Analysis of Captive Cogeneration Power Plant Upset ... · PDF fileTechniques# Machinery###...
Transcript of Analysis of Captive Cogeneration Power Plant Upset ... · PDF fileTechniques# Machinery###...
Analysis of Captive Cogeneration Power Plant Upset Scenarios using Dynamic Simulation
Software By : Arvind Kaushik – Chemical Engineer C Nageswara Rao – Mechanical Engineer Soumya Majumdar – Mechanical Engineer Ramesh Kumar G – Mechanical Engineer
Larsen & Toubro Limited – Hydrocarbon -‐ IC Research & Development -‐ Thermal Powai Works, Mumbai – 400076
India.
About Larsen & Toubro
• Turnover : US $ 11.7 bn (FY 11
-‐12)
• Employees: 50,000
• Ownership: Majority with Public
& Financial InsNtuNons
• Founded in 1938 by two Danish Engineers.
• Technology, engineering, construcNon and manufacturing company
• Ranks Among Top 5 Companies in India’s Private Sector.
• Professionally Managed since IncepNon.
• Successful Track Record in Oil & Gas, Refinery, Power, Petrochemicals, Cement & Infrastructure.
• Network of Offices Worldwide.
• State-‐of-‐the-‐art Manufacturing FaciliNes in India and Oman .
2
OCEAN ENGG.
Reforming & syngas related Processes
Hydrogen, Ammonia & Methanol
Gas Processing
SeparaUon Process
Well head & Process plaVorms
Water Treatment
DesalinaUon
-‐ RO -‐ Thermal
STP / ETP
Recycling
CHEMICAL ENGG.
WATER TECHNOLOGIES
Fired Heaters
Modular Systems
Super CriUcal Boilers
Power plant SimulaUon
CFD
THERMAL ENGG.
MECHANICAL ENGG.
MATL. SCI. & CORROSION
Stress Analysis
Structural Analysis
Piping Analysis
Experi-‐ mental Techniques
Machinery & System Design
Machinery / Structural DiagnosUcs
Rotor Dynamics & Tribology
ROTATING MACHINERY
Equip. Metallurgy
Cathodic ProtecUon
Residual Life Assessment
Composites Failure Analysis Corrosion Control)
Research & Development, Hydrocarbon IC
4
1. Study the effects of load disturbances on the system.
2. Study the effects of any one equipment trip or mulNple equipment trip . The trips could be isolated events or cascade.
3. To define, design and refine the operaNons / control philosophy, system and mechanism of a given power plant / system.
4. To test the plant operaNon under various modes of operaNon.
5. Tuning and adjustment of controller parameters.
6. Off-‐line training of plant operators.
5
1. Modular approach to mathemaNcal modeling of power plants.
2. One or more modules represents one equipment (e.g. boiler, turbine, valve, pipe, pump, duct , fan, motor, transformer, generator, etc., )
3. The plant/system model is created by interconnecNng modules through ports.
4. An MMS model is processed through automated steps that produce a simulaNon executable.
5. Programming languages – ACSL, Fortran and Visual C++.
6. Library of various modules – Electrical, Mechanical, BoP and Controls.
Features of Modular Modeling System (MMS) Soiware
6
1. Choice of integraNon algorithms such as Euler, Runge–kuja, Gear, Adam-‐Smith etc.,
2. AutomaNc sorNng and sequencing of differenNal equaNons for soluNon.
3. User needs to have understanding of ACSL, to build and execute models.
4. Knowledge of Visual C++ required if one needs to develop new modules.
5.In-‐built simplified property rouNnes for water, air, and fuels etc,
6. Vendor – nHance Technologies , US.
Features of MMS soiware – Contd.
7
1. Steady state heat balance diagram.
2. P&I diagram.
3. G.A. drawings.
4. Equipment specificaNon sheets (Pumps, Control valves, HX, etc).
5. Control system logic diagrams and descripNon.
6. OperaNon and control philosophy.
7. Start-‐up sequence.
8. Shut down sequence.
Dynamic Model PreparaNon – Data Required.
8
Modeling Sequence
Define the System
Boundaries and gather equipment
data
Generate model of
each equipment
and test
Link the equipment modules
Execution and
achieving the steady
state operation
Controller tunings
Generate upset
conditions Get results and analyze
Tie to a training
simulator, if desired
9
5 nos. Boilers – Thermax.
4 nos. Steam turbines; Triveni – 11.8 MWe base load; Condensing
4 nos. Generators – 11 kVA .
5 nos. deaerators.
5 no. boiler feed water pumps along with drive turbines
3 nos. power fluid pumps and 3 nos. injecNon water pumps
BOP (PRDS; De-‐aerators, Pipes, Pumps, Valves, condenser, FD fans, etc)
Transformers, Electrical network bus, Electrical motors, etc.
Major Equipment Modeled
LC
LC
PC
PC
PC PC
Boiler 1 Boiler 2 Boiler 3 Boiler 4 Boiler 5
STG 2 STG 4
PC
PC
PC
HP STEAM HEADER
MP STEAM HEADER
MP CONDENSATE HEADER
STG 1
ProducNon Heaters InjecNon
Heaters Offspec Oil / Skim Oil Heaters
Tank / Vessel Heaters
MP CONDENSATE FLASH DRUM
LP CONDENSATE FLASH DRUM
InjecUon Water Pump Turbines Power Fluid Pump Turbines Boiler Feed Water Pump Turbines
D D D D D D
S
ATM
ATM
ATM
Deaerators UNlity StaNons
600 psig & 700F 41.4 barg & 371°C
100 psig & 338F 6.9 barg & 180°C
7.2 psig & 234F 0.5 barg & 112°C
D D D D D PC D
S ATM
S ATM ATM
S ATM S S
ATM
STG 3
ATM
FC LC
To Deaerator To Deaerator To Deaerator To Deaerator
To BFW Pump To BFW Pump To BFW Pump To BFW Pump
To Boiler 2 To Boiler 3 To Boiler 4 To Boiler 5
BFW Makeup Tank Demineralised
Water Make-‐Up
N2 Blanket
LC Deaerator
ATM
43 psig & 304F 3 barg & 173°C
Thumbli Water Wells
Filter Package
DesalinaNon Package Condensate
Polishing Package
SCHEMATIC DIAGRAM: STEAM AND POWER GENERATION SYSTEM
AcNvated Carbon Filter Package Treated Condensate Storage
Tank
N2 Blanket
LP STEAM HEADER
LP CONDENSATE
ACC
ACC
LEGEND
STG Steam Turbine Generator
LP Low Pressure
MP Medium Pressure
HP High Pressure
ACC Air Cooled Condenser
ATM Atmospheric
PC Pressure Control
LC Level Control
FC Flow Control
D S
Desuperheater
Silencer
ACC
LC
LC
ACC ACC ACC
ATM ATM ATM
ATM LC LC LC
G1 G2 G3 G4
SB1 SB2 SB3 SB4 SB5 SB6
Well Pads Well Pads OperaNons Base
M1 M2
M3 M4
M5 M6
M7 M8
M9 M10
M11 M13 M12 M14
6.6 kV Motors
EM8 EM1
6.6 kV Emergency Motors/Loads
SB7 SB8 SB9 SB10 SB11 SB12 SB13 SB14
EM2 EM3
EM4 EM5
EM6 EM7 EM9
EM10 EM11
EM12 EM13
EM14 EM15
6.6 kV Bus
33 kV Bus
11 kV Bus B
6.6 kV Emergency Bus
11 /0.433 kV 11 /6.9 kV
SS SS
11 /6.9 kV
11 /6.9 kV 11 /6.9 kV
11 /35 kV 11 /35 kV
6.6 /0.433 kV
415 V Split Bus
415 V Split Bus
GENERATORS; 15 MVA,
12 MW, 11 kV, 3φ, 50 Hz 11 kV Bus A 11 kV Bus C
Plant Configuration (Electrical System)
TRANSFORMERS
EG1 EG2 EG3
EMERGENCY DIESEL GENERATORS
11
12
Control Systems Implemented
• UUlity Boilers
– Three-‐element / single element drum level control based
on steam drum level, Steam flow rate and the Feed water
flow rate.
– Firing rate control based on HP header pressure.
– Air fuel raNo control by FD fans
– Temperature control of steam by desuperheaNng
13
Control Systems implemented (Contd.)
• Steam Turbines
– Turbine Governor Model (vendor’s Controller Block
Diagram and Transfer FuncNon Diagram)
– Mechanical Power output, MW.
• Generators
– AutomaNc Voltage Regulator (AVR) vendor’s Transfer
FuncNon Diagram
14
Control System implemented (contd..)
• De-‐aerator
• Pressure & Level • Steam turbine drives for pumps
• BFW pump rpm is controlled based on steam flow
• Discharge pressure of power fluid pump is maintained @
203.91 bar) by controlling steam flow to the PF pump drive
turbine.
• InjecNon water pump discharge pressure is maintained at
121.02 barg • Soh starter for start-‐up of the power fluid pump motor
Work Procedure Step 1 -‐ Data Gathering
• Process flow diagrams, Heat Balance diagram and P&I diagram.
• Equipment specificaNons, physical and Geometric Details data • OperaNng parameters data, allowable metal temperatures.
• Control Valves, controllers specificaNons, and • Control system logic descripNon.
Step 2 -‐ Data Input to Modules and Individual Module TesUng • Fuel System
• Boilers complete with the Boiler feed pumps, economizer, superheater FD fans etc.,
• Steam Turbines with Condensers
• Generators • Heavy Duty Pumps with motors, • Heat Exchangers, InterconnecNng Pipes Valves etc.,
15
Work Procedure (Contd.)
Step 3 – InterconnecUng the Modules and System TesUng • Preliminary runs of the model to test the operaNon performance.
• Achieving trouble-‐free steady state operaNon of the plant matching with heat balance diagram.
Step 4 – Modeling disturbances, study and analyze their effects. • One Boiler trips. • One steam turbine trips.
• One steam turbine driven power fluid pump trips. • One electric motor power fluid pump trips.
• One boiler feed water pump trips.
• Fuel change-‐over from Fuel gas to Diesel.
• Plant Start-‐Up.
Step 5 – Suggest remedial acUon, if any. 16
Different Modes of Operation of Steam Turbines Modeled in the Project.
MODE -‐ A : 1 ST in Isochronous Mode and 3 STs in Droop Mode with Remote AutomaNc Set Point Change.
MODE -‐ B : 1 ST in Isochronous Mode and 3 STs in Droop Mode.
MODE -‐ C : All four STs in Droop Mode.
17
Note: This presentaUon gives results for all STs operaUng in MODE C
Features Considered for Modeling All Upset Conditions
All five boilers operaNng with HP Steam Header Pressure control on fuel firing in steady state.
All four steam turbines operaNng in DROOP Mode.
Steam Turbine Governor Model implemented as given by the Vendor (Triveni).
AutomaNc Voltage Regulator (AVR) implemented as given by Vendor (ABB).
Soi Starter modeled for start-‐up of Power Fluid Pump Motor.
18
Operating Parameter Trends When One Out Of Five Boilers Trips
Case of Steam Load Shedding To Maintain Plant Frequency
1 Boiler Trip Case Results 19
Upset Condition – One Boiler Trip
Steam supply lost due to the boiler trip = 110 TPH.
Steam deficiency will be met by remaining four Boilers
ramping up @ ~30 tph/min.
Steam supply to one InjecNon Water Pump Turbine is
stopped .
MP steam header pressure drops.
Flow through the HP to MP steam PRDS will increase to
maintain MP steam header pressure. 20 1 Boiler Trip Case Results
List of Control Actions – One Boiler Trip
IsolaNng Boiler steam line from HP steam Header.
Switching off Fuel supply to the tripped Boiler.
Closing the Boiler Feed water valve.
ConNnue 1 BFW Pump of tripped boiler in a minimum recycle mode.
FD Fan of the tripped boiler conNnues to operate at a reduced load.
IsolaNng boiler blow-‐down valve.
IsolaNng Boiler from BFW distribuNon Header.
To maintain plant frequency, steam load shedding is done by stopping one InjecNon water pump turbine drive and corresponding pump within a duraNon of 2 seconds of trip of the boiler.
Closing the XSVs on sucNon line to the turbine driven InjecNon Water pump .
No Electrical load shedding is required to be considered in this case 21 1 Boiler Trip Case Results
Effect on other operating boilers parameters- Flow (-------) kg/s, Pressure (-------) Pa, Temperature (-------) oC.
1 Boiler Trip Case Results
With drop in HP Steam Header pressure the remaining 4 Boilers Ramp by approx. 30 TPH/min
22
Effect on MP steam header pressure & steam Plow through the PRDS.
1 Boiler Trip Case Results
Flow through HP to MP PRDS increases to maintain the MP Steam Header Pressure.
23
1 Boiler Trip Case Results
Effect on steam Plow (---) kg/s and Power (----) MW of one boiler trip.
24
1 Boiler Trip Case Results
Effect on Plant Frequency, Hz
Plant frequency is maintained within acceptable limits (> 49).
The drop is due to the fall in HP Steam Pressure
25
Observations – One Boiler Trip
Due to a sudden shorvall of 110 tph steam the HP header pressure falls sharply from 43 barg to 33-‐34 barg.
It takes around 10 minutes for the HP header pressure to stabilize at a new value of 34 barg.
To stabilize the HP steam header pressure: Remaining 4 boilers are ramped-‐up to their maximum capacity InjecNon Water Turbine driven Pump is tripped aier 2 seconds.
HP Steam header pressure stabilizes at 34 bar.
Plant Frequency is maintained within acceptable limits so that there is no need for the load shedding.
26 1 Boiler Trip Case Results
1 Steam Turbine Trip Results
Operating Parameter Trends When One Out Of Four Steam Turbines Trips
Case of Electrical Load Shedding To Maintain Plant Frequency
27
Upset Condition – One ST Trip
Power Lost from Steam Turbine = 8.67 MW
The remaining 3 operaNng STGs ramp up to compensate for the power loss due to 1 Steam turbine trip.
To maintain plant frequency, electrical load shedding is done.
28 1 Steam Turbine Trip Results
List of Control Actions – One ST Trip
-‐ IsolaNng the tripped Steam Turbine from the HP steam Header.
-‐ IsolaNng the Generator connected to the tripped Turbine from the connected 11 kV Bus.
-‐ Total electrical load shedding of 5.171 MW is considered to keep frequency within a range of 48.5 to 51.5 Hz by tripping one motor driven IW pump and one export oil pump.
29 1 Steam Turbine Trip Results
Effect on 11 kV Bus Voltage, kV
1 Steam Turbine Trip Results
11 kV Bus voltage dips to a minimum 8.98 kV.
DuraNon of voltage dip below 9.9 kV is 0.8 s.
Thereaier the 11 kV Bus Voltage stabilizes within 40 seconds.
30
Fig.1 Total Plant Power MW
Effect on Plant Frequency, Hz
The plant stability is achieved by ramping remaining STs to 11.22 MW & shedding 5.17 MW load aier a Nme interval of 0.5 s.
If the electrical load shedding of 3.8 MW is done by tripping only one Motor Driven IW Pump then the frequency drops to 48 Hz.
Min. Frequency is 48.54 Hz.
31 1 Steam Turbine Trip Results
1 Steam Turbine Trip Results
Effect on operating boilers parameters- Steam Flow (-------) kg/s, Pressure (-------) Pa, Temperature (-------)
oC.
32
Boiler 1 Drum level (----) m, Feedwater Plow (----) kg/s & Steam generation (-----) kg/s
1 Steam Turbine Trip Results 33
1 Steam Turbine Trip Results
Tripping of ST results in short-‐fall of 8.67 MW of power. The plant stability is achieved by ramping remaining STs to 11.22 MW & shedding 5.17 MW of electrical load within a Nme interval of 0.5 s.
The maximum drop in frequency is up to 48.54 Hz.
If Electrical Load Shedding of 3.8 MW is done by tripping only one Motor Driven InjecNon Water Pump then the maximum drop in frequency is upto 48 Hz.
Immediately aier the trip due to sudden loss of power generaNon the 11 kV Bus voltage dips to a minimum value of 8.98 kV and the voltage dip is for a total duraNon of 0.8 s.
Thereaier the 11 kV Bus Voltage recovers back to 11 kV and stabilizes within 40 seconds.
Observations – One ST Trip
34
Operating Parameter Trends When Steam Driven PF Pump Trips
Case of Additional of Electrical Load
1 Boiler Trip Case Results 35
Upset Conditions - Steam Driven PF Pump Trips
Auto start of 1 Motor driven PF Pump aier the turbine driven pump trips.
Power GeneraNon from the steam turbines ramp-‐up to make up for the addiNonal electrical load of 4.583 MW to the Plant.
Soi Starter is modeled for the start up of motor driven PF Pumps having an iniNal voltage of 0.3 Nmes of the full voltage and a voltage ramp rate to achieve the full voltage within 20 seconds.
36 1 Steam Turbine Trip Results
List of Control Actions - Steam Driven PF Pump Trips
-‐ Tripping one Power Fluid Pump Turbine Drive.
-‐ IsolaNng PF Pump Turbine Drive from HP Steam Header.
-‐ Closing XSV on sucNon line of PFP.
-‐ Opening XSV on sucNon line to motor driven PFP.
-‐ Switching on the motor for the PFP by closing the Breaker connecNng it to the 6.6 kV Bus.
-‐ No Electrical Load Shedding is considered in this case.
37 1 Steam Turbine Trip Results
Fig.2 11 kV Bus Voltage, kV
Fig.1 Plant Frequency, Hz
Results for 1 PFP Changeover from Turbine Drive to Motor Drive
11 kV Bus Voltage drops to a minimum of 10.24 kV, 11.7 s aier the changeover.
At the instant the motor achieves its full speed, 11 kV Bus Voltage goes up to 15.7 kV.
Voltage stabilizes within 90 s.
The minimum Plant frequency is 48.38 Hz.
The dip in plant frequency below 48.5 Hz is for 4 s.
Plant Frequency stabilizes at a lower value of 49.79 Hz.
Fig.3 HP Steam Header Pressure, Pa
Fig.4 MP Steam Header Pressure & PRDS Flow
Results for 1 PFP Changeover from Turbine Drive to Motor Drive
Due to a sudden reducNon in HP steam consumpNon HP steam header pressure rises to 43.6 bar.
Sudden Loss of 61 TPH of HP Steam results in MP Steam Header pressure drop.
57.6 TPH of HP Steam is diverted through the HP to MP Header PRDS to maintain MP Steam Header Pressure.
Results for 1 PFP Changeover from Turbine Drive to Motor Drive
Fig.6 Total Electrical Load, MW
Corresponding to 11 kV bus voltage reaching a peak of 15.7 kV the total electrical load also reaches a peak of 55 MW resulNng in the plant frequency dipping to a minimum of 48.38 Hz.
Increase in Electrical Load corresponding to the addiNon of PF Pump Motor of 4.583 MW.
The motor achieves full speed within 28 seconds.
At the same instant the motor torque and the motor current drops rapidly, hence, the voltage goes up to a maximum of 15.7 kV.
Fig.5 PFP Motor Parameters
11 kV Bus Voltage drops to and reaches a minimum of 10.24 kV 11.7 s aier the changeover.
At the instant the motor achieves its full speed, 11 kV Bus Voltage going up to a maximum of 15.7 kV.
The 11 kV bus voltage exceeds 12.1 kV in a single peak for a total duraNon of 3.5 s. Thereaier the 11 kV bus voltage is stable.
Total electrical load also reaches a peak of 55 MW resulNng in the plant frequency dipping to a minimum of 48.38 Hz.
The dip in plant frequency below 48.5 Hz is for 4 seconds.
HP steam header pressure peaks to a maximum of 43.6 bar and this results in immediate reducNon in steam output from the boilers to bring the HP header pressure back to 42.5 bar.
Aier the PFP changeover is complete the plant frequency stabilizes at a lower value of 49.79.
This phenomenon is as per reducNon in turbine speed with increase in load as per Droop curve.
Observations - Steam Driven PF Pump Trips
Results for 1 PFP Changeover from Turbine Drive to Motor Drive
It is significant to note that steam load shedding is required during one boiler trip, whereas electrical load shedding is necessitated by the Steam Turbine trip.
MMS soiware from nHance Technologies Inc., is a robust, convenient and powerful tool available to the Power Plant equipment and control systems designers and analysts to predict performance of a given power plant to meet a given duty.
The power plant thermal and electrical systems and the associated downstream plants can be designed for all conNngencies with the performance predicNons available by using the MMS Soiware.
Conclusions
42
A complete thermal and electrical systems modeling was done using MMS Soiware from nHance Technologies Inc. for the 48 MWe thermal power plant.
Significant insights were gained about the power plant operaNon in island mode and the effect of various disturbances (i.e. equipment trips)
Although the study was carried out for a large number of cases such different operaNng loads during years 2, 4 and 6 of operaNon, start-‐up of the plant and the fuel change over etc. and with various turbine governor operaNng modes, this presentaNon is for two trips cases for year 6 (full load) operaNon.
Contd.
Conclusions
43
Author ProPiles
Mr. Arvind Kaushik is a post graduate (M.Tech) Chemical Engineer from Indian InsNtute of Technology (IIT) Kanpur, India, since 1990. He has wide experience of over 23 years in the design of thermal equipment, process opNmizaNon, energy conservaNon in process plants, dynamic simulaNon of process and power plants, commissioning and trouble-‐shooNng in India and overseas. At present, as Sr. Dy. General Manager (R&D) at Larsen & Toubro Limited, Mumbai, India, he is leading a team of Mechanical and Chemical Engineers in the Thermal Engineering Group of Research & Development for innovaNons in design of waste heat recovery equipment. His areas of interest include solar thermal energy, low temperature thermal desalinaNon, thermal energy storage systems, dynamic simulaNon of power plants, energy opNmizaNon of industrial processes and commissioning and trouble-‐shooNng of process equipment. E-‐mail: [email protected]
44
Author ProPiles (Contd.)
Mr. C. Nageswara Rao completed his Masters in Design & ProducNon of Thermal Power Equipment from NaNonal InsNtute of Technology, Trichy in 2004 and has since been working with R&D-‐Hydrocarbon IC of Larsen & Toubro. His work experience is in the areas of thermal design of Fired Heaters, Shell & Tube, Air-‐Cooled exchangers, Waste Heat Recovery Coils. He has also used CFD tools for criNcal troubleshooNng acNviNes and has carried out Dynamic SimulaNon studies of two capNve power plants. His other interests include design of specialized heat recovery equipment and energy efficiency of power plants. E-‐mail: [email protected]
45
Author ProPiles (Contd.)
Mr. Soumya Majumdar is Master of Technology in Mechanical Engineering (specializaNon in Fluid Mechanics & Thermal Science) from IIT Kanpur in 2004. At present he is working as a Manager in Thermal Engineering group of Research & Development -‐ Hydrocarbon Division at Larsen & Toubro Limited, Mumbai, India. Mr. Majumdar has worked in the areas related to the thermal design, analysis and troubleshooNng of heat transfer equipment such as Shell & Tube Heat Exchangers, Air Cooled Heat Exchangers, Waste Heat Recovery Coils and Waste Heat Recovery Boilers for various Hydrocarbon projects. He has also worked in the area of thermo-‐hydraulic design of regeneraNve type pebble-‐bed and cored-‐brick bed heaters. His varied work experience and field of interest also includes Dynamic SimulaNon of Power Plants and Process Gas Compression modules. E-‐mail: [email protected]
46
Author ProPiles (Contd.)
Mr. Gajam Ramesh kumar earned his Masters in Thermal Engineering from NaNonal InsNtute of Technology, Warangal. He did his thesis work on “ReacNve Flow Field Analysis using CFD” at Defense Research & Development Laboratory (DRDL), Hyderabad. At present he is working at the Research and Development Department (PRDH) of Larsen & Toubro Limited, Mumbai (India). The areas of his experNse are dynamic simulaNon of power plants, thermal design / analysis / trouble shooNng of heat transfer equipment such as S&T, ACHE, PFHE, WHR coils etc and other special heat transfer and fluid flow studies. E-‐mail: [email protected]
47