Page 1: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

ASHRAE Guideline 0-2005The Commissioning Process

Building Commissioning AssociationNortheast Chapter

Thomas Anderson, CCP

Page 2: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Purpose of Guideline 0-2005

Describe the Cx Process to verify a facility meets the Owner’s Project Requirements

Page 3: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Utilization

Guideline Describes the “Process” Technical Guidelines Detail

Technical Requirements

Page 4: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Guideline 0-2005 The Cx Process

ASHRAE Guideline 1-200X HVACR Cx Process (Tech Requirements)

NIBS Guidelines 2-200X through 14-200X Requirements Other Technical Cx Volumes Roofing, Lighting, Plumbing, Life Safety,

Etc.

Page 5: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Pre Design Phase

Develop Owner’s Project Requirements (OPR)

Cx Scope & Budget Develop Initial Cx Plan

Page 6: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Owner’s Project Requirements

Forms the basis from which all decisions are made… Design Construction Acceptance Operational Decisions

Page 7: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Owner’s Project Requirements

Primary Tool for Benchmarking Success and Quality At all Phases of Project Delivery Throughout the Life of Facility

Page 8: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Owner’s Project Requirements

Owner’s Objectives for a New Facility Guidance for Design Team & Others

Not developed by Design Team

Page 9: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

OPR Should Include…

Schedule & Budget Cx Scope & Budget User Requirements Energy Efficiency Goals Applicable Codes & Standards Etc.

Page 10: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

An OPR is Dynamic…

Evolves through each Phase Updated to Reflect Current Project

Requirements Feasibility Budget Limitations

Page 11: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Design Phase Cx Tasks

Verify Basis of Design (BoD) with OPR Update Cx Plan Defining Training Requirements Perform Focused Design Reviews

Developed by Design Team CxA Verifies BoD Conforms to OPR Systems Manual

Page 12: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Basis of Design

Basis of Design (BoD) Conveys Design Assumptions that Fulfill

OPR Intent Developed by Design Team Updated throughout Design Phase

Page 13: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Basis of Design Includes

System Selection Reasoning Assumptions

Narrative of System Selection & Reasoning

Environmental Conditions Load Calcs & Sizing Codes Operations

Page 14: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Systems Manual

Information Needed to… Understand Systems Operate Maintain

Page 15: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Systems Manual Includes

Index of Systems Manual Executive Summary OPR BoD O&M Manuals Cx Process Report

Page 16: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Construction Phase

Verify Systems & Assemblies Conform to OPR

Submittal Review (Spot Check) Develop Test Docs Witness Tests Verify Training Update Systems Manual (OPR, BoD,

Etc.)

Page 17: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Occupancy & Operations Phase

Begins at Substantial Completion Continue through end of

Contractual/Warranty Period Ideally, Continues through Life of the

Facility

Page 18: ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP.

Occupancy & Operations Phase

CxA Assists in Problem Solving Guidance on O&M to Achieve OPR Seasonal Testing Verify Training Systems Manual Update Cx Report