Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August 02, 2011

Transcript of Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban...

Page 1: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Balancing Competing Priorities in an Urban Creek RestorationToronto, Canada

Wolfgang WolterJohn Parish

Bruce Kilgour

August 02, 2011

Page 2: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo August 02, 2011Competing Priorities Page 2

Introduction and Context

Location

Page 3: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Channel and Valley

August 02, 2011Competing Priorities Page 3

Valley Segment 4A

Valley Segment 4

Page 4: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

The Problem: Hydrologic Response

August 02, 2011Competing Priorities Page 4

Hydrologic Response to Regional Storm in Markham Branch, Nodes 300-305, CN 3

0

10

20

30

40

50

60

0 2 4 6 8 10 12 14 16 18

Time (hours)

Rain

fall

(m

m/h

)

0

10

20

30

40

50

60

Flo

w (

cm

s)

Rainfall 300 Flow 301 Flow 302 Flow 303 Flow 304 Flow 305 Flow

Page 5: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

The Result: Channel Degradation

August 02, 2011Competing Priorities Page 5

Down-cut average of 3m (10 feet) since 1962

Rate of incision has drastically increased

Page 6: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Channel Condition

Repaired in 1980,entire systems have failed,

Some repairs are being done as ‘emergency work’

August 02, 2011Competing Priorities Page 6

Page 7: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Primary Stakeholders and Motivation,

August 02, 2011Competing Priorities Page 7

• Control Erosion, Protect Infrastructure, Sanitary Sewer System

Owner, City of Toronto

• Enhance Fish Habitat, provide stable sediment regime

Federal Review Agency: Department

of Fisheries and Oceans

• Protect and enhance terrestrial linkages, and improve valley health (forest)

Watershed Jurisdiction: Toronto Region Conservation

Authority

Competing Priorities

Page 8: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Design Obstacles

Factors against success

• Watershed shape (wide, high flow volume per unit of channel)

• Urban setting (75% impervious, one of the most urbanized watersheds in the Toronto area)

• Location on the watershed profile, (near the downstream end, erosional zone, steep inclination of channel bed)

• Significant infrastructure (provides working constraints – 4 exposed sanitary sewer crossings – 5 emerging)

• Highly incised valley setting (minimal floodplain access)

August 02, 2011Competing Priorities Page 8

Page 9: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Balancing Priorities

Engineering

Erosion Control

• Harden Bed

• Harden Banks

• Enlarge channel section

• Reduce flood risk

EcologyValley System

• Manage valley connectivity

• Increase forest cover

• Protect valley slopes

Geomorphology

Dynamic Stability

• Manage sediment

• Reduce flow velocity

• Allow fish passage

August 02, 2011Competing Priorities Page 9

Page 10: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Adaptive Management Approach

What is Adaptive Management?

• Many interpretations

• Understand mechanism of success and failure, assess associated risk, make decisions on future maintenance anticipated intervention, apply appropriate action – based on prediction and monitoring – attach redundancies on the anticipation of failure

Look at creeks as an asset, not a liability

• What can the creeks do for the community/water quality/flood protection (creeks as stormwater management) fix a creek, fix an ecosystem – geomorphic systems

August 02, 2011Competing Priorities Page 10

Page 11: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

AEM - Adaptive Environmental Management

August 02, 2011Competing Priorities Page 11

Page 12: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Infrastructure Protection

August 02, 2011Competing Priorities Page 12

There is a need to repair, protect and enhance the installed systems

Stabilize valley slopes to retain building foundations and roadway platforms

Desire to reduce the frequency of enacting repairs on an ‘emergency basis’

Protect, or reduce the risk to damage downstream of site

Page 13: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Terrestrial Linkages

August 02, 2011Competing Priorities Page 13

Forest cover in urban areas is at a premium

Loss of forest means loss of terrestrial linkages

Desire to reduce tree loss and connectivity platform

Concern over reduction in area in favour of creek habitat

Page 14: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Fisheries Resources – Fish Habitat

• Specifically watershed based climate change study completed suggests low peak storm events increasing in frequency (6mm to 10mm events)

• Fish inventories suggest fish are present, but monitoring shows spawning habitat is short lived

• Solution requires flow velocities to be halved (4.0m/s to 2.0 m/s max habitat threshold)

• Design channel cross section to convey large flow events, but maintain low flow channel

• Offset riffle crests to create local backwater

August 02, 2011Competing Priorities Page 14

Ph

ysi

ca

l H

ab

ita

t S

yst

em

An

aly

sis

(T

ab

les

2 -

4) Physical State

DynamicCondition(process)

PhysicalEnvironment (response)

Habitat

Physical Process BiologicalCharacteristics

(reset of physical state)

*

Page 15: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

How to Converge (habitat needs, erosion, valley health)

• Spawning for species need froude of 1.0

• Reduction in velocity is necessary to provide the parameter for low peak events (shows in hydraulic model)

• Harden channel to protect infrastructure, but create enough backwater to allow passage and energy reduction – achieve sub-critical flow condition

• Create valley retaining structures to reduce forest loss in conjunction with channel section enlargement

• Create in-stream training structures to direct flow in new plan form

• Sediment regime difficult to replicate in hardened conditions, create off line pools to provide habitat diversity

• Ensure channel stability is achieved without reliance on sediment source

August 02, 2011Competing Priorities Page 15

Page 16: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Philosophy – (intangible)

• Decisions, Politics and Compromise

• Weight of Fish Habitat vs. Terrestrial Habitat

• Infrastructure protection vs. sediment regime

August 02, 2011Competing Priorities Page 16

Compromise Decisions

Page 17: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Implementation and Monitoring

August 02, 2011Competing Priorities Page 17

600m of rock weirs and vanes U/S,

1400m of riffles and pools D/S,

Reduced meander amplitude,

Widened channel section

Landscape Restoration

Page 18: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

Reconstruction Concept

August 02, 2011Competing Priorities Page 18

Existing Typical Cross SectionRE-ALIGNMENT CROSS SECTION

ENTRENCHED CHANNEL

LIMITED FLOODPLAIN ACCESS

EXPAND VALLEY CROSS SECTION

WIDEN FLOW CHANNEL

ELEVATE STREAMBED

FILL OLD CHANNEL

STABILIZE CREEK BANKS

PROVIDE VEGETATIVE COVER AND PLANTING

Page 19: Balancing Competing Priorities in an Urban Creek … · Balancing Competing Priorities in an Urban Creek Restoration Toronto, Canada Wolfgang Wolter John Parish Bruce Kilgour August

Client logo

What did we learn

• That low peak events in an urban system can have dramatic impacts on habitat viability

• That flow velocities need to be reduced to sustain long term fishery resources

• That design redundancy can provide risk reduction, but at a high cost

• That decisions cannot be based on science alone

• That providing a Natural Channel in an urban setting is near impossible in the strict sense of the term, but providing one with ‘Natural Channel Design Principles’ is, and it can be made to co-exist with urban constraints.

August 02, 2011Competing Priorities Page 19