AUGEAN EAST NORTHANTS RESOURCE MANAGEMENT FACILITY March 2012 APPENDIX CRAD ENGINEERING DAYS

Transcript of APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior...

Page 1: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

AUGEAN EAST NORTHANTS RESOURCEMANAGEMENT FACILITY

March 2012

APPENDIX CRAD

ENGINEERING DAYS

Page 2: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

Having trouble viewing this email? Click here to view it in your browser.If you do not want to receive this email anymore please click here to unsubscribe.

Engineering Days 15 August 2011

See How a Landfill Site is Engineered

Augean are currently engineering a new landfill cell at the East NorthantsResource Management Facility, Stamford Road, Kings Cliffe. We would like toinvite members of the community to come to the site and see how the new cellis expertly designed and engineered to meet the modern requirements of acontained landfill site.

The engineering is available to view each week day from Monday 5 Septemberuntil Friday 16 September from 10.00 am to 4.00pm and on Saturday 10September from 9.00am until 1.00pm by appointment. You will need to allowan hour for your visit.

As the engineering work is in progress, and the site is operational, we need tocomply with health and safety regulations, therefore if you are interestedplease book a place by contacting us by email:

[email protected]

or by telephone:

01780 444905

stating your preferred day and time of visit.

To find out more about Augean please visit our website www.augeanplc.com

Contact Us

| East Northants Resource Management Facility |

| Stamford Road | Kings Cliffe | PE8 6XX

| Tel: 01780 444905 | Email: [email protected] |

Augean PLC respects your privacy; if you do not want to receive this email anymore pleaseclickhere to unsubscribe. Having trouble viewing this email? Click here to view it in yourbrowser.

WS010001/ENRMF/CONSAPPCRAD 1

Page 3: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

Having trouble viewing this email? Click here to view it in your browser.If you do not want to receive this email anymore please click here to unsubscribe.

Engineering Days - Reminder 1 September 2011

See How a Landfill Site is Engineered

Augean are currently engineering a new landfill cell at the East NorthantsResource Management Facility, Stamford Road, Kings Cliffe. We would like toinvite members of the community to come to the site and see how the new cellis expertly designed and engineered to meet the modern requirements of acontained landfill site.

We would like to remind you that the engineering is available to view eachweek day from Monday 5 September until Friday 16 September from 10.00 amto 4.00pm and on Saturday 10 September from 9.00am until 1.00pm byappointment. You will need to allow an hour for your visit.

As the engineering work is in progress, and the site is operational, we need tocomply with health and safety regulations, therefore if you are interestedplease book a place by contacting us by email:

[email protected]

or by telephone:

01780 444905

stating your preferred day and time of visit.

To find out more about Augean please visit our website www.augeanplc.com

Landfill Design

WS010001/ENRMF/CONSAPPCRAD 2

Page 4: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

Contact Us

East Northants Resource Management Facility

Stamford Road | Kings Cliffe | PE8 6XX

Tel: 01780 444905 | Email: [email protected]

WS010001/ENRMF/CONSAPPCRAD 3

Page 5: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

Having trouble viewing this email? Click here to view it in your browser.If you do not want to receive this email anymore please click here to unsubscribe.

Engineering at ENRMF 12 October 2011

High Density Polyethylene Liner

As you may know, the new landfill cell at the East Northants ResourceManagement Facility is currently being engineered.

Our contractors, Buckingham, are making excellent progress and have now laidand compacted the clay liner and tested its permeability. Today saw the start oflaying the High Density Polyethylene (HDPE) liner.

Once more we would like to invite members of the community to come to thesite and see how the new cell is being expertly engineered and constructed tomeet the modern requirements of a landfill site.

If you are interested, you can view the engineering at the site for the next twoweeks October 17-21 and 24 -28 by appointment Monday to Friday 10.00 amuntil 4.00 pm with the Site Manager, Simon Moyle on 01780 444905 or byemailing us at [email protected]

Augean operate an open door policy at all their sites. You are welcome to visitthe site at any other time, by appointment, if there are other aspects of siteoperations that interest you.

Contact Us

| East Northants Resource Management Facility |

| Stamford Road | Kings Cliffe | PE8 6XX |

| Tel 01780 444905 | Email [email protected] |

Augean PLC respects your privacy; if you do not want to receive this email anymore pleaseclickhere to unsubscribe. Having trouble viewing this email? Click here to view it in yourbrowser.

WS010001/ENRMF/CONSAPPCRAD 4

Page 6: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

East Northants Resource Management Facility

Cell 5A Engineering

Summer 2011

WS010001/ENRMF/CONSAPPCRAD 5

Page 7: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

CQA Requirements

• The Design and CQA plan are scrutinised by the EA prior toany construction works starting

• The EA must approve the design and CQA plan

• The engineering works are supervised by an independentthird party CQA engineer.

• The independent third party CQA testing carried out duringthe works is presented in a Verification Report.

• The Verification Report is submitted to the EnvironmentAgency for review and approval.

• No waste is placed in the constructed cell until theEnvironment Agency has approved the Verification Report.

WS010001/ENRMF/CONSAPPCRAD 6

Page 8: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Cell Preparation

• A site investigation is carried out to confirm the geology ofthe site.

• Samples of clay which will be used in the engineering worksare subject to laboratory testing to confirm their suitability.

• The overburden, boulder clay & upper estuarine clay isexcavated and either stockpiled or exported from the site.

WS010001/ENRMF/CONSAPPCRAD 7

Page 9: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Excavation of Overburden

WS010001/ENRMF/CONSAPPCRAD 8

Page 10: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Excavation of Clay

WS010001/ENRMF/CONSAPPCRAD 9

Page 11: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Excavation to Top of Limestone

• The material is excavated to the top of the limestone for theexisting site.

WS010001/ENRMF/CONSAPPCRAD 10

Page 12: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Excavation to Top of Limestone

WS010001/ENRMF/CONSAPPCRAD 11

Page 13: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Geo-physical Resistivity Survey

• A non-intrusive geophysical resistivity imaging survey iscarried out of basal area to identify whether there are anysignificant fissures or voids present in the underlyinglimestone.

• If significant features are identified the actions necessary toseal the fissures or voids will be agreed with theEnvironment Agency and implemented.

• No such features have been identified to date.

WS010001/ENRMF/CONSAPPCRAD 12

Page 14: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Resistivity Survey

WS010001/ENRMF/CONSAPPCRAD 13

Page 15: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Resistivity Survey

WS010001/ENRMF/CONSAPPCRAD 14

Page 16: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Regulating Layer

• Previously excavated overburden is placed and compactedon the base of the excavation to form shallow slopes aminimum of 1v:100h which fall towards the sumps.

WS010001/ENRMF/CONSAPPCRAD 15

Page 17: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Regulating Layer

WS010001/ENRMF/CONSAPPCRAD 16

Page 18: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Clay Liner

• Previously excavated clay is placed and compacted inlayers a minimum of 250mm thick to form a low permeabilitylayer at least 1.5m in thickness across the base and up thesides of the cell.

WS010001/ENRMF/CONSAPPCRAD 17

Page 19: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Clay Liner

WS010001/ENRMF/CONSAPPCRAD 18

Page 20: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Clay Liner

WS010001/ENRMF/CONSAPPCRAD 19

Page 21: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Clay Liner

WS010001/ENRMF/CONSAPPCRAD 20

Page 22: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

CQA Testing

• During the compaction works testing is carried out by anindependent third party Construction Quality Assurance(CQA) engineer on each layer.

• The nature and the frequency of the testing of eachcomponent of the engineered containment system isspecified in a Construction Quality Assurance Plan.

• Throughout the construction works testing is carried out asspecified in the CQA Plan.

WS010001/ENRMF/CONSAPPCRAD 21

Page 23: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Compaction Testing Using NDG

WS010001/ENRMF/CONSAPPCRAD 22

Page 24: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Compaction Testing Using NDG

WS010001/ENRMF/CONSAPPCRAD 23

Page 25: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

• A 2mm thick high density polyethylene(HDPE) geomembrane is laid over thecompacted clay on base and sides.

• Joins in the HDPE membrane areformed by welding the sheetstogether. A double layer of HDPE isinstalled in the leachate collectionsumps.

WS010001/ENRMF/CONSAPPCRAD 24

Page 26: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 25

Page 27: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 26

Page 28: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 27

Page 29: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 28

Page 30: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 29

Page 31: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 30

Page 32: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of HDPE Liner

WS010001/ENRMF/CONSAPPCRAD 31

Page 33: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Protection Layer

• A protective geotextile is placedabove the HDPE membrane toprotect it from indentation ordamage.

• A drainage geocomposite isplaced over the HDPE liner onthe side slopes.

WS010001/ENRMF/CONSAPPCRAD 32

Page 34: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Protection Layer

WS010001/ENRMF/CONSAPPCRAD 33

Page 35: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Protection Layer

WS010001/ENRMF/CONSAPPCRAD 34

Page 36: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Protection Layer

• A drainage geocomposite is placedover the HDPE liner on the sideslopes.

• A 150mm thick granular layer and tyrecomposite leachate drainage blanketis placed on the base of each cell andfor at least 2m up the side walls. Thisis made up of 3000 tyre bales and1000m3 of shred.

• Leachate collection pipework isinstalled running to the sump.

WS010001/ENRMF/CONSAPPCRAD 35

Page 37: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Drainage Layer

WS010001/ENRMF/CONSAPPCRAD 36

Page 38: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Drainage Layer

WS010001/ENRMF/CONSAPPCRAD 37

Page 39: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Drainage Layer

WS010001/ENRMF/CONSAPPCRAD 38

Page 40: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Installation of Drainage Layer

WS010001/ENRMF/CONSAPPCRAD 39

Page 41: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

www.augeanplc.com

Leak Detection Testing

• A leak detection survey is carried out on the completedsystem.

WS010001/ENRMF/CONSAPPCRAD 40

Page 42: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

Serial No: 10911 1 September 2011

NEWS RELEASE

ENGINEERING OPEN DAY

EAST NORTHANTS RESOURCE MANAGEMENT FACILITY

Augean PLC is once again opening up their East Northants Resource Management Facility (ENRMF)

to the public. Following the very successful Site Open Day in June, members of the local community

will this time be able to see the construction of one of the highly engineered cells where wastes are

deposited.

At the Site Open Day it was apparent that many local people were unaware of the extent of

engineering involved in the containment systems of a landfill site such as ENRMF. As work on the

engineering of cell 5A has begun, the Company has decided that this presents a valuable opportunity

show the public the nature and extent of the engineering of a waste cell and the high degree of

environmental protection this provides.

Each weekday from Monday 5 September until Friday 16 September, the public can see the

engineering in progress between 11:00 and 16:00 and also on Saturday 10 September from 9:00 to

13:00. As the site will be operational during most of these times, for Health and Safety reason

potential visitor are asked to telephone or email the site to arrange an appointment for their visit.

Dr Gene Wilson, Group Technical Director at Augean, said, ‘Unfortunately, it is a very common

misconception that landfill sites are just holes in the ground where rubbish is “dumped”. This could

not be further from the truth. In reality landfill sites have well-considered, highly engineered

containment systems that offer a very high level of environmental protection. We look forward to

welcoming as many people as possible to the site, so that they can see this for themselves.’

If you are unable to come to the Engineering Open Day but would like more information about the

proposals or would like to be updated about the applications through our information register

please visit www.augeanplc.com or email: [email protected] or telephone: 01904

654989.

ENDS

For further information please contact:

Jennings Nicholson Associates

The Tannery

York

YO10 3WH

Telephone: 01904 679891

Email: [email protected]

WS010001/ENRMF/CONSAPPCRAD 41

Page 43: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

From: David BurgessSent: 13 September 2011 09:24To: Simon MoyleSubject: Kings Cliffe RMF: Engineering

Hi Simon

Many thanks for your time and efforts on Saturday in describing the engineering of the site.

I came away with a good overview of both the phases and QA procedures of the construction the sitecells. Sight of the labelled diagram of the cross-section of the cell construction was particularly useful aswere your descriptions of the construction processes such as the rolling of the clay and the welding of theHDPE

Regards

David Burgess

WS010001/ENRMF/CONSAPPCRAD 42

Page 44: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

From: David Hellard

Sent: 12 September 2011 21:21

To: Simon Moyle

Subject: Thank you for the tour

Simon,

Just a short thank you to you for giving me and Philip Wright such an

excellent run down on operations, activities and procedures today at your

site. Very interesting and extremely helpful. Perhaps a few more local

worthies should avail themselves of such information.

Best wishes.

David Hellard

WS010001/ENRMF/CONSAPPCRAD 43

Page 45: APPENDIX CRAD ENGINEERING DAYS€¦ · • The Design and CQA plan are scrutinised by the EA prior to any construction works starting • The EA must approve the design and CQA plan

From: William BaxterSent: 07 September 2011 18:16To: Simon MoyleSubject: Monday's visit

I wish to thank you on behalf of Steve Reed and myself for your hospitality and tour of the sitelast Monday. I found it not only very interesting, but very informative. Certainly a change from theprevious site management. So much dis-information and inaccurate talk locally, one came away with thetrue picture and a great deal of confidence. I hope you achieve your aim and the local community have abetter understanding of your facility and gain trust. I certainly was assured, particularly with theengineering, and the vehicle movements.

Again I would like to thank you and all those involved in the grant scheme, which has beengenerous towards our community and St. Kyneburgha’s church.

William Baxter, Castor Parish Council, St. Kyneburgha Parochial Church Council, Treasurer and Trustee ofSt. Kyneburgha Building Preservation Trust.

WS010001/ENRMF/CONSAPPCRAD 44