Architectural Concept6

1
may be less demanding, suggesting a different finish, provided the combination is aesthetically pleasing or has a logical separation. Walls for top floor(s) The architect should balance the shape and size requirements for the top floor panels with a reasonable utilization of molds being used on the rest of the project. The top floor is not the place to use excessively large units unless the design and budget warrant the additional crane cost. Figure 2.1.3 illustrates the use of units that are narrower in width than those of the lower floors. The project in Fig. 2.1.4 shows an application of some of the major points made in this chapter. The center bay of the building contains stairs, special service areas, and an elevator core (Fig. 2.1.4[a]). The core was designed to transmit all horizontal loads to the foundation. The use of integrated, loadbearing architectural precast spandrels and a precast concrete core facilitated a tight construction schedule. The total precast concrete structure was erected in only eight weeks with two cranes. The horizontal mass of the building is broken by expressed vertical pilasters (Fig. 2.1.4[b]), which break the building into a series of regular bays, highlighted by granite and concrete accent medallions. Details such as reveals and medallions also help to reduce the building s scale and offer visual interest at the pedestrian level (Fig. 2.1.4[c]). The architect wanted to maximize the window space while also maintaining a heavier, substantial wall form. This was achieved with the detailing and implication of the beam-column look of the precast concrete panels.

description

architectural design

Transcript of Architectural Concept6

Page 1: Architectural Concept6

may be less demanding, suggesting a different finish,provided the combination is aesthetically pleasing orhas a logical separation.Walls for top floor(s)The architect should balance the shape and size requirementsfor the top floor panels with a reasonableutilization of molds being used on the rest of the project.The top floor is not the place to use excessivelylarge units unless the design and budget warrant theadditional crane cost. Figure 2.1.3 illustrates the useof units that are narrower in width than those of thelower floors.The project in Fig. 2.1.4 shows an application ofsome of the major points made in this chapter. Thecenter bay of the building contains stairs, special serviceareas, and an elevator core (Fig. 2.1.4[a]). The corewas designed to transmit all horizontal loads to thefoundation. The use of integrated, loadbearing architecturalprecast spandrels and a precast concrete corefacilitated a tight construction schedule. The total precastconcrete structure was erected in only eight weekswith two cranes. The horizontal mass of the buildingis broken by expressed vertical pilasters (Fig. 2.1.4[b]),which break the building into a series of regular bays,highlighted by granite and concrete accent medallions.Details such as reveals and medallions also help to reducethe building�s scale and offer visual interest at thepedestrian level (Fig. 2.1.4[c]). The architect wanted tomaximize the window space while also maintaining aheavier, substantial wall form. This was achieved withthe detailing and implication of the beam-column lookof the precast concrete panels.