not started by any underground shaftblasting in the urban area.
Temporary road closure will be realized until it will be demonstrated that anyAOP effects near the shafts are minimal and that motorists and pedestrians canuse the road safely without being affected by the blasting operation.
A flow chart of the general blasting activities has been included in appendix J forreference.
The details of blasting sequence, evacuation criteria, public and traffic control,checking for misfire, re-entry to tunnel and tunnel support for the shafts, aditsand de-aeration chamber will be further described in the Method Statement.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
37/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
8.0 BLASTING CONTAINMENT AND CONTROL MEASURES
8.1 BLAST RESTRICTIONS AND CONTROL LEVELS
It is proposed that Alert, Action and Alarm levels are attached to each productionblast to ensure adequate control. The following actions should be taken if a blastexceeds the specified limit for blast vibration monitoring points for controllingsensitive receivers near to the shaft entrances.
Blast Vibration Control Procedure.
Control
Level
SensitiveReceiver PPV
LimitControl Procedures / Requirements
ALERT PPV> 90%
Inform the RE, Project Manager, DSD Supervisor of occurrence.
Review monitoring data and recording equipment for accuracy.
Check secure placement of transducers.
Review blast pattern and parameters.
Inspect sensitive receivers affected. Prepare action plan.
Continue blasting.
ACTION PPV > 95%
Inform the RE, Project Manager, DSD Supervisor, GEO (MD) immediately.
Review/modify blast pattern and blast parameters.
Review and implement action plan if necessary.
Detailed inspection of all affected sensitive receivers.
Plan and prepare remedial works if necessary.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
38/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
iii. To show that the resulting ground vibrations are within acceptable limits
and will not adversely affect the safety or stability of adjoining structures,services and slopes, and the specified tolerances for the works can beachieved.
During the initial blasts at Intake I-2, the practice to be adopted will call for theimplementation of the blast monitoring procedures outlined in Sections 8.3 ~8.7below.
Should the resultant PPVs or airblast levels exceed the limits predicted basedon the approved GEO formula, then a reassessment of the blasting constants tobe used at the Intake I-2 will be required. This will entail an adequate number oftrial blasts, as agreed with the Mines Division, so that determination of the sitespecific blasting constants can be achieved. Continued monitoring will verify anyre-evaluations made.
The same procedure will be adopted during the commencement of blastingoperations at either of the two shafts at Intake I-2. Within close proximity of theblast area of the intake are a number of high ranking sensitive receivers
restricting the PPV values allowed which will call for an increased number ofmonitoring points leading to close scrutiny of the site specific blasting constantsto be applied.
Re-evaluation of the blast constants is essentially an ongoing process where anychanges to blasting regimes, such as the Contractors change to the his blastdesign, an increase in charge weights, length of round, number of blast locationsetc, will require a re-assessment of the blasting constants to be applied.
8.3 BLAST MONITORING
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
39/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
monitoring purposes. It is expected that there will be some tolerance on this
target based upon the public perception and the level of complaints received onthe actual observed air overpressure effects. Readings and any AOPs exceededwill be assessed on a case by case basis due to the difficulties of predicting air-overpressure and environmental factors such as wind.
8.6 BLAST MONITORING REPORTING
Prior to blasting the Contractor shall provide a Blast Monitoring Report forapproval to the Engineer identifying the blast location and the monitoring pointsof the controlling sensitive receivers to be monitored.
The report shall describe the current status of the controlling sensitive receiversand clearly identify any relevant observations that would reduce or constrain thedesign blast charge weights prior to blasting.
After the blast the Contractor shall produce a short report containing details ofthe actual blast design and the monitoring results showing vibration and airoverpressure readings highlighting any allowable limits that were exceeded.
The report shall also provide reference to the inspections carried out to verify theperformance of the existing slopes, boulders and nearby sensitive receivers andany proposed remedial measures necessary to ensure the safety of the works onthe surrounding area. Any corrective actions or follow up requirements orcomplaints from the general public shall also be noted in the report.
The Contractor shall provide examples of the reports to be submitted to theEngineer for agreement prior to commencing the blasting works.
Blast vibration response spectra shall also be provided with respect to the three
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
40/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Most manufacturers recommend detonation as the safest way to destroy
explosives. If detonation is not possible, the options are: Detonators must be detonated in a charged blast hole. They will not be
destroyed by burning or by mechanical means.
Cast boosters and detonating cord will be destroyed in charged blast holeaccording to the MIC.
Electronic detonator will be destroyed on site following the manufacturersrecommendations as stated in their MSDS sheets.
Only qualified personnel (Registered Shotfirer) should undertake destructionprocedures.
All safety procedures recommended by the manufacturer should be followedin the destruction of the explosives.
8.8.2 LOADED BLASTHOLES NOT BEING FIRED ON THE DELIVERY DAY
When unforeseen circumstances happen resulting to loaded explosives unable
to be discharged on delivery day, the following procedure would be adopted priorto the next working day when the firing is possible.
The Blasting Engineer shall inform the Mines Division, BCS, the Police andthe relevant government departments of the unforeseen circumstance and theblasting delay.
The non-blasted area shall be fenced up with colored ribbon stripe and at fourcorners hoisted with red flag indicating this being a danger zone and nobody
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
41/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
movement/vibration evidence), undisturbed ground or material is observed
within the blast during the detonation or upon inspection, cut offs oruninitiated explosives are observed.
If lead wires, detonating cord or signal (shock) tube is exposed in a portion ofa blasthole that was intended to have been fired, that blasthole will be treatedas a misfire. If there is a doubt as to whether a signal tube has initiated, ashallow angled cut into the tube to examine the inner surface of the tube forevidence of uninitiated explosive composition should be made.
Identification of un-detonated explosives after the all clear has been givenand site work has recommenced.
For all blast-induced incidents, the licensee shall submit to Mines Division aninvestigation report within 5 working days.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
42/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
9.0 BLASTING PROTECTIVE AND PRECAUTIONARY MEASURES
9.1 BLASTING PROTECTION MEASURES
For the purposes of blasting operations all measures shall be taken to protectpersons and property from the dangers normally associated with blastingoperations.
Drawings MCSJV/TW/I-2/2020119 and MCSJV/TW/I-2/2020120 in Appendix Loutline the expected measures required during blasting operations at Intake I-2blast area
9.1.1 BLAST PROTECTION MEASURES AT INTAKE I-2
Blast protection measures will be required to protect those works that are withinthe immediate vicinity of the blast area.
Protection measures could include but not be limited to the following:
Blast doors at the top of the shaft,
Blast barricades
Blast mats made of heavy flexible materials such as rubber or rope to placeover any parts of the blast area prior to blasting.
Noise Enclosure to reduce the magnitude of AOP
9.1.2 BLAST PROTECTION MEASURE WITHIN ADIT CONNECTIONS
As the adit connection advances and full face blasting operations take place, theneed for blast protection will generally decrease but there may be the odd
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
43/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
The predicted AOP induced to the sensitive receivers within the influence zone
of blasting operation are summarized as below.Structure (EBS
Ref. No.)AOP Induced (Before
ReductionFinal AOP (After Reduction)
Lo Wai Road(TWDT/S/026)
130.1 110.1
Ship Temple(TWDT/S/028)
131.5 111.5
Table 9.1.3: AOP Generated to the Sensitive Receiver
9.2 EVACUATION AND CLEARANCE REQUIREMENTS
In addition to the requirements of section 9.1 above, the Blasting Engineer alongwith the Chief Shotfirer will liaise with the Supervising Officer and DSDSupervisors and other stakeholders and give the final permission to blast.
The standard evacuation procedures will be followed for all blasts:
i. Notices will be posted at the site entrance and on boards visible to the roadusers advising the date and expected time of each blast.
ii. After all protective measures have been placed, explosives loading willcommence and tunnel / shaft clearance procedures will be initiated by theShotfirer.
iii. The Shotfirer will inform the Chief Shotfirer / Blasting Engineer and theContractors Site Agent by radio that blasting will take place within thirty
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
44/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Evacuation is required and evacuation procedures will be developed in method
statement.9.3 OUTLINE BLAST DESIGNS
The outline blast designs are attached in Appendix G for information. Daily blastdesign will be submitted to Mines Division for blasting operations. Outline blastdesigns and typical daily blast designs will be detailed in method statement.
9.4 PROGRAMME AND DEMAND FOR EXPLOSIVES
A tentative schedule and demand of explosives has been prepared and includedin Appendix J of this report. The programme and demand for explosives will bebased upon the final Method Statement and the quantities of high explosives thatcan be delivered to the shaft and entrances to the works.
The allowable delivery quantities given in the Method Statement will also dictatehow many working faces can be worked any one time if emulsion is not allowedat the lower charge weights.
The demand for explosives has been based upon the estimates number of blasts
that are required to complete the Works. A preliminary assessment estimatesthat 206 numbers of blasts will be carried out during the excavation of Intake I-2.The number of blast for different section has been summarized below.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
45/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
Section By length(mPD)/Ch (mPD)/Ch (m) Pull (m) Blast No.Upper ManAccessShaft
+82.5 +68.6 13.9 0.5/0.8 24
Upper ManAccess Adit
Ch0 Ch25 25 0.8 32
Lower Man
AccessShaft
+70 +56 14 0.8/1 15
Lower ManAccess Adit
Ch0 Ch5 5 1 5
VortexDrop Shaft
+74 +69.9 4.1 0.5/1 7
Heading inDe-aeration
Chamber
(Refer drawingMCSJV/TW/I-2/2020123
21.3 0.8 27
Bench inDe-aerationChamber
+65.9 +56.9 9 1 9x5=45
Main Adit Ch0 Ch50.4 50.4 1 51Total: 206
Table 9.4: Summary of Number of Blast
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
46/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
10.0 SPECIFIC SUPERVISION PERSONNEL
The details and implementation of a site supervision plan covering all aspects ofblast execution and post blast actions will be provided by the Contractor as partof his Method Statement. The Contractor shall provide a site supervision plan forthe works to the Engineer and Mines Division for approval prior to blastingcommencing.
In general, the following personnel shall be employed by the Contractor:
Site agent,
Area in-charge,
Competent person under F&IU Ordinance and its associated Regulations,
Registered Shotfirer,
Qualified Shotfirer, and
Area foreman.
The organization chart has been provided in Appendix J and the following is asuggested list of minimum duties for the position of the key personnel.
10.1 BLASTING ENGINEER (COMPETENT PERSON)
The Blasting Engineer is to supervise all blasting activities. He will ensure that allblasting works will be carried out in a safe and efficient manner, and inconformance with the Blasting Assessment Report, Method Statement and theDangerous Good License / Permit. All elements of the drilling and blasting cyclethat could result in any unsafe situation to the public or site personnel will be
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
47/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
10.3 THE CHIEF SHOTFIRER
He is a Registered Shotfirer, designated internally, to supervise, with the BlastingEngineer and Blasting Designer, all the blasting operations. He will ensure thatthe blasting works are conducted safely and shall be responsible for all blastingworks in the site including selecting blast location, inspection drill holes pattern,installing protection measures, loading explosives together with other shotfirers,arranging site clearance and check blasting results to identify misfires andimplement, with the Blasting Engineer, the remedial measures to treat it. He willoversee all shotfirers work and will act as a central control man during shotfiring
to arrange sequencing blasts if more than one blast is taken consecutively in theblast day.
10.4 THE SHOTFIRER
The Shotfirer is the individual that is responsible for charging the blasthole withexplosives (primer assembly, loading charge, stemming), initiating all blast withinnon electric system and correcting misfires under the supervision of the ChiefShotfirer. He is also responsible for singing the issue Voucher and the removal
permit. The Shotfirer is under the supervision of the Chief Shotfirer.10.5 AREA FOREMAN
He will be responsible working closely with Shotfirer to provide a workableplatform for driller to conduct drilling; arrange plant to clean the free face to floorfor a good heaving shot for the sake of elimination any heavy confinement statusas a result of rock muck blocking in front; the bench top is free from any looserock block pieces that may be blown out horizontally or vertically at front row. Heis also responsible to ensure the public area that needs to be evacuated is
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
48/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
11.0 CONCLUSIONS
Given the charge weight limits as indicated there will be an effect on thelength of round and hence a limited rate of advance in the shafts for eachblast achieved. This is compounded by the fact that if too many delays areused i.e. blast holes being initiated one at a time; this could lead tomisfires which in turn impede overall progress.
Where the Drawing MCSJV/TW/I-2/2020117 shows depth of 25m andabove, this is in reference to the underground blasting that will be requiredfor the adits and the de-aeration chamber where due to the depth andattenuation of the ground conditions, larger charge weights can be used.However, interpretation of the analysis results suggest that a maximumcharge weight of 0.2kg/0.33kg should be used for the Shafts and ManAccess Adit (Upper) and a maximum of 0.4kg for the Man Access Adit(Lower), De-aeration Chamber and Main Adit to avoid exceeding theallowable PPV limit.
The 5mm/s contour represents the extent of any significant effects of the
blast which is at an approximate distance of more than 15m from eithershaft.
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
49/402
Contract No. DC/2007/12Design and Construction of Tsuen Wan Drainage TunnelBlasting Assessment Report for Intake I-2 (Rev A)
12.0 RECOMMENDATIONS
It is recommended that if blasting operations are to take place asubstantial damping mechanism is to be implemented that will reduce tooverall effect of airblast and noise.
This could include, but not be limited to the following:
o Rigid well insulated (e.g. with gumpoles underside) shaft doors.
o Swinging timber blast barricades inside shaft
o Enclosed noise barrier over each shaft It is anticipated that there will be at least one blast per day. Therefore
good communications and control of operations will need to be adopted inensuring that the works are co-ordinated and carried out safely.
Prior to blasting operations, detailed condition surveys will be carried outby the Contractor on the existing registered features and existingbuildings within the influence zones shown, particularly those within very
close proximity to the blast sites. Temporary evacuation before and closestructural inspection after blasting may be a requirement.
Elsewhere, regular inspections shall have to be carried out to review andassess any deterioration in the sensitive receivers. Where significantdeterioration is noted an action plan and remedial works shall be put inplace and blasting suspended until the sensitive receiver fixed orconsidered safe to proceed with blasting.
For each blast, vibration control points will need to be specified and shall
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
50/402
Appendix A
Overall Layout of the Intake I-2
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
51/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
52/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
53/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
54/402
Appendix B
Geological Section of Intake I-2
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
55/402
LEGEND OF SOLID AND SUPERFICIAL GEOLOGY
SUPERFICIAL DEPOSITS
Sand Mixed Qd and Qt
Boulders Undivided, mainly dark grey marine mud
Beach rock Marine mud
Clay/silt, sand and gravel; well-sorted to semi-
sortedMarine sand, part silty
Unsorted sand, gravel, cobbles and boulders;
clay/silt matrixUndivided; red, yellow and grey clay, silt, sand and
gravel
Gravel, cobbles and boulders
SOLID GEOLOGYCourse ash crystal tuff
Fine ash tuff (within Yim Tin Tsai Formation)
Fine ash vitric tuff
Fine-grained granite, 2mm
Fine ash to coarse ash tuffs, tuff-breccia and
tuffite
Fine to medium-grained granite
Coarse ash crystal tuff
Medium-grained granite, 2-6mm
Eutaxite Coarse-grai ned granite, >6mm
Sandstone Fine-grained quartz syenite,
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
56/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
57/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
58/402
Appendix C
Reference Drawings for Intake I-2
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
59/402
Drawing ListProject
Page No.Job No. 0 7 2 5 7 W G
Temporary Works Design for Intake I-2
Permanent Works Design for Intake I-2
MCSJV/PW/I-2/2020021
1/2
Intake I-2 Temporary Works Design Temporary Support General Arrangement
Intake I-2 Air Vent Shaft (Upper Part) General Arrangement and Reinforcement Detail
Intake I-2 Man Access Shaft (Upper Part) General Arrangement
Intake I-2 Permanent Works Design Underground Structures and Shafts General Arrangement
MCSJV/TW/I-2/2020030
MCSJV/PW/I-2/2020015
MCSJV/PW/I-2/2020010
D
MCSJV/PW/I-2/2020022
MCSJV/PW/I-2/2030060
Intake I-2 Permanent Works Design Vortex Drop Shaft General ArrangementD
A
A
A
C
Intake I-2 Permanent Works Design Typical Connection detail between Main Tunnel & Main Adit Plan and Section
Intake I-2 Permanent Works Design Man Access Shafts General Arrangement
Design and Construction of Tsuen Wan Drainage Tunnel
C
B
A Intake I-2 Vortex Shaft (Upper Part) General Arrangement (Sheet 2 of 2)
C
Intake I-2 Vortex Shaft (Upper Part) General Arrangement (Sheet 1 of 2)MCSJV/PW/I-2/2020001
Drawing TitleRevDrawing No.
Intake I-2 Permanent Works Design For Main Tunnel & Main Adit Connection Section
MCSJV/PW/I-2/2030061
MCSJV/PW/I-2/2030062
A
MCSJV/PW/I-2/2020002
Intake I-2 General Arrangement and Layout Plan of Connection between Main Tunnel & Main Adit
Intake I-2 Temporary Works Design Temporary Support DetailsMCSJV/TW/I-2/2020031
MCSJV/PW/I-2/2020023 C Intake I-2 Permanent Works Design De-aeration Chamber General Arrangement
MCSJV/PW/I-2/2020024 D
MCSJV/PW/I-2/2020025 H Intake I-2 Permanent Works Design Air Vent Shaft General Arrangement
MCSJV/PW/I-2/2020026 E Intake I-2 Permanent Works Design Man Access Adit General Arrangement
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
60/402
Drawing ListProject
Page No.Job No. 0 7 2 5 7 W G
Design and Construction of Tsuen Wan Drainage Tunnel
2/2
Drawing No. Rev Drawing Title
Permanent Works Design for the Approach Channel along the streamcourse
MCSJV/SK/I-2/2104067 A Intake I-2 Concrete bund walls
MCL/4111CD/S/223 A Intake I-2 Sections & Reinforcement Arrangement (with mark-up) x 2
Permanent Works Design for the As-constructed H-pile wall along the streamcourse
MCSJV/SK/I-2/2104068 A Intake I-2 Concrete bund walls (Stage 1)
MCL/4111CD/S/220 A Intake I-2 Structure Lower Level Reinforcement Arrangement (with mark-up)
MCL/4111CD/S/209 A Intake I-2 Details of H-pile Wall
DC/2007/12/SK/0056 D H-pile wall details (Pile cut-off level higher than formation level) in Intake I-2
MCSJV/SK/I-2/2103007 A Intake I-2 Temporary Diversion of WSD Pipe
Drawings for Temporary Diversion of WSD pipe
DC/2007/12/SK/0068 B Revised Pile Wall Layout and Setting Out at Intake I-2
DC/2007/12/SK/0149 B Proposed River Channel Formation Level at Intake I-2
MCSJV/SK/I-2/2103008 B Intake I-2 Temporary Diversion of WSD Pipe Steel Work Support Detail
MCSJV/SK/I-2/2103009 A Intake I-2 Temporary Diversion of WSD Pipe On Grade Fixing Details: Support I
MCSJV/SK/I-2/2103011 A Intake I-2 Temporary Diversion of WSD Pipe Layout Plan
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
61/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
62/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
63/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
64/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
65/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
66/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
67/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
68/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
69/402
FOR I
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
70/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
71/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
72/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
73/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
74/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
75/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
76/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
77/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
78/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
79/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
80/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
81/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
82/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
83/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
84/402
FOR
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
85/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
86/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
87/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
88/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
89/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
90/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
91/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
92/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
93/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
94/402
FOR INFORMA
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
95/402
FOR INFORMA
FOR INFOR
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
96/402
FOR INFOR
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
97/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
98/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
99/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
100/402
Contract Doc Vol 4 of 11 Page 166 of 284
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
101/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
102/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
103/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
104/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
105/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
106/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
107/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
108/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
109/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
110/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
111/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
112/402
FOR INFORMATION ONLY
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
113/402
Appendix D
Rockhead and Groundwater Contours Plan
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
114/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
115/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
116/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
117/402
Appendix E
Inventory of Existing Buildings
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
118/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
119/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
120/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
121/402
Appendix F
Drawings of Existing Utilities
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
122/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
123/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
124/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
125/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
126/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
127/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
128/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
129/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
130/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
131/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
132/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
133/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
134/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
135/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
136/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
137/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
138/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
139/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
140/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
141/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
142/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
143/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
144/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
145/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
146/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
147/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
148/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
149/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
150/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
151/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
152/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
153/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
154/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
155/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
156/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
157/402
Appendix G
Typical Blast Patterns
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
158/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
159/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
160/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
161/402
Appendix H
Assessment of Affected Man-madeSlopes and Retaining Walls
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
162/402
dSite
tobe
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
163/402
'
c'
'
-
-
-
Para
meterswerederivedfromlaboratorytestinfresults.
-
-
-
Para
metersforCollandCDTwereadoptedbasedonlaboratorytestingresultsfrom'Ho
mefortheAged
Form
ation(1994).ParametersforFillwereassumed.
-
-
-
Labo
ratorytestingresultsfrom'WesternMon
asteryDevelopment'forFillrevealedfrict
ionangleof33.
Para
metersforCollwereassumed.
-
-
-
Para
metersforFillwereassumed.
-
-
-
Para
metersforFillwereassumed.
35
6
36
Para
menterswerederivedfromlaboratorytestinfresults.Laboratorytestingdatasfoun
d.
-
-
-
Pres
criptivemeasures
-
-
-
Pres
criptivemeasures
-
-
-
Para
metersforFillwereassumedandthefillisassumedtobederivedfromCDG.
-
-
-
Para
metersforfillwerederivedfromlaborato
rytestingresults.ParametersofAlluvium
wereassumed
thesameasFill.
-
-
-
Noa
nalysishasbeencarriedout
35
-
-
Para
metersofc'=0&f'=33wereadoptedforF
ill/Alluviumandc'=1&f'=35forC/HDGd
basedonthe
labo
ratorytestingresults.Laboratorytestingd
atasfound.
-
-
-
Stab
ilityAnalysiscarriedoutinEmpiricalAppr
oach.
-
-
-
Para
metersforFillwereassumed.
S/P
Highest
Recorded
-
-
GWMonitoring
Device
Remarks
GeotechnicalReportforthe
sRoadforYuenYuenCare&
onHomefortheAged'
Remarks
Remarks
HDGd
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
164/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
165/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
166/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
167/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
168/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
169/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
170/402
15
20
25
Q
6
9.75
7.70
6.41
0.200
8
12.52
9.89
8.24
0.330
0
13.78
10.8
9
9.07
0.400
0
13.78
10.8
9
9.07
0.400
0
13.78
10.8
9
9.07
0.400
15
20
25
Q
6
9.75
7.70
6.41
0.200
8
12.52
9.89
8.24
0.330
8
12.52
9.89
8.24
0.330
15
20
25
Q
8
12.52
9.89
8.24
0.330
0
13.78
10.8
9
9.07
0.400
0
13.78
10.8
9
9.07
0.400
13
15
20
25
Q
6
14.08
12.5
2
9.89
8.24
0.330
6
14.08
12.52
9.89
8.24
0.330
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
2
15.50
13.78
10.89
9.07
0.400
PPV
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
171/402
PPV Calculation for Existing Slopes/Retaining Wall
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
172/402
Project
TWDT Bl i A
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
173/402
TWDT - Blasting AssessmentLocation Approved by Page
Feature Checked by /
Rev.
Calculation of critical peak particle velocity for feature 7SW-C/C1384 at Lo Wai
critical peak particle velocity, PPVc = Kc g / (w Ka)
From SLOPE/W,
Kc = 0.21 with FOS = 1.102 for feature 7SW-C/C1384 (Cat I feature)
where y = 4 and y/H = 1.00
From Figure 8 of GEO Report No. 15,
when S/H = 75.00 where slope height, H = 4 m and S = 300 m/s
Ka = 1.23
g = 9.81
w = 2 x pi x f = 188.50 /s where f = 30 Hz
Therefore, PPVc = (Kc * g) / (w Ka) 8.89 mm/s
Max. PPV from PPV contour is 5 mm/s OK!
Lo Wai
7SW-C/C1384
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
174/402
Appendix I
Assessment of Existing Facilities
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
175/402
Sheet-pile (Above Upper Man Access Shaft) Check
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
176/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
177/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
178/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
179/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
180/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
181/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
182/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
183/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
184/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
185/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
186/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
187/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
188/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
189/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
190/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
191/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
192/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
193/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
194/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
195/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
196/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
197/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
198/402
Existing Air Vent Shaft Check
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
199/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
200/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
201/402
Appendix J
Explosive Quantities, Delivery Schedule and
Organization Chart
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
202/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
203/402
Organization and Flow Chart
for Blasting Works
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
204/402
-
8/7/2019 BAR RevA Resubmission - 24 Dec 2010
205/402
-
8/7/2019 BAR