ASHRAE Guideline 0-2005The Commissioning Process
Building Commissioning AssociationNortheast Chapter
Thomas Anderson, CCP
Purpose of Guideline 0-2005
Describe the Cx Process to verify a facility meets the Owner’s Project Requirements
Utilization
Guideline Describes the “Process” Technical Guidelines Detail
Technical Requirements
Guideline 0-2005 The Cx Process
ASHRAE Guideline 1-200X HVACR Cx Process (Tech Requirements)
NIBS Guidelines 2-200X through 14-200X Requirements Other Technical Cx Volumes Roofing, Lighting, Plumbing, Life Safety,
Etc.
Pre Design Phase
Develop Owner’s Project Requirements (OPR)
Cx Scope & Budget Develop Initial Cx Plan
Owner’s Project Requirements
Forms the basis from which all decisions are made… Design Construction Acceptance Operational Decisions
Owner’s Project Requirements
Primary Tool for Benchmarking Success and Quality At all Phases of Project Delivery Throughout the Life of Facility
Owner’s Project Requirements
Owner’s Objectives for a New Facility Guidance for Design Team & Others
Not developed by Design Team
OPR Should Include…
Schedule & Budget Cx Scope & Budget User Requirements Energy Efficiency Goals Applicable Codes & Standards Etc.
An OPR is Dynamic…
Evolves through each Phase Updated to Reflect Current Project
Requirements Feasibility Budget Limitations
Design Phase Cx Tasks
Verify Basis of Design (BoD) with OPR Update Cx Plan Defining Training Requirements Perform Focused Design Reviews
Developed by Design Team CxA Verifies BoD Conforms to OPR Systems Manual
Basis of Design
Basis of Design (BoD) Conveys Design Assumptions that Fulfill
OPR Intent Developed by Design Team Updated throughout Design Phase
Basis of Design Includes
System Selection Reasoning Assumptions
Narrative of System Selection & Reasoning
Environmental Conditions Load Calcs & Sizing Codes Operations
Systems Manual
Information Needed to… Understand Systems Operate Maintain
Systems Manual Includes
Index of Systems Manual Executive Summary OPR BoD O&M Manuals Cx Process Report
Construction Phase
Verify Systems & Assemblies Conform to OPR
Submittal Review (Spot Check) Develop Test Docs Witness Tests Verify Training Update Systems Manual (OPR, BoD,
Etc.)
Occupancy & Operations Phase
Begins at Substantial Completion Continue through end of
Contractual/Warranty Period Ideally, Continues through Life of the
Facility
Occupancy & Operations Phase
CxA Assists in Problem Solving Guidance on O&M to Achieve OPR Seasonal Testing Verify Training Systems Manual Update Cx Report