ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) •...

14
ATC Ten-Year Transmission System Assessment ATC Transmission Briefing October 29, 2008

Transcript of ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) •...

Page 1: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

ATC Ten-YearTransmission System

AssessmentATC Transmission Briefing

October 29, 2008

Page 2: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Transmission Planning Process

NERC Standards

Build Transmission

System Models

Identify Transmission System Needs

Develop Solutions to Satisfy Needs

Evaluate Solutions and Select Preferred

Alternative

Propose Transmission

Contruction Project

Planning Review and Approval of

Project

Project Included in Approved

Capital Budget

ATC Planning Criteria

A

A

Page 3: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

2008 Ten-Year Assessment (TYA)

• 2008 TYA Process Overview– Obtain/cleanse utility forecasts– Create ATC models using MISO models– Analyze performance of ATC system 1, 5, 10

and 15 years out– Identify system needs and possible solutions– Issue Project Request Forms for projects– Draft report and public communications– TYA website: www.atc10yearplan.com

Page 4: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

2008 TYA – Key Messages

• Continuing to Plan for a Reliable Future• Several New Challenges Facing Electric

Industry– Greater Plans for Use Renewable Energy

Resources– Regional Transmission Grid to Accommodate

Needs• Continued Education on Conditions

Affecting Transmission Projects– Siting Criteria– Environmental Concerns– Opportunities to Influence Projects– Cost of Electric System Reliability

Page 5: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

ATC Projects

Page 6: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Zone 2 Summary Projects

2013Addresses low voltages in the area, improves

stability of Presque Isle generation, addresses aging facilities in poor condition

2014Blaney Park-Munising 69-kV

line rebuild & conversion to 138 kV

4

New in 2008 AssessmentImproves reliability in the area2013

Increase ground clearance of M38-Atlantic 69-kV line from

120 to 167 degrees F3

Provisional projects

2009Improves reliability in the area, addresses aging facilities in poor condition2009Relocate Cedar substation

(North Lake)2

2008-2010

Part of Cranberry-Conover project (Zone 1) for Rhinelander Loop, improves voltage

profile in the area, addresses aging facilities with condition issues

2008-2010

Cranberry-Conover 115-kV line (completed in 2008) and

Conover-Iron River-Plains rebuild & conversion to 138 kV

1

Planned projects

2007 TYA In-service

yearNeed driver

2008 TYA In-service

yearProject description

Page 7: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

TYA Estimated Capital Costs

Category2007 Update 10-year capital estimate in

billions

2008 10-year capital estimate in billions

10-Year Assessment projects $1.44 $1.29

Asset Maintenance $0.44 $0.46Generator

interconnections $0.23 $0.29

Distribution interconnections $0.17 $0.16

Asset Protection & Control $0.13 $0.08

Network $0.11 $0.10Unspecified network

projects $0.22 $0.23

Other * $0.10 $0.09Total expenditures $2.84 $2.70

Page 8: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

TYA Capital Expenditures

Total 10-Year Capital Expenditures

0

0.5

1

1.5

2

2.5

3

3.5

4

1 2 3 4 5 6 7 8 9

TYA Date

$(bi

llion

s) Other CapitalExpenditures

Specified 10-YearAssessmentProjects

Mar 05

Sep 05

Nov 07

Sep 08

Mar 06 Nov 06

Sep 04

Mar 04

Sep 03

Page 9: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Issues

• Generation forecast uncertainty• Load forecasting

– Uncertainty– Declining forecasts

• Renewable portfolio standards and wind development

• Changing market power flows

Page 10: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Load - Forecasted

ATC 10-Year Assessment Forecasted Load Growth Rates

Compounded Annually

2.00%1.90%

2.20%2.10%

1.70% 1.70%

0.00%

0.50%

1.00%

1.50%

2.00%

2.50%

2003 2004 2005 2006 2007 2008

Page 11: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Wind in ATC Footprint

• Generator studies for the ATC footprint– Interconnected

over 3,000 MWs new generation in ATC footprint

• 274 MWs wind interconnected thus far in 2008

• 425 MWs wind by end of year

Page 12: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Stakeholder Involvement

• ATC Energy Collaborative, Michigan• FERC 890 Principles

– Coordination– Openness– Transparency– Information Exchange– Comparability– Economic Studies

Page 13: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

ATC Attachment FF

• Approved by FERC this past May• Defines types of Transmission

Planning– Distribution – Transmission– Generation – Transmission– Network Reliability– Economic Planning

• Sets criteria for– Stakeholder involvement– Sets planning criteria

Page 14: ATC Ten-Year Transmission System Assessment · 2009. 2. 12. · 2008 Ten-Year Assessment (TYA) • 2008 TYA Process Overview – Obtain/cleanse utility forecasts – Create ATC models

Economic Planning

• Customer/Stakeholder Meeting June 19th

2008– Defined futures– Received input on project recommendations

• Projects being evaluated:– Kenosha-Lakeview-Zion 138 kV – North La Crosse-Hilltop-Spring Green-

Cardinal 345 kV – Salem-Spring Green-Cardinal 345 kV

• Paddock-Rockdale first Economic justified project in WI