Assignment Problems
• Variation of transportation problems.
• One-to-one assignment.
• Workforce assignments, machine assignments, etc.
• (go to example)
![Page 2: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/2.jpg)
Project Modeling: CPM
• How to organize? How to plan?
• How long will the entire project take?
• Critical Path Model - Terms– Activity on Arc– predecessor– duration
![Page 3: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/3.jpg)
Project Modeling: CPM
• How to organize? How to plan?
• How long will the entire project take?
• Critical Path Model - Terms– Activity on Arc– predecessor– duration
As long as the longest (duration) series of activities takes -- also call the CRITICAL PATH.
![Page 4: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/4.jpg)
Critical Path Method - Terms.• Activity on Arc
1 2A
Nodes: milestones
Activity: process
6
Duration (EX: hrs., days)
![Page 5: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/5.jpg)
Critical Path Method: Terms• “Activity A must be done before B can
begin.” - Activity A is a PREDECESSOR of B.
1 2A
Nodes: milestones
3B
Activities: processes
![Page 6: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/6.jpg)
Critical Path Method: Terms• “Activities A and B must be done before C
can begin.” - A & B are PREDECESSORS of C.
1
2
A
Nodes: milestones
3
BActivities: processes
4C
![Page 7: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/7.jpg)
EX: build a house: the tasks (activities) in order
– get permits– pour foundations– frame walls – install plumbing systems– install electrical systems– install landscaping– move in.
![Page 8: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/8.jpg)
EX: build a house: add durations and label activities
– A: get permits– B: pour foundations– C: frame walls – D: install plumbing– E: install electrical – F: install landscaping– G: move in.
Durations:26
5
46
3
– A: get permits– B: pour foundations– C: frame walls – D: install plumb.– E: install elec.– F: install landscaping – G: move in.
Durations:26
5
46
9
3
![Page 9: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/9.jpg)
EX: build a house: create table– A: get permits– B: pour foundations– C: frame walls – D: install plumb.– E: install elec.– F: install landscaping – G: move in.
Durations:26
5
46
9
3
Act. Dur. Preds. Post.A 2 -- DB 6 -- C,FC 5 B DD 4 A,C EE 6 D GF 9 B GG 3 E,F
![Page 10: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/10.jpg)
EX: build a house: create CPMAct. Dur. Preds. Post.A 2 -- DB 6 -- C,FC 5 B DD 4 A,C EE 6 D GF 9 B GG 3 E,F
AED
G
FC
B6
5
4 63
9
2
![Page 11: Assignment Problems Variation of transportation problems. One-to-one assignment. Workforce assignments, machine assignments, etc. (go to example)](https://reader036.fdocuments.in/reader036/viewer/2022082417/56649d205503460f949f4ab2/html5/thumbnails/11.jpg)
But what is the Critical Path?
AED
G
FC
B6
5
4 63
9
2
The path of activities that takes the longest amount oftime; the path with the activities that cannot be alteredtime-wise without changing the overall project duration.
(We need to tell the family when they will be settled in their new house -- how soon?)
Use Excel to set up this problem and find the critical path.