Assignment-Level Tracking Field Calculations in Microsoft® Office Project

Kelly JonesKelly Jones

PMO Manager, Information SystemsPMO Manager, Information Systems

Sharp HealthcareSharp Healthcare

Page 2: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

AgendaAgenda

Why Track Why Track Progress?Progress?

Scope of Scope of PresentationPresentation

MS-Project Tracking MS-Project Tracking Fields Fields

Other Fields that Other Fields that Affect MS-Project Affect MS-Project TrackingTracking

Calculation Formulas Calculation Formulas and Optionsand Options

Report DefinitionsReport Definitions Viewing and Editing Viewing and Editing

Assignment Tracking Assignment Tracking FieldsFields

Project Server Project Server Timesheet Tracking Timesheet Tracking ModesModes

Page 3: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Why Track Progress?Why Track Progress?

MonitorMonitor Critical PathCritical Path BudgetBudget

Status ReportingStatus Reporting ForecastingForecasting

Earned ValueEarned Value Build historical information for future Build historical information for future

project metricsproject metrics

Page 4: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Scope of PresentationScope of Presentation

Updating of assignment Updating of assignment tracking fields onlytracking fields only No direct discussion of No direct discussion of

task-level tracking field task-level tracking field updatesupdates

No direct discussion of No direct discussion of costcost Actual Cost and Actual Cost and

Remaining Cost are Remaining Cost are byproducts of actual work byproducts of actual work and fixed workand fixed work

We will discuss Actual We will discuss Actual WorkWork

How do task types affect How do task types affect the calculations?the calculations?

How does an How does an assignment update assignment update affect a task with a affect a task with a single assignment?single assignment? Avoid multiple assignment Avoid multiple assignment

calculations!calculations! Only discuss assignment-Only discuss assignment-

level calculations for fields level calculations for fields that have both assignment that have both assignment and task levelsand task levels

Page 5: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

MS-Project Tracking MS-Project Tracking FieldsFields

Assignment-level Assignment-level tracking fieldstracking fields Actual StartActual Start Actual FinishActual Finish Actual WorkActual Work % Work Complete% Work Complete Remaining WorkRemaining Work Timephased Actual Timephased Actual

WorkWork

Task-level tracking Task-level tracking fieldsfields Includes all Includes all

assignment-level assignment-level fields plus duration-fields plus duration-based fieldsbased fields %Complete%Complete Actual DurationActual Duration Remaining DurationRemaining Duration

Page 6: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Other fields that affect Other fields that affect assignment-level assignment-level trackingtracking

Scheduled FieldsScheduled Fields Assignment Level Assignment Level

OnlyOnly Assignment UnitsAssignment Units

Task Level OnlyTask Level Only DurationDuration

Assignment and Task Assignment and Task LevelLevel WorkWork StartStart FinishFinish

Task TypeTask Type Fixed DurationFixed Duration Fixed UnitsFixed Units Fixed WorkFixed Work

Assignment DelayAssignment Delay Affects individual Affects individual

assignment start date assignment start date calculationscalculations

Page 7: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Calculation FormulasCalculation Formulas

Duration formulas (task level only)Duration formulas (task level only) % Complete = 100 x (Actual Duration / Duration)% Complete = 100 x (Actual Duration / Duration) Duration = Actual Duration + Remaining DurationDuration = Actual Duration + Remaining Duration

Work formulas (task and assignment levels)Work formulas (task and assignment levels) % Work Complete = 100 x Actual Work / Work% Work Complete = 100 x Actual Work / Work Work = Actual Work + Remaining WorkWork = Actual Work + Remaining Work

Scheduling formulaScheduling formula Work = Duration * UnitsWork = Duration * Units

Page 8: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Calculation OptionsCalculation Options

Updating task status Updating task status updates resource statusupdates resource status The default value The default value

(checked) is assumed(checked) is assumed

Status DateStatus Date Determines date that Determines date that

actuals are postedactuals are posted Defaults to today if left NADefaults to today if left NA Useful if you are entering Useful if you are entering

actuals from previous dayactuals from previous day Can be changed using Can be changed using

Project, Project Project, Project InformationInformation

New options on the New options on the Calculations tab of the Calculations tab of the Options dialog box Options dialog box Move end of completed Move end of completed

parts after status date parts after status date back to status dateback to status date And move start of And move start of

remaining parts back to remaining parts back to status datestatus date

Move start of remaining Move start of remaining parts before status date parts before status date forward to status dateforward to status date And move end of And move end of

completed parts forward completed parts forward to status dateto status date

Page 9: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Report DefinitionsReport Definitions

Assignment/ Task Assignment/ Task StatusStatus StartedStarted

Actual Start <> NAActual Start <> NA

Not StartedNot Started Actual Start = NAActual Start = NA

FinishedFinished Actual Finish <> NAActual Finish <> NA

Not FinishedNot Finished Actual Finish = NAActual Finish = NA

Updated ValueUpdated Value Field value that is Field value that is

being updatedbeing updated

Scheduled ValueScheduled Value Scheduled value of Scheduled value of

field corresponding to field corresponding to actual field being actual field being calculatedcalculated

Page 10: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Viewing and editing Viewing and editing assignment tracking assignment tracking fieldsfields

Standard MS-Project Standard MS-Project assignment viewsassignment views Task UsageTask Usage

Groups assignments Groups assignments by task and sorts by by task and sorts by resourceresource

Resource UsageResource Usage Groups assignments Groups assignments

by resource and sorts by resource and sorts by taskby task

Other methods for Other methods for updating these fieldsupdating these fields Assignment Assignment

Information DialogInformation Dialog Double-click an Double-click an

assignment to see the assignment to see the assignment-specific assignment-specific fields.fields.

Assign Resources Assign Resources dialogdialog

Task FormTask Form

Page 11: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Project Server Timesheet Project Server Timesheet TrackingTracking

All updates performed at the assignment All updates performed at the assignment levellevel

ModesModes Percentage of Work CompletePercentage of Work Complete Total Actual Work and Remaining WorkTotal Actual Work and Remaining Work

Timesheet Calculation: Timesheet Calculation: scheduled Work – Actual Work = Remaining Workscheduled Work – Actual Work = Remaining Work

Timephased Actual Work and Remaining Timephased Actual Work and Remaining WorkWork Timesheet Calculation: Timesheet Calculation:

scheduled Work – Actual Work = Remaining Workscheduled Work – Actual Work = Remaining Work

Page 12: Assignment-Level Tracking Field Calculations in Microsoft® Office Project Kelly Jones PMO Manager, Information Systems Sharp Healthcare.

Assignment-Level Tracking Field Calculations in Microsoft® Office Project

Kelly JonesKelly Jones

PMO Manager, Information SystemsPMO Manager, Information Systems

Sharp HealthcareSharp Healthcare