Key Engineering Issues for Economically Viable Ocean Wave ...

53
Key Engineering Issues Key Engineering Issues for for Economically Viable Economically Viable Ocean Wave Energy Conversion Ocean Wave Energy Conversion Michael Raftery Doctoral Candidate, Ocean Engineering Stevens Institute of Technology [email protected] Office: 201 216 8704

Transcript of Key Engineering Issues for Economically Viable Ocean Wave ...

Page 1: Key Engineering Issues for Economically Viable Ocean Wave ...

Key Engineering IssuesKey Engineering Issuesforfor

Economically ViableEconomically ViableOcean Wave Energy ConversionOcean Wave Energy Conversion

Michael RafteryDoctoral Candidate, Ocean EngineeringStevens Institute of [email protected]: 201 216 8704

Page 2: Key Engineering Issues for Economically Viable Ocean Wave ...

AgendaAgenda

•• Survivability is ParamountSurvivability is ParamountDeployment ChallengesDeployment ChallengesOperational ChallengesOperational ChallengesDeployment TechniquesDeployment Techniques

•• StevensStevens’’ Research GoalsResearch GoalsFocus on Commercial ProductionFocus on Commercial ProductionSimplify Deployments & RecoverySimplify Deployments & RecoveryTune Waves to Expand Viable RegionsTune Waves to Expand Viable RegionsPerform Hydrodynamic ResearchPerform Hydrodynamic ResearchPerform ExtremePerform Extreme--Wave Scale Model TestingWave Scale Model Testing

•• AppendixAppendix

Page 3: Key Engineering Issues for Economically Viable Ocean Wave ...

Survivability is ParamountSurvivability is Paramount

•• Deployment, maintenance, and recovery Deployment, maintenance, and recovery logistics, redundancy, faillogistics, redundancy, fail--safes, mooring loads, safes, mooring loads, and buoyant integrity must lead design and buoyant integrity must lead design hierarchyhierarchy

•• Review deployment sinking of the Applied Review deployment sinking of the Applied Research Technology Research Technology Ltd.(ART)/WavegenLtd.(ART)/Wavegen--OSPREY (1996) and Trident Energy DECM OSPREY (1996) and Trident Energy DECM (2009)(2009)

•• Review operational sinking of Review operational sinking of FinaveraFinavera--AquaBuOYAquaBuOY (2007)(2007)

Page 4: Key Engineering Issues for Economically Viable Ocean Wave ...

Deployment ChallengesDeployment Challenges

•• Commercial systems must deploy and maintain Commercial systems must deploy and maintain maximum plate capacity per ship day to be maximum plate capacity per ship day to be economically viableeconomically viable

•• High energy regions have short deployment High energy regions have short deployment windowswindows

•• Large units (100 ton +) are required for Large units (100 ton +) are required for commercial viabilitycommercial viability

•• Two largeTwo large--scale devices have sunk during scale devices have sunk during deploymentdeployment

Page 5: Key Engineering Issues for Economically Viable Ocean Wave ...

ARTART--Wavegen OSPREY 2MW OWCWavegen OSPREY 2MW OWC

http://www.wave-energy.net/Library

Page 6: Key Engineering Issues for Economically Viable Ocean Wave ...

OSPREY Aug 1996OSPREY Aug 1996

Page 7: Key Engineering Issues for Economically Viable Ocean Wave ...

OSPREYOSPREY

•• Sank in August 1996 off Clyde, ScotlandSank in August 1996 off Clyde, Scotland•• 22--3 meter seas ruptured unfilled ballast 3 meter seas ruptured unfilled ballast

tanks during deploymenttanks during deployment•• Ballast tanks required sand for structural Ballast tanks required sand for structural

stabilitystability

Page 8: Key Engineering Issues for Economically Viable Ocean Wave ...

Trident Energy 20 kWTrident Energy 20 kW--DECMDECM

http://www.tridentenergy.co.uk/index.php

Page 9: Key Engineering Issues for Economically Viable Ocean Wave ...

Trident Energy Trident Energy -- DECMDECM

•• 20 Sep 2009 unit overturns during 20 Sep 2009 unit overturns during deploymentdeployment

•• 5 Oct 2009 unit recovered and returned to 5 Oct 2009 unit recovered and returned to LowestoftLowestoft Harbor, Suffolk, England to Harbor, Suffolk, England to assess damages assess damages

Page 10: Key Engineering Issues for Economically Viable Ocean Wave ...

Operational ChallengesOperational Challenges

•• Wave energy provides a low frequency (<1 Hz), high Wave energy provides a low frequency (<1 Hz), high density input which causes dead band issuesdensity input which causes dead band issues

•• Extreme waves typically have 100x the power of average Extreme waves typically have 100x the power of average wave conditionswave conditions

•• Moving arrays to avoid storms is not economically viable Moving arrays to avoid storms is not economically viable or realisticor realistic

•• Commercial systems must operate unmanned for years Commercial systems must operate unmanned for years to be viable to be viable

•• The The FinaveraFinavera--AquaBuOYAquaBuOY sank after 51 days of operation sank after 51 days of operation due to a bilge pump failuredue to a bilge pump failure

•• Buoyant integrity is criticalBuoyant integrity is critical

Page 11: Key Engineering Issues for Economically Viable Ocean Wave ...

FinaveraFinavera AquaBuOYAquaBuOY 250 kW250 kW

Page 12: Key Engineering Issues for Economically Viable Ocean Wave ...

AquaBuOYAquaBuOY DeploymentDeployment

•• 7 Sep 2007 Deployed off Reedsport, Oregon7 Sep 2007 Deployed off Reedsport, Oregon•• 27 Oct 2007 Sank due to bilge pump failure27 Oct 2007 Sank due to bilge pump failure•• The unit did not have a redundant bilge pump The unit did not have a redundant bilge pump

and was negatively buoyant with a flooded and was negatively buoyant with a flooded buoyancy compartmentbuoyancy compartment

•• http://www.theregister.co.uk/2007/11/09/aquabuoy_wave_power_renehttp://www.theregister.co.uk/2007/11/09/aquabuoy_wave_power_renewable_sinkswable_sinks//

Page 13: Key Engineering Issues for Economically Viable Ocean Wave ...

Deployment TechniquesDeployment Techniques

•• Anchors are placed prior to unit Anchors are placed prior to unit deployment, integrated into unit, or deployment, integrated into unit, or placed by towing or support vesselplaced by towing or support vessel

•• Units are loaded on the deck or towed to Units are loaded on the deck or towed to sea by service vesselssea by service vessels

•• Commercial scale units require seafloor Commercial scale units require seafloor cable installation to shorecable installation to shore

Page 14: Key Engineering Issues for Economically Viable Ocean Wave ...

RMERME-- AirWECAirWECtmtm 2 kW Deployment 2 kW Deployment Jan 2009Jan 2009

Courtesy Resolute Marine Energy, Inc. 

Page 15: Key Engineering Issues for Economically Viable Ocean Wave ...

AirWECAirWEC Deployment DetailsDeployment Details

•• AirWECAirWEC and anchors were loaded on deck and anchors were loaded on deck and transported to site by service vessel and transported to site by service vessel (Lisa Ann II)(Lisa Ann II)

•• One sortieOne sortie•• Designed with data transmission Designed with data transmission

capabilities to monitor performance from capabilities to monitor performance from shoreshore

•• Small scale fish farm applicationSmall scale fish farm application

Page 16: Key Engineering Issues for Economically Viable Ocean Wave ...

Oregon State University 10kW Oregon State University 10kW SeaBeavSeaBeav I I Deployment Oct 2008Deployment Oct 2008

Courtesy Oregon State University 

Page 17: Key Engineering Issues for Economically Viable Ocean Wave ...

SeaBeavSeaBeav I Deployment DetailsI Deployment Details

•• SeaBeavSeaBeav I was towed to sea by service I was towed to sea by service vessel (Pacific Storm) and connected to an vessel (Pacific Storm) and connected to an independent mooring systemindependent mooring system

•• Power cable was routed to service vessel Power cable was routed to service vessel to monitor performanceto monitor performance

Page 18: Key Engineering Issues for Economically Viable Ocean Wave ...

PelamisPelamis 750 kW Deployment750 kW Deployment

Courtesy Pelamis Wave Power, Ltd. 

Page 19: Key Engineering Issues for Economically Viable Ocean Wave ...

PelamisPelamis Deployment DetailsDeployment Details

•• Location: Location: AguAguççadouraadoura, Portugal, Portugal•• Project boundary markers installedProject boundary markers installed•• Mooring spreads installedMooring spreads installed•• Subsea power cables installedSubsea power cables installed•• Latch assemblies installedLatch assemblies installed•• 3 units towed to sea and connected3 units towed to sea and connected•• Various vessels usedVarious vessels used•• Numerous sortiesNumerous sorties

http://www.pelamiswave.com/

Page 20: Key Engineering Issues for Economically Viable Ocean Wave ...

StevensStevens’’ Research GoalsResearch Goals

•• Focus on Commercial ProductionFocus on Commercial Production•• Use a Barge Based PlatformUse a Barge Based Platform•• Develop Redundancy, FailDevelop Redundancy, Fail--Safes, Wave Tuning, Safes, Wave Tuning,

Storm Avoidance, and Energy Storage FeaturesStorm Avoidance, and Energy Storage Features•• Quantify Mooring Loads and Wave Tuning LimitsQuantify Mooring Loads and Wave Tuning Limits•• Perform Hydrodynamic ResearchPerform Hydrodynamic Research•• Perform ExtremePerform Extreme--Wave Scale Model TestsWave Scale Model Tests

Page 21: Key Engineering Issues for Economically Viable Ocean Wave ...

BargesBarges-- Simple, Proven PlatformsSimple, Proven Platforms

Page 22: Key Engineering Issues for Economically Viable Ocean Wave ...

Integrate Power TakeIntegrate Power Take--OffOff

Page 23: Key Engineering Issues for Economically Viable Ocean Wave ...

Towed to Mooring SiteTowed to Mooring Site

Page 24: Key Engineering Issues for Economically Viable Ocean Wave ...

Prototype Design FeaturesPrototype Design Features

•• Variable Depth PlatformVariable Depth Platform•• Redundant Data and Power SystemsRedundant Data and Power Systems•• Power TakePower Take--Off Decoupled from Electricity GenerationOff Decoupled from Electricity Generation•• 100 kWh Energy Storage (240100 kWh Energy Storage (240--4500psi cylinders)4500psi cylinders)•• Data Cables Integrated with Strength CablesData Cables Integrated with Strength Cables•• FoamFoam--Filled CompartmentsFilled Compartments•• Bulkhead Fittings for Generators (No shaft seals)Bulkhead Fittings for Generators (No shaft seals)•• Pressure Compensated Winch Shaft SealsPressure Compensated Winch Shaft Seals•• Components Submersed in Bio Degradable Oil ReservoirComponents Submersed in Bio Degradable Oil Reservoir

Page 25: Key Engineering Issues for Economically Viable Ocean Wave ...

Wave Tuning & Storm AvoidanceWave Tuning & Storm Avoidance

Page 26: Key Engineering Issues for Economically Viable Ocean Wave ...

Mooring LoadsMooring Loads

•• Determine probable extreme wavesDetermine probable extreme waves•• Calculate hydrostatic and hydrodynamic Calculate hydrostatic and hydrodynamic

loadsloads•• Use a fourUse a four--point mooringpoint mooring•• Design each mooring leg to hold design Design each mooring leg to hold design

loadload

Page 27: Key Engineering Issues for Economically Viable Ocean Wave ...

Extreme Wave Height PredictionsExtreme Wave Height Predictions

10.250*9.325*920*

8.210*7.77

7.35

6.63

6.12

5.21

Extreme Wave Height (m)Return Period (years)

Westhampton, NY 1994 - 2000

http://sandbar.wes.army.mil/public_html

Page 28: Key Engineering Issues for Economically Viable Ocean Wave ...

Extreme Wave DurationExtreme Wave Duration

Buoy Data from NDBC 44013, 16 Nautical Miles East of Boston, MA during the “Perfect Storm”

722.618.2367311091

6.822.819.5326311091

7.62319.1375311091

7.725.120.3324311091

7.624.219.6253311091

9.126.422.7292311091

8.228.122.5291311091

7.725.220270311091

7.825.620.82723301091

7.723.219.22522301091

7.624.219.62821301091

6.925.619.62820301091

6.223.818.93019301091

5.924.219.52918301091

5.22217.62517301091

Wave Height (m)

GustWind Speed (m/s)

WindDirection

HourDayMonthYear

Page 29: Key Engineering Issues for Economically Viable Ocean Wave ...

Water Particle VelocitiesWater Particle Velocities

)cos(sinh

)(cosh.2

tkxkh

zhkHx

u

)sin(sinh

)(sinh.2

tkxkh

zhkHz

w

Page 30: Key Engineering Issues for Economically Viable Ocean Wave ...

10m 8s wave 50m depth

-60

-50

-40

-30

-20

-10

00 0.5 1 1.5 2 2.5 3 3.5 4 4.5

max horizontal velocity due to surface wave (m/s)

dept

h (m

)

Page 31: Key Engineering Issues for Economically Viable Ocean Wave ...

10m 8s wave 50m depth

-60

-50

-40

-30

-20

-10

00 0.5 1 1.5 2 2.5 3 3.5 4 4.5

max vertical velocity due to surface wave (m/s)

dept

h (m

)

Page 32: Key Engineering Issues for Economically Viable Ocean Wave ...

Calculating LoadsCalculating Loads

•• For wave energy conversion systems, For wave energy conversion systems, mooring loads are functions of device mooring loads are functions of device displacement, drag, weight (mass), water displacement, drag, weight (mass), water particle velocities, damping, and device particle velocities, damping, and device geometry geometry

Page 33: Key Engineering Issues for Economically Viable Ocean Wave ...

DisplacementDisplacement

•• A fully submerged, 10m diameter, 2m A fully submerged, 10m diameter, 2m high cylindrical buoy will displace high cylindrical buoy will displace ~160,000 kg of seawater (1025 kg/m3)~160,000 kg of seawater (1025 kg/m3)

•• Or ~80 kg per mm of draftOr ~80 kg per mm of draft

Page 34: Key Engineering Issues for Economically Viable Ocean Wave ...

Added Mass/ Drag ForceAdded Mass/ Drag Force

•• MMaa = = rprpaa22HH•• where a is the cylinder radius and Hwhere a is the cylinder radius and H is the is the

cylinder height.cylinder height.•• = 1025 x 3.14 x 25 x 2 ~ 160,000 kg= 1025 x 3.14 x 25 x 2 ~ 160,000 kg•• Cylinders and Flat plates have the Cylinders and Flat plates have the

potential for added mass equal to total potential for added mass equal to total displacement depending on the direction displacement depending on the direction of water particle acceleration of water particle acceleration

Page 35: Key Engineering Issues for Economically Viable Ocean Wave ...

Buoy Design LoadBuoy Design Load•• 10m diameter, 2m high, cylindrical foam core buoy10m diameter, 2m high, cylindrical foam core buoy•• Buoy weight = 47,000 kgBuoy weight = 47,000 kg•• Added mass = 160,000 kgAdded mass = 160,000 kg•• = 160k displacement + 160k added mass = 160k displacement + 160k added mass –– 47k buoy 47k buoy

weightweight•• = 273,000kg vertical load= 273,000kg vertical load•• Max Max ww = 4m/s= 4m/s•• KE = KE = ½½ mv^2mv^2•• (273,000 kg x 16 m^2/s^2)/2(273,000 kg x 16 m^2/s^2)/2•• = 2,184,000 N max tether/anchor line load= 2,184,000 N max tether/anchor line load•• = 491,000 lb/246 ton required anchor holding power per = 491,000 lb/246 ton required anchor holding power per

buoybuoy

Page 36: Key Engineering Issues for Economically Viable Ocean Wave ...

Platform Anchor LoadPlatform Anchor Load

Submerged, Flooded, Platform Lift = 115 tonsSubmerged, Flooded, Platform Lift = 115 tonsAdded Mass:Added Mass:Ma = Ma = aa22/4 * b/4 * ba is platform width and ba is platform width and b is platform lengthis platform length= 1025 x 3.14 x 36 x 30 = 3,500,000 kg= 1025 x 3.14 x 36 x 30 = 3,500,000 kgKE = KE = ½½ mv2mv2= (3.5M x .25)/2 = 437,500 N lift = 50 tons= (3.5M x .25)/2 = 437,500 N lift = 50 tons

Page 37: Key Engineering Issues for Economically Viable Ocean Wave ...

Total Design Anchor LoadTotal Design Anchor Load

115 tons static platform lift115 tons static platform lift50 tons kinetic platform lift50 tons kinetic platform lift492 tons buoy lift (246 tons x 2)492 tons buoy lift (246 tons x 2)= 657 tons= 657 tons

Page 38: Key Engineering Issues for Economically Viable Ocean Wave ...

Wave TuningWave Tuning

•• Determine available wave height, period, Determine available wave height, period, and lengthand length

•• Determine maximum tuning (shoaling) Determine maximum tuning (shoaling) prior to breaking criteria (1:7 slope)prior to breaking criteria (1:7 slope)

Page 39: Key Engineering Issues for Economically Viable Ocean Wave ...

Buoy DataBuoy Data

Page 40: Key Engineering Issues for Economically Viable Ocean Wave ...

NDBC 44005 78NM East of NHNDBC 44005 78NM East of NH

Page 41: Key Engineering Issues for Economically Viable Ocean Wave ...

44005 44005 TpTp 200m water depth200m water depth

Page 42: Key Engineering Issues for Economically Viable Ocean Wave ...

Tuning July Waves at 44005Tuning July Waves at 44005

•• Hs = 1m Hs = 1m TpTp = 7s= 7s•• L= 76m C= 10.9 L= 76m C= 10.9 m/sm/s Cg= 5.46 Cg= 5.46 m/sm/s•• P =6852 W/mP =6852 W/m•• By conservation of mass:By conservation of mass:•• Hs = 2.5m L = 30m slope= 1:12Hs = 2.5m L = 30m slope= 1:12•• Cg= 2.18 Cg= 2.18 m/sm/s•• P = 17, 139 W/mP = 17, 139 W/m

Page 43: Key Engineering Issues for Economically Viable Ocean Wave ...

Tuned Wave Power Tuned Wave Power

•• 17 kW/m x 10m diameter x 2 buoys17 kW/m x 10m diameter x 2 buoys•• = 340 kW wave power acting on buoys= 340 kW wave power acting on buoys•• Conservative, simple, linear approximation Conservative, simple, linear approximation

without added mass/drag effectswithout added mass/drag effects

Page 44: Key Engineering Issues for Economically Viable Ocean Wave ...

Tuned WaveTuned Wave

Page 45: Key Engineering Issues for Economically Viable Ocean Wave ...

Tuned Wave (NonTuned Wave (Non--Linear Transition)Linear Transition)

Page 46: Key Engineering Issues for Economically Viable Ocean Wave ...

1:10 Scale Extreme Wave Tests1:10 Scale Extreme Wave Tests

•• Stevens granted $50,000 to research wave Stevens granted $50,000 to research wave energy by DOD (Oct 2009)energy by DOD (Oct 2009)

•• 1:10 Scale wave tuning model being built1:10 Scale wave tuning model being built•• Estimated completion April 2010Estimated completion April 2010•• StevensStevens’’ wave tank tests April 2010wave tank tests April 2010-- Sep Sep

20102010•• Simulate 10m waves at OHMSETT facility Simulate 10m waves at OHMSETT facility

(Fall 2010)(Fall 2010)

Page 47: Key Engineering Issues for Economically Viable Ocean Wave ...

AppendixAppendix

•• New EnglandNew England’’s Electricity Uses Electricity Use•• Seafloor CablesSeafloor Cables•• Wave Power Resource (NonWave Power Resource (Non--Directional)Directional)•• EPRI Wave Power Estimate (2005)EPRI Wave Power Estimate (2005)•• Enabling TechnologiesEnabling Technologies

Page 48: Key Engineering Issues for Economically Viable Ocean Wave ...

New EnglandNew England’’s Electricity uses Electricity use

•• 2007 2007 –– 1232 trillion Btu for Electric Power1232 trillion Btu for Electric Power•• MAMA--423, CT423, CT--322, NH322, NH--234234•• MEME--127, VT127, VT--70, RI70, RI--56 56 •• = 225 billion kW= 225 billion kW--hrhr•• = 40GW average production= 40GW average production•• 1GW = 1 kW1GW = 1 kW--hr every 0.0036 secondshr every 0.0036 seconds

http://www.eia.doe.gov/emeu/states/sep_sum/html/pdf/sum_btu_eu.pdf

Page 49: Key Engineering Issues for Economically Viable Ocean Wave ...

Seafloor CablesSeafloor Cables

http://www.3ehabitat.fr/tag/gaz/

Page 50: Key Engineering Issues for Economically Viable Ocean Wave ...

50

Wave Power ResourceWave Power Resource

•• Based on regional buoy data, 4.89 trillion Based on regional buoy data, 4.89 trillion watts (4.89TW) of wave power are watts (4.89TW) of wave power are available between the New England available between the New England shores and the Continental Shelf (170NM shores and the Continental Shelf (170NM offshore) in average wave conditionsoffshore) in average wave conditions

•• Harnessing 5% of the resource and Harnessing 5% of the resource and converting to electricity at 20% efficiency converting to electricity at 20% efficiency would produce 49GW of electricity or would produce 49GW of electricity or more thanmore than New EnglandNew England’’s use s use

Page 51: Key Engineering Issues for Economically Viable Ocean Wave ...

Wave Power CalculationsWave Power Calculations

•• Average power for New England area:Average power for New England area:•• 1255 J/m2 x 5.46 1255 J/m2 x 5.46 m/sm/s = 6852 W/m x 250,000m = 6852 W/m x 250,000m

of wave crest north to south = 1.7GW per wave of wave crest north to south = 1.7GW per wave crestcrest

•• 220,000 m of wave travel/76.44m between 220,000 m of wave travel/76.44m between wave crest = 2878 wave crests propagating wave crest = 2878 wave crests propagating through the areathrough the area

•• Total wave power = 1.7GW x 2878 = 4892GW Total wave power = 1.7GW x 2878 = 4892GW or 4.892TW of wave power propagating through or 4.892TW of wave power propagating through this area in average wave conditions.this area in average wave conditions.

Page 52: Key Engineering Issues for Economically Viable Ocean Wave ...

EPRI Wave Energy AssessmentEPRI Wave Energy Assessment2100 2100 TWhTWh/yr (240GW), /yr (240GW), BedardBedard et. et. al. 2005al. 2005

http://my.epri.com/

Page 53: Key Engineering Issues for Economically Viable Ocean Wave ...

Enabling TechnologiesEnabling Technologies

•• Submersible winchesSubmersible winches-- DynaconDynacon Inc.Inc.•• Offshore communicationsOffshore communications-- Space Data LLCSpace Data LLC•• Integrated strength, communications, and Integrated strength, communications, and

power cablespower cables-- Honeywell, PMI IndustriesHoneywell, PMI Industries•• BioBio--degradable oildegradable oil-- HydroTexHydroTex•• AnchorsAnchors-- Delmar 700 ton Delmar 700 ton OmniMaxOmniMax•• LoadLoad--sensing hydraulicssensing hydraulics-- BoschBosch--RexrothRexroth