ARC FLASH REQUEST - BidNet

19
REQUEST FOR PROPOSAL For ARC FLASH HAZARD ANALYSIS BID #6540RFP TOWN OF WEST HARTFORD

Transcript of ARC FLASH REQUEST - BidNet

Page 1: ARC FLASH REQUEST - BidNet

REQUEST FOR PROPOSAL

For

ARC FLASH HAZARD ANALYSIS

BID #6540RFP

TOWN OF WEST HARTFORD

Page 2: ARC FLASH REQUEST - BidNet

ProjectINFORMATION

ARC FLASH HAZARD ANALYSIS6540RFP

PROJECT MANAGER

MICHAEL LONGOFACILITIES MANAGER

ALL QUESTIONS DIRECTED TO

TAMMY BRADLEYSENIOR BUYER

All questions must be submitted in writing via e-mail to the Purchasing Officeat tammy1iiwesthartfordct.gov or faxed to 860-561-7492 at least sevencalendar days prior to the date established for the opening of bids. Please do notcall the Engineer, Project Manager or Purchasing Department with questions.

Page 3: ARC FLASH REQUEST - BidNet

1. GENERAL INFORMATION AND PROJECT NARRATIVE:

.1. The Town of \Vest Hartford is seeking an engineering firm to perform Arc Flash Hazard studiesfor select Town of West Hartford buildings and structures. The intent of this contract is to provideenhanced electrical safety at Town of West Hartford buildings to comply with the applicableOSHA Regulations, NFPA Standards and the 2012 edition of the NFPA 70E Standard. Theprogram applies to facilities in which qualified employees and contractors may work on or nearelectrical switchboards, distribution boards, motor control center, panelboards and electricalequipment and wiring that exceed 50 volts.

1.2. Contract Management1.2.1 .The selected engineering firm will assign one qualified individual as the contact person

responsible for directing and coordinating the activities of the consultant’s personnel and anysub-contractors in all aspects of the project.

2. INSTRUCTIONS FOR PROPOSALS:

2.1. The orimnal proposal along with four (4) copies shall be placed in one sealed envelope, bearingthe name and address of the respondent and clearly marked with “ARC FLASH HAZARDANALYSIS, Bid #6540RFP. Sealed proposals for Arc Flash Hazard Analysis will be received inthe Purchasing Division Office, Room 223, Town Hall, 50 South Main Street, West Hartford, CT06107 on November 2,2016 at 2:00 PM.

2.2. A pre-bid meeting will be held on October 19. 2016 at 1:00 PM in room 217 of Town Hall, 50South Main St. West Hartford. Contractors are strongly encouraged to attend as this is the primeopportunity to meet the project team and visit the locations. It is the intent to meet at town halland visit a sampling of locations via caravan. Interested attendees should plan on a minimum ofone hour possibly two to visit the locations.

2.3. Addenda and [nterpretations: Any request from a prospective bidder for interpretation ofmeaning of the Request for ProposaL shall be made in writing to Tammy Bradley, via email attammybwesthartfordct.cov or via fax at 860-561-7492 no later than close ofbusiness on October25, 2016. Any addenda shall be posted on the website (www.westhartfordct.gov bid list) no laterthan three (3) days prior to the bid opening date.

2.4. Site Conditions: Prior to submitting bids, each bidder will have made an examination of each site;to satisfied himself as to acmal conditions, requirements, and quantities of work, and has read andbecome thoroughly familiar with this RFP. SuccessfUl bidder will need to field verify all existingconditions. For access to a particular building, email Tammy Bradley your request attammyb(1iwesthaftfordct.aov.

2.5. The relationship between the Town and the Contractor is expected to be mutually beneficial inwhich respective strengths in experience, technology and resources will be shared. The intent ofthis relationship is to constantly improve the efficiency and quality of service provided.

2.6. Respondents shall include a cover letter, addressed to Peter Privitera, Purchasing Agent, signed byall authorized principals or agents of the respondent, which provides an overview of therespondents’ offer, as well as the name, title, fax number, e-mail address and phone number ofthe person to whom the Town may direct questions concerning the proposal. The letter shouldalso include a statement by the respondent accepting all terms and conditions conlained in this

-3-

Page 4: ARC FLASH REQUEST - BidNet

request, signed by an officer or other individual with authority to bind the firm. All proposalsubmissions and materials will become the property of the Town and will not be returned.

2.7. All firms who are solicited but decide not to offer a Proposal to the Town of West Hanford areasked to submit a negative reply. Specific feedback comments and observations are encouraged.

2.8. The Town will not be liable for any costs incurred in the preparation of the response to this request.Proposals must be bound, paginated, indexed and pages numbered consecutively. The firm’sprincipal official must sign all proposals.

2.9. Equal Opponunitv: During the performance of this Contract, the Contractor agrees and warrantsthat it will not discriminate or permit discrimination against any person or group of persons,including employees or applicants for employment, on the grounds of age, sex, race, color,religion, physicaL impairment or national origin in any manner prohibited by the law of the UnitedSlates, the State of Connecticut, or the Town of West Hanford. The successffil bidder will takeaffirmative action to ensure that applicants are employed and that employees are treated equallyduring employment without regard to their race, color, religion, age, sex or national origin. Suchaction shall include, but not be limited to, the following: layoff or termination; rates of pay orother forms of compensation; and selection for training including apprenticeship.

2.10. Recipients of this RFP are hereby notified that all proposals submitted and informationcontained therein and attached thereto will not become public information until after theselection of successffil respondent.

2.11. Detailed Proposal shall include:

2.11.1. References and Experience: Please provide a detailed written summary of therespondents’ experience and capability in providing similar services elsewhere. Referencesshall be provided upon request.

2.11.2. Service and Staffing Plan: Describe how services required herein will be provided tothe Town. Describe how the respondent will staff the assignment including positiondescriptions, hours worked annually, and level of responsibility, experience, and background.The proposal shall specifically list the tasks the consultant will accomplish and a list of itemsthe consultant’s proposal shall does not include.

2.11.3. Fee Proposal: Respondent shall submit a fee proposal for all services outlined in the RFP.The fee shall include all materials, supplies, tools, personnel and whatsoever necessary toperform the services described herein. The fee proposal shall provide an all-inclusive priceper building. The Town is exempt from excise taxes, transportation and sales taxes imposedby the Federal Government and/or the State of Connecticut. Such taxes must not be includedin the fee proposal.

The Town reserves the right to negotiate fees and payment schedules with the selectedrespondent. State the proposed software package to be utilized.

2.11.4. Exclusions: Any and all exclusions shall be clearly identified iii the proposal.

2.11 .5. Required information to be submitted wit!: proposal:

2.11.5.1. Taxpayer’s Identification Number: Every respondent, whether an individual,proprietor, partnership or a non-profit corporation or organization must fill out and

-4-

Page 5: ARC FLASH REQUEST - BidNet

submit with their proposal the Internal Revenue Service Form W-9, Request forTaxpayer ldentjflcation Thunber and Certjflcation. Or register online at wwiv.westhanfordct.gov.

2.11.5.2. Certificate of Insurance: A certificate of insurance shall be submitted naming theTown of West Hartford indicating conformance with insurance limits specified.

2.11.5.3. The Respondent must sign all Proposals. Unsigned proposals cannot and will notbe considered.

2.11.5.4. A sample work product within the last 12 months that is most similar to the workbeing proposed (client information excluded).

3. PROPOSAL EVALUATION/SELECTION CRITERIA:

The following criteria will be used, without limitation, in determining the successful respondent:

3.1. The Respondent’s Technical Understanding of the project, its purpose, scope and field asevidenced by the quality of the proposal submitted, relative to the services and staffing plan. Thisshall include the background and experience of the Respondent in providing similar proposedservices elsewhere. The proposal shall specifically list the tasks the consultant will accomplishand a list of items the consultant’s proposal does not include.

3.2. Competitiveness of Proposed Fee: The Town is not bound to select the respondent who proposesthe lowest fee rather the respondent offering the best value for services requested. The Townreserves the right to negotiate fees with the selected respondent. It is the intent of the Town toaward the project to a single Engineering firm.

3.3. The References and Experience; the background, qualifications, and relevant experience of thefirm and individuals designated to provide the services defined.

Proposals in response to this request will be reviewed against the criteria listed above, andAward ofcontract shall be made in accordance iiith standard purchasing procedures.

4. SELECTION PROCEDURES:

4.l.The Purchasing Agent reserves the right to reject any or all proposals or parts thereof for anyreasons, to negotiate changes to proposal terms, and to waive minor inconsistencies with this RFP.

4.2. A Selection Committee will assist the Purchasing Agent in choosing the successful respondent todeliver the requested services. Respondents submitting the best proposals may be invited to aninterview with the Selection Committee prior to final recommendation of contract award. TheTown reserves the right to make an award solely on the basis of the proposals submitted.

4.3.The Town intends to negotiate and enter into a contract with the most desirable respondent whoseproposal is determined to be in the best interest of the Town.

5. PRINCIPALS/COLLUSION:

By submission of a proposal, the respondent does declare that the only person or persons interestedin the proposal as principal or principals is/or, are named therein and that no other person otherthan therein mentioned has any interest in this proposal or contract to be entered into; that this

-5-

Page 6: ARC FLASH REQUEST - BidNet

proposal is made without connection with any person, company or parties making a similarproposal, and that it is in all respects fair and in good faith without collusion or fraud.

6. PROPOSAL SUBMISSION

6.1. MI proposals must be received by November 2. 2016 at 2:00 PM. One original and four (4)copies shall be submitted to

Peter Privitera, Purchasing AgentTown of West HartfordPurchasing Division, Room 22350 South Main Street\Vest Hanford, CT 06107

7. OTHER CONDITIONS- INDEMNIFICATION

7.1. The bidder is aware of and agrees that, if awarded the contract, he is bound by the followingindenmification language:

7.1.1 .To the Mlest extent permitted bylaw, the successful bidder shall release, defend, indemnify,and hold harmless the Town of West Hartford and the West Hartford Board of Education,their respective boards, commissions, officers, officials, employees, agents, representatives,and servants from any and all suits, claims, losses, damages, costs (including withoutlimitation reasonable attorneys’ fees), compensation, penalties, fines, liabilities orjudgmentsor any name or nature for:

7. 1 .1.1. Bodily injury, sickness, disease, or death; and/or

7.1.1.2. Damage to or destruction of property, real or personal; and/or

7.1.1.3. Financial losses (including, without limitation, those caused by loss of use) sustainedby any person or concern, including officers, employees, agents, subcontractors orservants of the Town, the Board of Education, or the contractor, or by the public, whichis cause or alleged to have been caused in whole or in part by the act (s) or omission(s)of the contractor, its officers, employees, agents, or Subcontractors, in the performanceof the contract or from the inaccuracy of any representation or warranty of the contractorcontained in the Contract Documents. This indemnity shall not be affected by otherportions of the contract relating to insurance requirements.

7.1.1.4. To the fullest extent permitted by law, the contractor agrees to release, defend,indemnify, and hold harmless the West Hartford Board of Education and the Town of\Vest Hartford, their respective boards and commissions, officials, officers, employees,agents, representatives, and servants from any Loss, claim, cost penalty, fine or damagethat may arise out of the employees or Subcontractors to comply with any laws orregulations of the United States of America, the State of Connecticut, the Town of WestHartford, or their respective agencies. This undertaking shall not be affected by otherportions of the contract relating to insurance requirements.

-6-

Page 7: ARC FLASH REQUEST - BidNet

8. SCOPE OF SERVICES

8.1. SCOPE8.1.1 .Fumish a short circuit and protective device coordination study.

8.1 .2.Fumish an Arc Flash Hazard Analysis Study as per NEPA 70E - Standard for Electrical Safetyin the Workplace, 2012 edition. The arc flash hazard analysis shall be performed according tothe IEEE 1584. The contractor shall use computer software as per Section 8.4 of this RFP.

8.l.3.The arc flash and the incident energy shall be calculated at all locations in the electricaldistribution system (switchboards, switchgear, motor-control centers, transformers,panelboards and equipment with that is fed from an overcurrent protective device equal to orexceeding 200 amperes. where work could be performed on energized pans.

8.1.4.Existing Conditions shall be verified and/or documented. All data shall be obtained underthis contract.

8.1 .5.Buildings or facilities to be included in this scope of work. (All buildings or facilities arelocated in West Hartford, Connecticut)

8.1.5.1. Conard High School located at 110 Berkshire Road-See Attachment #18.1.5.2. DuffS’ School located at 95 Westminster Drive-See Attachment #28.1.5.3. Elmwood Community Center Located at 1106 New Britain Ave.-See Attachment

#38.1.5.4. Faxon Branch Library located at 1073 New Britain Ave.-See Attachment #48.1.5.5. Fire Station #2 located at 20 Brace Road-See Attachment #58.1.5.6. Noah Webster Library (West Hartford Library) located at 20 South Main Street-

SeeAttachment #6

8.1.5.7. Police Station located at 103 Raymond Road-See Attachment #78.1.5.8. Sedgwick Middle School located at 128 Sedgwick Road-See Attachment #88.1.5.9. Town Hall located at 50 South Main Street-See Attachment #98.1.5.10. Wolcott School located at 71 Wolcott Road-See Attachment #10

8.2. REFERENCES

8.2.1 Institute of Electrical and Electronics Engineers, Inc. (IEEE):

8.2.1.1. IEEE 141 — Recommended Practice for Electric Power Distribution and Coordinationof Industrial and Commercial Power Systems

8.2.1.2. IEEE 242 — Recommended Practice for Protection and Coordination of Industrial andCommercial Power Systems

8.2.1.3 WEE 399—Recommended Practice for Industrial and Commercial Power SystemAnalysis

8.2.1.4 IEEE 241 — Recommended Practice for Electric Power Systems in CommercialBuildings

8.2.1.5 IEEE 1015 — Recommended Practice for Applying Low-Voltage Circuit BreakersUsed in Industrial and Commercial Power Systems.

8.2.1.6 IEEE 1584- Guide for Performing Arc-Flash Hazard Calculations

-7-

Page 8: ARC FLASH REQUEST - BidNet

8.2.2.American National Standards Institute (ANSI):

8.2.2.1 ANSI C57. 12.00— Standard General Requirements for Liquid-ImmersedDistribution, Power, and Regulating Transformers

8.2.2.2 ANSI C37.13 — Standard for Low Voltage AC Power Circuit Breakers Used inEnclosures

8.2.2.3ANSI C37.OlO — Standard Application Guide for AC High Voltage CircuitBreakers Rated on a Symmetrical Current Basis8.2.2.4 ANSI C 37.41 — Standard Design Tests for High Voltage Fuses, DistributionEnclosed Single-Pole Air Switches, Fuse Disconnecting Switches and Accessories.

8.2.3 The National Fire Protection Association

8.2.3.1 NFPA 70-National Electrical Code, latest edition8.2.3.2 NFPA 70E_Standard for Electrical Safety in the Workplace., 2012 edition

8.3 QUALIFICATIONS

8.3.1 The short-circuit, protective device coordination and arc flash hazard analysis studiesshall be conducted under the direct supervision of a Registered Professional ElectricalEngineer skilled in performing and interpreting power system studies.

8.3.2 The Registered Professional Electrical Engineer shall be a full-time employee of theengineering firm. The Registered Professional Engineer shall be licensed in the state of

Connecticut as an Electrical Engineer.

8.3.3 The Registered Professional Electrical Engineer shall have a minimum of five (5) years ofexperience in performing similar power system studies.

8.3.4 The engineering firm shall demonstrate experience with Arc Flash Hazard Analysis bysubmitting names of at least three similar arc flash hazard analysis it has performed in thepast year.

8.3.5 The engineer performing the study shall visit the site at least once to become familiar withthe data that has been gathered and to perform a photographic survey of the powerdistribution system.

8.4 COMPUTER ANALYSIS SOFTWARE

8.4.1. The studies shall be performed using the latest revision of the SKIM SystemsAnalysis PowerTools for Windows (PTW) software program or approved equal.

8.4.2 An electronic copy of the project data file shall be included with the final report.

8.5 SUBMITTALS

8.5.1 A preliminary submittal shall be made for review and comment. The submittal shallinclude but not limited to the following:

8.5.1.1 Engineers photographic survey, digital images on USB stick.

-8-

Page 9: ARC FLASH REQUEST - BidNet

8.5.1.2 Data gathering field work notes, sketches, etc. scanned to PDF.8.5.1.3 Computer model as built one line diagram in PDF format.8.5.1.4 Engineers cursory review of the one line diagram noting any and all

deficiencies observed.

8.5.2 The completed study/report shall be submitted for review and comment in PDF format.Proposed sample arc flash label shall be included with this submittal.

8.5.3 Three hard copies of the final report shall be provided in heavy duty 3 ring binders.

8.5.4 Electronic copy of the final report shall be provided including electronic copy of the datafile of the short circuit coordination study and the arc flash study.

8.5.5 Letter certifying all adjustable relays and circuit breakers have been set to therecommended settings and all arc flash labels are installed. Digital photos on USB stickshall be included showing all settings made and arc flash labels installed.

8.6. PRODUCT

8.6.1.STUJJIES

8.6.1.1. Furnish short-circuit and protective device coordination studies approved, sealedand signed by a Registered Professional Electrical Engineer licensed in the State ofConnecticut.

8.6.1.2. Furnish an Arc Flash Hazard Analysis Study per NFPA 70E Standard for ElectricalSafety in the Workplace, reference Article 130 of the 2012 edition.

8.7. DATA COLLECTION

8.7.1. Obtain all data as required for the power system studies. The Engineer performing theshod-circuit, protective device coordination and arc flash hazard analysis studies shalloversee the data collection process immediately after award of the contract.

8.7.2. Source combinations may include present and future motors, generators. Include allmotors 50 HP and above. Multi motor machines totaling 50 1W and above shall also beincluded.

8.7.3. Field data collection shall be performed by a qualified (as defined by the OSHAGeneral Industry Regulations) person to ensure accurate equipment modeling.

8.7.4. Field personnel shall have up-to-date training in electrical safety’ and shall supply andutilize their own Personal Protective Equipment for electrical shock hazards and arc flashhazards. Submit information describing your safety training and program prior to startingdata collection process.

8.7.5. Review all Town of West Hartford electrical safety requirements and shall comply withall requirements.

-9-

Page 10: ARC FLASH REQUEST - BidNet

8.7.6.For the purposes of this RFP the drawings (if available) shall represent the existingconditions, but are not deemed complete or accurate. Bidder shall take this into accountwhen calculating the study pricing.

8.7.7. Visually inspect and collect all nameplate data to be used in the analysis includingconductor types, sizes, quantities and material.

8.7.8. Where data is available from the existing drawings or in the RFP documentation,engineering firm may use this data in building the model, but shall field verify allinformation.

8.7.9.Data collection shall include the step down transformer from the utility (including theprimary) down through each Switchboard, panelboards, motor control center (MCC), lowvoltage transformers and 240/208 volt panels for all systems. Equipment circuits 200amperes and larger shall also be included.

8.7.10. Obtain from the utility the minimum, normal, and maximum operating service voltagelevels, three-phase short circuit MVA and X/R ratio, as well as line-to-ground short circuitMVA and XIR ratio at the point of connection. including the local or internal disconnectswitch, fuse or circuit breaker.

8.7.11. Field personnel shall have an internal safety program and up-to-date electrical safetytraining that includes electric shock and arc flash hazards. Field personnel shall complywith their safety program requirements and the Town of West Hartford safety regulationsduring field data collection. A minimum of Category #2 PPE rated 8 cal/cm2 shall be wornby field data collection personneL at all times when exposed to energized electricalequipment.

8.7.12. Data collection shall be performed off hours where occupants could be in close proximityto the arc flash boundary.

8.7.13. Data collection in areas which are likely to be dangerous, a system shutdown shall bescheduled, off hours at a time and date acceptable to the Town of West Hartford. MIassociated cost shall be included in the bid.

8.7.14. Field work data collection notes, sketches, etc. shall be included in the report.

8.8. ONE LINE DIAGRAM(S)

8.8.1. As A minimum the one line diagram(s) shall display the following:

8.8.1 .1. Where data is available from the existing drawings or in the RFPdocumentation, engineering firm may use this data in building themodel, but shaLl field verify all information.

8.8.1.2. Data collection shall include the step down transformer from theutility (including the primary) down through each Switchboard,panelboards, motor control center (MCC), low voltage transformers

- 10-

Page 11: ARC FLASH REQUEST - BidNet

and 240/208 volt panels for all systems. Equipment circuits 200amperes and larger shall also be included.

8.8.1.3. Obtain from the utility the minimum, normal, and maximumoperating service voltage levels, three-phase short circuit MVA andX/R ratio, as well as line-to-ground short circuit MVA and X/R ratioat the point of connection, including the local or internal disconnectswitch, fuse or circuit breaker.

8.8.1.4. Field personnel shall have an internal safety proram and up-to-date electrical safety training that includes electric shock and arcflash hazards. Field personnel shall comply with their safetyprogram requirements and the Town of West Hartford safetyregulations during field data collection. A minimum of Category #2PPE rated 8 cal/cm2 shall be worn by field data collection personnelat all times when exposed to energized electrical equipment.

8.8.2.Data collection shall be performed off hours where occupants could be inclose proximity to the arc flash boundary.

8.8.3.Data collection in areas which are likely to be dangerous, a systemshutdown shall be scheduled, off hours at a time and date acceptable tothe Town of West Hartford. All associated cost shall be included in thebid.

8.8.4.Field work data collection notes, sketches, etc. shall be included in thereport.

8.8.4.1. Name of each and every component8.8.4.2. Utility voltage, three phase MVA and X/R ratio8.8.4.3. Transformer KVA, impedance, and secondary voltage. Primary

andSecondan’

8.8.4.4. Connection type by symbol8.8.4.5. Bus ampere rating and operating voltages8.8.4.6. Circuit breaker trip amperes and type8.8.4.7. Conductor size, quantity, and length. Material AL/CU may be

indicated in a general note.8.8.4.8. Conductor size, quantity, and length. Material AL/CU may be

indicated in a general note.8.8.4.9. Conductor size, quantity, and length. Material AL/CU may be

indicated in a general note.8.8.4.10. Fuse ampere rating and type

8.8.4.11. Motor horsepower rating8.8.4.12. Starter type and size8.8.4.13. Disconnect safety switch voltage and ampacity8.8.4.14. Equipment voltage and ampere rating8.8.4.15. Generator rating in KW/KVA, voltage and sub transient

impedance8.8.4.16. Feeder and plug-in busway voltage and ampacity

-11-

Page 12: ARC FLASH REQUEST - BidNet

8.8.4.17. Display the worst case incident energy and associated arcingfault current at each location requiring an arc flash label.

8.8.4.18. The room name or building area shall be noted adjacent to thepower distribution system equipment.

8.9. SHORT-CIRCUIT AND PROTECTIVE DEVICE EVALUATION STUDY8.9.1. Use actual conductor impedances if known. If unknown, use typical

conductor impedances based on IEEE Standard 141-1993.8.9.2. Transformer nameplate impedances shall be used.8.9.3. Provide the following:

8.9.3.1. Calculation methods8.9.3.2. Selected base per unit quantities8.9.3.3. One-line diagram of the system being evaluated8.9.3.4. Source impedance data, including electric utility system and

motor fault contribution characteristics as well as any emergencystandby generators

8.9.4. For the short circuit equipment evaluation study use the available utilityfault current plus the addition of a prudent factor of safety

8.9.5. Tabulations of calculated quantities8.9.6. Results, conclusions, and recommendations.8.9.7. Calculate short-circuit momentary and interrupting duties for a three-

phase bolted fault at each:8.9.7.1. Electric utility’s supply termination point8.9.7.2. Incoming switchgear and/or switchboards8.9.7.3. Unit substation primary and secondary terminals8.9.7.4. Low voltage switchgear8.9.7.5. Motor control centers8.9.7.6. Standby generators and automatic transfer switches8.9.7.7. Branch circuit and distribution panelboards8.9.7.8. Dry type transformers8.9.7.9. My other significant locations throughout the system.

8.9.8. For grounded systems, provide a bolted line-to-ground fault current studyfor areas as defined for the three-phase bolted fault short-circuit study.

8.10. PROTECTIVE DEVICE EVALUATION

8.10.1. Evaluate equipment and protective device ratings and compare to shortcircuit study results

8.10.2. Adequacy of switchgear, motor control centers, and panelboardbus bars to withstand short-circuit stresses

8.10.3. Notify Owner in writing, of existing, circuit protective devices equipmentimproperly rated for the calculated available fault current.

8.10.4. Equipment duty pass/fail results shall be displayed in tabular report.

8.11. PROTECTIVE DEVICE COORDINATION STUDY

8.11.1. Protective device coordination time-current curves (TCC) shall bedisplayed on log-log scale graphs.

8.11.2. Include on each TCC graph, a complete title and partial one-linediagram. A description of each TCC shall be provided.

8.11.3. Terminate device characteristic curves at a point reflecting maximumsyimnetrical fault current to which the device is exposed.

- 12-

Page 13: ARC FLASH REQUEST - BidNet

8.11.4. Identi1’ the device associated with each curve by name, manufacturertype, function, and, if applicable, tap, time delay, and settingsrecommended.

8.11.5. Plot the following characteristics on the TCC graphs, where applicable:

8.11.5.1. Electric utility’s overcurrent protective device8.11.5.2. Medium voltage equipment overcurrent relays8.11.5.3. Medium and low voltage fuses including manufacturer’s

minimum melt, total clearing, tolerance, and damage bands8.11.5.4. Low voltage circuit breaker trip devices, including

manufacturer’s tolerance bands8.11.5.5. Transformer full-load current, magnetizing inrush

current, and ANSI through fault protection curves8.11.5.6. Conductor damage curves8.11.5.7. Ground fault protective device curves8.11.5.8. Pertinent motor starting characteristics and motor

damage points, where applicable8.11.5.9. Pertinent generator short-circuit decrement curve and

generator damage point -As a minimum model the service equipmentdistribution panelboard. The largest feeder circuit breaker in eachmotor control center and panelboard. For emergency/standbydistribution, model down to the branch circuit level.

8.11.6. Provide adequate time margins between device characteristicssuch that selective coordination is provided, while providing properprotection.

8.12. ARC FLASH HAZARD ANALYSIS

8.12.1. The arc flash hazard analysis shall be performed in accordance with theIEEE 1584 and using the latest revision of the SKM Systems AnalysisPowerTools for Windows (PTW) software program or approved equal.

8.12.2. The arc flash boundary and the incident energy shall be calculated at alllocations in the electrical distribution system (switchboards, switchgear,motor-control centers, transformers, panelboards and equipment with that isfed from an overcurrent protective device equal to or exceeding 200amperes).

8.12.3. The Arc-Flash Hazard Analysis shall include all panelboards in 240 voltand 208 volt systems fed from transformers equal to or greater than 10WA.

8.12.4. Calculated arc flash boundary shall be based on an incident energy of 1.2caL’cm2.

8.12.5. Ground overcurrent relays should not be taken into consideration whendetermining the clearing time when performing incident energy calculations

- 13 -

Page 14: ARC FLASH REQUEST - BidNet

8.12.6. The short-circuit calculations and the corresponding incident energycalculations for all operating scenarios must be compared and the greatestincident energy must be uniquely reported for each equipment location.Calculations must be performed to represent the maximum and minimumcontributions of fault current magnitude for all operating conditions. Theminimum calculation will assume that the utility contribution is at aminimum and will assume a minimum motor contribution (all motors off).Conversely, the maximum calculation will assume a maximum contributionfrom the utility and will assume the maximum amount of motors to beoperating.

8.12.7. The incident energy calculations must consider the accumulation ofenergy overtime when performing arc flash calculations on buses withmultiple sources. Interactive calculations must take into account thechanging current contributions, as the sources are interrupted ordecremented with time. Fault contribution from motors and generatorsshould be decremented as follows:

8.12.7.1. Fault contribution from induction motors should not beconsidered beyond 5 cycles.

8.12.7.2. Fault contribution from synchronous motors and generatorsshould be decayed to match the actual decrement of each as closely aspossible.

8.12.8. For each equipment location with a separately enclosed main device(where there is adequate separation between the line side terminals of themain protective device and the work location), calculations for incidentenergy and flash protection boundary shall include both the line side of themain breaker and the downstream bus.

8.12.9. When performing incident energy calculations the line sideand load side contributions must be included in the calculation.

8.12.9.1. Mis-coordination cai be checked amongst devices within thebranch containing the immediate protective device upstream of thecalculation location and the calculation can utilize the fastest deviceto compute the incident energy for the corresponding location, andthe number of levels shall be subject to the judgement of theengineer.

8.12.9.2. Arc Flash calculations shall be based on actualovercurent protective device clearing time. Maximum clearing timewill be capped at 2 seconds based on IEEE 1584-2002 section 8.1.2.Where it is not physically possible to move outside of the flashprotection boundary in less than 2 seconds during an arc flash event, aclearing time based on the specific location shalt be utilized.

- 14-

Page 15: ARC FLASH REQUEST - BidNet

8.12.10. Upon completion of the arc flash study review the recommendedsettings for potential arc flash reduction. Recommended settings andTCC’s shall be adjusted accordingly. Nuisance tripping shall be avoided.

8.12.11. If the available fault current at the bus exceed the rating of theupstream device, the arc flash label shall be modeled as ihough that devicewere not in the circuit.

8.13. REPORT SECTIONS

8.13.1. Executive Summary: Include an overview of the study/report,highlighting pertinent data, findings and issues. The executive summaryshall address each section in the report. Cursory’ review comments of theone line diagram shall also be included.

8.13.2. Input Data Report: Report of all data input forming the basis of the studyreport.

8.13.3. Short Circuit Study: Report indicating the results of the short circuitstudy throughout the distribution system.

8.13.4. Equipment Evaluation: Pass fail analysis results comparing the availablefault current to protective devices and buss ntings.

8.13.5. Settings Report: Recommended relay and circuit breaker settings toinclude all overcurrent and ground fault settings.

8.13.6. Time Current Curves: Graphical representation of coordination betweenovercurrent protective devices.

8.13.7. Arc Flash Study: Arc Flash Study results of each scenario modeled aswell as Arc Flash Study worst case results.

8.13.8. Appendix: Include all equipment data sheets obtained during the studyand supporting documentation.

8.13.9. One Line Diagrams: One Line Diagrams reflective of the as builtconditions. Worst case arc flash results shall be displayed on the as builtone line diagram or an additional one line diagram may be provided.

8.13.10. Compact Disc: Containing the entire report in PDF format and the datafile for the study.

8.14. EXECUTION

8.14,1. FIELD ADJUSTMENT

8.14.1.1. Adjust relay and protective device settings according to therecommended setting table in the coordination study prior to installing

- 15 -

Page 16: ARC FLASH REQUEST - BidNet

arc flash labels. Adjustments to existing settings shall be fieldperformed and included in the bid.

8.15. ARC FLASH WARINThJG LABELS

8.15.1. Provide a 4 in. x 6 in, thermal transfer type labels of high adhesion vinylfor each work location analyzed. All labels shall be indoor/outdoor rated fordurability.

8.15.2. All labels will be based on recommended overcunent device settings andwill be provided after the results of the analysis have been accepted by theowner.

8.15.3. The label shall include the following information, at a minimum:8.15.3.1. Equipment designation8.15.3.2. Nominal voltage8.15.3.3. Arc Flashboundary8.15.3.4. Hazard risk category8.15.3.5. Incident energy8.15.3.6. Working distance8.15.3.7. Shock boundaries8.15.3.8. Labels shall be machine printed, with no field markings. A

sample arc flash label shall be submitted for written approval prior toprinting.

8.15.3.9. Arc flash labels shall be provided in the following manner andall labels shall be based on recommended overcurrent device settings.

8.15.3.10. For each 600, 480, 240 and 208 volt panelboard, one arcflash label shall be provided.

8.15.3.11. For each motor control center, one arc flash label shall beprovided for every other section

8.15.3.12. For each low voltage switchboard, one arc flash label shall beprovided for every other section.

8.15.3.13. For each switchgear, one flash label shall be provided for everyother section.

8.15.3.14. For medium voltage switches one arc flash label shall beprovided

8.15.3.15. Arc Flash labels shall be field installed by the person whoperformed the data collection. Installation of arc flash labels shall beincluded in the bid.

- 16-

Page 17: ARC FLASH REQUEST - BidNet

INS URAN CE EXHIBIT A

For the purpose of this exhibit: the term “Engineering Firm” shall also include their respective agents, representatives,employees or subcontractors; and the term “Town of West Hanford and West Hanford Board of Education”(hereinafter called the “Town”) shall include their respective officials, boards and commissions, officers.representatives, agents, servants, employees and volunteers.

The Engineering Firm shall obtain and maintain at its own cost and expense all the insurance described belowcontinuously for the duration of the contract, including any and all extensions. Engineering Firm shall assume any andall related costs, including but not limited to, deductibles, retentions, losses, claim expenses, premiums, taxes, and auditcharges earned and payable under the required insurance.

A. Minimum Scope and Limits of Insurance:The required insurance shall meet the minimum scope and limits of insurance specified in this exhibit, or requiredby applicable federal, state and/or municipal law, regulation or requirement, whichever coverage is greater.Providing proof of the minimum scope and limits described in this exhibit shall not exclude the Town fromadditional limits and coverage available to the Engineering Firm.

1) Commercial General Liability:$1,000,000 combined single limit each occurrence for bodily injury, personal injury, property damage, contractualliability and products /completed operations. Engineering Firm shall continue to provide products/completedoperations coverage for two (2) years after completion of the work

2) Professional Liability: $1,000,000 each occurrence’ $2,000,000 annual aggregate.

3) Automobile Liability and Physical Damage Coverage:5500.000 combined single limit each occurrence for any auto, including statutory uninsured1underinsuredmotorist coverage and S 1,000 medical payments. Policy shall include collision and comprehensive propertydamage coverage.

4) Umbrella Liability:$1,000,000 each occurrnc / $2,000,000 annual aggregate. All excess/umbrella policies shall be following formand list the existing underlying insurance policies.

5) Workers’ Compensation and Employer’s Liability:Statutory workers’ compensation limits in compliance with the laws of the State of Connecticut. Policy shallinclude Employer’s Liability with minimum limits of$ 100,000 each accident, $500,000 disease/policy limit,$100,000 disease/each employee.

The Engineering Firm represents that they are currently in compliance with all requirements of the State ofConnecticut regarding Workers’ Compensation, Connecticut Statutes Section 3 1-275 et seq., and that it shallremain in compliance for the duration of this Agreement The Engineering Finn agrees that Workers’Compensation is their sole remedy and shall indemnify and hold harmless the Town of \Vest Hartford, \VestHartford Board of Education and their respective officials, boards and commissions, officers, representatives,agents, servants, employees and volunteers from all suits, claims, and actions arising from personal injuries toEngineering Finn, their agents, representatives, employees or subcontractors sustained during the course ofproviding services to the Town. however caused. This indemnity shall not be affected by a lapse of Workers’Compensation coverage and/or if the Engineering Firm failed, neglected, reflased or is unable to obtain Workers’Compensation insurance.

6) Personal Property:“MI risk” property insurance on a replacement cost basis to cover the value of personal property belonging to theEngineering Firm and others (including but not limited to the personal property of subcontractors). All personalproperty of the Engineering Firm and its agents are the sole risk of the Engineering Firm. To the extent permitted

-17-

Page 18: ARC FLASH REQUEST - BidNet

by law, the Engineering Firm agrees to indemni’, defend and hold harmless the Town from any and all lossesor damages, however caused, to any and all personal property belonging to the Engineering Finn, its agents,representatives, employees and/or subcontractors.

B. Additional Insured Endorsement:MI liability policies (with the exception of Worker’s Compensation and Professional Liability shall includethe Town of West Hartford, the West Hartford Board of Education, and their respective officials, boardsand commissions, officers, representatives, affents, servants, employees and volunteers as an AdditionalInsured. The policy shall not contain any special limitations on the scope of protection afforded to the Town.Any Insured vs. Insured language shall be amended to eliminate any conflicts or coverage restrictions betweenthe respective Insureds.

C. Acceptability of Insurers:Engineering Finn’s policies shall be written by insurance companies authorized to do business in the State ofConnecticut, with a Best’s rating of no less than A:VII, or otherwise deemed acceptable by the Towns RiskManager.

D. Subcontractors:All subcontractors are required to comply with all the insurance requirements stated herein. The Engineering Firmshall include all subcontractors as an Insured under its policies or shall finish separate certificates andendorsements for each subcontractor.

E. Waiver of Subrogation:All required insurance policies shall include a waiver of subrogation clause that states that it is agreed that in noevent shall the insurance company have any right of recovery against the Town. When the Engineering Firm isself-insured, the Engineering Firm agrees it shall not have any right of recovery against the Town.

F. Claims-Made Form:When insurance coverage is underwritten on a claims-made basis, the retroactive date shall be prior to orcoincident with the date of the contract. The certificate of insurance shall state the retroactive date and that thecoverage is claims-made. The Engineering Firm shall maintain coverage for the duration of the contract and forthe two (2) years following the completion of the contract. Evidence of such coverage shall be provided to theTown thirty (30) days prior to each policy expiration.

0. Aggregate Limits:When a general aggregate is used, the general aggregate limit shall apply separately to the project or shall betwice the occurrence limit. The certificate of insurance shall state the aggregate limits. The Engineering Firmshall noti& the Town with reasonable promptness with information conceming the erosion of limits due to claimspaid under the general aggregate during the contract term. When the aggregate limit is eroded, the EngineeringFirm shall reinstate or purchase additional limits to meet the minimum limit requirements at the EngineeringFirm’s expense.

H. Deductibles and Self-Insured Retentions:The certificate of insurance shall declare the deductibles and/or self-insured retentions for all required policies.The Engineering Firm shall assume all costs related to the all deductibles or self-insured retentions.

Notice of Cancellation orNonrenewal:Each required insurance policy shall not be suspended, voided, cancelled or reduced except after thirty (30) daysprior written notice has been given to the Town, ten (10) days for non-payment.

J. Other Insurance Provisions:1) Engineering Firm’s insurance coverage shall be primary and non-contributory with respect to the Town.

Any Town insurance or self-insurance shall he excess of the Engineering Finn’s insurance and shall notcontribute with it.

- 18 -

Page 19: ARC FLASH REQUEST - BidNet

2) Required policies shall not contain any special limitations on the scope of protection afforded to the Town.

3) Required policies shall state that the insurance coverage shall apply separately to each insured against whoma claim is made or suit is brought.

4) Any failure to comply with the claim reporting provisions of the policy shall not affect coverage provided tothe Town.

K. Verification of Coverage:The Engineering Firm shall provide the Town with certificates of insurance, declaration pages, policyendorsements or provisions confirming compliance with this exhibit before work commences. The certificatesand endorsements for each insurance policy are to be signed by a person authorized by the insurer to bindcoverage on its behalf. Renewal of expiring certificates shall be filed thirty (30) days prior to expiration. TheTown reserves the right to require complete, certified copies of all required policies, at any time.

All insurance documents required by this exhibit should be mailed to: Town of West Hartford, Risk ManagementDivision, 50 South Main Street, West Hanford, Connecticut 06107.

L. Failure to Purchase or Maintain Insurance:

if the Town or the Engineering Finn is damaged by failure of the Engineering Firm to purchase or maintain therequired insurance, the Engineering Fizm shall bear all reasonable costs including, but not limited to, attorney’sfees and costs of litigation, properly attributable thereto.

Initials! Engineering Finn Initials I Town of West Hanford

Date Date

- 19-