Page 1: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Andy Martin, PE

James Kerrigan, PE

Page 2: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Need for the project Wet weather CSOs into White River

Federal Consent Decree

LTCP to reduce the CSO volume by 83% and CSO frequency to 8/yr based on typical year rainfall

Page 3: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Alternative Analysis CSO Storage Basin

In line Storage using Inflatable dam

In Line Storage using Weir Wall with Orifice

Page 4: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

CSO Storage Basin Larger footprint

Does not enable the use of existing infrastructure

Cost - $ 5.2/gal based on the EPA cost curves for open storage basins

Page 5: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Inflatable Dam Enables the use of existing infrastructure

Requires external power source

Requires security alarm – Inflatable Dam Installation in remote location

Requires control system and telemetry

Requires maintenance

Failure results in overflow event

Cost - $ 1.2/gal

Page 6: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Inflatable Dam

Page 7: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Weir Wall With Orifice

Page 8: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Weir Wall With Orifice

Page 9: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Weir Wall With Orifice Enables the use of existing infrastructure

It is a passive device

Doesn’t require external power source

Needs no maintenance

Cost - $ 0.8/gal

Page 10: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Sewer Location Map

ISD2

ISD1

Page 11: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Existing Condition of the Sewer

Page 12: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

108” Relief Sewer Max Flow Depth for Storm Events

Page 13: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Profile of the Relief Sewer

Page 14: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Site Plan for Construction – ISD 1

Page 15: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Site Plan for Construction – ISD2

Page 16: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

Working Model of In-Line Storage

Page 17: Andy Martin, PE James Kerrigan, PE - c.ymcdn.comc.ymcdn.com/sites/ Martin, PE James Kerrigan, PE . Need for the project

CSO Reduction CSO volume reduced from 84 MG to 24 MG (70%)

CSO frequency reduced from 43 to 8 times per year (81%)