Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

36
Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE

Transcript of Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Page 1: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Arch 330Fall 2008

FORMWORK

AND

REINFORCING

FOR

CONCRETE

Page 2: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Formwork

• Temporary Support for Concrete – curing

• Almost a Temporary Building – support weight and pressure of wet concrete

• Major Expense $$$

Page 3: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Formwork Design

• No Leaks• Support without Excessive

Deflection• Easily Removed - Taper• No Corners, Pockets to Trap

Concrete

Page 4: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Form Release Compound

• Prevents Adhesion of Concrete to Form - Oil, Wax, Plastic

• KEEP OFF Reinforcing Bars – effect bond between concrete and steel

Page 5: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

FORM MATERIAL

• WOOD

• METAL

• PLASTIC

Page 6: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

• Reuse Formwork

• High Q. Surface Form = High Q. Surface Finish Conc.

• Formwork Texture = Concrete texture

• Quality of Finished Conc. – Quality of Form

• Top Grade Formwork for High Finish Concrete

Page 7: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 8: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

STUD---WALER----Diagonal Brace---

Form Tie

Page 9: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

• Studs

• Walers

• Brace

• Tie

Page 10: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 11: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 12: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Brace

Page 13: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 14: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 15: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 16: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Wall cut out

Page 17: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 18: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 19: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 20: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 21: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 22: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 23: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 24: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 25: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 26: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 27: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Beam Form- Taper

Page 28: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Column Form

Page 29: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 30: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 31: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 32: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 33: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Column Footing Form

Page 34: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Continuous Footing Form

Page 35: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.
Page 36: Arch 330 Fall 2008 FORMWORK AND REINFORCING FOR CONCRETE.

Wall Tie