Welcome Everyone!
Tactical Guide for Building a PMO – How to run a Successful
PMO
Running a Successful PMO
© Copyright 2012 – B Dow
Hands On
Bill Dow, PMP
SocialAuthorGiving Back
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Importance of Project Communicationso 1. Project Failures & Survey’s
o 2. Common Communication Problems
o 3. Project Communication Planning
o 4. Project Management & Social Media
o 5. Project Communications & Agile Projects
o 6. Project Management & Business Intelligence
Agenda
1. Building a PMO
2. Running a PMO
3. PMO Reports
4. PMO Day to Day Operations
5. PMO Resources
6. PMO Wrap-up & More
Information
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Building a PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Start with a Plan
Obtain Executive Support
Create PMO Staples
Select 4 P’s of PMO (including Methodologies)
Select PMO Model
Create PMO Maturity Model (Categories and Measurement)
Obtain PMO Resources
Select PMO Training
Implement PMO Methodologies
Select PMO Reporting
Select PMO Tools and Processes
PMO Complete
(1)
Remember the 12 Steps to Building your PMO
Steps to building a PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Did you apply the 12 steps?
Go back and do that now!
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Running a PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Develop Executive Reports
Develop PMO Reports
PMO Day to Day Operations
PMO Resources (Mentor & Buddy System)
(1)
Steps to Running a PMO
(9)
(2)
(3)
(4)
© Copyright 2016 – B Dow
Running a PMO
Executive Reports
© Copyright 2012 – B Dow
• One of the key components of running a successful PMO is keeping your Executives happy with various PMO Reports
• These reports can include
• Scorecards
• Milestone Calendars
• Dashboards
• Etc.….
Executive Reports
Get the Executives the Reports they need!
Running a Successful PMO
© Copyright 2012 – B Dow
Executive Reports Examples
Very valuable at a glance to see how projects are tracking.
Running a Successful PMO
© Copyright 2012 – B Dow
Executive Reports Example – PMO Milestone Report
Very valuable to see the various stages the project are at across the lifecycle!
Running a Successful PMO
© Copyright 2012 – B Dow
Executive Reports Example – PMO Resource Report
Valuable to see when Resources are rolling on and off the project, vacations, other OOF activities.
Running a Successful PMO
© Copyright 2012 – B Dow
Executive Reports
Regardless of the reports the executives ask and you provide there will always-always be another report needed!
Running a Successful PMO
© Copyright 2012 – B Dow
• Executive reporting is a critical aspect of keeping your PMO’s going for many years.
• Executive reporting is continual process and will be a ongoing process while running a successful PMO.
• Spend time with your executives and make sure the reports are working for them!
Executive Reports Summary
Get the Executives the Reports they need!
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Reports
© Copyright 2012 – B Dow
• Once you have the specific reports down and going for the Executives, there may be some additional reports that are just for the PMO.
• These reports could be too detailed, or not at the right level for executives.
• Again, everyone PMO Manager is going to require specific report for their environment.
PMO Specific Reports
Running a Successful PMO
© Copyright 2012 – B Dow
PMO Specific Reports
Good Reports but there will and should be specific reports for you to run your PMO!
Running a Successful PMO
© Copyright 2012 – B Dow
PMO Specific Reports
Project Dependency reports are critical for most PMO’s
Running a Successful PMO
© Copyright 2012 – B Dow
• Specific Organizations and PMO Managers are going to demand their own list of PMO reports.
• There are two many that could be listed, however do consider the software our using as a valuable source.
• Remember to look at your reporting in the 3 buckets we talked about in setting up a PMO
• Portfolio
• Program
• Project
PMO Specific ReportsRunning a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Dashboards
Portfolio Reports
• Past Reports
• Current Reports
• Future Reports
Program Reports
• Past Reports
• Current Reports
• Future Reports
Project Reports
•Past Reports
•Current Reports
•Future Reports
Running a Successful PMO
© Copyright 2012 – B Dow
• Don’t get tied down creating massive amounts of reports for your PMO outside of Executive reports you already created.
• Be aware that executives will not want the day to day reports you need to run your PMO, but they will be critical to your role.
• Software packages often come with a ton of reports that you can utilize. Don’t ignore these reports!
PMO Specific Reports Summary
Running a Successful PMO
© Copyright 2016 – B Dow
PMO – Day to Day Operations
© Copyright 2012 – B Dow
• Many PMO managers struggle when it comes to running their PMO on a day to day bases.
• Some don’t know what to, what reports to run, how involved do they get with the projects…etc.
• The list goes on and one and yes… It can be challenging some times.
PMO Day to Day Operations
Running a Successful PMO
© Copyright 2012 – B Dow
• One of the most important tasks the PMO Manager can do to effective run their PMO is to setup a PMO Cadence Calendar.
• In that calendar, you are going to cover all the key PMO meetings. PMO Members will schedule where possible around these key meetings.
• PMO Meetings are mandatory attendance and gives PMO Managers the opportunity to understand exactly what is going on.
PMO Day to Day Operations
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
PMO Cadence Calendar
Wk1
Wk2
Wk3
Monday Tuesday Wednesday Thursday Friday
PMO Review Weekly Meeting
BI-Weekly LT Meeting
Summit all Status Reports
PMO Review Weekly Meeting
BI-WeeklyInterdependency Meeting
Summit all Status Reports
PMO Review Weekly Meeting
BI-Weekly LT Meeting
Summit all Status Reports
PMO Review Weekly Meeting
BI-WeeklyInterdependency Meeting
Summit all Status ReportsWk4
Simple but effective tool to help Drive your PMO Cadence
Running a Successful PMO
© Copyright 2012 – B Dow
• Once you have your cadence calendar setup, you can fill in your time attending Program and Project meetings where applicable.
• Your PMO Cadence should have all major Program/Project meetings documented.
• Once everything is document, take another view of the calendar from a reporting perspective. What Reports and When?
PMO Day to Day Operations
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
PMO Cadence Calendar + Program/Project Meetings
Wk1
Wk2
Wk3
Monday Tuesday Wednesday Thursday Friday
Project BluetoothStatus Meeting
PMO Review Weekly Meeting
Project Atlas status meeting
BI-Weekly LT Meeting
Summit all Status Reports, Marketing Project Status Meeting
Project Bluetooth Status Meeting
PMO Review Weekly Meeting
BI-WeeklyInterdependency Meeting, ProjectAtlas status meeting
Summit all Status Reports, , Marketing Project Status Meeting
Project Bluetooth Status Meeting
PMO Review Weekly Meeting
Project Atlas status meeting
BI-Weekly LT Meeting
Summit all Status Reports, , Marketing Project Status Meeting
Project Bluetooth Status Meeting
PMO Review Weekly Meeting
BI-WeeklyInterdependency Meeting, ProjectAtlas status meeting
Summit all Status Reports, Marketing Project Status Meeting
Wk4
This gets very complicated but so valuable when you have this information at your fingertips!!
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
PMO Vacation Calendar
Wk1
Wk2
Wk3
Monday Tuesday Wednesday Thursday Friday
Wk4
This is a great tool I have been using for years and something I strongly suggest you setup as well!
Running a Successful PMO
Bill Jones is OOF
Bob Smith is OOF
Mary Jones is out on Leave
Mary Jones is out on Leave
Bill Jones is OOF
© Copyright 2016 – B Dow
Key Components to Running a PMO
© Copyright 2012 – B Dow
Define Color Definitions
Setup CR Process
Develop Portfolio/Program/Project Playbooks
Define PMO Priority List
Define PMO Weekly Checklist
Setup Project Transition Plans
Develop PMO Templates
Execute PMO Reports
Review and Select PMO Tools
Continue to support Management and Value Discussions
Key Components of Running a PMO SummaryRunning a Successful PMO
1
5
9
© Copyright 2012 – B Dow
• Every PMO is going to require some key components that are critical to have in executing a PMO.
• These components vary from Color Definitions to CR Processes, to Playbooks. Regardless of what it is, PMO Managers are going to need these key items to run a successful PMO.
• Without these items, PMO Managers will struggle to be successful!
PMO – Key Components to Running a PMO
Running a Successful PMO
© Copyright 2012 – B Dow
PMO – Key Components to Running a PMO
Running a Successful PMO
# PMO Component Definition
1 Color Definitions Every PMO needs a standard Definition of what Red, Yellow and Green means for their projects. Otherwise, the project managers decide.
2 CR Process A CR Process is one of the first processes that PMO managers should create and implement in their organizations
3 Program/Project Playbooks Program and Project Playbooks are important aspects of how Program and Project Managers do their jobs. These playbooks are so important to setup for your PMO members
4 PMO Priority list Every PMO should ensure they publish a Priority list. When executives decide the priority list, PMO managers must publish that page and make it a priorty for people to see and use. People will be asking you for this, so ensure you publish
5 PMO Weekly Checklist There will be a series of PMO items that Program and Project Managers will have to execute weekly as part of their job duties.
6 Project Transition Plans Every Project should have a transition plan in case a Program and Project manager leaves. If there are no transition plans in place and a project manager leaves that can be a huge problem.
7 PMO Templates Every PMO will require a variety of templates. From Status reports, to project schedule files, and as PMO Manager, you will have to create these templates for your team members.
8 Execute PMO Reports There will be a series of PMO reports that you will run each week to execute your PMO.
9 Review & Select PMO Tools Part of running a PMO is evaluating tools and getting the right tools for your team members. MS Project, WBS Schedule Pro whatever the tool is, this is going to be critical to continue to do as PMO Manager
10 Continue Management Support and Value Discussions
As PMO Manager, you are going to have to continue to sell the value of your PMO. This will be a constant discussion with your executives, your peers, and anyone who questions the value of the PMO.
© Copyright 2012 – B Dow
Color Definitions
• Every PMO must have a definition for their project colors? What does Red mean, Yellow, Green?
• If this is not defined, project managers will create their own definitions. That’s not good and not scalable.
• Here is an example: o Red – The Project is in trouble, from a scope, schedule, budget perspective and needs management support.
o Yellow – Project is not on track from a scope, schedule, budget perspective and management needs to pay attention.
o Green — Everything is fine, on track and in control.
Running a Successful PMO
© Copyright 2012 – B Dow
CR Process
• Every PMO must have a Change Request process. A change request process will be in place after the project has been “baselined” and approved to proceed.
• Without a Change Request of process, project managers will struggle handling changes on their projects. They just won’t know what to do!
• CR Processes can be very simple or complex, however critical to the success of running a project.
Running a Successful PMO
© Copyright 2012 – B Dow
Project Manager and customer meet of
project to go over the CR Process
Does Customer agree to Process?
If Customer agree, then project can start as it
normally would
Project Manager is approached with change
Project Manager has customer fill in a
standard Scope Change control template
Project Manager receives the document and
presents to team for review and impacting
Project Manager work with team and fills in
impact assessment for change.
Project Manager sends to requestor for approval
Once Change is approved!
Team performs the change
Team does not perform the change and goes back to the requestor
with details.
CR Process Example Running a Successful PMO
1 2 3
© Copyright 2012 – B Dow
Portfolio/Program/Project Manager Playbooks
• Every PMO will have a variety of roles from Portfolio Manager to Project Managers. Most PMOs have a variety of both.
• When you have the different roles, it is important to have playbooks or operating manuals for each of those roles.
• Otherwise, if you don’t set the foundation of what you want the roles to do, they won’t perform the same way. That’s not scalable in a large PMO
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Playbook Examples
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Portfolio Management Playbook
# Task
1. Develop a portfolio management document control system
2. Determine portfolio scope
3. Create the portfolio charter document
4. Develop portfolio metrics/dashboards
5. Develop a portfolio management team, including the selection of the Portfolio Leader/Manager
6. Develop a roles and responsibilities document
7. Develop a portfolio review board process
8. Develop a portfolio Work Breakdown Structure (WBS)
9. Hold the portfolio kickoff meeting
10. Develop any applicable training plans on process or tools implemented in this phase
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Program Management Playbook
# Task
1. Develop a program repository for all documentation
2. Develop a program charter
3. Develop a program oversight table
4. Develop a program benefits table
5. Develop or utilize the Business case analysis report
6. Develop a program organization structure
7. Develop a list of projects for the program
8. Develop a program stakeholder register
9. Develop a program scope report
10. Develop and initiate the program team
11. Develop a program status report
12. Develop the Program management kickoff material
13. Develop applicable training plans on process or tools implemented in this phase
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Project Management Playbook
# Task
1. Develop a project charter document
2. Develop a project management plan
3. Develop project kickoff materials
4. Obtain project budget information and create a budget spreadsheet
5. Develop an initial project schedule with initial dates and high-level deliverables
6. Develop a “lessons learned” process and repository for storing ongoing lessons learned information
7. Create a centralized project repository for storing all project information
8. Develop a project communications plan
9. Develop a project roles and responsibilities document
10. Prepare purchase orders or any acquisition-type documents to ensure you have the right staff identified for the project
11. Develop the project’s change control process
12. Develop a project governance
13. Develop a project escalation process
14. Develop the project organization chart
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Priority List
© Copyright 2012 – B Dow
PMO Priority List
• Every PMO Manager must setup a priority of their programs and projects occurring in the PMO.
• PMO team members will use this priority list as a trade off matrix that will allow them to set priority to the work they are doing.
• With a priority list, your team members are not going to what effort is the most important and therefore where they should focus their attention.
You would be surprised how many PMO’s don’t have this list!
Running a Successful PMO
© Copyright 2012 – B Dow
Running a Successful PMOPMO Priority List
• This list does not have to be complex, but every PMO needs one! Teams will use to set work priorities and determine where to put their efforts.
© Copyright 2016 – B Dow
PMO Weekly Check List
© Copyright 2012 – B Dow
PMO Weekly Checklist
• One of the follow-ups of the playbooks that would be creating a weekly checklist.
• What is it? It is a series of the tasks you expect your PMO team members to complete. Examples would be the following:
• Develop Weekly Status Report
• Update your Project’s schedule
• Update Risks & Issues on SharePoint/Project Website
• Take the critical tasks from the Playbook and pull them out and provide to team members.
Running a Successful PMO
© Copyright 2012 – B Dow
Project Transition Plans
• What is a transition plan? It is a document that describes all the key areas of the project that allows one project manager to take over from another.
• Ensure you setup a transition plan for every project in your PMO. Even if the project manager is not leaving, setup a transition plan!
• Without a transition plan, the handing off a project is much more complex and takes much longer.
Running a Successful PMO
© Copyright 2012 – B Dow
Project Transition Plans
• Types of topic covered in the plan:
• Location of Project Documents & Key Links to any materials
• Project Key Meetings & Calendar of events
• Project Key Stakeholders
• Project Distribution Lists
• Any material that project manager is using that he/she would need to provide to someone taking over the project
Running a Successful PMO
You would be surprised how fast PM’s come and go in a PMO! Don’t get caught without these valuable documents!
© Copyright 2016 – B Dow
PMO Templates & Reports
© Copyright 2012 – B Dow
PMO Templates
• PMO Managers must have a series of templates established for their PMOs
• Templates would include:
• Project Kickoff deck
• Project Go/No Go deck
• Project Go Live deck
• Project Go Live Templates/emails
• These are just some of the various templates that you would create, but getting these templates in place is important. You want your PMO to have the same look and feel across all the PMO decks.
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Dashboards
Portfolio Reports
• Past Reports
• Current Reports
• Future Reports
Program Reports
• Past Reports
• Current Reports
• Future Reports
Project Reports
•Past Reports
•Current Reports
•Future Reports
Execute PMO Reports
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Tool
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Portfolio Management Tools Program & Project Management Tools
There are hundreds of Portfolio and Program/Project Management software products to choose from for every PMO Manager….
• CA Clarity Project and Portfolio Management
• Compuware • UMT• Oracle Primavera• Microsoft Project Server 2013 & 2016
• and many others…..
• Microsoft Project 2013 & 2016• WBS Schedule Pro• Deltek Active Risk Manager• @Risk• and many others…..
Reviewing & Selecting PMO Tools
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Day to Day Operations Summary
© Copyright 2012 – B Dow
Define Color Definitions
Setup CR Process
Develop Program/Project
Playbooks
Define PMO Priority List
Define PMO Weekly Checklist
Setup Project Transition Plans
Develop PMO Templates
Execute PMO Reports
Review and Select PMO Tools
Continue to support
Management and Value Discussions
Key Components of Running a PMO Summary
Running a Successful PMO
© Copyright 2012 – B Dow
Key Components of Running a PMO Summary
• We covered the top 10 areas in running a PMO from day to day. There is a lot of items, but to run a successful PMO these areas are critical.
• These areas will be valid in most PMOs today regardless of the industry.
• Take the time and build out each of these areas to set yourself up for running a successful PMO!
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Resources
© Copyright 2012 – B Dow© Copyright 2012 – B Dow
• One of the areas that PMO Managers are going to want to setup and get going sooner than later is a PMO Mentoring Program or PMO Buddy System.
• The PMO Mentoring Program is much more formal and can be tied to PMO team members performance reviews.
• The PMO Buddy System is much less formal, however often depending on the environment much more successful.
PMO Resources
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Mentor & Buddy Program
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
PMO Mentor Program
• Many companies will offer a employee mentor program that pairs employees with like careers to learn and grow from each other.
• PMO’s should have Mentoring programs within them. These programs either are standalone if the company doesn’t have them, or sublimit the companies offerings.
• PMO Mentoring Programs are formal in nature and pair employees usually for a one year period.
• PMO Managers should create a PMO Mentoring Program and drive that program as very formal part of running their PMO.
• All employees and all roles will be allowed to be part of the PMO Mentoring Program.
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
PMO Buddy System
PMO Buddy System - tends to have very few rules or restrictions; it is much less formal than an official PMO mentoring program.
The PMO Buddy system pairs “like” roles together to act in a mentor/mentor type of role where no one person is the lead or takes on the leadership position. The simple process of pairing employees who share the same type of role gives them each someone who they can talk to, share concerns with, bounce ideas off of, and act as a sounding board about their projects.
Running a Successful PMO
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
PMO Buddy System – Guidelines to Consider
• PMO buddies commit to the program for a certain amount of time. Three months min should be the commitment from each partner.
• PMO buddies share ideas, suggestions, and best practices whenever possible.
• PMO buddies commit to 1–2 “buddy” meetings, monthly, to share ideas and connect with each other.
• PMO buddies commit to being open and honest with both their “employee buddy” and management on whether the relationship is working, sooner rather than later.
• Neither “employee buddy” is obligated to take on the leadership role in the relationship.
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Resources Summary
© Copyright 2012 – B Dow
PMO Resources Summary
• We covered 2 of the critical tools that you should setup as PMO Manager to support your team members.
• With the Mentoring Program that is going to require more formality and possibly work with the HR team, but the payoff is worth it!
• The PMO Buddy system we covered is much more informal, but something you can easily get started on immediately.
• Supporting your PMO team members is a critical way to ensure they are happy and they have the resources they need to be successful.
Running a Successful PMO
© Copyright 2016 – B Dow
PMO Wrap-up
© Copyright 2012 – B Dow
• We covered a number of areas of running a successful PMO in your organization.
• Each of these components are critical to your success in managing your organization!
• Don’t underestimate how much time you will spend justifying your PMO, so be ready and prepared for that conversation. This will be a daily routine that you must be prepared for!
Running a Successful PMO Summary
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Check out my book “The Tactical Guide for Building a PMO”
For more information!
© Copyright 2012 – B Dow
Project Management
Communication Tools
- Published 2015
Bill Dow, PMP
@dowpublishing
@billdow
dowpublishingllc
Bill Dow, PMP
The Tactical Guide for Building
a PMO
-Published 2012
Dowpublishingllc.comw w
w
© Copyright 2012 – B Dow© Copyright 2017 – B Dow
Thanks!