Assignment 2b (Individual Assignment) · Web viewIn 2009 as the world's economy was in the midst of...
Transcript of Assignment 2b (Individual Assignment) · Web viewIn 2009 as the world's economy was in the midst of...
Assignment 2b (Individual Assignment)
ContentsAssignment 2b (Individual Assignment)...................................................................................1
Scenario..................................................................................................................................2Context...................................................................................................................................3General Company Background..............................................................................................3The Production Process..........................................................................................................3
Examples of typical products (flanges)..............................................................................4Facility Layout...................................................................................................................5Product route......................................................................................................................6Current Value Stream Map................................................................................................8
Appendix................................................................................................................................9Current Value Stream Map..................................................................................................15Flange Production: Saw Cutting Process Data.....................................................................16Administrative Process.........................................................................................................17
Table of FiguresFigure 1 Aerial photograph of Evenort. (Building with white roof.)........................................2Figure 2 0.75" Diameter Flange.................................................................................................4Figure 3 16" Diameter Flange....................................................................................................4Figure 4 Shop Floor Layout.......................................................................................................5Figure 5 Production Route 1......................................................................................................6Figure 6 Manufacturing Process and Product Route..................................................................7Figure 7 Current Value Stream Map..........................................................................................8Figure 8 Product Route 1.........................................................................................................10Figure 9 Product Route 2.........................................................................................................11Figure 10 Product Route 3.......................................................................................................12Figure 11 Product Route 4.......................................................................................................13Figure 12 Some ideas for improving the site...........................................................................15
1
Scenario
Manufacturing and logistics industries involve the movement of physical items through a series of processes and acted upon by discrete resources. Being aware that industry is under constant pressure to provide high quality, timely products while utilising the minimum of resources you are required to research and apply appropriate Lean Tools and techniques within Evenort, a small manufacturing business situated based in South Yorkshire. Thereby helping the business better identify and remove waste. Below, Figure 1, is an aerial photograph of Evenort's premises. It should be noted from the photograph that there is little room for expansion as there is a train track behind the factory and buildings on either side. It may be possible to extend the building towards the main road if required.
Figure 1 Aerial photograph of Evenort. (Building with white roof.)
2
Context
In 2009 as the world's economy was in the midst of recession Evenort, an SME based in South Yorkshire, was seeking to increase efficiency within the business through implementing a process improvement strategy. In conjunction with Sheffield Hallam University a Knowledge Transfer Partnership was entered into providing the opportunity to change. Lee, the Knowledge Transfer Associate having an awareness of Lean, 6 Sigma, and discrete-event simulation has the opportunity to make significant improvements to the bottom line of the business; but before making any change to the business he must first identify what improvements could be made and devise a strategy for making those improvements. What could, where would you and in what order would you implement changes? Make your recommendations.
The Evenort Case is intended for using on a process improvement course. The normal participant is recent graduate who may be taking this module on a full or part-time basis and has little prior exposure to the practical side of process improvement.
General Company Background
Incorporated in Sheffield in 1982, Evenort is currently situated over two sites. The Head Office and main manufacturing site is at Houghton Road, Dinnington, Sheffield, S25 4JJ, UK. With its plasma cutting workshop based at: Shop 12, Robert Jenkins Works, Wortley Road, Rotherham, S61 1LT, UK.
Evenort's commitment to manufacturing excellence has established the company as a reliable partner in the processing of Stainless Steel. Evenort's business proposition is to supply high value bespoke products, typically flanges, produced within 24hours of order, to the highest quality standards and manufactured from alloys appropriate to the environment, be it sour or acidic. As such their products are often used in the oil and gas industries.
The Production Process
Evernort offers a range of products and services which includes: Steel & Alloy Flanges Bar Processing Advanced Manufacturing Deep Water Shipments Plasma Cutting
However, the focus of this case study is Evenort's Head Office where flanges are machined, either from cut bar or semi finished castings.
3
Semi finished forgings are usually purchased from Hilton Metal Forging Ltd. based in India of whom Evenort owns a substantial share of and is the official UK agent.
Examples of typical products (flanges).
The flanges come in a variety of sizes but typically range in size from 98mm Dia to 597mm Dia and are manufactured from stainless steel. Figure 2 and Figure 3 illustrate and provide schematics of the products.
0.75" ASA 150LB RFSO 316/L
Dimensions in mm
D K L C N H B R O F No.Holes98 69.8 15.9 12.7 38 15.9 27.7 3 42.9 1.6 4
Figure 2 0.75" Diameter Flange
16.00" ASA 150LB RFSO 316/L
Dimensions in mm
D K L C N H B R O F No.Holes597 539.8 28.6 36.5 457 63.5 410.5 9.5 469.9 1.6 16Figure 3 16" Diameter Flange
4
Facility Layout
The manufacturing facility has grown and expanded as demand for specific products has increased. This led to equipment being purchased and located where there was space, which Lee thinks may or may not be in the best location from a process efficiency point of view. The current layout can be seen in Figure 4.
Figure 4 Shop Floor Layout.
5
[Machine] Saw:HA500, HA700, HA400 (6 machines), HA250 (6 machines) Turning Machine:CNC Turning: CNC-T1, CNC-T2, CNC-T3, CNC-T4, CNC-T&D5 Manual Lathe: M-L1, M-L2, M-C-L3, M-L4, M-L5Adv CNC Turning&Drilling: INT200, INT300Drilling Machine:CNC-D1, CNC-D2, CNC-D3, CNC-D4, CNC-D5VAX500 (mill and drill)Mark:Mark 1, Mark 2, Mark 3, Mark 4Crane:Crane 1, Crane 2, Crane 3[OP]DayShift 12 operatorsNightShift 5 operators+1 laybour[Delivery]
VAX500
INT200
INT300Bar Stock
Area
Bar Stock Shelf
Saw HA250 (6) Saw HA400
(6)
Saw HA700
Saw HA500
ScrapCoolant &
Oil Scrap
CNC-D5
CNC-T&D5
Crane 3
Crane 2
Crane 1
Office
Forged flanges container
Inspect
Mark
Packing
OfficeForge Stock Shelf ML2
ML4
CNC-T4
CNC-T3CNC-T1 CNC-D3
CNC-D1
CNC-D4
CNC-D2CNC-T2
ML5
ML1
MCL3
Product route
Lee has spent several weeks collecting data and has been able to identify four different routes through the factory. The first of which is shown in Figure 5 with the remainder given in the appendix.The generic process route consists of Sawing the bar to length (if manufactured form bar and not from a semi finished forging), turning, drilling, inspecting, marking and packing.
PRODUCT ROUTE 1 (Ø75-Ø340mm, Stainless Steel 304, 316)
Bar
Saw Cutting OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Blade Band change Conditions for change
Day Night
1 1
HA250 Ø75-Ø200mm 10mins ± 2
15mins±5 Assume after 500 cuts
HA400 Ø152-Ø355mm 10mins ± 2
1 person in charge all the saws
Turning OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Tool/Tip change Conditions for change
Day Night
1 0.5CNC-T1 Ø75-Ø150mm 5mins ± 3 5mins ± 2
Your assumption for batch size 1 minCNC-T3 Ø125-Ø254mm 5mins ± 3 5mins ± 2CNC-T4 Ø125-Ø254mm 5mins ± 3 5mins ± 2
1 1 ML-1 Ø75-Ø340mm 15mins ± 5 5mins ± 21 0 ML-2 Ø75-Ø340mm 15mins ± 5 5mins ± 2
Note: means at night shift 1 person on both turning and drilling machine
Drilling OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Tool/Tip change Conditions for change
Day Night
1 0.5CNC-D2 Ø75-Ø400mm 3mins ± 1 5mins ± 2 Your assumption for batch size
1 minCNC-D3 Ø75-Ø400mm 3mins ± 1 5mins ± 2CNC-D4 Ø75-Ø400mm 3mins ± 1 5mins ± 2
Inspection, Mark & PackOP M/C Job Size Cycle Time Changeover Conditions for changeover
Day Night
2 operators0.5 0 Inspect Station All jobs 30secs±5
Assume no changeover1.5 0 Mark 1 Ø75-Ø380mm 20secs±5Mark 2
see cutting process data
Normally change per batch. Batch size varies very much depending on customer order quantity (could be from 1 to 200), make your own assumption.
Forged Flange
Make your own assumption. E.g. change tip when finish 50 items.
Make your own assumption.
Figure 5 Production Route 1
6
An alternative representation of the process route can be seen in Figure 6.
Parker Job
Big Job
Note:
EVENORT MANUFACTURING PROCESS & PRODUCT ROUTE
Main Process
Machine and Product Route
Main process
Product route
Second route
1. Jobs are scheduled daily when customer orders are received. 2. Generally, product route is determined by the size instead of type, but product with complicated shape only goes to advanced CNC machine. 3. and, duplex steel and nickel alloy product only goes to advanced CNC machine.
CNC-Turing
Adv. CNC–T&D
Manual Lathe-T
SawBar
CNC-T1 (Ø75-Ø150mm)
CNC-T2 (Ø220-Ø457mm)
CNC-T4 (Ø125-Ø254mm)
M-L1 (Ø75-Ø340mm)
CNC-T3 (Ø125-Ø254mm)
M-L2 (Ø75-Ø340mm)
M-C-L3 (Ø75-Ø340mm)
M-L4 (Ø300-Ø520mm)
M-L5 (Ø500-Ø700mm)
INT200 (Ø75-Ø200mm)
INT300 (Ø175-Ø380mm)
Turning (Boring, Facing, Taping, etc.) Drilling (Bolt Hole)
CNC-T&D5 (Ø340-Ø1200mm)
CNC-D1 (Ø300-Ø640mm)
CNC-D2 (Ø75-Ø400mm)
CNC-D3 (Ø75-Ø400mm)
CNC-D4 (Ø75-Ø400mm)
CNC-D5 (Ø75-Ø580mm)
Inspection Marking Packing
VAX-500(Ø75-Ø380mm)
HA500
Forges
HA700
HA400 (5 M/C)
HA250 (5 M/C)
Mark 1
Mark 2
Mark 3
Mark 4
Figure 6 Manufacturing Process and Product Route.
7
Evenort Current Value Stream Map
BARSAW
112 M/C
C/T
C/O
Uptime
Shifts=2
Avail.=25920 secs
CNC TURNINGT1, T3, T4
Day 1, Nigt 0.5M/C Day 3, Nigt 1
MANUAL LATHEML1, 2 ML3 (center)
Day 2 Nigt 1M/C Day 2, Nigt 1
ADV.CNC TURNING & DRILLING INT200
Day 1, Nigt 0.41 M/C
DRILLING D2, 3, 4
Day 1, Nigt 0.5M/C Day 3, Nigt 1
INSPECTION
0.5
C/T
C/O
Uptime
Shifts=1
Avail.=25920 secs
MARK
1.5 4 M/C
C/T
C/O
Uptime
Shifts=1
Avail.=25920 secs
PACKAGE
0.5 0.5 for dispatch
C/T
C/O
Uptime
Shifts=1
Avail.=25920 secs
EVE. (10%) Weekly
TNT (90%) Daily
Customers
Pieces/wk= 1134
Pieces/Day =225
Takt= 231 secs
PRODUCTIONCONTROL
Daily ScheduleBars
Sandvik and etc.
Weekly
4mths
0.3 days
Orders
1 month Schedule
Order as Reuqired
1.5 days 0.4 days 0.2 days
Forge FlangesHMFL(India) andSL, DSF (China)
2 wks
6Weeks
Ship
Staging
0.5days
DailyWork Routine / Inspection
ADV.CNC Milling& DRILLING
Day 1, Nigt 0.31 M/C
C/T
C/O
Uptime
Shifts=2
Avail.=25920 secs
Ø75-Ø250 3M/C
CNC TURNING & DRILLING
0.51 M/C
C/T
C/O
Uptime
Shifts=2
Avail.=25920 secs
Ø75-Ø340 3M/C
Ø75-Ø200 1M/C
Ø300-Ø640 2M/C
Ø220-Ø457 1M/C
Ø175-Ø380 1M/C
Ø340-Ø1200 1M/C
CNC TURNING T2
0.2 only day shift1 M/C
MANUAL LATHE ML4, 5
1 only day shift 2 M/C
ADV.CNC TURNING & DRILLING INT300
Day 1, Nigt 0.31 M/C
DRILLING D5
0.3 day shift1 M/C
Bar FlangesForge Flanges
Current Value Stream Map
From compiling the above data and direct observation Lee has created the following Value Stream Map, Figure 7.
8Figure 7 Current Value Stream Map
Appendix
9
PRODUCT ROUTE 1 (Ø75-Ø340mm, Stainless Steel 304, 316)
Bar
Saw Cutting OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Blade Band change Conditions for change
Day Night
1 1
HA250 Ø75-Ø200mm 10mins ± 2
15mins±5 Assume after 500 cuts
HA400 Ø152-Ø355mm 10mins ± 2
1 person in charge all the saws
Turning OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Tool/Tip change Conditions for change
Day Night
1 0.5CNC-T1 Ø75-Ø150mm 5mins ± 3 5mins ± 2
Your assumption for batch size 1 minCNC-T3 Ø125-Ø254mm 5mins ± 3 5mins ± 2CNC-T4 Ø125-Ø254mm 5mins ± 3 5mins ± 2
1 1 ML-1 Ø75-Ø340mm 15mins ± 5 5mins ± 21 0 ML-2 Ø75-Ø340mm 15mins ± 5 5mins ± 2
Note: means at night shift 1 person on both turning and drilling machine
Drilling OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Tool/Tip change Conditions for change
Day Night
1 0.5CNC-D2 Ø75-Ø400mm 3mins ± 1 5mins ± 2 Your assumption for batch size
1 minCNC-D3 Ø75-Ø400mm 3mins ± 1 5mins ± 2CNC-D4 Ø75-Ø400mm 3mins ± 1 5mins ± 2
Inspection, Mark & PackOP M/C Job Size Cycle Time Changeover Conditions for changeover
Day Night
2 operators0.5 0 Inspect Station All jobs 30secs±5
Assume no changeover1.5 0 Mark 1 Ø75-Ø380mm 20secs±5Mark 2
see cutting process data
Normally change per batch. Batch size varies very much depending on customer order quantity (could be from 1 to 200), make your own assumption.
Forged Flange
Make your own assumption. E.g. change tip when finish 50 items.
Make your own assumption.
Figure 8 Product Route 1
10
Day NightHA250 Ø75-Ø200mm 10mins ± 2HA400 Ø152-Ø355mm 10mins ± 2
1 person in charge all the saws
Day Night
1 0.4 Mazak INT 200 Ø75-Ø200mm 10mins ± 5 15mins ± 5
1 0.3 Mazak INT 300 Ø175-Ø380mm 20mins ± 10 15mins ± 5
Day Night
1 0.3 Mazak VAX 500 Ø75-Ø380mm 45mins ± 15 20mins ± 5 Your assumption for batch size 1 minMake your own assumption.
Day NightInspect Station All jobs 30secs±5Mark 1Mark 2
Mark 3For top face marking, make assumption
Pack Station All jobs 25secs±5
Assume no changeover
Inspection, Mark & PackOP M/C Job Size Cycle Time Changeover Conditions for changeover
Tool/Tip change Conditions for changeOP M/C Job Size Cycle Time Changeover Conditions for changeover
Forged Flange
OP M/C Job Size Cycle Time
see cutting process data
Depends on order quantity (1 to 200), make assumption
15mins±5 Assume after 500 cuts
Milling Operation (Optional depends on custmer requirment, assume 50% of parts needs milling opteration)
Turning & Drilling Operation
Changeover Conditions for changeover Tool/Tip change Conditions for change
Note: 1 OP on 3 machine at night, the figures are assumption work loading distribution.
Your assumption for batch size 1 min
Make your own assumption. E.g. change tip when finish 40 items.
Ø75-Ø380mmSampe operators with Route 1
20secs±5
PRODUCT ROUTE 2 (Adv. CNC Ø75-Ø380mm, assume 40% Duplex and Nickel Alloy, 60% stainless steel)
Bar
Saw Cutting OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Blade Band change Conditions for change
1 1
Figure 9 Product Route 2
11
12
13
Day NightHA500 Ø304-Ø457mm 10mins ± 2HA700 Ø406-Ø640mm 10mins ± 2
1 person in charge all the saws
Day Night
CNC-T2 Ø220-Ø457mm 15mins ± 5 5mins ± 2
ML-4 Ø300-Ø640mm 25mins ± 5 10mins ± 5ML-5 Ø300-Ø640mm 25mins ± 5 10mins ± 5
Day Night
CNC-D5 Ø75-Ø580mm 7mins ± 2 5mins ± 2 Your assumption for batch size. 1 minMake your own assumption.
Day NightInspect Station All jobs 60secs±5
Mark 4 Ø400-Ø1200mm30secs±5
Pack Station All jobs 180secs±10
Tool/Tip change Conditions for changeOP M/C Job Size Cycle Time Changeover Conditions for changeover
Assume after 200 cuts
Drilling Operation
Turning OperationForged Flange
OP M/C Job Size Cycle Time Changeover Conditions for changeover Tool/Tip change Conditions for change
Your assumption for batch size 1 min
Make your own assumption. E.g. change tip when finish 30 items.
1 1 see cutting process data
Depends on order quantity (1 to 50), make assumption
20mins±5
PRODUCT ROUTE 3 (Ø380-Ø640mm stainless steel 304, 316)
Bar
Saw Cutting OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Blade Band change Conditions for change
Sampe operators with Route 1
1 0
same OP on CNC-T1, T3, T4
Same OP on CNC T&D5
Inspection, Mark & PackOP M/C Job Size Cycle Time Changeover Conditions for changeover
Assume no changeover
Figure 10 Product Route 3
Day Night
1 1 HA700 Ø400-Ø640mmsee cutting process data
10mins ± 2Depends on order quantity (1 to 20), make assumption
20mins±5 Assume after 200 cuts
1 person in charge all the saws
Day Night
1 1 CNC T&D5 Ø400-Ø1200mm180 mins ± 60 10mins ± 3Depends on order quantity,
make assumption1 min
Make assumption. E.g. after 20 items
(Ø400-Ø1200mm)
Day Night
Inspect Station All jobs 60secs±5
Mark 4 Ø400-Ø1200mm30secs±5
Pack Station All jobs 180secs±10
Forged Flange
Assume no changeover
Inspection, Mark & PackOP M/C Job Size Cycle Time Changeover Conditions for changeover
Sampe operators with Route 1
Turning & Drilling OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Tool/Tip change Conditions for change
Conditions for change
PRODUCT ROUTE 4 (Ø400-Ø1200mm, majority stainless steel 304, 316)
Bar (Ø400-Ø640mm)
Saw Cutting OperationOP M/C Job Size Cycle Time Changeover Conditions for changeover Blade Band change
Figure 11 Product Route 4
14
Current Raw Material Inventory and WIP for Reference to Make Batch Size Assumptions
Bar
Route 1
For CNC-T1,T3,T4 For CNC-D2, D3, D4 For Inspect For Mark For Pack
2 weeks stock 137 parts, 1 to 10 types of parts79 parts, 1 to 7 types of parts 20 0 45
Forge For M-L1, L24 months stock 64 parts, 1 to 10 types of parts
Route 2
For Mazak INT 200 For Mazak VAX 500 5 10 10
40 parts, 1 to 5 types of parts77 parts, 1 to 5 types of parts
For Mazak INT 30017 parts, 1 to 3 types of parts
Route 3For CNC-T2, M-L3, L4 For CNC-D5 4 0 4
16 parts, 1 to 5 types of parts6 parts, 1 to 2 types of parts
Route 4For CNC-T&D5 6 0 06 parts, 1 to 4 types of parts
Note: This inventory and WIP is just for reference so that you have an rough idea when you make assumption on batch size.
The WIP of parts number for different operation and types number varies day by day. They are average figures based on my one week statistics.
15
Evenort Current Value Stream Map
BARSAW
112 M/C
C/T
C/O
Uptime
Shifts=2
Avail.=25920 secs
CNC TURNINGT1, T3, T4
Day 1, Nigt 0.5M/C Day 3, Nigt 1
MANUAL LATHEML1, 2 ML3 (center)
Day 2 Nigt 1M/C Day 2, Nigt 1
ADV.CNC TURNING & DRILLING INT200
Day 1, Nigt 0.41 M/C
DRILLING D2, 3, 4
Day 1, Nigt 0.5M/C Day 3, Nigt 1
INSPECTION
0.5
C/T
C/O
Uptime
Shifts=1
Avail.=25920 secs
MARK
1.5 4 M/C
C/T
C/O
Uptime
Shifts=1
Avail.=25920 secs
PACKAGE
0.5 0.5 for dispatch
C/T
C/O
Uptime
Shifts=1
Avail.=25920 secs
EVE. (10%) Weekly
TNT (90%) Daily
Customers
Pieces/wk= 1134
Pieces/Day =225
Takt= 231 secs
PRODUCTIONCONTROL
Daily ScheduleBars
Sandvik and etc.
Weekly
4mths
0.3 days
Orders
1 month Schedule
Order as Reuqired
1.5 days 0.4 days 0.2 days
Forge FlangesHMFL(India) andSL, DSF (China)
2 wks
6Weeks
Ship
Staging
0.5days
DailyWork Routine / Inspection
ADV.CNC Milling& DRILLING
Day 1, Nigt 0.31 M/C
C/T
C/O
Uptime
Shifts=2
Avail.=25920 secs
Ø75-Ø250 3M/C
CNC TURNING & DRILLING
0.51 M/C
C/T
C/O
Uptime
Shifts=2
Avail.=25920 secs
Ø75-Ø340 3M/C
Ø75-Ø200 1M/C
Ø300-Ø640 2M/C
Ø220-Ø457 1M/C
Ø175-Ø380 1M/C
Ø340-Ø1200 1M/C
CNC TURNING T2
0.2 only day shift1 M/C
MANUAL LATHE ML4, 5
1 only day shift 2 M/C
ADV.CNC TURNING & DRILLING INT300
Day 1, Nigt 0.31 M/C
DRILLING D5
0.3 day shift1 M/C
Bar FlangesForge Flanges
Current Value Stream Map
Figure 12 Some ideas for improving the site
16
Flange Production: Saw Cutting Process Data304, 316 Material Bar Saw Cutting Data
Bar Size (Ømm) Saw Type Used for Cutting Cutting Time (mins) Varation76 3 ±1828895
101 5 ±1107114120 HA250127133139152 10 ±2165177185190200 17 ±3203215220228 HA400241254 25 ±4279285304 38 ±4340355 59 ±5381 HA500406 75 ±6431457 100 ±7520 HA700 150 ±8580640 220 ±10
Duplex Steel e.g. F44 and Nickel Alloy e.g. 625 Material Bar Saw Cutting Data76 4 ±1828895
101 10 ±2107114120 HA250127133139
17
152 22 ±3165177185190200 37 ±4
Administrative Process
Physical equipment in process
4 x PC for orders (4 staff)1 printer - job sheets (carbon paper)1 printer - WRI cards, drawings, test certificates (normal)1 PC - Diana/Peter -digital filing, printing(Peter also has PC but not necessarily required for this particular process)
18
Start
Order received
PO required?
Inputdetails into unityRaisePO
Jobsheet printedWRI card & drawing
printed
Drawingadequate?
Jobwritten in job sheet log book
Reprint or print drawing
Jobsheet placed in blue tray
Jobsheets sorted into days
Job complete?
Marksheet to indicate job complete
Locaterequired material
Document pack out together
Test certificate printed
Inspection note & test certificate filed
digitally
Jobsheettop copy to dispatch / invoicing
Document pack matched with
completed part
Allcorrect documents with finished part?
Partdispatched with documentation
Printmissing documents
Locatepart
Process customer payments
White top sheet filed
End
NoYes
Yes
No
Yes
No
Yes
No