Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard...

40
Astoria Boulevard ADA and Station Renewal Track Improvements February 19, 2019

Transcript of Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard...

Page 1: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Astoria BoulevardADA and Station Renewal Track Improvements February 19, 2019

Page 2: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Major Scope of Work

Work Description

• Replace Street and Platform Stairs

• Install Two Street-to-Mezzanine Elevators

• Install Two Mezzanine-to-Platform Elevators

• Demolish and Rebuild Entire Mezzanine. Raise Underside of Mezzanine and Lower Street Surface to Prevent Future Vehicular Hits

• Reinforce Street Columns and Foundations For Additional Loads due to Elevators and New Facilities

• Replace Platform Roofs (Wooden Canopies) and Mezzanine Overpass Walkway Roofs

Page 3: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Street Elevator atColumbus Triangle

New

Sid

ewal

k bu

mp

out

New Street Elevator

Hoy

t Ave

nue

Sout

h

31st Street

North

Page 4: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Street Elevator at Columbus Triangle

New Street Elevator Locations

Page 5: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Street Elevator at Intersection of 31st Street and Hoyt Avenue North

31st Street

Hoy

t Ave

nue

Nor

th

North

New Street Elevator

Stairs moved to accommodate elevator

Removal of two trees is required for elevator installation

Page 6: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Street Elevator at Intersection of 31st Street and Hoyt Avenue North

Page 7: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Replacement of Street-to-Mezzanine and Mezzanine-to-Platform Stairs

Page 8: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Concrete Slab and Topping Repair

Page 9: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Steel Repair

Page 10: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Replacement of Mezzanine Walkways at Hoyt Avenue North and South

Page 11: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

West Elevation – Art Glass Panels

Page 12: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

East Elevation – Art Glass Panels

Page 13: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Platform Scope of Work

Work Description

ADA Boarding Zone

New Platform Edges

Replace Damaged Platform Precast Planks and Repair Concrete Cast in Place Slab

Repair Damaged Steel

Replace Existing Platform Canopies Damaged during Hurricane Sandy

Replace Existing Stair Refuge Enclosure with New Glass Enclosure at all Four Platform Stairs

Replace Platform Light Posts, Signs, Gates, Railings, Benches, Sandboxes and Refuse Bins

Page 14: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Damaged Platform Precast Panels

Page 15: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Cross Section through New Proposed Mezzanine

Section A-A

Use shallower beam to raise underside of mezzanine

Reinforce street columns and foundation

Street

Mezzanine

Platform

New Elevator

New CanopyNew Canopy

Page 16: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

North

Fall 2018—March 2019

Page 17: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Traffic Stipulations

Work Hours

Monday-Friday 9:30 AM to 2:30 PMSaturday-Sunday 7:00 AM to 8:00 PM

Traffic Enforcement Agents at these Intersections

Hoyt Ave. North at 31st StreetHoyt Ave. South at 31st Street

Astoria Blvd. at 31st Street

Monday-Friday 9:30 AM to 2:30 PMSaturdays 8:00 AM to 5:00 PMSundays 9:00 AM to 5:00 PM

Travel Lanes

31st StreetOne Lane in each direction during Work HoursTwo Lanes in each direction during Non-Work

Hours

Hoyt Ave. North4 Travel Lanes and One Bus Lane at all times

Hoyt Ave. South5 Travel Lanes at all times

Page 18: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

• 31st Street and Hoyt Avenue South

• Up to 20 Weekends in 2019• Required to demolish and

rebuild the mezzanine• Signage, Traffic Enforcement

Agents, and Crossing Guards will be provided

Intersection Closure

Page 19: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

To be replaced with new map/rendering

Page 20: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Detour During All Track GOs and Complete Intersection Closure

Page 21: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Saturday Traffic Conditions

Page 22: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Detour During Complete Intersection Closure

Other maps/renderings of detour

Page 23: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Detour During Complete Intersection Closure

Other maps/renderings of detour

Page 24: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Saturday Traffic Conditions

Page 25: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Saturday Traffic Conditions

Page 26: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Detour During Complete Intersection Closure

Other maps/renderings of detour

Page 27: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Detour During Complete Intersection Closure

Other maps/renderings of detour

Page 28: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Bus Routes

Page 29: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Astoria Boulevard Station

Closing March 17, 2019

Station Reopens December 2019 (9 months)

Elevators Operational August 2020

Finished November 2020

Ditmars Boulevard Station

Major work complete March 2019

Finished June 2019

Ditmars Blvd MajorConstruction finishedMarch 2019 (Station stays open through construction)

Astoria Blvd closed Mar-Dec 2019(after all other stations reopen)

Current Work39 Av-Dutch Kills and Broadway

Reopened January 2019

Finished June 2019

Page 30: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Train Service During the Closure

• Nine month full closure; March-December

• During the closure Ditmars Blvd and 30th Av provide alternate subway service

• During 13 Weekends, N/W service will not run north of Queensboro Plaza. Shuttle buses will be provided during these weekends.

• (Feb 23-24), March 16-18, March 23-24, April 6-7, April 13-14, June 15-16, and June 22-23.

Ditmars Blvd MajorConstruction finishedMarch 2019 (Station stays open through construction)

Astoria Blvd closed Mar-Dec 2019(after all other stations reopen)

Page 31: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Track Replacement

Improves the reliability of the track and signal equipment

Fewer delays for customers

Replaced 2,496 feet of track and ten track switches since 2017

Queensboro – 39 AvDitmars – Astoria Blvd

ADA compliant platform gaps

Page 32: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Track Replacement

Winter/Spring 2019: Replacing nearly 5,000 feet of track on the northbound track between 36 Av and 30 Av.

Track is over 35 years old

Work will overlap with station work

Requires northbound trains to run express during weekdays, skipping stations in one direction

ADA compliant platform gaps

Increase reliability and reduce delays

Page 33: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Monday-Friday 9:45 AM to 3:30 PM

February 4 – April 19(except Presidents Day, Feb 18)

Weekends:February 23-24, *March 9-10*, March 16-17, March

23-24, & *March 30-April 1*

Northbound N trains run express from QueensboroPlaza to Astoria Blvd (express to Ditmars Blvd after

Astoria Blvd closure)

W Trains run along the Q line to 96 St

Work is weather dependent

Track Replacement

Service Plan

During Track work we need to detour some traffic from 31st St

Exact detour will change as the location of the track replacement changes

Current detour until March 1:31st Street between 31st Ave and 34th Ave

North Bound: Will run “Against the Normal Direction of Traffic”, between 31st Ave & 34th Ave.

South Bound: Will be diverted at 31st Ave onto Crescent St

Traffic PlanWork Hours

Page 34: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Work Performed to Date Astoria Blvd

Page 35: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Asbestos Material Removed from the Platform Roofs

Page 36: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Relocated Bus Stop and Detoured Walkway to Facilitate Work

Page 37: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Removed Stair at Hoyt Playground

Page 38: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Relocated M60 Bus StopFrom Columbus Triangle to Astoria Blvd.

Page 39: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

Removed Stair at Columbus Triangle

Page 40: Astoria Boulevard ADA and Station Renewal Track Improvements Blvd ADA and... · Astoria Boulevard Station Closing March 17, 2019 Station Reopens December 2019 (9 months) Elevators

New Website: https://new.mta.info/system_modernization/astoria