Available Transfer Capability Determination

31
Available Transfer Capability Determination Chen-Ching Liu and Guang Li University of Washington Third NSF Workshop on US-Africa Research and Education Collaboration Abuja, Nigeria, December 13-15, 2004 TECHNO LO G Y & EN VIR O N M EN T ENERG Y & ED U C A TIO N

description

Third NSF Workshop on US-Africa Research and Education Collaboration Abuja, Nigeria, December 13-15, 2004. Available Transfer Capability Determination. Chen-Ching Liu and Guang Li University of Washington. Overview. Background of Available Transfer Capability (ATC) Definitions of ATC - PowerPoint PPT Presentation

Transcript of Available Transfer Capability Determination

Page 1: Available Transfer Capability Determination

Available Transfer Capability Determination

Chen-Ching Liu and Guang LiUniversity of Washington

Third NSF Workshop on US-Africa Research and Education Collaboration

Abuja, Nigeria, December 13-15, 2004

TECHNOLOGY &

ENVIRONMENT

ENERGY &

EDUCATION

TECHNOLOGY &

ENVIRONMENT

ENERGY &

EDUCATION

Page 2: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

2

Overview

• Background of Available Transfer Capability (ATC)

• Definitions of ATC• Determination of ATC• Examples of ATC in Nigerian NEPA 330kV Grid• Optimization Technique to Calculate ATC• Stability-Constrained ATC Calculation Method• Conclusions

Page 3: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

3

Background

• ATC is the transmission limit for reserving and scheduling energy transactions in competitive electricity markets.

• Accurate evaluation of ATC is essential to maximize utilization of existing transmission grids while maintaining system security.

Page 4: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

4

Transmission Service Types

• Recallable transmission service: Transmission service that a transmission provider can interrupt in whole or in part.  

• Non-recallable transmission service: Transmission service that cannot be interrupted by a provider for economic reasons, but that can be curtailed for reliability.

Page 5: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

5

ATC Under Operating Constraints

• Transfer capability must be evaluated based on the most limiting factor.

Time

Voltage Limit

Stability LimitPower Flow A to B (MW)

Thermal Limit

Total Transfer Capability

Page 6: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

6

Available Transfer Capability (ATC) (North American Electric Reliability Council)

MW A->B

TimeOperating Horizon Planning Horizon

Nonrecallable Scheduled

Recallable Scheduled

Nonrecallable Reserved

Recallable Reserved

Total TransferCapability (TTC)Transmission

Reliability Margin

TRM

TRM

Nonrecallable Reserved

Nonrecallable Available Transfer

Capability

Nonrecallable ATC

ATCRecallable

Recallable ATC

Page 7: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

7

Definition of ATC

• ATC = TTC – TRM – Existing Transmission Commitments (including CBM)

• Transmission Transfer Capability Margins– Transmission Reliability Margin (TRM)– Capacity Benefit Margin (CBM)

Page 8: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

8

Transmission Reliability Margin (TRM)

• Uncertainty exists in future system topology, load demand and power transactions

• TRM is kind of a safety margin to ensure reliable system operation as system conditions change.

• TRM could be 8% or 10% of the TTC

Page 9: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

9

Capacity Benefit Margin (CBM)

• CBM is reserved by load serving entities to ensure access to generation from interconnected systems to meet generation reliability requirements.

• Intended only for the time of emergency generation deficiencies

Page 10: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

10

State of the Art: ATC Methods

ATC MethodsATC Methods DescriptionDescription

Linear Approximation MethodDC Power Flow Model,

Thermal Limit Only

Optimal Power Flow Method AC Power Flow Model, Thermal Limit + Voltage Limit

Continuation Power Flow MethodAC Power Flow Model,

Thermal Limit + Voltage Limit (Voltage Collapse)

Stability-Constrained ATC Method Time Domain Simulations with Dynamic Model

Page 11: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

11

First Contingency Incremental Transfer Capability (FCITC) & First Contingency Total

Transfer Capability (FCTTC)

FCTTC

FCITC

BASE POWER TRANSFERS

Page 12: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

12

Total Transfer Capability (TTC)

• System Conditions

• Critical Contingencies

• Parallel Path Flows

• Non-Simultaneous and Simultaneous Transfers

• System Limits

Page 13: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

13

Procedure to Calculate TTC

• Start with a base case power flow• Increase generation in area A and increase

demand in area B by the same amount• Check the thermal, stability and voltage

constraints.• Evaluate the first contingency event and ensure

that the emergency operating limits are met.• When the emergency limit is reached for a first

contingency, the corresponding (pre-contingency) transfer amount from area A to area B is the TTC.

Page 14: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

14

Example 1: 2-Area NEPA 330kV Grid

Page 15: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

15

2-Area Base-Case Tie Flow

21 23

Area 1

4.64 MW

Area 2

No thermal limit (assumed 120% base case flow) reached

Single transmission line contingency

First thermal limit reached

Notation

Tie Line Flow

Page 16: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

16

Area 1 to Area 2 ATC Calculation

21 23

Area 1

> 4.64 MW

Area 2

Increasing

Generation

P MW

Increasing

Demand

P MW

21 23

Area 1

4.96 MW

Area 2

7-25

2-8

Increased

Generation

0.32 MW

Increased

Demand

0.32 MW

FCITC

FCTTC

Page 17: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

17

Area 2 to Area 1 ATC Calculation

21 23

Area 1

< 4.64 MW

Area 2

Increasing

Demand

P MW

Increasing

Generation

P MW

21 23

Area 1

4.54 MW

Area 2

7-25

5-24

Increased

Demand

0.1 MW

Increased

Generation

0.1 MW

FCITC

FCTTC

Page 18: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

18

2-Area ATC Calculation

Direction Area 1 to Area 2 Area 2 to Area 1

Critical Contingency

Line 7-25 (Delta-Aladja)

Line 7-25 (Delta-Aladja)

Thermal Limit

Reached

Line 2-8 (Jebba G.S.-Jebba T.S.)

Line 5-24 (Alam-Aba)

FCTTC 4.96 MW 4.54MW

FCITC 0.32 MW 0.1 MW

Page 19: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

19

Example 2: 4-Area NEPA 300kV Grid

AREA 1

AREA 2

AREA 3

AREA 4

Page 20: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

20

4-Area Base-Case Tie Flows

Area 1

4.64 MW

Area 2Area 4

16.6 MW

Area 3

8.24 MW8.5 MW

Page 21: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

21

Area 3 to Area 1 ATC calculation (Example of Parallel Path Flows)

Area 1

4.64 MW

Area 2Area 4

17.2 MW

Area 3

8.65 MW9.1 MW

7-25

1-7

Increased Generation 1.01 MW

Increased Demand 1.01 MW

FCTTC = 9.1+ 8.65 = 17.75 MW

FCITC = 17.75 (8.5 + 8.24) = 1.01 MW

Page 22: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

22

Area 4 to Area 2 Simultaneous ATC with a Pre-existing Area 3 to Area 1 17.75 MW Transfer

Area 1

4.85 MW

Area 2Area 4

16.99 MW

Area 3

8.65 MW9.1 MW

7-25

4-10

Increased Generation 0.21 MW

Increased Demand 0.21 MW

FCTTC = 16.99 (17.2) = 0.21 MW

FCITC = 4.85 4.64 = 0.21 MW

Page 23: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

23

Optimization Technique to Calculate ATC

A area

maxi

iΔP

0),(

),(

0

),(0

),(

maxmin

maxmax

max

yxEM

VVV

FyxFF

PPP

yxg

yxfx

iii

Objective:

Subject to

sum of generation in sending area A

- system dynamic behavior

- power flow equations

- active power output

- thermal limit

- voltage profile

- energy margin

Page 24: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

24

Stability-Constrained ATC

Second-Kick based Energy Margin Computation

Second-Kick based Energy Margin Computation

Time Domain Simulation (ETMSP)

System trajectory

No

Energy Margin Sensitivity Analysis with BFGS Method

Energy Margin Sensitivity Analysis with BFGS Method

Generation AdjustmentGeneration Adjustment

(EM = 0) ?(EM = 0) ?

Yes

ATCATC

Page 25: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

25

Second-kick-based energy margin computation

Perform time-domain simulation

Obtain system trajectory following a pre-specified disturbance sequence

Compute potential energy of first- and second-kick trajectories

Potential energy difference at the respective peaksof the first- and second-kick disturbances

- Simulation

- Trajectory

- Potential energy

- Energy margin

Page 26: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

26

Energy margin sensitivity computation

• Determine the search direction with the Broyden-Fletcher-Goldfarb-Shanno (BFGS) method

D is an approximation to the inverse of Hessian matrix

)(,

)(1,

)(

)(

)(1

)(

knm

km

k

kn

k

k

P

EM

P

EM

D

S

S

S

Page 27: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

27

Generation adjustment

nm

m

pkn

kn

kk

nm

m

P

P

kEM

S

S

P

P

,

1,

1)()(

1)(1

)(1

,

1,

nm

m

oldnm

oldm

newnm

newm

P

P

P

P

P

P

,

1,

,

1,

,

1,

- Adjustment

- Update

Page 28: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

28

2-Area Test System

120 110 11

12

13

101 1

3

2

10 20 G1

G2 G12

G11

• Net power transferred from area A to area B in the base case = 453 MW

453 MWArea A Area B

Page 29: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

29

Stability-Constrained ATC Results

Power Transfer

(Area AArea B) & Energy Margin

Gen.

453 MW G1 666 1.9008 1.9008 0.5333 3.745EM = 13.35 G2 754 1.4688 1.4688 0.4667 4.242

461 MW G1 669.745 1.1483 1.1483 0.5161 4.935EM = 10.98 G2 758.242 0.9503 0.9503 0.4838 5.59471.6 MW G1 674.68 0.4748 1.4562 0.3757 2.833EM = 5.50 G2 763.832 0.0864 2.136 0.6242 3.208

G1 677.51 -1.417G2 767.04 -1.604

474.6 MW G1 676.094 1.8204 1.8204 0.4809 0.587EM = 2.22 G2 765.436 1.7345 1.7345 0.5191 0.665475.8 MW G1 676.681 2.4251 2.4251 0.5125 0.047EM = 0.22 G2 766.101 2.0364 2.0364 0.4875 0.054

(MW)

1

2

4 477.6 MW EM = N/A

System goes unstable with

the 1st kick disturbance.

(MW)

5

6

Iteration

3

kmP ,

kmP

EM

,

ksk kmP ,

Page 30: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

30

Conclusions

• ATC provides a reasonable and dependable indication of available transfer capabilities in electric power markets.

• ATC considers reasonable uncertainties in system conditions and provides operating flexibility for the secure operation of the interconnected network.

• The effects of simultaneous transfers and parallel path flows are studied.

• Need for ATC calculation method to incorporate voltage, angle stability limits as well as thermal limits.

Page 31: Available Transfer Capability Determination

Third US-Africa Research and

Education Collaboration WorkshopAbuja, Nigeria, December 13-15, 2004

31

References

[1] North American Electric Reliability Council, “Available Transfer Capability Definitions and Determination”, June 1996.

[2] North American Electric Reliability Council,“Transmission Transfer Capability”, May 1995.

[3] S. K. Joo, C. C. Liu, Y. Shen, Z. Zabinsky and J. Lawarree, “Optimization Techniques for Available Transfer Capability (ATC) and Market Calculations,” IMA Journal of Management Mathematics (2004) 15, 321-337.