Automatic Generation Control (AGC) Pilot Scope The GTG-RISE Initiative, in collaboration with Karnataka Power Corporation Limited (KPCL) and Karnataka Power Transmission Corporation Limited (KPTCL), is implementing this pilot to enhance the ancillary reserves in Karnataka. The GTG-RISE pilot will assess AGC's ability to provide a secondary response in southern India. The pilot will cover both hydel and renewable power plants and identify technical requirements and compensation mechanisms for those generation units that participate in the AGC secondary reserve market. The key activities under this pilot are enhancement of existing control facilities at two hydro units at Varahi and Sharavathi, one solar power plant at Shivanasamudra and NP-Kunta each, and one wind farm in Karnataka. Developing roadmap for policy makers and regulation for facilitation of AGC. Pilot Implementing Phase 2018 2019 Partners KPCL, SLDC- Karnataka, KPTCL Regional Load Despatch Centre (RLDC). Pilot Progress GTG-RISE has prepared a pre-feasibility report for AGC implementation at the Varahi and Sharavati hydro power plants and the solar power plant at Shivanasamudra. Following approval of KPCL and KPTCL, Grantee(s) for carrying out enhancements of existing energy management systems and communication network at the select pilot generation sites (Varahi and Sharavati Power Plants) has been appointed in December 2018. In addition, based on suggestion from POSOCO, a 250 MW solar plant at NP Kunta (commissioned by NPTC) is selected for the AGC pilot and the selection process for the grantees has been commenced. Outcome The pilot will demonstrate the techno-economic benefits of AGC and aid in the development of a scalable roadmap for the policy makers and regulators for adoption of AGC. The pilot will provide the data to help CERC specify regulations for AGC's phased implementation with accompanying compensation mechanisms. Background The Government of India's plan for integration of large quantum of variable renewable energy (VRE) into the power grid presents a number of challenges for power system operators and electricity market participants. Allied with faster scheduling and despatch is the need for harnessing flexibility from all available sources in the grid. The Central Electricity Regulatory Commission (CERC) has outlined a roadmap for adoption of Automatic Generation Control (AGC) in the country to enable secondary control necessary for ancillary services. One of the pilots implemented under USAID's Greening the Grid (GTG)-RISE Initiative is intended to support adoption of AGC for hydro, solar and wind power plants in the southern region. Disclaimer This factsheet is made possible by the support of the American People through the United States Agency for International Development (USAID). The contents of this factsheet are the sole responsibility of Deloitte Consulting LLP., and do not necessarily reflect the views of USAID or the United States Government. This factsheet was prepared under Task Order AID-386-TO-17-00001.

Transcript of Automatic Generation Control (AGC) - GTG India...2019/06/24  · (Varahi and Sharavati Power Plants)...

  • Automatic GenerationControl (AGC)

    Pilot ScopeThe GTG-RISE Initiative, in collaboration with Karnataka Power Corporation Limited (KPCL) and Karnataka Power Transmission Corporation Limited (KPTCL), is implementing this pilot to enhance the ancillary reserves in Karnataka. The GTG-RISE pilot will assess AGC's ability to provide a secondary response in southern India. The pilot will cover both hydel and renewable power plants and identify technical requirements and compensation mechanisms for those generation units that participate in the AGC secondary reserve market. The key activities under this pilot are enhancement of existing control facilities at two hydro units at Varahi and Sharavathi, one solar power plant at Shivanasamudra and NP-Kunta each, and one wind farm in Karnataka.

    Developing roadmap for policy

    makers and regulation for

    facilitation of AGC.

    Pilot

    Implementing

    Phase

    2018 2019 PartnersKPCL, SLDC- Karnataka, KPTCL Regional Load Despatch Centre (RLDC).

    Pilot ProgressGTG-RISE has prepared a pre-feasibility report for AGC implementation at the Varahi and Sharavati hydro power plants and the solar power plant at Shivanasamudra. Following approval of KPCL and KPTCL, Grantee(s) for carrying out enhancements of existing energy management systems and communication network at the select pilot generation sites (Varahi and Sharavati Power Plants) has been appointed in December 2018. In addition, based on suggestion from POSOCO, a 250 MW solar plant at NP Kunta (commissioned by NPTC) is selected for the AGC pilot and the selection process for the grantees has been commenced.

    OutcomeThe pilot will demonstrate the techno-economic benefits of AGC and aid in the development of a scalable roadmap for the policy makers and regulators for adoption of AGC. The pilot will provide the data to help CERC specify regulations for AGC's phased implementation with accompanying compensation mechanisms.

    BackgroundThe Government of India's plan for integration of large quantum of variable renewable energy (VRE) into the power grid presents a number of challenges for power system operators and electricity market participants. Allied with faster scheduling and despatch is the need for harnessing flexibility from all available sources in the grid. The Central Electricity Regulatory Commission (CERC) has outlined a roadmap for adoption of Automatic Generation Control (AGC) in the country to enable secondary control necessary for ancillary services. One of the pilots implemented under USAID's Greening the Grid (GTG)-RISE Initiative is intended to support adoption of AGC for hydro, solar and wind power plants in the southern region.

    Disclaimer This factsheet is made possible by the support of the American People through the United States Agency for International Development (USAID). The contents of this factsheet are the sole responsibility of Deloitte Consulting LLP., and do not necessarily reflect the views of USAID or the United States Government. This factsheet was prepared under Task Order AID-386-TO-17-00001.

  • Connect with us:

    GreeningthegridIndia/

    GTG_India

    Greening the Grid

    www.gtg-india.com (Under design)

    Monali Zeya HazraSenior Clean Energy SpecialistUSAID/IndiaEmail: [email protected]

    Greening the Grid (GTG) ProgramGreening the Grid (GTG) Program

    India plans to deploy 175 GW of renewable energy (RE) on its power grid by 2022, aimed at strengthening the country's energy security and reducing its carbon intensity. Compared to conventional power, RE options are more variable, less predictable, and often located further from demand centers. Experience with other systems demonstrates that when RE penetration reaches significant levels, the power grid needs the capacity to manage operations to avoid challenges to reliability and affordability of electricity.

    Greening the GRID (GTG) Program

    USAID’s Greening the Grid (GTG) initiative is a five-year program implemented in partnership with India’s Ministry of Power (MOP) under the Asia EDGE (Enhancing Development and Growth through Energy) Initiative. The GTG initiative supports Government of India (GOI) in managing the issue of large-scale integration of renewable energy (RE) into the Indian power grid. The program combines three components which interact with each other. These include:Ÿ Power system planning reforms and targeted analysis for large RE parks and RE integration pilots implemented by U.S. Department

    Of Energy (DOE) laboratoriesŸ Renewable Integration and Sustainable Energy (RISE) initiative to implement innovation pilots, aimed at testing and evaluating

    building blocks to improve the integration of REŸ Peer-to-Peer exchanges between U.S.-India system operators (System Operator Partnership) and regulators (India Regulatory

    partnership)

    Background

    Renewable Integration and Sustainable Energy (RISE) Initiative

    Central to GTG, is the design, implementation, and scaling of a series of prioritized innovation pilots that support the integration of RE into the grid. As part of the GTG-RISE Initiative, successful deployment and scale-up of the following pilot solutions across the select states will offer new market opportunities for innovative technologies, solutions and services.

    *PAN India covered under the pilot for “Regional Platform forReserves Sharing”

    Battery Energy Storage System (BESS) in Transmission & Distribution

    Flexible PowerGeneration

    01

    02

    0304

    05

    06

    Automatic GenerationControl (AGC)

    Regional platform for reserves sharing

    Dynamic Compensationfor Large Solar ParkIntegration

    Real-time monitoring of rooftop solar PV andnet-load forecasting for DISCOMs

    Puducherry, New Delhi

    Tushar SudChief of PartyUSAID GTG-RISE InitiativeEmail: [email protected]

    Andhra Pradesh

    Karnataka, Andhra Pradesh