Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of...

46
Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C Principal Brent Weigel, Ph.D., P.E., LEED AP BD+C Senior Engineer

Transcript of Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of...

Page 1: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Phase Commissioning – The Advantage of Quality Assurance Before Construction

Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+CPrincipal

Brent Weigel, Ph.D., P.E., LEED AP BD+CSenior Engineer

Page 2: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Presentation Learning Objectives

1. Be able to list the essential elements of design phase commissioning.

2. Be able to describe how design phase commissioning supports construction phase commissioning.

3. Be able to explain how the elements of design phase commissioning support project delivery and risk management.

4. Be able to explain how design phase commissioning can identify opportunities for improved building performance.

Page 3: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

• Owner’s Project Requirements (OPR)• Cx Plan and Cx Kickoff Meeting• Basis of Design (BoD)• Construction Documents - Specifications• Design Review

3

Page 4: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

4

Page 5: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

5

Page 6: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

6

Page 7: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

7

Page 8: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

8

Page 9: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

9

Page 10: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Elements of Design Phase Cx

10

Page 11: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Team Collaboration

11

Page 12: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Owner’s Project Requirements (OPR)

• Plain English documentation of an owner’s criteria for success.

• Quantifiable criteria wherever possible

12

Page 13: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Owner’s Project Requirements (OPR)

• If possible, include the budget.

13

Page 14: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Owner’s Project Requirements (OPR)

• Develop the OPR with input from ALL project stakeholders.

14

Page 15: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Basis of Design (BoD)

• Narrative description of how the design team intends on satisfying the OPR.

• Relatively little effort compared with drawings and specs

• Provides an opportunity to modify approaches without significant rework.

15

Page 16: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Basis of Design (BoD)

EXAMPLE:OPR = Building Energy Use target of 20% better than code.

OPR = Individual HVAC control per office

BoD = Use VRF.

16

Page 17: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Commissioning Plan

• Describes the commissioning process in non-spec language.• Roles and responsibilities

17

• Documentation and communication protocols

• Description of commissioning tasks and schedule.

Page 18: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewHighly Cost Effective

• Desk side review = very time efficient = very low cost

18

Page 19: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewHighly Cost Effective

• On nearly every project, we find savings that pay for our services.

19

FEE

SAVINGS

Page 20: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review

• Two types of design review:

20

OPR compliance review

Peer review

Page 21: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review

• Two types of design review:

21

P OPR compliance review

Peer review

Page 22: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review

• Two types of design review:

22

OPR compliance review

P Peer review

Page 23: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review• Challenges, issues, and trends in the design engineering industry

that increase the need for peer review:– Design engineers spend fewer hours in the field during and after

construction– Less design fee available for internal QC & detailed investigation

/ analysis of options.– Internal QC can be blind to internal biases / errors

• External QC (Cx peer review) allows for knowledge sharing across firms

• Cx providers see designs from numerous engineering firms (Pick the good stuff from each).

– Weakness of controls sequence of operations in design documents

23

Page 24: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review “Objectives”

• OPR compliance• First cost reduction• Energy efficiency• Systems simplification• Future proofing• Maintainability• Commissionability• Bidability• Risk Management

24

Page 25: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewFirst Cost Reduction

• Right-sizing equipment – size the equipment to meetthe load.

• Example – RTU ReplacementExisting = 10 Ton, 30 Ton, 40 Ton RTUsReplacement = 5 Ton, 20 Ton, 20 Ton RTUs

Savings = $33,000

25

OPR compliance review

P peer review

Page 26: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewFirst Cost Reduction

• Alternative manufacturers• Example – Local Hotel

Design-Build HVACProposed a ventilation unit w/o local representationFrom a service standpoint, we suggested another manufacturer.

Savings = $10,000

26

OPR compliance review

P peer review

Page 27: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewFirst Cost Reduction

27

P OPR compliance review

P peer review

• Reducing equipment quantity

Page 28: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewFirst Cost Reduction

• Alternative design approaches

28

• Reducing equipment quantity

P OPR compliance review

P peer review

www.ebtron.com

Page 29: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design ReviewFirst Cost Reduction

• Alternative design approaches

29

• Reducing equipment quantity

P OPR compliance review

P peer review

Savings = $230 per $18,400 total

Page 30: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Energy Efficiency

• Code compliance review – 2015 VT CBES

30

P OPR compliance review

P peer review

Page 31: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Energy Efficiency

• Code compliance review – 2015 VT CBES

31

P OPR compliance review

P peer review

Page 32: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Energy Efficiency

• Opportunities to exceed code compliance with proven strategies

• Primary only chilled water system.• Lighting only what you need to light• Using building indicators to reset temperatures (not outdoor

air conditions).

32

P OPR compliance review

P peer review

Page 33: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Future proofing

• Ensure facility planning objectives are included in project design.

• Example – Hospital RTU with room for Chilled Water Coil

33

P OPR compliance review

P peer review

Page 34: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Maintainability

• Equipment access

34

P OPR compliance review

P peer review

Page 35: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Maintainability

• Consistency with existing equipment / systems

35

P OPR compliance review

P peer review

Page 36: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Commissionability

• Provide a Cx specification

36

Page 37: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Commissionability

• Construction Documents:– Sufficient detail for installation

(construction verification)– Sufficient detail for sequence of operations

(functional performance testing)

37

OPR compliance review

P peer review

Page 38: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Design Review:Bidability

• Minimize variance of bid estimates

• Minimize change orders during construction

38

OPR compliance review

P peer review

Page 39: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Risk Management

• Identify where and for whom risks exist

39

Page 40: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Risk Management

• Owner Risks:

40

www.videouniversity.com

Page 41: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Risk Management

• Owner Risks:

41

Page 42: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Risk Management

• Design Team Risks:• Errors and Omissions

42

coloradononprofitinsurance.org

Page 43: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Risk Management

• Design Team Risks:• Reputation

43

Page 44: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Risk Management

• Contractor Risks: All of the above and the kitchen sink!

44

assets.inhabitat.com

Page 45: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

Thank You!

Matt Napolitan - [email protected] Weigel – [email protected]

Page 46: Weigel Napolitan Design Phase Commissioning...Design Phase Commissioning – The Advantage of Quality Assurance Before Construction Matthew Napolitan, P.E., CCP, CPMP, LEED AP BD+C

• Outline:

• Elements of design phase commissioning.– describe how design phase commissioning supports construction phase commissioning.– how the elements of design phase commissioning support project delivery and risk management.– how design phase commissioning can identify opportunities for improved building performance.

• Design review– describe how design phase commissioning supports construction phase commissioning– how the elements of design phase commissioning support project delivery and risk management.– how design phase commissioning can identify opportunities for improved building performance.– Two types of design review

• Compliance w/ OPR• Peer review

– First cost reduction– Energy efficiency– Systems simplification– Future proofing– Maintainability– Commissionability– Communication style/tone– Collaboration– “BOD review” and expectations for design documents by phase

46