Future LuToN: Making best use of our runway
Preliminary Environmental Information Report Volume 3: Appendices
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | October 2019
Appendix 3-1 Alternative Options Appraised
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
11 September 2019
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019
Contents Page
1.1 Sift 1 1
1.2 Sift 2 2
1.3 Sift 3 3
1.4 Landform 4
1.5 Drainage 13
1.6 Fuel Farm 17
1.7 Fuel Farm 2.0 20
1.8 Car Park 22
1.9 Car Park Combination 13 23
1.10 Masterplan 24
1.11 Preferred option 34
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 1
1.1 Sift 1
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 2
1.2 Sift 2
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 3
1.3 Sift 3
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 4
1.4 Landform
Option 1 – Excavate ridgeline to the northeast of the existing airport up to Winch Hill Lane
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 5
Option 2 – Retain ridgeline to the northeast of the existing airport by excavating east up to Winch Hill Lane.
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 6
Option 3 – Retain ridgeline to Winch Hill by excavating both to the north and to the south of the ridgeline.
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 7
Option 4 – Retain land to the north east adjacent to Darley Road, remove material from west and east of Winch Hill Lane
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 8
Option 5
5a – Partial import of fill material into east
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 9
5b – Partial import of fill material into Winch Hill
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 10
Option 6
6a – Full import of fill material into east
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 11
6b – Full import of fill material into Winch Hill
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 12
Option 7 – Retain Wigmore Valley Park, excavate to the east of Winch Hill Lane.
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 13
1.5 Drainage
Surface water drainage strategy – Forced aeration lagoon option
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 14
Surface water drainage strategy – Waste water treatment plant option
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 15
Proposed surface water catchment areas
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 16
Proposed surface water catchment areas including existing terminal
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 17
1.6 Fuel Farm
Proposed fuel farm delivery options (Option A, B and C)
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 18
Proposed fuel farm storage options
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 19
Proposed fuel farm distribution options
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 20
1.7 Fuel Farm 2.0
Option 1: Optimal earthworks profile
Option 2: Current option
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 21
Option 3: Possible connection outside LLAL land boundary
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 22
1.8 Car Park
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 23
1.9 Car Park Combination 13
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 24
1.10 Masterplan
Western terminal
38mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 25
32mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 26
25mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 27
Central terminal
38mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 28
32mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 29
25mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 30
Eastern terminal
38mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 31
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 32
32mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 33
25mppa
Luton Airport Expansion Project
Preliminary Environmental Information Report Volume 3: Appendices
Appendix 3-1 Alternative Options Appraised
LLADCO-3B-ARP-00-00-RP-YE-0007 | Issue 1 | 11 September 2019 Page 34
1.11 Preferred option