Are hydropower investment in Nepal economically viable
-
Upload
dilip-jena -
Category
Documents
-
view
79 -
download
3
Transcript of Are hydropower investment in Nepal economically viable
1
Are hydropower investments economically viable for Nepal? Applying cost and benefit analysis tool for economic analysis of hydropower investments
2
TABLE OF CONTENT
Are hydropower investments economically viable for Nepal? Applying cost and benefit analysis tool for economic analysis of hydropower investments 1
Abstract 4
1. Introduction 6
2. Literature review 7
2.1. Approach of economists and funding agencies 7
2.2. Approach of Federal Electricity Regulatory Commission (FERC) (USA) for hydropower 10
2.3. Approach of Reventazon Hydroelectric Project (PHR) in Costa Rica 12
3. Methodology 15
3.1. Scenarios 15
3.2. Hypothesis 16
3.3. Approach and key assumptions 17
4. Results, Interpretation and Recommendations 21
4.1. Results for Scenario 1 21
4.2. Results for Scenario 2 24
4.3. Interpretation of results and key recommendations 27
5. Conclusion 30
6. Bibliography 31
3
TABLE OF TABLES
Table 1: Costs of economic analysis ......................................................................................9
Table 2: benefits of economic analysis................................................................................ 10
Table 3: FERC’s cost and benefit elements for re-licensing hydropower project ............. 11
Table 4: PHR hydropower project- technical details ........................................................... 13
Table 5: PHR hydropower project- cost benefit analysis approach ................................... 13
Table 6: Basis of calculations of cost and benefits for Nepal Hydropower development . 17
Table 7: Other key details for data analysis ........................................................................ 20
Table 8: NPV, EIRR and Benefit/Cost Ratio for Scenario 1 ............................................... 21
Table 9: Sensitivity analysis for Scenario 1......................................................................... 21
Table 10: NPV, EIRR and Benefit/Cost Ratio for Scenario 2............................................. 24
Table 11: Sensitivity analysis for Scenario 2....................................................................... 24
TABLE OF FIGURES
Figure 1: Economic analysis process .....................................................................................8
Figure 2: CBA of Tanahu Hydropower Project, Nepal ...........................................................8
Figure 3: Methodology for economic analysis for hydropower licensing by FERC ........... 11
Figure 4: Supply against peak system load ........................................................................ 15
4
Abstract
It is ironic to state that Nepal has hydropower potential of 83,000 MW and yet the
country observed a load shedding of 12 hours per day per consumer in 2013. Apart from
the difficulties faced by connected consumers, 60% of population doesn’t have access to
electricity. World Bank (2013) cites poor reliability and access to power as most serious
infrastructure bottlenecks for economic development of Nepal. The timely development of
hydropower sector in cost-effective way requires assessment of the costs and benefits
related to the hydropower sector investments.
This research paper seeks to find the answer for research topic – “Are hydropower
investments economically viable for Nepal? Applying cost and benefit analysis tool for
economic analysis of hydropower investments”.
Literature review for carrying out CBA of hydropower investments is followed by the
methodology, results & interpretation of economic analysis. The paper finally presents
recommendation.
Word Count: 4160
5
Abbreviations
CBA Cost and Benefit Analysis
CIF Cost, Freight & Insurance
EIRR Economic Internal Rate of Return
FERC Federal Electricity Regulatory commission
FPA Federal Power Act
IRR Internal Rate of Return
kWh Kilo watt hour
MW Mega watt
NEA Nepal Electricity Authority
NPV Net Present Value
6
1. Introduction
It is ironic to state that Nepal has hydropower potential of 83,000 MW (The World Bank,
2013) and yet the country observed a load shedding of 12 hours per day per consumer
in 2013 (Nepal Electricity Authority, 2013). Apart from the difficulties faced by connected
consumers, 60% of population doesn’t have access to electricity (Hydroelectricity
Investment & Development Company Limited, 2013). World Bank (2013) cites poor
reliability and access to power as most serious infrastructure bottlenecks for economic
development of Nepal. Therefore it is important for Nepal to focus on increasing reliability
and accessibility of electricity for its population through development of Hydropower
project in cost-effective manner as stated by the World Bank:
“Increasing access to electricity in a timely and cost-effective manner is one of the most
significant development challenges facing Nepal today.”
The timely development of hydropower sector in a cost-effective way requires
assessment of the costs and benefits related to the hydropower sector investments. The
hydropower investment costs are generally huge and may require host government to set
aside a greater proportion of limited resources for its development, therefore such
investments must be carefully analysed using economic analysis tools. One of such tools
is cost-benefit analysis (CBA) (B., 2011).
This research paper seeks to find the answer for research topic – “Are hydropower
investments economically viable for Nepal? Applying cost and benefit analysis tool for
economic analysis of hydropower investments”
The second chapter presents literature review for carrying out economic analysis of
hydropower investments followed by the methodology for economic analysis of the
hydropower investments in Nepal in the third chapter. The fourth chapter presents the
results & interpretation of the economic analysis followed by recommendations. The fifth
chapter presents the conclusion.
7
2. Literature review
While there is a vast amount of literature on economic analysis of investment projects, it
is important to understand the views offered by the economists, governments, regulatory
agencies as well the donors or funding agencies for hydropower project. Standard
literature (B., 2011) (Squire & Tak, 1975) discuss the central problem facing all
economies i.e. the limited availability of resources for allocation. In addition, the concern
over the limited availability of natural resource, like flowing water from which hydropower
is harnessed, dates back to the days of Malthus (Malthus, 1798). Tools for economic
analysis help in making such allocation decisions by measuring costs and benefits and
then by comparing them. If benefits exceed the costs then investments should be made
or resources should be allocated, else, rejected (B., 2011). Elements of economic
analysis of hydropower projects have essentially the same elements as any other project
but industry specific issues are also valued. The next paragraphs have been divided into
three broad economic analysis approaches as listed below:
Approach of economists and funding agencies (including Asian Development Bank);
Approach of Federal Energy Regulatory Commission (USA) for hydropower; and
Approach of Project Developer: Reventazon Hydroelectric Project (PHR) in Costa
Rica.
2.1. Approach of economists and funding agencies
2.1.1. Objective of economic analysis
The objective of a society is of paramount importance and the economic analysis of
hydropower investments must measure the extent to which the investment project
deviates or promotes achievement of society’s objective (Squire & Tak, 1975). In other
words enhanced incomes for investments or consumptions through better allocation of
resources may also be termed as the purpose of economic analysis (Asian Development
Bank, 1997). The traditional practices of economic analysis focused on maximisation of
economic growth or national income (Squire & Tak, 1975). The belief was that the equity
objective could be met by redistributing the maximum economic benefits through subsidy
or taxation programmes. This led to less focus on equity objective as growth objective
always valued the income generated from investment or consumption activity equally.
8
The shadow prices, of input (consumed by project) or output (produced by project) which
would have better reflected the contribution to society, were ignored over the prevailing
market prices (Squire & Tak, 1975). However situations are changing and valuations are
being done more or less considering shadow pricing, wherever appropriate, of inputs and
outputs to society. In subsequent paragraphs, this paper focuses on the process and
elements of cost and benefits analysis.
2.1.2. Process followed in economic analysis
The process followed in cost and benefit analysis may graphically be depicted as in
Figure 1:
Figure 1: Economic analysis process
2.1.3. Costs and benefits in economic analysis
Before we discuss key elements of cost and benefits, the economic analysis of Tanahu
hydropower project (144 MW) in Nepal, funded by Asian Development Bank is
summarized below (Asian Development Bank, 2013).
Figure 2: CBA of Tanahu Hydropower Project, Nepal
Identification of project (Assumption
stage)
• At this stage the project is identified and assumptions are developed for project conceptualisation
Identification and estimation of costs and benefits related
to investments
• At this stage costs and benefits related to project are identified
• The cost and benefits are valued
Comparisions of cost and benefits
• At this stage the cost and benefits are compared and conclusions are drawn
Tanahu Hydropower Project, Nepal
Costs
Valuation of traded inputs: Border price equivalent values
Valuation of non-traded inputs: World price numeraire*(1/Shadow Price (1.07)) Estimates of capital costs and O&M cost: Detailed project report
Treatment of data: adjustment to remove taxes, financing costs and contingencies
Benefits
Benefits: 527.92 GW, Average resource cost savings- US$ 0.279/kWh
Valuation: Incremental Benefits- measure of willingness to pay; non incremental – alternative energy consumed.
Economic Analysis Results
NPV (@12%): US$ 160 million EIRR: 18.40 %
Source: Asian Development Bank
9
2.1.4. Costs in hydropower investments
The basic principle of cost estimation is to find out the costs of additional resources
required for the hydropower project. It is essentially the difference in costs between “with
and without” project situations (Asian Development Bank, 1997). The proper measure of
economic cost is opportunity cost (B., 2011). The main cost elements of hydropower
projects are as presented in Table 1:
Table 1: Costs of economic analysis
Cost element/type Description
System cost Past projects in Nepal have focused on costs incurred in creating
complementary facilities (e.g. approach roads, transmission lines)
for realising the benefits of hydropower investments(Asian
Development Bank, 1997)
Sunk costs Sunk costs are not used in economic analysis for new hydropower
projects (Asian Development Bank, 1997)
Contingencies The contingencies resulting from engineering challenges of
hydropower are considered.
Working capital Only those inventory costs which claim additional resources of the
nation are considered as working capital for economic analysis.
Transfer payments Since taxes, subsidies and duties are considered in price therefore
transfer payments are not considered separately
Depreciation It’s not considered in economic analysis.
External costs For hydropower projects the external costs like environmental
pollution and noise pollutions are minimal
Source: Asian Development Bank, 1997, Subhes, 2011
10
2.1.5. Benefits
The main benefits are as presented in Table 2:
Table 2: benefits of economic analysis
Benefit element/type Description
Sales Sales of power (incremental and non-incremental) are
considered for economic analysis in Nepal hydropower
investments (Asian Development Bank, 1997)
Pollution reduction Benefits on account of pollution reduction is included in cost
benefit analysis
Unquantifiable benefits Unquantifiable benefits such as improvement in scenic beauty
Source: Asian Development Bank, 1997, Subhes, 2011
2.1.6. Valuations, comparison and sensitivity
Valuations: Valuations are done at shadow pricing. Shadow price would exist if
market operates perfectly and resources are allocated efficiently (B., 2011).
Comparison: The cost benefit analysis may be compared using NPV (positive
NPV is preferred), benefit to cost ratio (ratio greater than ‘1’ are preferred) and
EIRR (greater it is better is the viability.)
Sensitivity: Sensitivity analysis is carried out to measure the impact on NPV and
EIRR by changing the various variables of investments. The variables for which
the project viability is highly sensitive are further analysed and mitigation measures
are designed (Asian Development Bank, 1997).
2.2. Approach of Federal Electricity Regulatory Commission (FERC) (USA) for hydropower
FERC is empowered under Federal Power Act (FPA) to issue hydropower licenses for
non-federal projects and it has jurisdiction has over two third of the hydropower project in
USA (U.S. Fish & Wildlife Service, 2014). For issuance of license FERC carries out cost
benefit analysis based on methodology presented in Figure 3.
11
Annual Gross
Power
Benefit
Annual
Benefits of
avoided
pollution
Annual Costs
of Operation
Annual
Benefits of
Project
Service
Annual Costs
of
Environmental
Measure
Annual
Benefits of
Environment
al Measure
Power
Generation
Environmental
Measures
Project
Operation
Annual Net
Benefits
+
=
+ - + -
Framework of FERC’s Economic Analysis Methodology
Colored boxes indicate the quantified benefits and dotted boxes indicate parameters which
are quantified qualitatively or not taken into consideration for evaluation
Figure 3: Methodology for economic analysis for hydropower licensing by FERC
Source: U.S. Fish and Wildlife Service, 2014
The methodology presented in Figure 3 is explained at Table3.
Table 3: FERC’s cost and benefit elements for re-licensing hydropower project
Parameters Cost/ Benefit elements Explanations
Power Generation Annual Gross Power
Benefits
These are avoided cost for sourcing
power from alternative (coal fired)
sources
Annual Benefits of
avoided pollution
These are avoided cost of pollution due
to securing power from the hydropower
project
12
Parameters Cost/ Benefit elements Explanations
Project Operation Annual Costs of
Operation
It reflects the past and future costs of
investments and current operation &
maintenance of costs
Annual Benefits of
Project Service
The annual benefits due to flood control,
irrigation, navigable waterways and water
supply
Environmental
Measure
Annual Costs of
Environmental
Measure
Direct cost introduced to mitigate the
damage to environment
Annual Benefits of
Environmental
Measure
May result in fish & wildlife improvement,
recreational facilities etc.
Source: U.S. Fish and Wildlife Service, 2014
There have been some important recommendations for improvement in this methodology
by U.S. Fish and Wildlife Service; few of them are listed below:
Discount rate for evaluation to be lowered to two to seven percent instead of ten
percent.
Plant life of 30 years or more to be considered.
Market price of electricity should be used for evaluation instead of least cost
thermal coal option.
2.3. Approach of Reventazon Hydroelectric Project (PHR) in Costa Rica
PHR is a new hydropower project with a capacity of 305 MW on Reventazon River in
Costa Rica (John A. Dixon, Inter American Development Bank, 2013, 2013). The details
of project are as presented in Table 4:
13
Table 4: PHR hydropower project- technical details
Project Parameters Remarks
Height of dam 130.0 meters
Flooding area 6.9 sq. km. (690 Ha)
Reservoir length 8.0 km
River diversion 4.2 km
Project cost US$ 1380 million
Project life 40 years
The economic analysis was carried out to assess the impact of mitigation measures. This
is also known as expanded or enhanced CBA. The CBA analysis results for PHR are
presented at Table 5:
Table 5: PHR hydropower project- cost benefit analysis approach
Cost benefit
analysis
Remarks CBA results
Normal CBA
(CBA 1)
Costs (normal project costs)
+ Benefits (normal cost benefits)
US$115.16 million
Second CBA
(CBA 2)
Costs (normal project cost + unmitigated
environmental cost)
+ Benefits (normal project benefits + positive
environment externalities)
US$88.99 million
Enhanced CBA
(CBA 3)
Costs (normal project costs+ costs of
environmental intervention after project re-
design + remaining environmental costs after re-
design)
+ Benefits (normal project benefits + positive
environment externalities +additional benefits
after mitigation, if any)
US$96.85 million
14
Table 5 shows that environmental mitigation measures improve CBA.
The next chapter discusses the CBA approach to be followed for the Nepal’s hydropower
investments.
15
3. Methodology
Nepal’s hydropower investments would be analysed using CBA tool. Analysis approach
will draw from the experiences of FERC along with the enhanced CBA from PHR, Costa
Rica. Further, the CBA will be carried out for following scenarios.
3.1. Scenarios
3.1.1. Scenario 1: Capacity addition in line with Nepal Electricity Authority (NEA) projections
Scenario 1 is situation where Nepal develops its hydropower potential to meet its
projected internal peak demand (Appendix A).
In 2013, the peak demand of power in Nepal was 1094.62 MW, however the available
supplies were 719.6 MW. The power supply mix against demand is as shown in
Figure 4.
This scenario is based on the projected peak load of the system given by the NEA.
It is assumed that the unmet peak demand is mainly met by adding hydro-power
capacity.
Figure 4: Supply against peak system load
Source: Nepal Electricity Authority, 2013
607 , 56%
10 , 1%
103 , 9%
375 , 34%
Power supply- source wise (in MW and percentage)
HYDRO (NEA+IPP+Others)
NEA Thermal
Power Imports from India
Unment Demand
16
3.1.2. Scenario 2: Rapid capacity additions
Nepal develops its hydropower project for internal demand and exports (Appendix A).
In this hypothetical scenario, Nepal develops its hydropower potential rapidly to meet
internal as well as external demand from India.
The hydropower capacity expansion stop on reaching capacities which are close to
43,000 MW as this is the maximum exploitable economical limit (Hydroelectricity
Investment & Development Company Limited, 2013).
3.2. Hypothesis
3.2.1. Uneconomic Investment
The investments in hydropower sector are uneconomic if economic analysis of “Scenario
1” gives following results:
NPV is negative; or
EIRR is less than 10%; or
Benefit to cost ratio is less than one.
3.2.2. Economic Investment
The investments in the hydropower sector in Nepal are economic, if CBA of “Scenario 2”
gives following results:
NPV is positive;
EIRR is more than 10%; and
Benefit to cost ratio is more than one.
3.2.3. Conditionally Economic Investment
The investments in hydropower sector in Nepal are conditionally economic if economic
analysis of “Scenario 2” gives following results:
NPV is negative; or
EIRR is less than 10%; or
17
Benefit to cost ratio is less than one.
AND
Economic analysis of “Scenario 1” gives following results:
NPV is positive; and
EIRR is more than 10%; and
Benefit to cost ratio is more than one.
3.3. Approach and key assumptions
Cost and benefit calculation are explained in Table 6
Table 6: Basis of calculations of cost and benefits for Nepal Hydropower development
Parameter Cost/ Benefit
elements
Explanations Values
Power
Generation
Annual
Gross Power
Benefits
For Scenario 1: The gross
power benefit is the avoided
cost of purchase of power
from alternate sources
(imports from India or DG set
generated power). The 2013
average tariff paid by Nepal is
assumed for benefit
calculation.
Tariff rate = US$ 0.07/
kWh (Please refer to
Appendix B). This is far
less than the
assumptions made by
ADB for Tanahu hydro-
project which values
power sales at US$
0.161/kWh (Asian
Development Bank,
2013).
Power generation with
capacity factor of 50%
(International
Renewable Energy
Agency, 2012) by a
unit size plant
18
Parameter Cost/ Benefit
elements
Explanations Values
= 1*50%*8760 MWh =
4380 MWh = 4380000
kWh
Annual Benefits/MW =
US$ 0.07/
kWh*4380000 kWh =
0.3066 ~ US$ 0.31
millions
For Scenario 2: The gross
power benefit is summation of
benefits in scenario 1 and
benefits from power exports.
Prevailing tariffs in India are
assumed to be market prices.
Tariff rate = US$ 0.071/
kWh (Please refer to
Appendix C)
Annual Benefits/MW =
US$ 0.071/ kWh *
4380000 kWh = US$
0.3109 ~ US$ 0.31
million
Annual
Benefits of
avoided
pollution
For benefits of avoided
pollution, prices of CO2
would be multiplied to the
annual avoided CO2. It is
assumed that the Carbon
Emission Reduction (CER)
benefits will be equally shared
between Nepal and India
Avoided CO2 = 3345 t
CO2 /MW/ Year (CDM
– Executive Board,
2012)
Assumed price of 1 t
CO2 = US$ 11.56
(CDC Climat
Research, 2012) =
US$ 38668/MW/year ~
US$ 0.0387 million
Benefits to Nepal =
50%*US$ 0.0387 ~
0.0193 million
19
Parameter Cost/ Benefit
elements
Explanations Values
/MW/year
Project
Operation
Annual
Costs of
Operation
The following costs have
been considered:
Incremental capital costs
needed for installation of
unit size plant has been
arrived by the key
projects undertaken in
Nepal since 2000
onwards.
Cost of unit generation
has been taken from the
NEA.
Economic cost of land is
taken separately by
assuming that every 100
MW plant creates a
reservoir of 2 sq. km. =
200 hectares and this
translates to 2 Ha/ MW. It
is further assumed that
5% of this land supports
agriculture = 0.1 Ha/MW
Cost of investment =
US$ 2.28 million/ MW
(Please refer Appendix
D)
Cost of generation =
US$ 0.0148/kWh
(Please see Appendix
B)
Annual Cost/MW =
US$ 0.0148/kWh*
4380000 = US$ 0.0648
~ 0.07 millions
Economic cost of one
hectare land = US$
61182.00/year (Please
see Appendix E) = US$
0.0061 million
MW/Year
Annual
Benefits of
project
service
The annual benefits from
services is assumed to be
zero as it is difficult to quantify
the benefits
It is assumed to be zero
Environme
ntal
Annual
Costs of
Costs of environmental
measure are assumed to be
US$ 0.02 million/ MW/
Year
20
Parameter Cost/ Benefit
elements
Explanations Values
Measure Environment
al Measure
US$ 1 million for every 50
MW of capacity addition.
These estimates are quite
close to the values assumed
in PHR, Costa Rica analysis.
Annual
Benefits of
Environment
al Measure
Since such benefits are
difficult to measure in light of
limited data, it has been
assumed to be zero.
It is assumed to be zero
Table 7 consists of other key assumptions
Table 7: Other key details for data analysis
Other parameters Values, if any Rationale
Life of
hydropower
projects
30 to 50 years FERC considers life to be more than 30. Nepal uses
50 years for evaluation purpose (Department of
Electricity Development, Ministry of Energy, 2003)
Discount Rate 10% Suggested for evaluation by Department of
Electricity Development, 2003
Prices used 2013 prices All prices are 2013 prices; 1 US$ = NRs.98.14
(Nepal Rastra Bank, 2014)
21
4. Results, Interpretation and Recommendations
4.1. Results for Scenario 1
(Please Refer to Appendix F)
Table 8: NPV, EIRR and Benefit/Cost Ratio for Scenario 1
Case NPV (US$ millions) EIRR
Benefit/Cost ratio
(B/C)
Case with benefits
from CER included 423.94 11.30% 1.08
Case without the
benefits from CER 62.18 10.20% 1.01
Table 9: Sensitivity analysis for Scenario 1
Sensitivity Graph
1. Sensitivity with respect to changes in investment costs
0%
2%
4%
6%
8%
10%
12%
14%
16%
$0.00
$0.20
$0.40
$0.60
$0.80
$1.00
$1.20
$1.40
-30% -20% -10% 0% 10% 20% 30%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
22
Sensitivity Graph
2. Sensitivity with respect to changes in operating costs
3. Sensitivity with respect to changes in environmental mitigation costs
0%
2%
4%
6%
8%
10%
12%
14%
$0.00
$0.10
$0.20
$0.30
$0.40
$0.50
$0.60
$0.70
$0.80
-30% -20% -10% 0% 10% 20% 30% 40%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
10%
10%
10%
10%
11%
11%
11%
11%
11%
$0.00
$0.05
$0.10
$0.15
$0.20
$0.25
$0.30
$0.35
$0.40
$0.45
0% 20% 40% 60% 80% 100% 120%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
23
Sensitivity Graph
4. Sensitivity with respect to changes in avoided costs of power purchased from other sources (tariff)
5. Sensitivity with respect to changes in price of CER
0%
2%
4%
6%
8%
10%
12%
14%
16%
$0.00
$0.20
$0.40
$0.60
$0.80
$1.00
$1.20
$1.40
$1.60
$1.80
-10% -5% 0% 5% 10% 15% 20% 25%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
10%
10%
10%
11%
11%
11%
11%
11%
12%
12%
12%
$0.00
$0.10
$0.20
$0.30
$0.40
$0.50
$0.60
$0.70
-150% -100% -50% 0% 50% 100%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
24
4.2. Results for Scenario 2
(Please Refer to Appendix g)
Table 10: NPV, EIRR and Benefit/Cost Ratio for Scenario 2
Case NPV (US$ millions) EIRR Benefit/Cost ratio
(B/C)
Case with benefits
from CER included 6143.92 11.56% 1.09
Case without the
benefits from CER 1738.97 10.45% 1.03
Table 11: Sensitivity analysis for Scenario 2
Sensitivity Graph
1. Sensitivity with respect to changes in investments costs
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
$14.00
$16.00
$18.00
-30% -20% -10% 0% 10% 20% 30%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
25
Sensitivity Graph
2. Sensitivity with respect to changes in operating costs
3. Sensitivity with respect to changes in environmental mitigation costs
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
-30% -20% -10% 0% 10% 20% 30% 40% 50%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
9.80%
10.00%
10.20%
10.40%
10.60%
10.80%
11.00%
11.20%
11.40%
11.60%
11.80%
$0.00
$1.00
$2.00
$3.00
$4.00
$5.00
$6.00
$7.00
0% 100% 200% 300% 400% 500%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
26
Sensitivity Graph
4. Sensitivity with respect to changes in avoided costs of power purchased from other sources (tariff)
5. Sensitivity with respect to changes in price of CER
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
$0.00
$5.00
$10.00
$15.00
$20.00
$25.00
-15% -10% -5% 0% 5% 10% 15% 20% 25%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
10%
10%
11%
11%
11%
11%
11%
12%
12%
12%
12%
12%
$0.00
$1.00
$2.00
$3.00
$4.00
$5.00
$6.00
$7.00
$8.00
$9.00
-150% -100% -50% 0% 50% 100%
Bil
lio
ns
NPV (@10% dicount rate) EIRR
27
4.3. Interpretation of results and key recommendations
Parameters Explanations
Economic viability of
hydropower
investments
Interpretation
Results of Scenario 1 and Scenario 2 demonstrate economical
viability of hydropower investments in Nepal. In both cases NPV
is positive, EIRR is more than 10% and B/C is greater than 1.
Therefore, as per hypothesis, the hydropower investments in
Nepal are economic.
Recommendation
Nepal should continue to develop its hydropower project to not
only meet its internal peak system demand but also to meet the
needs from India. Nepal may resort to rapid capacity additions if
required. These results are in consonance with the views of the
World Bank (The World Bank, 2013)
Investment costs Interpretation
Nepal’s hydropower development is economically sensitive to the
investment costs. Though, at average costs of US$ 2.28
million/MW, the hydropower development is economical but if
costs of development rise by more than 10% then the capacity
addition targets might not be economically viable.
Recommendation
It may be important for Nepal to develop large hydro projects
where economies of scale may be realised. Recently Nepal has
been trying to attract foreign investments in medium and large
hydropower investments (New Spotlight News Magazine, 2013)
Further, Nepal may resort to competitive bidding for developing
hydropower projects with multiple stages of bidding where in initial
stages technical competency of parties are evaluated. Once the
technical evaluation is done, the technically shortlisted parties
may be asked to submit their price offer and final selection is
made only on the least cost basis (least tariff or least EPC). This
28
Parameters Explanations
is consistent to Nepal’s Hydropower Development Policy, 2001
(Ministry of Energy, 2001)
Operating costs Interpretation
Hydropower investments are moderately sensitive to the changes
in operating costs and are uneconomical when operating costs
inflate more than 30% (Scenario 1) or 40% (Scenario 2).
Recommendations
Though the economic viability is moderately sensitive to the
operating costs, the need for keeping the costs low are important
as they provide for:
Avenues of possible low tariff for impoverished population; and
Generating reasonable profit margins for sustaining
operations.
NEA may like to identify high cost items in its operating costs and
take proactive action to minimise them for current and new
projects (Nepal Electricity Authority, 2013).
Environmental
mitigation costs
Interpretation
Hydropower investments are less sensitive to the environmental
mitigation costs. Even a 100% (Scenario 1) or 400% (Scenario 2)
increase in mitigation costs keeps the NPV of investments
positive.
Recommendations
Wherever possible, the environment mitigation costs may be set
aside for mitigation measures and if needed, may be increased as
well. The PHR project in Costa Rica, has indicated that projects
with economic mitigation costs have more benefits (reflected in
NPV) compared to projects which do not have such mitigation
plans (John A. Dixon, Inter American Development Bank, 2013).
Avoided costs of
power purchased
Interpretation
Hydropower investments are highly sensitive to the avoided cost
29
Parameters Explanations
from other sources
(tariff)
of power from alternate sources. An eight percent reduction in
average prices of power from imports and/or diesel generation
may lead to NPV being negative. Reduction in price of power may
be highly unlikely as average power tariff from alternate sources
are rising at a compounded average annual growth rate of 5%
since 2008 onwards (Appendix E) (Nepal Electricity Authority,
2013).
Recommendations
Nepal should, while planning for hydropower potential, may like to
sell power to industrial consumers in India as they have more
flexibility to pay over and above the market prices. Further these
sales could be through long term Power Purchase Agreement to
secure long terms benefits from investments.
Avoided cost of
pollution. Carbon
Emission Reduction
Benefits
Interpretation
Hydropower investments are not so sensitive to the changes in
the avoided cost of pollution. The avoided cost of pollutions may
be measured from the CER revenues. Registered CER add
another benefit line and may improve the economic viability of the
hydropower investments.
Recommendations
Nepal may like to include consider CER for estimating benefits
specifically for their power exports. The developers need to
proactively register their project for CERs.
30
5. Conclusion
Economic analysis tool used for analysing hydropower investments in Nepal provides a
rather lucid answer to the question set at the beginning of this paper. The objective was
to assess whether the hydropower investments in Nepal is economically viable or not.
Under the adopted methodology and assumptions the answer is “Yes”. This answer is in
consonance with the views of many stakeholders including funding agencies (The World
Bank, 2013) and Government of Nepal (Department of Electricity Development, Ministry
of Energy, 2003).
Also, the scenario where Nepal develops its hydropower projects, not only to meet its
internal peak demand but also for exports of power to India, is economically more viable
than the option where Nepal just meets its internal peak demand. Government of Nepal
may think of rapid hydropower capacity additions as this will help the country in realising
its human development goals (The World Bank, 2013).
Further, the sensitivity analysis results highlighted that investments are highly sensitive to
changes in the capital costs and tariff rates. The economic viability of investments
improves with decrease in development & installation costs. Government may adopt a
policy to invest in large hydro project where economies of scale could be realised.
Further, for reducing development costs government may select developers
competitively.
In addition to above, government may also proactively initiate & support efforts for
efficiency improvement of hydropower operations. Further, government may promote
CER registration for new projects to improve the economic viability of projects.
31
6. Bibliography
Asian Development Bank, 1997. Guidelines for Economic Analysis of Projects. Manila:
Economics and Development Resource Center.
Asian Development Bank, 2013. Tanahu Hydropower Project. [Online]
Available at: http://www.adb.org/sites/default/files/43281-013-nep-ea.pdf
[Accessed 2014 01 2014].
B., S. C., 2011. Economic analysis of energy investments. In: Energy Economics:
Concepts, Issues, Markets & Governance . London: Springer Verlag London Limited, pp.
163,164.
CDC Climat Research, 2012. Will there still be a market price for CERs and ERUs in two
years time?. [Online]
Available at: http://www.cdcclimat.com/IMG/pdf/12-05_climate_brief_no13_-
_supply_demand_for_cer_eru_in_the_ets.pdf
[Accessed 15 01 2014].
CDM – Executive Board, 2012. UPPER MARSYANGDI-2 HYDRO : PROJECT DESIGN
DOCUMENT FORM FOR CDM PROJECT ACTIVITIES (F-CDM-PDD). [Online]
Available at:
https://cdm.unfccc.int/filestorage/q/8/GYSRJLTPV58WNCZ0BA17EOM42IX6KD.pdf/PDD
_Revised_2%20Aug%202012.pdf?t=bHd8bXpmNjFyfDDdYbRuRmSsHRmPpkUAXMUj
[Accessed 15 01 2014].
Department of Electricity Development, Ministry of Energy, 2003. Guideliness for study of
hydropower project. [Online]
Available at: http://www.doed.gov.np/documents/Guidelines-for-Study-of-Hydropower-
Projects.pdf
[Accessed 15 01 2014].
Hydroelectricity Investment & Development Company Limited, 2013. Hydroelectricity
Investment & Development Company Limited. [Online]
Available at: http://www.hidcl.org.np/nepal-hydropower.php
[Accessed 10 01 2014].
32
International Renewable Energy Agency, 2012. RENEWABLE ENERGY
TECHNOLOGIES: COST ANALYSIS SERIES, Abu Dhabi: IRENA Secretariat.
John A. Dixon, Inter American Development Bank, 2013, 2013. An Expanded Cost-
Benefit Analysis (CBA) of the Reventazón Hydroelectric Project (PHR), in Costa Rica,
Washington, D.C.: Inter-American Development Bank, Felipe Herrera Library.
Malthus, T., 1798. An Essay on Principle of Population. London: Electronic Scholarly
Publishing Project.
Ministry of Energy, 2001. The Hydropower Development Policy. [Online]
Available at: http://www.doed.gov.np/policy/hydropower_development_policy_2001.pdf
[Accessed 16 01 2014].
Nepal Electricity Authority, 2013. A YEAR IN REVIEW - FISCAL YEAR 2012/13,
Kathmandu: Nepal Electricity Authority.
Nepal Rastra Bank, 2014. Nepal Rstra Bank. [Online]
Available at: http://www.nrb.org.np/fxmexchangerate.php
[Accessed 14 01 2014].
New Spotlight News Magazine, 2013. More Than Fantastic Hydropower Meet. [Online]
Available at: http://www.spotlightnepal.com/News/Article/More-Than-Fantastic-
Hydropower-Meet
[Accessed 16 01 2014].
Squire, L. & Tak, H. G. v. d., 1975. Economic Analysis of Project: A World Bank
Research Publication, 8th Edition. Baltimore: The International Bank for Reconstruction
and Development/ The World Bank.
The World Bank, 2013. Nepal Overview. [Online]
Available at: http://www.worldbank.org/en/country/nepal/overview
[Accessed 09 01 2014].
U.S. Fish & Wildlife Service, 2014. U.S. Fish & Wildlife Service. [Online]
Available at: http://www.fws.gov/policy/hydrochap1.pdf
[Accessed 13 01 2014].
33
Appendix A. - Projected internal peak demand by NEA and assumed capacity additions under Scenario 1 and Scenario 2
Projected
Demand
(NEA)
Existing Supplies (Real for 2013, assumed
from 2014 onwards)
Scenario 1 (Capacity addition at
normal rate) New assumed
hydropower capacity addition to
meet peak demand
Scenario 2: (Rapid capacity addition) New assumed
hydropower capacity addition (a) to meet peak
demand and (b) to exports power to India
Fiscal
Year
No. of
years
System Peak
Load
HYDRO
(NEA+IPP+
Others) (MW)
NEA Thermal
(MW)
Power
Imports from
India (MW)
Unmet
Demand (MW)
Supplies from
new hydropower
(MW)
Year on year (y-
o-y) capacity
additions (MW)
Year on year (y-
o-y) capacity
additions (MW)
for exports to
India
Year on year (y-
o-y) capacity
additions (MW)
for meeting
Nepal's internal
peak demand
Additional
capacity
additions for
exports (MW)
Total Power
Availability
Actual for 2013
2013 1 1,094.62 607.10 10.00 102.50 375.02 - -
-
Projected by
NEA Assumed Projections from 2014 onwards
2014 2 1,271.70 607.10 10.00 200.00 454.60 454.60 454.60 500.00 454.60 954.60 1,771.70
2015 3 1,387.20 607.10 10.00 100.00 670.10 670.10 215.50 1,000.00 215.50 2,170.10 2,887.20
2016 4 1,510.00 607.10 10.00 100.00 792.90 792.90 122.80 2,000.00 122.80 4,292.90 5,010.00
2017 5 1,640.80 607.10 10.00 100.00 923.70 923.70 130.80 2,500.00 130.80 6,923.70 7,640.80
2018 6 1,770.20 607.10 10.00 100.00 1,053.10 1,053.10 129.40 3,000.00 129.40 10,053.10 10,770.20
2019 7 1,906.90 607.10 10.00 100.00 1,189.80 1,189.80 136.70 3,000.00 136.70 13,189.80 13,906.90
2020 8 2,052.00 607.10 10.00 100.00 1,334.90 1,334.90 145.10 3,000.00 145.10 16,334.90 17,052.00
2021 9 2,206.00 607.10 10.00 - 1,588.90 1,588.90 254.00 3,000.00 254.00 19,588.90 20,206.00
2022 10 2,363.00 607.10 10.00 - 1,745.90 1,745.90 157.00 3,000.00 157.00 22,745.90 23,363.00
34
Projected
Demand
(NEA)
Existing Supplies (Real for 2013, assumed
from 2014 onwards)
Scenario 1 (Capacity addition at
normal rate) New assumed
hydropower capacity addition to
meet peak demand
Scenario 2: (Rapid capacity addition) New assumed
hydropower capacity addition (a) to meet peak
demand and (b) to exports power to India
Fiscal
Year
No. of
years
System Peak
Load
HYDRO
(NEA+IPP+
Others) (MW)
NEA Thermal
(MW)
Power
Imports from
India (MW)
Unmet
Demand (MW)
Supplies from
new hydropower
(MW)
Year on year (y-
o-y) capacity
additions (MW)
Year on year (y-
o-y) capacity
additions (MW)
for exports to
India
Year on year (y-
o-y) capacity
additions (MW)
for meeting
Nepal's internal
peak demand
Additional
capacity
additions for
exports (MW)
Total Power
Availability
2023 11 2,545.40 607.10 10.00 - 1,928.30 1,928.30 182.40 3,000.00 182.40 25,928.30 26,545.40
2024 12 2,741.10 607.10 10.00 - 2,124.00 2,124.00 195.70 3,000.00 195.70 29,124.00 29,741.10
2025 13 2,951.10 607.10 10.00 - 2,334.00 2,334.00 210.00 3,000.00 210.00 32,334.00 32,951.10
2026 14 3,176.70 607.10 10.00 - 2,559.60 2,559.60 225.60 3,000.00 225.60 35,559.60 36,176.70
2027 15 3,418.90 607.10 10.00 - 2,801.80 2,801.80 242.20 3,000.00 242.20 38,801.80 39,418.90
2028 16 3,679.10 607.10 10.00 - 3,062.00 3,062.00 260.20 3,000.00 260.20 42,062.00 42,679.10
Source: Nepal Electricity Authority, 2013 and Author’s assumptions
35
Appendix B. - Average electricity tariff rates in Nepal in 2012 and 2013 (in US$/kWh)
Parameters 2013 2012
Generation expenses (US$/kWh) 0.0044 0.0037
Administration Expenses (US$/kWh) 0.0037 0.0031
Provision for Employee benefits (US$/kWh) 0.0066 0.0132
Total Generation expenses (US$/kWh) – Operating cost for purpose of analysis 0.0148 0.0201
Transmission Expenses (US$/kWh) 0.0016 0.0014
Average Tariff (US$/kWh) from alternate sources
0.0699 0.0703
Average tariff since 2008 from alternative sources: CAGR = 5%
2008 2009 2010 2011 2012 2013
0.05 0.07 0.06 0.06 0.07 0.07
Source: Nepal Electricity Authority (Nepal Electricity Authority, 2013)
36
Appendix C. - Average electricity tariff rates in India in 2013 (in US$/kWh)
Non domestic Domestic Average
State Power tariff rates (US$/kWh) State Power tariff rates
(US$/kWh) State
Power tariff rates
(US$/kWh)
Maharashtra 0.18 Maharashtra 0.14 Maharashtra 0.16
Andhra Pradesh 0.15 West Bengal 0.13 Andhra Pradesh 0.13
Kerala 0.14 Kerala 0.12 West Bengal 0.13
West Bengal 0.13 Andhra Pradesh 0.12 Kerala 0.13
Karnataka 0.13 Madhya Pradesh 0.11 Karnataka 0.11
Andaman & Nicobar 0.12 Delhi 0.10 Delhi 0.11
Delhi 0.12 Karnataka 0.10 Tamil Nadu 0.10
Tamil Nadu 0.11 Punjab 0.09 Andaman & Nicobar 0.10
Odisha 0.11 Tamil Nadu 0.09 Odisha 0.10
Rajasthan 0.11 Haryana 0.09 Rajasthan 0.10
Tripura 0.10 Tripura 0.09 Madhya Pradesh 0.10
Lakshadweep 0.10 Odisha 0.09 Punjab 0.10
Punjab 0.10 Rajasthan 0.09 Tripura 0.10
Uttar Pradesh 0.09 Andaman & Nicobar 0.08 Haryana 0.09
Haryana 0.09 Bihar 0.08 Lakshadweep 0.08
Madhya Pradesh 0.09 Meghalaya 0.07 Uttar Pradesh 0.08
37
Non domestic Domestic Average
State Power tariff rates (US$/kWh) State Power tariff rates
(US$/kWh)
State Power tariff rates
(US$/kWh)
Jammu & Kashmir 0.08 Lakshadweep 0.07 Bihar 0.07
Chattisgarh 0.07 Himachal Pradesh 0.07 Meghalaya 0.07
Meghalaya 0.07 Uttar Pradesh 0.06 Himachal Pradesh 0.07
Puducherry 0.07 Goa 0.06 Jammu & Kashmir 0.07
Bihar 0.07 Jammu & Kashmir 0.05 Goa 0.06
Uttarakhand 0.07 Uttarakhand 0.05 Uttarakhand 0.06
Himachal Pradesh 0.07 Dadra & Nagar Haveli 0.04 Puducherry 0.05
Goa 0.07 Daman & Diu 0.04 Chattisgarh 0.05
Daman & Diu 0.06 Puducherry 0.04 Daman & Diu 0.05
Dadra & Nagar Haveli 0.05 Chattisgarh 0.04 Dadra & Nagar Haveli 0.04
Source: PHD Research Bureau, 2013, (Progress Harmony Development Research Bureau, 2013)
For analysis purpose the prevailing tariffs in state of Bihar, Uttar Pradesh and Himachal Pradesh are used because they are neighbouring state of
Nepal. West Bengal has not been considered in analysis despite being a neighboring state because the tariff were significantly higher than the
average tariff of US$ 0.071/kWh prevailing in other three neighboring states
38
Appendix D. - Investments in hydropower projects in Nepal in 2013 prices (in US$)
Inv estment Years Type Of Costs Name Of The Project Capacity (MW) Cost (Million UE$) Cost Per MW (Million US$/MW)
2014 Onwards Present Estimated Costs (2013) Kulekhani Ii i Hydroelectric Project 14.00 24.76 1.77
Chameliya Hydroelectric Project 30.00 99.90 3.33
Rahughat Hydroelectric Project 32.00 67.00 2.09
Upper Trishuli 3a Hydroelectric Project 60.00 125.78 2.10
Ilam (Puwakhola) Hydropower Station 6.20 15.70 2.53
Trisuli Jalvidyut Company Limited (Tjcl) 42.00 57.73 1.37
Tanahu Hydropower Limited (Thl) 140.00 403.00 2.88
Upper Tamakoshi Hydropower Limited 456.00 441.17 0.97
Sanjen Jalavidhyut Company Limited (Sjcl) 57.30 73.77 1.29
Madhya Bhotekoshi Jalavidhyut Company Limited 102.00 125.16 1.23
Rasuwagadhi Hydropower Company Limited 111.00 139.43 1.26
Bagmati Storage Hydroelectric Project 418.00 875.00 2.09
Uttar Ganga Storage Project 300.00 775.00 2.58
Upper Modi A Hydroelectric Project 335.00 479.00 1.43
2000-2013 Inflation Adjusted Costs (2013) Kali Gandaki 'A' Model Test Project 144.00 843.27 5.86
Middle Marsyangdi 70.00 329.29 4.70
Modi Khola 14.80 18.37 1.24
Average Cost 2.28
Source: Nepal Electricity Authority, 2013 (Nepal Electricity Authority, 2013)
39
Appendix E. - Economic cost of land in 2013 (in US$)
2004 2005 2006 2007 2008 2009 2010 2011 2012
Land Area (Ha) 14,335,000.00 14,335,000.00 14,335,000.00 14,335,000.00 14,335,000.00 14,335,000.00 14,335,000.00 14,335,000.00 14,335,000.00
Percentage of Land
(for agriculture)
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Contribution of
Agriculture to GDP
37% 36% 35% 34% 33% 34% 37% 38% 37%
GDP (US$) 7,273,933,993.00 8,130,258,976.00 9,043,715,356.00 10,325,618,017.00 12,545,438,605.00 12,854,834,975.00 16,010,389,262.00 19,123,129,346.00 18,962,962,963.00
Per Hectare
Contribution (US$/Ha)
23,468.40 25,522.26 27,601.15 30,613.10 36,100.41 38,111.65 51,655.42 63,365.79 61,181.52
Source: The World Bank, 2013 (http://data.worldbank.org/indicator/AG.YLD.CREL.KG)
It is assumed that economic contribution by per hectare of agricultural land in 2013 is same as that of year 2012.
40
Appendix F. - Economic analysis of Scenario 1
Fiscal
Year
No. of
years
Cumulativ
e capacity
(MW)
Year on
year
(y-o-y)
capacity
additions
(MW)
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironm
ental
damage
(US$
millions)
Benefits
from
Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discounti
ng factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
Present
Values of
yearly
Benefits
(US$
millions) 2014 0 454.60 454.60 1,036.49 29.46 2.77 9.09 139.38 8.77 (929.66) 1.00 (929.66) 1,077.81 148.15
2015 1 670.10 215.50 491.34 43.42 4.09 13.40 205.45 12.93 (333.87) 0.91 (303.52) 502.05 198.53
2016 2 792.90 122.80 279.98 51.38 4.84 15.86 243.10 15.30 (93.65) 0.83 (77.40) 290.96 213.56
2017 3 923.70 130.80 298.22 59.86 5.63 18.47 283.21 17.83 (81.15) 0.75 (60.97) 287.14 226.17
2018 4 1,053.10 129.40 295.03 68.24 6.42 21.06 322.88 20.32 (47.55) 0.68 (32.48) 266.89 234.41
2019 5 1,189.80 136.70 311.68 77.10 7.26 23.80 364.79 22.96 (32.07) 0.62 (19.91) 260.68 240.77
2020 6 1,334.90 145.10 330.83 86.50 8.14 26.70 409.28 25.76 (17.13) 0.56 (9.67) 255.24 245.57
2021 7 1,588.90 254.00 579.12 102.96 9.69 31.78 487.16 30.67 (205.73) 0.51 (105.57) 371.30 265.72
2022 8 1,745.90 157.00 357.96 113.13 10.65 34.92 535.29 33.70 52.33 0.47 24.41 241.03 265.44
2023 9 1,928.30 182.40 415.87 124.95 11.76 38.57 591.22 37.22 37.28 0.42 15.81 250.71 266.52
2024 10 2,124.00 195.70 446.20 137.64 12.96 42.48 651.22 40.99 52.94 0.39 20.41 246.47 266.88
2025 11 2,334.00 210.00 478.80 151.24 14.24 46.68 715.60 45.05 69.69 0.35 24.43 242.18 266.60
2026 12 2,559.60 225.60 514.37 165.86 15.61 51.19 784.77 49.40 87.14 0.32 27.76 238.03 265.79
2027 13 2,801.80 242.20 552.22 181.56 17.09 56.04 859.03 54.07 106.21 0.29 30.76 233.73 264.49
2028 14 3,062.00 260.20 593.26 198.42 18.68 61.24 938.81 59.10 126.31 0.26 33.26 229.52 262.78
2029 15 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.24 172.26 66.63 238.89
41
Fiscal
Year
No. of
years
Cumulativ
e capacity
(MW)
Year on
year
(y-o-y)
capacity
additions
(MW)
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironm
ental
damage
(US$
millions)
Benefits
from
Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discounti
ng factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
Present
Values of
yearly
Benefits
(US$
millions) 2030 16 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.22 156.60 60.57 217.17
2031 17 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.20 142.36 55.07 197.43
2032 18 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.18 129.42 50.06 179.48
2033 19 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.16 117.66 45.51 163.17
2034 20 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.15 106.96 41.37 148.33
2035 21 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.14 97.24 37.61 134.85
2036 22 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.12 88.40 34.19 122.59
2037 23 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.11 80.36 31.08 111.44
2038 24 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.10 73.05 28.26 101.31
2039 25 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.09 66.41 25.69 92.10
2040 26 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.08 60.38 23.35 83.73
2041 27 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.08 54.89 21.23 76.12
2042 28 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.07 49.90 19.30 69.20
2043 29 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.06 45.36 17.55 62.91
2044 30 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.06 41.24 15.95 57.19
2045 31 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.05 37.49 14.50 51.99
2046 32 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.05 34.08 13.18 47.26
2047 33 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.04 30.98 11.98 42.97
42
Fiscal
Year
No. of
years
Cumulativ
e capacity
(MW)
Year on
year
(y-o-y)
capacity
additions
(MW)
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironm
ental
damage
(US$
millions)
Benefits
from
Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discounti
ng factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
Present
Values of
yearly
Benefits
(US$
millions) 2048 34 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.04 28.17 10.89 39.06
2049 35 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.04 25.61 9.90 35.51
2050 36 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.03 23.28 9.00 32.28
2051 37 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.03 21.16 8.19 29.35
2052 38 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.03 19.24 7.44 26.68
2053 39 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.02 17.49 6.76 24.25
2054 40 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.02 15.90 6.15 22.05
2055 41 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.02 14.45 5.59 20.04
2056 42 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.02 13.14 5.08 18.22
2057 43 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.02 11.95 4.62 16.57
2058 44 3,062.00 - - 198.42 18.68 61.24 938.81 59.10 719.57 0.02 10.86 4.20 15.06
Present value of all costs : 5,684.66
Present value of all benefits: 6,108.60
Net Present Value: 423. 94
Benefit to Cost Ratio: 1.075 ~ 1.08
Economic IRR: 11.30%
43
Appendix G. - Economic analysis of Scenario 2
Fiscal Year No. of
years
Cumulativ
e capacity
(MW) over
and above
scenario 1
Year on
year
(y-o-y)
capacity
additions
(MW) over
and above
scenario 1
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironme
ntal
damage
(US$
millions)
Benefits
from Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discountin
g factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
including
the costs
of
scenario 1
Present
Values of
yearly
Benefits
(US$
millions)
including
the
benefits of
scenario 1
2014 0 500.00 500.00 1,140.00 32.40 3.05 10.00 156.00 9.65 (1,019.80) 1.00 (1,019.80) 2,263.26 313.80
2015 1 1,500.00 1,000.00 2,280.00 97.20 9.15 30.00 468.00 28.95 (1,919.40) 0.91 (1,744.91) 2,698.73 650.31
2016 2 3,500.00 2,000.00 4,560.00 226.80 21.35 70.00 1,092.00 67.55 (3,718.60) 0.83 (3,073.22) 4,322.49 1,171.86
2017 3 6,000.00 2,500.00 5,700.00 388.80 36.60 120.00 1,872.00 115.80 (4,257.60) 0.75 (3,198.80) 4,979.41 1,719.63
2018 4 9,000.00 3,000.00 6,840.00 583.20 54.90 180.00 2,808.00 173.70 (4,676.40) 0.68 (3,194.04) 5,497.48 2,270.96
2019 5 12,000.00 3,000.00 6,840.00 777.60 73.20 240.00 3,744.00 231.60 (3,955.20) 0.62 (2,455.87) 5,185.08 2,709.30
2020 6 15,000.00 3,000.00 6,840.00 972.00 91.50 300.00 4,680.00 289.50 (3,234.00) 0.56 (1,825.51) 4,885.90 3,050.72
2021 7 18,000.00 3,000.00 6,840.00 1,166.40 109.80 360.00 5,616.00 347.40 (2,512.80) 0.51 (1,289.46) 4,720.93 3,325.89
2022 8 21,000.00 3,000.00 6,840.00 1,360.80 128.10 420.00 6,552.00 405.30 (1,791.60) 0.47 (835.79) 4,322.45 3,511.07
2023 9 24,000.00 3,000.00 6,840.00 1,555.20 146.40 480.00 7,488.00 463.20 (1,070.40) 0.42 (453.95) 4,076.75 3,638.60
2024 10 27,000.00 3,000.00 6,840.00 1,749.60 164.70 540.00 8,424.00 521.10 (349.20) 0.39 (134.63) 3,829.82 3,715.60
2025 11 30,000.00 3,000.00 6,840.00 1,944.00 183.00 600.00 9,360.00 579.00 372.00 0.35 130.38 3,595.35 3,750.16
2026 12 33,000.00 3,000.00 6,840.00 2,138.40 201.30 660.00 10,296.00 636.90 1,093.20 0.32 348.33 3,373.26 3,749.35
2027 13 36,000.00 3,000.00 6,840.00 2,332.80 219.60 720.00 11,232.00 694.80 1,814.40 0.29 525.57 3,162.93 3,719.26
2028 14 39,000.00 3,000.00 6,840.00 2,527.20 237.90 780.00 12,168.00 752.70 2,535.60 0.26 667.70 2,964.24 3,665.20
44
Fiscal Year No. of
years
Cumulativ
e capacity
(MW) over
and above
scenario 1
Year on
year
(y-o-y)
capacity
additions
(MW) over
and above
scenario 1
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironme
ntal
damage
(US$
millions)
Benefits
from Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discountin
g factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
including
the costs
of
scenario 1
Present
Values of
yearly
Benefits
(US$
millions)
including
the
benefits of
scenario 1
2029 15 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.24 2,244.44 915.30 3,332.00
2030 16 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.22 2,040.40 832.09 3,029.09
2031 17 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.20 1,854.91 756.45 2,753.72
2032 18 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.18 1,686.28 687.68 2,503.38
2033 19 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.16 1,532.99 625.16 2,275.80
2034 20 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.15 1,393.62 568.33 2,068.91
2035 21 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.14 1,266.93 516.66 1,880.83
2036 22 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.12 1,151.75 469.69 1,709.84
2037 23 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.11 1,047.05 426.99 1,554.40
2038 24 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.10 951.86 388.18 1,413.09
2039 25 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.09 865.33 352.89 1,284.63
2040 26 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.08 786.66 320.81 1,167.85
2041 27 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.08 715.15 291.64 1,061.68
2042 28 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.07 650.14 265.13 965.16
2043 29 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.06 591.03 241.03 877.42
2044 30 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.06 537.30 219.12 797.66
45
Fiscal Year No. of
years
Cumulativ
e capacity
(MW) over
and above
scenario 1
Year on
year
(y-o-y)
capacity
additions
(MW) over
and above
scenario 1
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironme
ntal
damage
(US$
millions)
Benefits
from Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discountin
g factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
including
the costs
of
scenario 1
Present
Values of
yearly
Benefits
(US$
millions)
including
the
benefits of
scenario 1
2045 31 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.05 488.46 199.20 725.14
2046 32 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.05 444.05 181.09 659.22
2047 33 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.04 403.68 164.62 599.29
2048 34 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.04 366.98 149.66 544.81
2049 35 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.04 333.62 136.05 495.28
2050 36 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.03 303.29 123.69 450.26
2051 37 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.03 275.72 112.44 409.32
2052 38 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.03 250.66 102.22 372.11
2053 39 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.02 227.87 92.93 338.28
2054 40 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.02 207.15 84.48 307.53
2055 41 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.02 188.32 76.80 279.57
2056 42 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.02 171.20 69.82 254.16
2057 43 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.02 155.64 63.47 231.05
2058 44 39,000.00 - - 2,527.20 237.90 780.00 12,168.00 752.70 9,375.60 0.02 141.49 57.70 210.05
Present value of all costs: 69,369.38
Present value of all benefits: 75,513.30
46
Fiscal Year No. of
years
Cumulativ
e capacity
(MW) over
and above
scenario 1
Year on
year
(y-o-y)
capacity
additions
(MW) over
and above
scenario 1
Capital
cost (US$
millions)
Operating
costs
(US$
millions)
Land cost
(US$
millions)
Cost of
mitigation
of
env ironme
ntal
damage
(US$
millions)
Benefits
from Tariff
(US$
millions)
Benefits
from
av oided
pollution
(US$
millions)
Total
(US$
millions)
Discountin
g factor
(US$
millions)
Discounte
d Total
(US$
millions)
Present
Values of
yearly
costs
(US$
millions)
including
the costs
of
scenario 1
Present
Values of
yearly
Benefits
(US$
millions)
including
the
benefits of
scenario 1
Net Present Value: 6,143.92
Benefit to Cost Ratio: 1.088~1.09
Economic IRR: 11.56%