“Quality Water for all, forever”
Phakamani ButheleziChief Executive Officer
AREA OF OPERATION
GOVERNANCE STRUCTURE
ORGANOGRAM OVERVIEW
UNDERSTANDING THE BREEDE-GOURITZ WATER MANAGEMENT AREA
THE BREEDE-GOURITZ CATCHMENT MANAGEMENT AREA
BACKGROUND TO THE BREEDE-GOURITZ CMA
WATER RESOURCE MANAGEMENT
HUMAN RESOURCE MANAGEMENT
PERFORMANCE INFORMATION
FINANCIAL REPORT 2013/14
Table of Contents
Worcester – Head Office George – Satellite Office
Area of operation
Governing Board Committees – Reporting to the Governing
Board* Audit & Risks Committee* Human Resources & Remuneration Committee* Technical Committee* Water Use Authorisation Licence Committee
Governance Structure
ORGANOGRAM OVERVIEW
CEO
WATER RESOURCES MANAGEMENT: SNR
MANAGERFINANCE: CFO
Board Secretariat ServicesIT & STRATEGIC SUPPORT
HUMAN RESOURCESPUBLIC RELATIONS
Understanding the Breede Water
Management Area
The Breede-Gouritz Catchment
Management Area
Background to The Breede-Gouritz CMA
07/2005• Established in terms of NWA
09/2007• Appointment of Representative Board
2007-2010• Initial functions in terms of Section 80 of the NWA
12/2010• Additional functions delegated by the Minister
05/2014
• Establishment of the Breede-Gouritz Catchment Management Agency
2015• Further additional functions delegated by the Minister
Strategic Priority Areas
Water resources planning
Water use management
Institutional engagement
Water allocation reform
Resource protection
Information systems
Management & Governance
Strategic support (Finance & Human Resources)
Current Employment Equity
POSITION BF BM CF CM IF IM WF WM TOTALCEO 1 CFO 1 Snr Manager WR 1 IT Manager 1
(Disabled)
PA to CEO 1 HR Specialist 1 HR Admin 1 Finance Manager 1 Finance Officer 1 Finance Admin 1 Admin Officer 1 Data Manager 1 ISR Manager 1 Water Liaison Officer X3 1 2 Snr Data Capturer 1 Data Capturer X2 1 1 Water Data (GIS) 1 Water Use Specialist X2 1 1 Water Use Officer X4 1 3 Licensing Clerk 1
(Disabled)
Receptionist 1 Cleaner 1 TOTAL 10 4 5 4 0 0 3 3 29
Water Resources Planning
PLANNING PROCESSES
320 Land use planning and
rezoning applications
assessed and commented on, exceeding target of 140 by 228%
Engage with All 8 Local Authorities
on water use planning on 50
issues.
Onrus river Water Quality
Objectives Report finalised
Onrus Surface-
Groundwater interaction
study report finalised
Draft Salinity Management Plan Finalised
1 Status Quo report
finalised for Langeberg
Municipality (4 towns)
The Breede-Gouritz Catchment Management Strategy process could not commence as the establishment of the
BGCMA as formal entity was only finalised late
2014.
Water Use Management
Water Use Registrations, License Applications And
The V&V Process
Water Use Registration
373 Water Users
Registered on WARMS,
74.5% of target
reached
Water use license applications
16 Water Use License
applications, 9 had adequate
information and were
processed for Recommenda
tion
65 General Authorizations for water
use Applications confirmed which is
150% more than targets
reached
Water Use compliance
(WULA / GA
conditions)
33 compliance visits
conducted. Inspections on
water users with valid
permits were carried out,
82.5% reached
Validation & Verification of Water Use in
selected Priority Areas
Validation of the BOCMA area done
1 428 verification letters were sent to
water users, exceeding target
with 78.5%
Institutional Engagement
Marketing and communication
6200 people reached through Land Care
camps, Water Week, Youth day and
awareness days
Forums established and
Maintained25 Water Forums
which includes the Masazane Women’s
Water Forum, National Institute of the deaf, WUAs and Irrigation
Boards were supported
3 new partnerships established
Regulate Water Management InstitutionsDue to he Gazetted Water Policy Review
the target for finalisation of new
Water User Associations could not
be reachedDue to the Gazetted Water Policy Review
Irrigation Boards could not be transformed
into WUASupport of WUA with
business plan development could not
be done as the proforma business plan was not
finalised
Contribution To Improved Intergovernmental Relations And Capacity Building
WATER ALLOCATION REFORM
Support and facilitation for resource-poor
farmers
Assisted with 22 water use
enquiries with Water Allocation
Reform, 77% more than target
9 RPF applications for O&M capital
costs recommended through CCAW
192 Rain Water Harvesting Tank applications facilitated• 63 erected as
part of World Food day as joint project between BGCMA, DOA and DWS
RESOURCE PROTECTION:Quality monitoring, Riparian Integrity
Resource Protected
Alien clearing and River Rehabilitation
programmes still continue in the Upper and Central Breede
River
BGCMA assisted DWS with 13
enforcement cases thorough initial
investigations and confirmations of illegal activities
National Eutrophication and
Microbiological Monitoring projects
sampled on behalf of DWS
64 Water Quality Monitoring points
sampled (including pollution incidents)
Strategic Support: Human Resources Water Resources Management
Water Resource Planning Water Use Management Institutional Engagement Water Allocation Reform Resource Protection
Performance information
Strategic SupportHuman Resources
OUTCOMES OUTPUTS
Performance Measures 2014/15 Results Comments
Policies developed 1 1 (achieved) Organisational Strengthening
Policies Reviewed 1 1 (achieved) Organisational Strengthening
Number of Personnel Recruited 2 2 (achieved) Organisational
DevelopmentPerformance Management Reports 29 29 (achieved) Organisational
StrengtheningNumber of signed evaluations for all staff 1 1 (achieved) Organisational
strengthening
Number of Leave Up-date reports 12 12 (achieved)
Management control & monitoring
Number of Labour issues managed Nil Nil Employee
Relations
Performance Information: Water Resource Planning
OUTCOMES OUTPUTSPerformance Measures 2014/15 Results Comments
Number of CMS documentation completed
Approved Gazetted CMS
BGCMA CMS development in process
BGCMA establishment finalised 2014/2015
Number of land use planning and rezoning applications commented on
140 320Demand drive. Difficult to predict.
Number of Engagements with Local Authorities 7
Local Authorities engaged in 50 issues
Unforseen issues
Water Quality Objective Reports completed Onrus River
Onrus River Water Quality Objectives Report finalised
Salinity Management Plan Salinity Management Plan
Salinity Management Plan finalised
Infrastructure Status quo report
2 Status Quo Report
1 Status Quo Report finalised
Langeberg Municipality reviewed the Water Services Development Plans for the Municipal area. (4 towns)
Onrus Surface – Groundwater interaction study
Collaboration of monitoring data
Onrus Surface Groundwater interaction study report finalised
Performance Information: Water Use Management
OUTCOMES OUTPUTS
Performance Measures 2014/15 Results Comments
Number of water users registered 500 373
Incomplete registration application forms and lack of feedback from applicants hampered the finalisation of applications.
Number of “Record of Recommendations” to DWS 16 9
Applications received remained incomplete after requests for information was done. These files will be prioritised during 2015/16 and may be declined due to incomplete information.
Number of General Authorisation confirmed 26 65
Increased applications for section 21 (c) and (i) due to River Maintenance Management Plans
Number of Audit for water use compliance reports 40 33
82% of target reached. Action plan already in place to reach target for 2015/16
Number of letters to apply for the verification of water use.
800 1 428 More properties with water use that was originally envisaged.
Performance Information: Institutional Stakeholder
RelationsOUTCOMES OUTPUTS
Activities Performance Measures2014/20
15Result
sComments
The BGCMA activities marketed and communicated to stakeholders
Number of persons reached during water campaigns (water week, land care, etc.)
1 600 6 200High interest from learners in water campaigns.
Number of newsletters 4 4
HDI financial support in water related projects
Number of HDI projects supported in water related projects
10 17
Forums Established and maintained
Number of existing water related forums supported
14 25
Water management institutions regulated
Number of new WUA applications finalised
1 None
The Minister gazetted the Water Policy review for comment which halted applications.
Number of IB transformed 3 NoneMoratorium was placed on transformation of IB’s
Number of existing WUA supported with development of Business plans
4 0
The pro-forma business plan was not approved and could not be implemented
Institutional cooperation
Number of new partnerships established and maintained
2 3The BGCMA was approached for an additional partnership.
Performance Information: Water Allocation Reform
OUTCOMES OUTPUTS
Performance Measures 2014/15 Results Comments
Number of RPF / HDI assisted with water use 5 22 Demand driven.
Number of RPF / HDI assisted with financial applications for Government subsidies
5 264
9 x RPF Applications for O&M & Capital Costs
192 Rain water harvesting tank applications received & assisted with. 63 Rain water harvesting tanks were erected as part of World Food day project in Suurbraak in a joint project between BGCMA, DOA and DWS
Performance Information: Water Resource Protection
OUTCOMES OUTPUTS
Performance Measures 2014/15 Results Comments
Number of DWS Water Quality monitoring projects sampled (NEMP & NMMP)
2 2 NEMP & NMMP
Number of BGCMA water quality points monitored 50 64
Additional points because of pollution incidents and a demand for more water quality data from water users.
Number of warning letters/directives issued 20 13
Only 13 CME cases were reported to the BGCMA which was investigated with the DWS CME unit.
FINANCIAL REPORT 2014/15
THE BREEDE-GOURITZ CATCHMENT MANAGEMENT AGENCY RECEIVED AN UNQUALIFIED AUDIT REPORT
FOR THE FINANCIAL YEAR 2014/15
Statement of Financial Performance:
Income and Expenditure Financial Report
STATEMENT OF FINANCIAL PERFORMANCEINCOME AND EXPENDITURE FINANCIAL REPORT
ITEMS 2013/14 2014/15
Revenue23 625 000 40 787 311
Other Income34 210 1 364
Operating expenditure(26 268 423) (24 384 331)
Operating Surpluses/deficit (2 609 213) 16 404 344
Interest received322 683 277 952
Gain on insurance proceeds 7 239 -Surplus/Deficit for the year (2 279 291) 16 682 296
Statement of Financial Performance:
Overview of Actual Expenditure
OVERVIEW OF ACTUAL EXPENDITURE:
ITEMS 2013/14 2014/15 2014/15Audited Audited %
EMPLOYEE COSTS 13 141 603 14 484 871 59,40%
TOTAL GOODS AND SERVICES 12 543 837 9 335 553 38,29%
TOTAL CAPITAL OUTLAY 257 640 64 104 0,26%
TOTAL BOARD RELATED COSTS 328 493 499 803 2,05%
GRAND TOTAL 26 271 573 24 384 331 100%
Detailed Actual Expenditure
20121/13 - 2014/15
ACTUAL EXPENDITURE: OPERATIONAL ACTIVITIES
OPERATIONAL ACTIVITIES
Audited Outcomes
2012/13R’000
2013/14R’000
2014/15R’000
Advertising -99 -234 348
General Expenses -1 892 -2 406 -2 195
Computer expenses -222 -475 -311
Consultant & professional fees -34 -425 -114
CMS development/ water resource management
-6 530 -6 302 -4 192
Salaries , allowances and benefits -10 878 -13 141 -14 485
Stipend - board members -412 -328 -500
Travel & accommodation -1 177 -1 538 -859
Recruitment costs -282 -223 -211
Hiring & rentals -686 -795 -749
Motor vehicle expense -82 -96 -109
Repairs & maintenance -20 -25 -11
Training fees -276 -280 -300
Total Expenditure -23 453 -26 268 -24 384
Detailed Actual Expenditure
20121/13 - 2014/15continues
ACTUAL EXPENDITURE: OPERATIONAL ACTIVITIES
OPERATIONAL ACTIVITIES
Audited Outcomes
2012/13R’000
2013/14R’000
2014/15R’000
Revenue 19 000 23 625 40 787
Other Income 424 34
1
Less: Operating expenses -23 453 -26 268 -24 384
Operating surplus/deficit -4 029 -2 609
16 404
Capital expenditure (included in total expenditure) 412 257
64
We never know the worth of water till the well is dry.