Appendix A Collaborative drainage - Water UK€¦ · A framework for the production of Drainage and...
Transcript of Appendix A Collaborative drainage - Water UK€¦ · A framework for the production of Drainage and...
A framework for the production of Drainage and Wastewater Management Plans
Appendix A Collaborative drainage and wastewater planningCommissioned by Water UK in collaboration with Defra, Welsh Government, Ofwat, Environment Agency, Natural Resources Wales, Consumer Council for Water, ADEPT and Blueprint for Water
September 2019
Report commissioned by Water UK in collaboration with Defra, Welsh Government, Ofwat, Environment Agency, Natural Resources Wales, Consumer Council for Water, ADEPT and Blueprint for Water.First issued September 2018.Updated May 2019 and September 2019.
NoticeThis document and its contents (including all associated appendices) have been prepared for Water UK. All information contained in this document and associated appendices is made available without responsibility or liability of any nature (including in negligence) on the part of Atkins Limited, and is not to be relied upon as a statement or representation of facts. Atkins Limited does not make or give, nor has any person authority on its behalf to make or give, any representation or warranty whatever in relation to the contents of this document.
3
A.1. Introduction
This appendix supplements the information provided within the main framework document for drainage and wastewater management plans (DWMPs). The main document (and appendices) aim to provide water and sewerage companies (hereinafter referred to as ‘companies’ or variations thereof), operating within England and Wales, with a framework within which DWMPs can be developed. The DWMP framework is also expected to be of relevance to other parts of the UK.
This appendix provides:
> Further information on the management structure for the level 2 strategic planning groups (section A.2);
> Additional information on approaches to facilitate effective, collaborative planning between all relevant stakeholders (section A.3).
A.2. Drainage and wastewater management planning - management structure
Information on developing the management structure has been provided in section 4.2.4 of the main methodology document. In brief, as a minimum, a three-level management structure should be developed (shown schematically in Figure A-1):
> Level 3 – the basic tactical planning unit (TPU) will be the wastewater treatment works (WwTW) and its catchment (or aggregations thereof for small catchments, or discrete sub-catchments for larger wastewater treatment works (WwTW) catchments).
> Level 2 – an aggregation of level 3 units into larger level 2 strategic planning areas (SPAs). The Level 2 SPAs are to describe the local drivers for change as well as facilitating a more strategic and collaborative level of planning above the detailed catchment assessments.
> Level 1 water company drainage and wastewater management plan – planning at level 2 and 3 to be brought together within an overarching company level DWMP to provide a strategic, long-term plan for drainage and wastewater resilience and associated investment over the plan period.
For consistency the same terminology as used in the main report will be applied here.
In respect of the level 2 SPAs, the principle is that companies endeavour to align level 2 areas with the river basin district (RBD) management catchments. These management catchments, as shown in Figure A-2, represent the level within river basin management plans (RBMPs) and flood risk management plans (FRMPs) at which actions in respect of receiving water quality and flood risk management are taken.
Aligning the level 2s in this way reflects the need for level 2s and the DWMP to take on board potential impacts on the environment and the potential impacts that flood management activities by other responsible bodies may have on company and related systems. The number of RBD management catchments that intersect with water company operating boundaries will initially define the number of level 2s for each company (however, see subsequent text on flexibility in this approach).
4
Planning Levels
Existing arrangements(beyond existing Strategic Planning Groups)
Two way dialog - DWMPs informingengagement (’live’ process), existing
arrangements informing DWMP development
Individual planningelements oraggregations
Different ‘lenses’ for different stakeholders
DWMP frameworkmanagement structure
Level 1Company Company
level DWMP
Action plansco-created with
stakeholders
Strategic PlanningGroups
Level 2Strategic Planning Area
Reporting
Planning & working together
Level 3Tactical Planning Unit
(’Building Block’)
Level 4Local Planning
Needs
DSF studies /outputs from otherplanning activities
E.g. – local planning authority
E.g. – local council
E.g. – local flood action group
Current DSFImplementation level
(individual (sub) WwTWcatchment studies)
Figure A-1 – Drainage and wastewater management plan - framework management structure
5
Table A-1 presents a GIS analysis of RBD catchment management boundaries and company operating areas and provides an indication of the potential number of level 2s per company. Further comment is provided to puts these figures into context.
Table A-1 - Potential number of RBD catchment management areas by company
Company RBD catchment management areas / potential level 2 SPAs
Anglian Water 13
Dŵr Cymru Welsh Water 13
Northern Ireland Water 11 (based on Cycle 1 data)
Northumbrian Water 6
Scottish Water 9 (based on Area Advisory Groups)
Severn Trent Water 14
South West Water 7 (including Isles of Scilly)
Southern Water 12
Thames Water 14
United Utilities 14
Yorkshire Water 7
Wessex Water 4
Figure A-2 - Potential level 2 strategic planning area boundaries; equivalent to RBD catchment management boundaries (note for Northern Ireland boundaries are based on Cycle 1)
Woodcote Grove, Ashley Road, Epsom, Surrey, PE2 6FZ.www.atkinsglobal.com
© Crown copyright and database rights (2018) Ordnance Survey (INSERT LICENCE NUMBER HERE). Contains Ordnance Survey data. © Crown copyright and database right (2018).Project: Z:\GBEMC\WGE\Projects\Cities\20160016 Katara Phase IV EIA, Qatar\4 WIP\C) EIA\temp\7.3 Map of boundaries\DWMP Map 1.mxd
±
Key
Wastewater service area boundaries
Cycle 2 WFD_River_Basin_Districts
Project Short Name (Arial, 14pt, bold, left)
Figure #.#: Insert title hereArial, 12pt, bold, left
Reference:50XXXXXX
Drawn: PMdd/mm/yyyy
Checked: PMdd/mm/yyyy
Authorised: PMdd/mm/yyyy
0 30 60 90 12015 Km
Scale (at A3): 1:3,125,168
Northern Ireland Water
Neagh BannNorth Western
North Eastern
Western Wales
Scottish Water
Anglian
Humber
Severn
Thames
South West
Solway Tweed
North West
South East
Dee
Northumbria
Anglian WaterDwr Cymru
Severn Trent Water
Thames Water
Yorkshire Water
Wessex Water
United Utilities
Southern Water
South West Water
Northumbrian Water
-80,000 -30,000 20,000 70,000 120,000 170,000 220,000 270,000 320,000 370,000 420,000 470,000 520,000 570,000 620,000 670,000 720,000
40,0
0090
,000
140,
000
190,
000
240,
000
290,
000
340,
000
390,
000
440,
000
490,
000
540,
000
590,
000
640,
000
690,
000
740,
000
790,
000
840,
000
890,
000
940,
000
990,
000
Data sources: Environment Agency, Natural England, English Heritage, Ordnance Survey
Status:S1
Purpose of issue:For coordination
Rev:REV
Model File Identifier:FILE_IDENTIFIER
WFD Cycle 2 RBD catchment management area – proposed
Level 2 Strategic Planning Area boundary
River Basin catchment management boundary
River Basin District boundary
WaSC operating boundary
6
The DWMP framework provides a management structure that operates at levels 1 and 2, drawing upon, and influencing, activities (the detailed planning and assessment) undertaken at level 3.
A more collaborative, shared planning approach coupled to an understanding of other risk management authority (RMA) plans and funding cycles is essential to the successful production of a DWMP (and resultant delivery plans that arise from it). Therefore, companies are advised to establish an early collaborative planning framework to identify where high priority risks (to achievement of planning objectives) are likely, and the issues that presents in terms of delivery of the DWMP.
As outlined in the main methodology document, it is acknowledged that in developing their existing long-term planning approaches, companies will have developed planning structures that best reflect their needs. As such, it is considered appropriate that in practice there be some flexibility around how the level 2 and 3 structures are established. The schematic diagram in Figure A-3, coupled to the following text, outlines examples where such flexibility might be appropriate:
> Companies can aggregate WwTW catchments to form larger level 3 planning areas. Individual WwTW catchments might be considered in isolation as level 4 components.
> Companies may decide that a significantly large, predominantly urban, catchment should be a level 2 SPA in its own right. In this case sub-catchment elements (e.g. terminal pumping stations and upstream network), would represent a level 3 TPU. In such cases, companies would need to be able to demonstrate how the stand-alone level 2 management area tied in with others linked to the same RBD catchment management area or areas (where the stand-alone level 2 management area crosses more than one RBD).
> It is noted that, for some companies, the approach outlined could result in a considerable number of level 2 SPAs. Companies may consider aggregating the level 2s to form larger level 2 SPAs; however, it is considered important that the alignment to RBD catchment management areas is maintained.
The structure outlines a key principle of aligning company planning areas to RBMP and FRMP areas to ensure water quality impacts and flood risk are appropriately captured within the process. It is important that, while there needs to be flexibility in the development of the planning structure, ultimately the planning areas need to be additive to define the overall DWMP. It is envisaged that as the DWMP process becomes embedded in companies’ planning processes this element of the methodology will likely become redundant and be superseded by companies’ developed management structures.
Planning Levels
NoteLevel 2 Strategic Planning Area: endeavour to align with RBD management catchmentsto capture synergies with other drivers, but provide flexibility to reflect existing arrangements
Multiple WwTWcatchments
(further aggregation)
Multiple WwTW catchments
(e.g. rural areas)
Multiple WwTWcatchments
Single WwTWcatchment
Single WwTWcatchments
WwTW sub-catchments(e.g. hydraulically
discrete areas)
All variations combine to completethe Company-wide viewIncreasing WwTW catchment
size/complexity
Level 1Company
Level 2Strategic Planning Area
Level 3Tactical Planning Unit
(’Building Block’)
Figure A-3 - Options for developing level 2 and 3 boundaries
7
A.3. Approaches to facilitate effective, collaborative planning
Collaborative drainage and wastewater planning, and partnership working, will be key to delivering resilient wastewater and drainage systems in the future and a driving principle of the DWMP framework is that better and more successful outcomes are generally more likely to be achieved by stakeholder organisations working together. The DWMP should provide the facilitation framework to ensure the essential integration of partners and co-creation of interventions and in so doing foster much greater understanding of the related needs and works of others in this space. The intention is, through collaborative planning, to identify more robust and integrated interventions that are also able to provide multiple benefits to achieve best value to the economy, society and the environment over the long term.
This section expands upon the information provided in the main document relating to the management structure proposals a DWMP, and the stakeholder engagement required to make the process work. Good drainage and wastewater planning is underpinned by collaboration with partners, and engagement with others needs to be carefully planned.
The UKWIR project, ‘How best to align the funding processes with the various bodies involved in resolving flooding’ (UKWIR, 2016)1 provides guidance that supports a common and systematic approach to unlocking collaborative opportunities. The project identified numerous examples which demonstrate that collaboration can reduce the costs of infrastructure to individual partners, unlock investment that would otherwise not be feasible, and deliver multiple benefits to the public and the environment. The report provided practical examples of assessment of costs and benefits accruing to different organisations, enabling suitable funding contributions for collaborative projects to be determined. It can be expected that organisation involved in DWMP production will closely follow the good practice detailed with the document. The DWMP will ensure good practice within the UKWIR report is brought to the forefront and, in identifying opportunities for collaboration and co-creation of measures, will add value to those mechanisms already in place.
The following are two further examples of industry good practice; organisations involved in DWMP production are encouraged to utilise such resources when planning their approach to collaboration:
> ‘Working with others’ guide produced by the Environment Agency2 - the Environment Agency have produced a guidance document detailing how they approach working with others, including the required skills and techniques. The guidance has been provided to flood risk management authorities for them to use/adapt for their own engagement purposes.
> Defra’s catchment based approach (CaBA) policy framework (May 2013)3 – the framework details the behaviours, skills and organisational culture required for successful catchment-based partnership working. The framework was based on the learning gained from over 25 catchment pilots. An accompanying ‘Guide to Collaborative Catchment Management’ was produced, with supporting appendices on methods/tools and case studies. This can be found on the website detailed in the footnote.
Appendix E (case studies) provides some further examples of good practice that will assist organisations to effectively work together to achieve DWMP objectives.
1 https://www.ukwir.org/How-best-to-align-the-funding-processes-with-the-various-bodies-involved-in-resolving-flooding2 Available upon request from the Environment Agency3 https://www.catchmentbasedapproach.org
8
A.3.1. Alignment with the plans of other risk management authorities and environmental organisations
Water companies have a duty (under the Flood and Water Management Act, 2010) to cooperate with other RMAs when undertaking drainage and wastewater planning (having been defined a RMA due to their duties arising from the Water Industry Act, 1991). In return, other RMAs “must co-operate with other relevant authorities in the exercise of their flood and coastal erosion risk management functions”. Companies “must act in a manner consistent with the national strategy” and “have regard to local strategies”. A DWMP developed in collaboration with other RMAs will help demonstrate discharging these duties. Therefore, a DWMP must demonstrate strong links with the plans of other RMAs:
> RBMPs
> FRMPs
> Local plans produced by local authorities (e.g. local flood risk management strategies, local development plans)
The DWMP should also demonstrate strong links where activities being promoted may significantly impact other plans (e.g. nutrient management plans, diffuse water pollution plans).
The DWMP provides a long term planning framework, setting out near, medium and long-term investment risks, uncertainties and planned investment requirements. In so doing, it will be essential to understand where wider drainage risks and management plans may integrate with those identified by companies to create a more integrated and resilient drainage and wastewater plan. The integration of needs and potential solutions may also identify more efficient, cost-effective delivery of outcomes. As a result, this should encourage and facilitate more collaborative planning across RMAs.
In addition, companies have an obligation to ensure that their activities, and the potential impacts on the environment, are consistent with the requirements of the Water Framework Directive and other relevant environmental legislation. It is important that companies engage and work with environmental regulators and other stakeholders as appropriate, to ensure that planning processes encompass wider environmental objectives.
Figure A-4 - The ‘working with others’ approach
Source: Environment Agency ‘Working with others, a guide for staff’ (2016)
ThinkPlanPreparewith others for
collaboration work
Step oneWHAT do we want to
achieve?
Step fiveDELIVER Let's do it!
Step threeWHO do we need to
work with?
Step twoWHY work with
others?
Step fourHOW do we work with
others?
Re-assess
Re-assess
ResultsAchieved more for
people and the environment
Step six EVALUATE How did it go and what did we learn?What might success look like for our business objectives?
What might success look like for the engagement?
What indicators will help us measure success?
How and when will we measure the success indicators we've identified?
Measure success and use feedback to revise plans
Use, learn from and share evaluation results
The Working with others approach
9
John Sutherland / Gian Illari / Brian ArkellAtkins LimitedWoodcote Grove Ashley Road Epsom Surrey KT18 5BW
Tel: +44 (0)1372 726140Fax: +44 (0)1372 740055