ASME Temporary Repairs 101410-1

download ASME Temporary Repairs 101410-1

of 41

Transcript of ASME Temporary Repairs 101410-1

  • 8/6/2019 ASME Temporary Repairs 101410-1

    1/41

    Temporary Repairs

    Presented by: Charlie RutanFormally Senior Engineering Advisor for LyondellBasell

    Fixed Equipment Inspection, Repair, and Failure Analysis

    Houston, Texas

    October 14, 2010

  • 8/6/2019 ASME Temporary Repairs 101410-1

    2/41

    2

    Special Acknowledgements

    Michael Guillot, Ph.D., P.E. Stress Engineering

    Services, Inc.; [email protected] ASME Fixed Equipment Inspection, Repair, andFailure Analysis SeminarHouston, Texas

    August 1820, 2009

    mailto:[email protected]:[email protected]
  • 8/6/2019 ASME Temporary Repairs 101410-1

    3/41

    3

    Contents of Presentation

    Repairs made at every plant to keep things

    running, but considered as temporary repairs byAPI or other governing bodies

    On-line, non-welded repairs

    On-line, welded repairs Documentation and tracking of temporaryrepairs

  • 8/6/2019 ASME Temporary Repairs 101410-1

    4/41

    4

    Temporary Repairs Definitions

    From API 510 3.60: Repairs made to pressure vessels to restore sufficientintegrity to continue safe operation until permanent

    repairs can be conducted

    From API 570 3.45: Repairs made to piping systems to restore sufficientintegrity to continue safe operation until permanent

    repairs can be scheduled and accomplished within atime period acceptable to the Inspector or PipingEngineer

  • 8/6/2019 ASME Temporary Repairs 101410-1

    5/41

    5

  • 8/6/2019 ASME Temporary Repairs 101410-1

    6/41

    6

    Temporary Repairs Definitions

    (Continued) On-line, non-welded repairs

    Flange repair Enclosures

  • 8/6/2019 ASME Temporary Repairs 101410-1

    7/41

    7

    Flange Repair

    Wire-wrap procedure

    Used in flange gaps up to10 mm (0.4 inches)

    Pressure limitations

    Immediate off-the-truck

    repair

    Excessive peening mustbe avoided to preventbolts from being

    overloaded

  • 8/6/2019 ASME Temporary Repairs 101410-1

    8/41

    8

  • 8/6/2019 ASME Temporary Repairs 101410-1

    9/41

    9

  • 8/6/2019 ASME Temporary Repairs 101410-1

    10/41

    10

  • 8/6/2019 ASME Temporary Repairs 101410-1

    11/41

    11

  • 8/6/2019 ASME Temporary Repairs 101410-1

    12/41

    12

  • 8/6/2019 ASME Temporary Repairs 101410-1

    13/41

    13

    Mechanical Clamp Repair (continued)

    Hot Tapping can be performed throughmechanical clamps. This is a very effective wayof preventing a crack to propagate.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    14/41

    14

  • 8/6/2019 ASME Temporary Repairs 101410-1

    15/41

    15

  • 8/6/2019 ASME Temporary Repairs 101410-1

    16/41

    16

  • 8/6/2019 ASME Temporary Repairs 101410-1

    17/41

    17

  • 8/6/2019 ASME Temporary Repairs 101410-1

    18/41

    18

  • 8/6/2019 ASME Temporary Repairs 101410-1

    19/41

    19

    Hot Tap

    Hot Tapping

    Line Stops

  • 8/6/2019 ASME Temporary Repairs 101410-1

    20/41

    20

    Physical limitations (continued) Metal Thickness > 0.75 Difficulties excessivemetal shavings

    Required thickness calculations, body bound bolts, and nopilot drill

    Hot Tapping in the horizontal direction Turn thevalve up side down and let the shavings fall into thevalve bonnet

    Local stress relieving may be required for carbonsteels due to the steels thickness This may be areal issue! (Cooper Heat)

  • 8/6/2019 ASME Temporary Repairs 101410-1

    21/41

    21

    On-Line Weld Repairs (continued)

    In some cases these repairs can be consideredpermanent repairs. Allow clamp to come to line temperature

    Use the proper welding procedure First weld will be a circumferential weld at one end ofthe clamp Second welds are the longitudinal welds After welds have cooled the circumferential weld canbe made.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    22/41

    22

    On-Line Weld Repairs Welding Procedures (continued)

    Process conditions are key and will define the welding criteria

    TIG welding is preferred for the first 3 or 4 passes.

    A 3/32 diameter weld rod should be used for the next 3 to 4passes

    Typically then a 1/8 diameter rod can then be usedNote: on the inside of a 6 pipe with a wall thickness of 0.280 the

    wall temperature was measured to be 740oF with the TIG heatarea of .39 in2 while the 3/32 diameter weld rod had the sametemperature but the area was increased 1.83 times from 0.39 in2

    to 0.95 in2

  • 8/6/2019 ASME Temporary Repairs 101410-1

    23/41

    23

    History of Hot Tapping

    The first hot taps were made withsledgehammers and pointed bars

    H. Muller, founder of Muller Company, patentedfirst tapping machine (1872)

    Frank Wheatley Company of Tulsa Oklahomadeveloped first tapping machine for oil and gasindustry

    In 1932, J. E. Polston and A. M. Hill inventedP&H Tapping Machine. A telescoping boring barwas the special design feature.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    24/41

    24

    Very Early Hot Tap

  • 8/6/2019 ASME Temporary Repairs 101410-1

    25/41

    25

    Tapping Through A Pipe Wall

  • 8/6/2019 ASME Temporary Repairs 101410-1

    26/41

    26

    Pipe ID Flow Stop

  • 8/6/2019 ASME Temporary Repairs 101410-1

    27/41

    27

    Modified Muller Hot Tap

  • 8/6/2019 ASME Temporary Repairs 101410-1

    28/41

    28

    Modified Muller Line Stop

  • 8/6/2019 ASME Temporary Repairs 101410-1

    29/41

    29

    Hot Tap vs. Clamp for Repair

  • 8/6/2019 ASME Temporary Repairs 101410-1

    30/41

    30

  • 8/6/2019 ASME Temporary Repairs 101410-1

    31/41

    31

  • 8/6/2019 ASME Temporary Repairs 101410-1

    32/41

    32

    Hot Tap for Repairs

  • 8/6/2019 ASME Temporary Repairs 101410-1

    33/41

    33

  • 8/6/2019 ASME Temporary Repairs 101410-1

    34/41

    34

    Lap patch in a refinery FCCU In FCCU units, catalyst continually circulates attemperatures of 1200 to 1400F (650 to 750C). Catalyst is

    circulating at high velocity, so it is extremely erosive.

    Carbon steel is used in services < 750F (400C). At highertemperatures, it loses mechanical strength, and therefore itsability to withstand pressure.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    35/41

    35

    Documentation & Tracking of Temporary Repairs

    API 510 8.1.5.1 Temporary Repairs

    8.1.5.1.1 General

    Temporary repairs should be removed and replaced with suitable permanentrepairs at next available maintenance opportunity.

    Temporary repairs may remain in place for a longer period of time only ifevaluated, approved, and documented by engineer and inspector.

    Documentation of temporary repairs should include

    Location of temporary repairSpecific details, e.g., material of construction, thickness, size of welds, NDE

    performed

    Details of analyses performedRequirements for future inspections

    Due date for installing permanent repair

    Inspection plans shall include monitoring integrity of temporary repairuntil permanent repairs are complete

  • 8/6/2019 ASME Temporary Repairs 101410-1

    36/41

    36

    Documentation & Tracking of Temporary Repairs

    API 510 8.1.5.1 Temporary Repairs (contd.) 8.1.5.1.2 Fillet-Welded PatchesFillet-welded patches may be used to make temporary repairs to

    damaged, corroded, or eroded areas of pressure vessel components.

    Cracks shall not be repaired in this manner unless the engineerdetermines that cracks will not be expected to propagate from underthe patch. In some cases, the engineer may need to perform afitness-for-service analysis.

    Temporary repairs using fillet-welded patches shall be approved byan inspector and engineer. Use of fillet-welded patches may be

    subject to acceptance of governing jurisdiction.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    37/41

    37

    Documentation & Tracking of Temporary Repairs

    API 570 7.6 Reporting and Records for Piping SystemInspection

    Any significant increase in corrosion rates shall be reported toowner/user for appropriate action (Change in process conditions)

    Owner/user shall maintain appropriate permanent and progressiverecords of each piping system covered by API 570.

    These records shall contain pertinent data such a

    Piping system service

    ClassificationIdentification numbersInspection intervalsDocuments necessary to record name of individual performing testing, date,

    types of testing, results of thickness measurements and other tests,inspections, repairs (temporary and permanent), alterations, or rerating.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    38/41

    D t ti & T ki f T R i

  • 8/6/2019 ASME Temporary Repairs 101410-1

    39/41

    39

    Documentation & Tracking of Temporary Repairs

    API 570 8.1.3 Welding Repairs (including on-stream)

    8.1.3.1 Temporary Repairs (contd.)For minor leaks, properly designed enclosures may be welded overthe leak while piping system is in service, provided inspector issatisfied that adequate thickness remains near weld, and pipingcomponent can withstand welding without likelihood of furthermaterial damage, such as from caustic service.

    Temporary repairs should be removed and replaced with a suitable

    permanent repair at next available maintenance opportunity.Temporary repairs may remain in place for a longer time only ifapproved and documented by piping engineer.

    Documentation & Tracking of Temporary Repairs

  • 8/6/2019 ASME Temporary Repairs 101410-1

    40/41

    40

    Documentation & Tracking of Temporary Repairs

    Temporary repairs should be removed and

    replaced with a suitable permanent repair at thenext available maintenance opportunity.

  • 8/6/2019 ASME Temporary Repairs 101410-1

    41/41

    41

    Questions and Comments