ANALYSIS OF ALTERNATIVES (TECHNOLOGY)

474
E E N N V V I I R R O O N N M M E E N N T T A A L L I I M M P P A A C C T T A A S S S S E E S S S S M M E E N N T T / / E E N N V V I I R R O O N N M M E E N N T T A A L L M M A A N N A A G G E E M M E E N N T T P P L L A A N N For Expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill At Village: Heti, Tahsil: Umred, District : Nagpur, Maharashtra Project Proponent M/s Topworth Urja and Metals Ltd. EIA Consultant Pollution and Ecology Control Services, Nagpur NABET No. 118

Transcript of ANALYSIS OF ALTERNATIVES (TECHNOLOGY)

  • EENNVVIIRROONNMMEENNTTAALL IIMMPPAACCTT AASSSSEESSSSMMEENNTT//

    EENNVVIIRROONNMMEENNTTAALL MMAANNAAGGEEMMEENNTT PPLLAANN

    FFoorr

    Expansion of Sponge iron plant, Induction furnaces,

    TMT Rolling mill & installation of Ferro alloys unit,

    Alloy steel billet plant, Rolling mill and Structure mill

    At

    Village: Heti, Tahsil: Umred, District : Nagpur,

    Maharashtra

    Project Proponent

    M/s Topworth Urja and Metals Ltd.

    EIA Consultant

    Pollution and Ecology Control Services,

    Nagpur

    NABET No. 118

  • I

    INDEX

    Sr.

    No.

    Particulars Page No.

    Chapter 1- Introduction 1 19

    1.0 Introduction 1

    1.1 Profile of Project Proponent 1

    1.2 Site Selection Criteria 2

    1.3 Details of the Project Site 2

    1.4 Purpose of the EIA 7

    1.5 Need for the Project 7

    1.6 Scope of the Study 9

    1.6.1 Environmental Impact Assessment 13

    1.6.2 Preparation of Environmental Management Plan 13

    1.6.3 Contents of the Report 14

    1.7 Site Photographs 16

    Chapter 2- Project Description 20 - 64

    2.1 Plant Layout 20

    2.1.1 Project Cost 22

    2.1.2 Production Scenario 23

    2.1.3 Raw Material Requirement 24

    2.1.4 Water Requirement 24

    2.1.4.1 Water Treatment Plant 29

    2.1.5 Power Requirement 30

    2.1.6 Land Requirement 31

    2.1.7 Employment potential 32

    2.1.8 Transport 32

    2.2 Process Details 32

    2.2.1 Ferro Alloys Plant for 50000 TPA Capacity 33

    2.2.2 4 LAC TPA Electric Arc Furnace Based Alloy Steel Billet Plant 36

    2.2.3 Enhancement of Capacity From 240 TPD TO 480 TPD by Installing 2 X 12 48

  • II

    Sr.

    No.

    Particulars Page No.

    Ton Induction Furnace Based Steel Billet Plant and Installation of Ladle

    Refining Furnace

    2.2.4 TMT Bars Rolling Mill Capacity Enhancement From 66000 to 150000 TPA 53

    2.2.5 Proposed 1.5 Lacs TPA Light Section Rolling Mill 56

    2.2.6 Proposed 2.5 Lacs TPA Heavy Section Rolling Mill 58

    2.2.7 Expansion of Existing Sponge Iron Plant Capacity from 60,000 TPA to

    2,91,000 TPA by Installing 2 X 350 TPD Rotary Kilns and other Ancilliary

    Units

    60

    2.3 Fire Fighting System 63

    2.4 Health and Sanitation Facilities 64

    Chapter 3- Description of the Environment 65 - 127

    3.1 Introduction 65

    3.2 Climate 67

    3.3 Meteorology 68

    3.3.1 Wind Speed And Wind Direction 68

    3.3.2 Findings 68

    3.3.3 Temperature And Humidity 69

    3.3.4 Rain Fall 70

    3.4 Ambient Air Quality 70

    3.4.1 Methodology of Monitoring 70

    3.4.2 Frequency for Monitoring 71

    3.4.3 Observations 71

    3.5 Noise Environment 85

    3.5.1 General 85

    3.5.2 Locations of Noise Level Monitoring 85

    3.5.3 Parameters Measured During Monitoring 87

    3.5.4 Method of Monitoring 87

    3.5.5 Observations 88

  • III

    Sr.

    No.

    Particulars Page No.

    3.5.6 Ambient Noise Level Standards 89

    3.6 Hydrogeology 89

    3.6.1 Consolidated Formations 89

    3.6.2 Semi-Consolidated Formations 90

    3.6.3 Unconsolidated Alluvial Formations 90

    3.7 Geology 91

    3.8 Water Quality 93

    3.8.1 Location of Sampling Stations 93

    3.8.2 Methodology for Sampling 94

    3.8.3 Analytical Techniques 96

    3.8.4 Observations 96

    3.9 Soil Quality 102

    3.9.1 Location of Sampling Sites 102

    3.9.2 Methodology of Sampling 104

    3.9.3 Methodology of Analysis 104

    3.9.4 Observations 105

    3.9.5 Standard Soil Classification 108

    3.10 Land Use Pattern 111

    3.10.1 Satellite Imagery Based Landuse pattern 111

    3.10.2 Census Based Landuse pattern 114

    3.11 Socio- Economic Environnent 118

    3.11.1 Base line Data 118

    3.11.2 Demographic Structure 118

    3.11.3 Economic Resource Base 119

    3.11.4 Health Status 119

    3.11.5 Cultural and Aesthetic Attributes 119

    3.11.6 Socio-Economic Survey 120

    3.12 Positive and Negative Impact on Demography and Socio-Economics 126

  • IV

    Sr.

    No.

    Particulars Page No.

    Chapter 4 : Anticipated Environmental Impacts & Mitigation Measures 128 - 144

    4.1 General 128

    4.2 Air Environment 129

    4.2.1 Construction Phase Impacts and Mitigation Measures 129

    4.2.2 Operation Phase Impacts and Mitigation Measures 130

    4.2.3 Simulation Model for Prediction using Industrial Source Complex

    AERMOD View

    132

    4.3 Water Environment 139

    4.3.1 Wastewater Generation 139

    4.4 Noise Environment 140

    4.4.1 Construction Phase Impact 140

    4.4.2 Operation Phase Impact 140

    4.4.3 Mitigation Measures 140

    4.5 Land Environment 141

    4.5.1 Source of Soil Pollution 141

    4.5.2 Impact and Mitigation Measures 141

    4.6 Solid Waste 142

    4.7 Socio Economic Environment 143

    4.8 Impact on Ecology and Mitigative Measures 143

    4.9 Greenbelt Development Plan 144

    4.9.1 Effect on Plant 144

    Chapter 5 : Analysis of Alternatives (Site & Technology) 145 - 147

    5.1 Analysis of Site Selection 145

    5.2 Alternate Technology 146

    5.3 Conclusion 147

    Chapter 6 : Environmental Monitoring Programme 148 - 154

    6.1 Environmental Monitoring Programme 148

    6.1.1 Environment Monitoring Cell 148

  • V

    Sr.

    No.

    Particulars Page No.

    6.1.2 Environmental Monitoring and Control 148

    6.1.2.1 Monitoring Schedule 149

    6.1.2.2 Plantation Monitoring 151

    6.1.2.3 Health Monitoring 151

    6.1.2.4 Action Plan 151

    6.2 Monitoring Equipment 151

    6.3 Reporting & Documentation 153

    6.4 Budget & Procurement Schedule 153

    Chapter 7: Additional Studies 155 - 179

    7.0 Social Impact Assessment 155

    7.1 Ecological Biodiversity 155

    7.2 Corporate Social Responsibility 155

    7.3 Risk Assessment 155

    7.4 Identification of Hazards/Risk 155

    7.4.1 Material Hazards 156

    7.4.2 Fire and Explosion Index 156

    7.5 Consequence Analysis 159

    7.6 Conclusions and Recommendations 161

    7.7 Risk Mitigation Measures 163

    7.8 Disaster Management Plan 164

    7.8.1 On-Site Emergency Plan 166

    7.8.2 Offsite Emergency Plan 177

    Chapter 8: Project Benefits 180 - 182

    8.1 Socio Economic Benefits 180

    8.2 Benefits to the Infrastructure 181

    8.3 Other Benefits 181

    8.4 Conclusion 182

    Chapter 9: Environmental Management Plan 183 - 216

  • VI

    Sr.

    No.

    Particulars Page No.

    9.1 Introduction 183

    9.2 Environmental Management Plan 183

    9.3 Details of Environmental Management Plan 184

    9.3.1 During Construction Phase 184

    9.3.1.1 Air Environment 184

    9.3.1.2 Water Environment 185

    9.3.1.3 Solid Waste 185

    9.3.1.4 Noise Environment 185

    9.3.1.5 Land Environment 186

    9.3.1.6 Ecology 186

    9.3.1.7 Socio-Economic 186

    9.3 During Operation Phase 187

    9.3.1 Air Environment 187

    9.3.2 Water Environment 193

    9.3.3 Solid Waste 194

    9.3.4 Noise Environment 196

    9.3.5 Land Environment 197

    9.3.6 Biological Environment 197

    9.3.6.1 Green Belt Development Plan 197

    9.3.7 General Considerations 204

    9.4 Occupational Health and Safety 205

    9.4.1 Hazards and health 205

    9.4.2 Physical Hazards 206

    9.4.2.1 Noise 206

    9.4.2.2 Heat Stress 208

    9.5 Environmental Organization 211

    9.6 Action Points Under CREP 213

    Chapter 10: Summary and Conclusion 217 - 225

  • VII

    Sr.

    No.

    Particulars Page No.

    10.1 Project Description 217

    10.2 Description of Environment 217

    10.3 Anticipated Environmental Impacts and Mitigation Measures 220

    10.4 Environmental Monitoring Programme 223

    10.5 Additional Studies 224

    10.6 Project Benefits 224

    10.7 Environment Management Plan 225

    Chapter 11: Disclosure of Consultant 226 - 227

  • VIII

    LIST OF TABLES

    Sr. No. Particulars Page No.

    1.1 Details of the Project 6

    1.2 List of the Industries Around the Project Site 9

    1.3 Applicable Acts and Guidelines for the Proposed Project 11

    2.1 Breakup of Proposed Investment 22

    2.2 Existing and Proposed Production Capacities 23

    2.3 Utility Requirement 23

    2.4 Raw Materials Requirements & Sources 24

    2.5 Water Balance 26

    2.6 Power Consumption 31

    2.7 Break-up of Land Use 32

    3.1 The schedule of Environmental Monitoring Programme 66

    3.2 Monitored Parameters and Frequency of Sampling 71

    3.3 Description of Ambient Air Monitoring Stations 72

    3.4 A to I AAQ Observations 74 - 81

    3.5 A to B Summarized report of Ambient Air Quality 82

    3.6 National Ambient Air Quality Standards 83

    3.7 Details of Sampling Stations of Noise Level Measurement 85

    3.8 Measured Noise Levels at Monitored Stations 88

    3.9 National Ambient Noise Level Standards 89

    3.10 Surface and Ground Water Sampling Stations 93

    3.11 Standard operating procedure (SOP)for water and wastewater sampling 95

    3.12 Methodology for sampling and analysis of water & wastewater 96

    3.13 Analysis Report of Surface and Ground Water Samples 97

    3.14 Details of Soil Sampling Locations 102

    3.15 Analytical Techniques for Soil Analysis 104

    3.16Ato C Soil Results 105 - 107

    3.17 Standard soil classification 108

    3.18 Landuse/ Land Cover Breakup 114

  • IX

    LIST OF FIGURE

    3.19 Land use pattern based on Census data 2001 115

    3.20 Summary of Demographic Structures in the Study Area 121

    3.21 Village Wise Demographic Structure of the Study Area 122

    3.22 Employment pattern 123

    4.1 Stacks & Emissions details of M/s Topworth Urja and Metals Ltd 131

    4.2 Resultant Concentrations of Particulate Matter (PM10) due to incremental

    GLCs

    135

    4.3 Resultant Concentrations of Sulphur dioxide (SO2) due to incremental GLCs 137

    4.4 Resultant Concentrations of Oxides of Nitrogen (NOx) due to incremental

    GLCs

    139

    4.5 Solid waste Generation 142

    6.1 Monitoring Schedule for the Environmental Parameters 150

    6.2 Budgetary for Environment Management and Monitoring 154

    7.1 Storage details of High Speed Diesel 156

    7.2 Characteristics of HSD 156

    7.3 Risk Index 158

    7.4 Physiological effects of threshold thermal doses 158

    7.5 Damage due to Incident Radiation Intensity 159

    7.6 Heat Radiation Hazards due to Storage 160

    9.1 Location of Fugitive Monitoring 188

    9.2 Unit wise Solid Waste Generation 195

    9.3 Plant Species for Green Belt Development 202

    9.4 CREP compliance 214

    Sr.

    No.

    Particulars Page

    No.

    1.1 Location of the Project Site 3

    1.2 Topographical Map 4

    1.3 Google Image 5

  • X

    2.1 Plant Layout 21

    2.2 Water Balance Diagram of Existing Project 27

    2.3 Water Balance Diagram of Proposed Project 28

    2.4 Process Flow Diagram For Ferro Alloy Plant 36

    2.5 Process Flow Diagram of Rolling Mill 60

    3.1 Study Area Map of the project area 67

    3.2 Wind Rose Diagram 68

    3.3 Temperature variations during study period 69

    3.4 Relative humidity variations during study period 69

    3.5 Locations of Ambient Air Quality Monitoring Stations 73

    3.6 Figure Showing Locations of Noise Level Monitoring 86

    3.7 Figure Showing Locations of Ground & Surface Water Sampling 94

    3.8 Figure Showing Locations of Soil Sampling Sites 103

    3.9 Satellite Imagery 113

    3.10 Landuse/ Land cover breakup 113

    3.11 Landuse Pattern in Study Area (Census Based) 117

    3.12 Comparison of SC, ST & Other Population 121

    3.13 Literacy % 125

    3.14 Sex Ratio Comparison 125

    3.15 Vocational Pattern of the Study Area 126

    4.1 Resultant Concentrations of Particulate Matter (PM10) due to incremental GLCs 134

    4.2 Resultant Concentrations of Sulphur Dioxide (SO2) due to incremental GLCs 136

    4.3 Resultant Concentrations of Oxides of Nitrogen (NOx) due to incremental GLCs 138

    7.1 Risk Contour 161

    9.1 Organization of Environment Management Cell 123

  • XI

    LIST OF ANNEXURES

    Sr. No. Annexure No. Annexure Name

    1 Annexure I TOR

    2 Annexure II Compliance of TOR

    3 Annexure III Copy of existing Environmental Clearances and its Compliance

    4 Annexure IV Water Withdrawal Permission Letter

    5 Annexure V Fly Ash Utilization

    6 Annexure VI Minutes of Public Hearing

    7 Annexure VII Flora and Fauna Report

    8 Annexure VIII CSR Report

    9 Annexure IX Study area of radius 10 Kms

    10 Annexure X Coal linkage document

    11 Annexure XI Geo-technical report

    12 Annexure XII Copy of NABET accreditation

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 1 ~ PECS, Nagpur

    CHAPTER 1

    INTRODUCTION

    1.0 INTRODUCTION

    M/s. Topworth Urja and Metals Limited (TUML) has proposed to set up the expansion

    unit for Sponge Iron Plant, Induction Furnaces, TMT Rolling Mill & Installation of Ferro

    Alloys Unit, Alloy Steel Billet Plant , Rolling Mill and Structure Mill at village Heti,

    Mouza Ukkerwahi, Post Udasa in Tehsil Umred, District Nagpur, State Maharashtra.

    M/s Topworth Group is one of India's fastest growing conglomerates, with over 2,500

    employees, and revenues exceeding 1.0 Billion USD.

    1.1 PROFILE OF PROJECT PROPONENT

    The Project is promoted by M/s Topworth Urja and Metals Limited (TUML), which is

    one of the leading metallurgical company in India. M/s.Topworth Group is headed by

    Chairman Mr. Abhay Lodha. The company was incorporated as "Shree Virangana Steels

    Private Ltd" in November 1993 and the name was changed to "Shree Virangana Steels

    Limited" in the year Nov 2001. The present name of "Topworth Urja & Metals Limited"

    was given in the year 2010 in accordance with the group name and the business carried

    out.

    M/s. TUML proposed to enhance the production of Sponge iron from 60,000 TPA to

    2,91,000 TPA by installing 2 x 350 TPD rotary kilns, M.S Billets from240 TPD to 480

    TPD by installing 2 x 12 Ton Induction Furnaces & TMT Bars from 66,000 TPA To 1.5

    Lac TPA , in addition to this it is also proposed to install 2 X 16.5 MVA Submerged Arc

    Furnaces to produce 50000 TPA Ferro Alloys, Arc Furnace Based 4 Lac TPA Steel Melt

    Shop, 3 Lac TPA Alloy Steel Bar Mill, 1.5 Lac TPA Light & Medium Section Mill for

    Rolling of Steel sections and 2.5 Lac TPA Heavy Section Mill for Rolling of Structural

    Steel Heavy Sections at Village Heti, Tehsil Umred, District Nagpur, Maharashtra.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 2 ~ PECS, Nagpur

    1.2 SITE SELECTION CRITERIA

    Existing Plant in operation.

    Availability of 160 acres of land.

    No Rehabilitation/Resettlement required.

    No National Park, Biosphere Reserve and Wildlife Sanctuary including Notified

    Eco Sensitive Areas within 10 km radius.

    No archaeological monument, interstate boundary and defense installation.

    No notified critically polluted area.

    No nallah/water body, public roads, forests within the project site.

    Availability of Raw Material.

    Availability of Water.

    Market available for finished products.

    Availability of man power.

    Availability of industrial infrastructure.

    1.3 DETAILS OF THE PROJECT SITE

    The plant of M/s. TUML proposed to enhance the production of Sponge iron from

    60,000 TPA to 2,91,000 TPA by installing 2 x 350 TPD rotary kilns, M.S billets from

    240 TPD to 480 TPD by installing 2 x 12 Ton Induction Furnaces & TMT Bars From

    66,000 TPA to 1.5 Lac TPA , in addition to this it is also proposed to install 2 X 16.5

    MVA Submerged Arc Furnaces to produce 50000 TPA Ferro Alloys, Arc Furnace Based

    4 Lac TPA Steel Melt Shop, 3 Lac TPA Alloy Steel Bar Mill, 1.5 Lac TPA Light &

    Medium Section Mill for Rolling of Steel sections and 2.5 Lac TPA Heavy Section Mill

    for Rolling of Structural Steel Heavy Sections at Village Heti, Tehsil Umred, District

    Nagpur, Maharashtra.

    The location map is shown in the Figure 1.1 and the topographical map and Google

    image is shown in Figure 1.2 and Figure 1.3 respectively. Details of the project site are

    presented in Table 1.1.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 3 ~ PECS, Nagpur

    Source: Map of India, Maharashtra, Nagpur given on Official Websites

    Figure 1.1: Location of the Project Site

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 4 ~ PECS, Nagpur

    Source: SOI Toposheet

    Figure 1.2: Topographical Map

    N

    STREAMS

    RIVER / NALA

    ROAD

    HABITATION

    INDEX

    FOREST BOUNDARY

    POND

    RAILWAY

    7910'

    2055'

    200'

    Canal

    Can

    al

    Can

    al

    Canal

    Cana

    l

    Amb Nadi

    BHIWAPUR R.F

    Dense Mixed Jungle

    Dense Mixed Jungle

    BHIWAPUR R.F

    Open mixed jungle

    Open mixed jungle

    Open mixed jungle

    7915' 7920'

    7920'7915'7910'

    2055'

    200'

    TOPOSHEET NO

    Phukeahwar

    Dudha

    Makaedhokra

    Dahegoon Amb NadiHeoti

    DawhaSayaki

    Sirpur

    Kursapar

    Paradgoon

    Masaikkund

    Bhiwapur

    UtiHaladgoon

    ParsodiTikhadiUmra

    Sukli Khurd

    Champa Chanpa

    Mangli

    Undri

    Khapri

    KHAPRI TALAV

    Sonegaon

    Knetapur

    Sonegaon Talav

    Kolarmet

    Talav

    Takli Kalan

    Kolarmet

    Kalandri

    BorgaonKalandri Talav

    Khairi

    Nirwah

    Wadegaon BarwaPipra

    Ukharwahi Talav

    Heti Akola

    UkharwahiWirli

    Aptur

    Welsakhra

    Udasa

    Rajulwari

    Thomra

    Ganpaoli

    Gangapur

    Kanhwa

    PREPARED BY-POLLUTION AND ECOLOGY CONTROL SERVICES

    Village-:Heti,Taluka-Umred,District-Nagpur.

    10 km. STUDY AREA

    55- P/1,P/5 & 55- O/4, O/8

    M/s. Topworth Urja and Metals Limited.

    PROJECT SITE

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 5 ~ PECS, Nagpur

    Source: Google Earth

    Figure 1.3: Google Image

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 6 ~ PECS, Nagpur

    TABLE 1.1: DETAILS OF THE PROJECT

    Sr. No. Particulars Details

    1. Project Site Village-Heti, Post-Udasa, Tehsil Umred, District Nagpur, Maharashtra.

    2. Nearest major road NH 7 : 24 km MSH 9 : 0.5 km

    3. Coordinates Latitude: 2055'39.10"N Longitude: 7914'47.96"E

    4. Nearest railway station Butibori Railway station, which is 35 Km from the plant site & Nagpur railway station 35 Km from the site.

    5. Elevation above MSL 310m

    6. Toposheet 55 P/1, 55P/5, 55 O/4, 55 O/8

    7. Climatic conditions (Based on IMD)

    Annual Max. Temperature : 47.0C

    Annual Min. Temperature : 4.0C

    Average Annual Rainfall : 1000 mm

    Predominant annual wind direction: North-West

    Relative Humidity: 35 to 81 %.

    8. Nearest village Welsakhra : 2 km

    9. Nearest major city Nagpur - 35 Kms

    10. Nearest water body Ukkarwahi lake : 0.5 km : N Amb River : 5 km : SE

    Paradgaon Lake : 3.0 Km : SW

    11. Sensitive locations Archaeological structures, Historical places, Sanctuaries

    and Biosphere are not present within 10 km

    11. Nearest forest Bhivapur range forest 1.0 km : N

    12. Water Required 3009 m3/Day

    13. Water source for the project Paradgaon Dam 3 km from the site

    14. Land 160Acres

    15. Power 75 MW

    16. Project Cost Rs. 1637.55 Crores

    17. EMP Cost Rs. 26.8 Crores

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 7 ~ PECS, Nagpur

    1.4 PURPOSE OF THE EIA

    As per the Environmental Impact Assessment (EIA) Notification dated 14th September,

    2006, the proposed ferroalloys manufacturing unit is categorized as Category A under

    the Schedule 3(a) Metallurgical industries (ferrous & nonferrous), which mandates

    obtaining prior Environmental Clearance from MoEF & CC, GOI, New Delhi.

    The application to prior EC (Form-1) for the proposed project was submitted to MoEF &

    CC for approval of Terms of Reference (TOR). The proposal was considered by the

    Expert Appraisal Committee (EAC) during its 14th

    Reconstituted Expert Appraisal

    Committee (Industry) held during 19th

    to 20th

    December, 2013for the TOR for preparation

    of EIA report. The EAC has suggested TOR for preparation of the EIA report and the

    compliances of the TOR are given in Table 1.2. Subsequently, the Company had made

    an application for revised capacities of the Project and revised TOR was granted in the

    23rd

    Meeting of the Reconstituted Expert Appraisal Committee (Industry) held on 18th

    September 2014. The EIA report for Topworth Urja & Metals Limited is prepared as per

    the guidelines of MoEF & CC and contains 11 chapters including Environmental

    Management Plan.

    In order to obtain the required Environmental Clearances, M/s Pollution and Ecology

    Control Services (PECS) Nagpur have entrusted the task of undertaking Environmental

    Impact Assessment (EIA) study and prepare Environmental Impact Assessment report.

    This EIA report is prepared based on the data and information provided by the Proponent

    and the field studies undertaken by PECS during the period of 6th

    January 2014 to 6th

    April

    2014.

    1.5 NEED FOR THE PROJECT

    Global steel industry has been growing at a rapid pace during the last decade. The global

    crude steel production had increased from about 900 million tonnes per annum (MTPA)

    in the year 2002 1050 MTPA in the year 2004, recording a CGAR of more than 8%.

    The steel production is projected to grow about 1300 MTPA by the year 2010 with a

    CGAR of about 3.6%. The growth has been primarily concentrated in the developing

    countries. Along with a growth in consumption, the steel industry has also witnessed a

    steep increase in the prices from the year 2002-03 onwards. World Steel Dynamics

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 8 ~ PECS, Nagpur

    (WSD) estimates that the share of the top five players in the steel industry will grow from

    21% in the year 2004 to 39% by the year 2010.

    India is the fourth largest producer of crude steel in the world today. Indian steel industry

    is aiming for high growth during the next 5-7 years, supported by economic growth and

    positive change in consumption behavior of the large and growing population. The prime

    factors which will support growth of Indian steel Industry are demand driving factors,

    government policies and capacity addition plan for steel.

    There is a tremendous potential to create new steel capacities in India considering the

    following intrinsic advantages of India in this industry,

    Availability of major raw materials

    Availability of technically competent personnel at relatively lower cost.

    Proximity to the major consuming markets of South Asia, Middle East,

    etc.

    The easy availability of rich iron ore from nearby mines and water from Paradgaon

    reservoir makes the said Steel manufacturing unit an optimum place to go for

    establishment. There are few companies working around the proposed project, the list of

    companies in 25 km radius area is as follows:-

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 9 ~ PECS, Nagpur

    Table 1.2 List of the Industries around the project site

    1.6 SCOPE OF THE STUDY

    With view to assess the Environmental impacts due to the proposed expansion project

    within the premises of already existing project at Heti Village, Tehsil Umred, District

    Nagpur, M/s Topworth Urja & Metals Ltd. Nagpur has availed the services of Pollution

    and Ecology Control Services, Nagpur (PECS), which is NABET accredited consultant

    and has drafted the report as per generic structure of EIA prescribed in EIA Notification

    2006. All the Water, Air, Soil and Noise monitoring were performed by M/s. Nilawar lab

    Pvt. Ltd. Nagpur (MoEF & CC Accredited).

    The EIA report is prepared based on the one season baseline data as per the guideline of

    MoEF & CC and CPCB. The Environmental monitoring has been carried out during

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 10 ~ PECS, Nagpur

    (6th

    January to 6th

    April 2014) and used to identify potential significant impact. Modelling

    exercises have been carried out to predict and evaluate the impact due to proposed

    activity.

    The scope of present study is in line with the TOR as recommended by MoEF & CC.

    The scope of study broadly includes:

    Field sampling of Environmental attributes at various representative locations in

    the study area to establish the baseline environmental status.

    Collate and compile secondary data include socio-economic data from published

    literature/ govt publications.

    Estimate pollution load that would be generated by proposed project.

    Predict incremental level of pollutant in the study area due to proposed project.

    Prepare Environmental Management Plan (EMP) to mitigate the predicted impacts.

    COMPLIANCE TO TOR CONDITIONS

    The scope of the present study is in line with the TOR as recommended by MoEF & CC

    vide ToR letter No. J-11011/283/2013-IA-II (I) dated 5th

    November, 2014. A copy of TOR

    letter Annexure-I and the Compliance to the TOR is given in Annexure-II. The copy of

    existing Environmental Clearances and its compliance is attached as Annexure III.

    APPROACH AND METHODOLOGY OF EIA STUDY

    Approach of the EIA Study

    The EIA study includes delineation of the baseline conditions of the TUML project site at its

    study area of 10 km (around the project site). Based on the baseline conditions and the

    project activities the potential impacts (both positive and adverse) are identified. For the

    identified potential impacts, mitigation measures to negate the potential adverse impacts and

    enhancement measures to enhance the positive impacts are proposed.

    The proposed control measures are detailed in the Environmental Management Plan. The

    entire EIA study has been carried out on the basis of the applicable environmental legislation,

    regulations and guidelines of MoEF&CC .

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 11 ~ PECS, Nagpur

    Policy and Legal Framework

    The project developer, Nagpur TUML will ensure that it conforms to all National

    legislations, regulations, and conventions, relating to various aspects of metallurgical

    development in India. Table 1.2 shows list of various applicable Acts and Rules as set by

    MoEF&CC , CPCB and CECB.

    Table 1.3: Applicable Acts and Guidelines for the Proposed Project

    Issues Applicable Legislation

    Water 1) The Water (Prevention and Control of Pollution)

    Act,1974, and amendments thereafter.

    2) Water Cess Act, 1977 and amendments thereafter

    Air 3) The Air (Prevention and Control of Pollution) Act,

    1981and amendments thereafter.

    Other Issues under the

    Environment (Protection) Act,

    1986,and Rules

    4) The Public Liability Insurance Act, 1991 and Rules

    1991.

    Noise 7) The Environment (Protection) Second Amendment

    Rules, 2002 (Noise Limits for New Generator Sets).

    8) The Noise (Regulation & Control) Rules, 2000.

    Establishment of Baseline Environmental Condition

    A comprehensive database on the baseline environmental status/conditions of the study

    area has been established through review, compilation and analysis of:

    Existing secondary data/ literature/ information collected, and

    Primary data collected through field study, survey and monitoring

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 12 ~ PECS, Nagpur

    Collection of Secondary Data

    Besides inputs from the TUML on relevant information about the project, available

    relevant secondary data/ information/ records and published literature with respect to the

    environment of the study area around TUML has been collected, reviewed and analyzed

    to provide the overview and details of the study area.

    Geology & topography of the study area including geological setting,

    topography and Seismicity.

    Land use and Land cover pattern was delineated by processing and analyzing

    the satellite imagery (Source NRSA Hyderabad).

    Meteorological data consisting of parameters like temperature, relative

    humidity, rainfall, cloud cover, wind speed and wind direction, and weather

    phenomena were collected and analyzed.

    1Flora and fauna data from existing literature of Forests Departments,

    Botanical Survey of India, Zoological Survey of India, earlier studies

    conducted in the area and field survey.

    Environmentally Sensitive Areas: The details about the ecologically sensitive

    areas like reserve forests, national parks and wildlife sanctuaries within 10 km

    of the proposed expansion project site have been given in Chapter 3.

    Other Features: The distance of the project site from the nearest highways,

    railway lines and airports has been established. Sites/places of archaeological,

    historical and national importance, places/sites of cultural, religious and

    tourist interests, defense installations etc., within a radius of 10 km of the

    project site have also been explored

    Field Study/Monitoring for Generation of Primary Data

    The secondary data collected has been appropriately supplemented by conducting the

    necessary primary data collections through field study/monitoring for one season study

    period (January, February, March and April 2014). The studies which were conducted are

    listed below:

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 13 ~ PECS, Nagpur

    Ambient Air Quality Monitoring: For drawing up the baseline status of ambient air

    quality in the 10 km study area around TUML, ambient air quality monitoring was

    conducted in the representative locations. The parameters namely Particulate Matter 10

    (PM10), Particulate Matter 2.5 (PM2.5), Sulphur dioxide (SO2) and Nitrogen dioxide

    (NOx) were analyzed.

    Noise Monitoring: To establish the ambient noise condition in the study area, ambient

    noise level monitoring has been carried out at representative locations in the study area

    using a suitable portable sound level meter over a period of twenty-four hours to obtain

    day and night time Leq.

    Water Quality Monitoring: To identify the water quality in and around the study area,

    water samples were collected from the representative locations (both surface and ground)

    and were analyzed for their physico-chemical characteristics.

    Soil Monitoring: To study the soil characteristics in the study area, soil samples from

    representative locations in the study area were collected and analyzed to identify the

    physicochemical characteristics of the soil.

    1.6.1 Environmental Impact Assessment

    The environmental assessment has been conducted in accordance with the norms and

    guidelines of the Govt. of India. The project data/activities has been analyzed & linked

    with the existing baseline environmental conditions in order to list out the affected

    environmental parameters and assess the likely impacts on such parameters. Wherever

    practicable, a quantitative analysis has been performed. Compliance of the project with

    national standards has been duly checked.

    1.6.2 Preparation of Environmental Management Plan

    Environmental Management Plan (EMP) is the key to ensure negligible impact to the

    environment due to the proposed project. The desired results of the environmental

    mitigation measures proposed in the project may not be obtained without a management

    plan to ensure its proper implementation & function. The EMP envisages the plans for

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 14 ~ PECS, Nagpur

    the proper implementation of mitigation measures to reduce the adverse impacts arising

    out of the project activities.

    1.6.3 Contents of the Report

    The EIA Report is based on the primary field data generated at the project site and data

    collected from secondary sources. The report comprises of 11 chapters.

    Chapter 1.0 - Introduction

    This chapter provides purpose of report, background information of the proposed and

    expansion project, brief description of nature size and location of the project,

    environmental setting of the proposed location, estimated project cost, scope,

    organization of the report,

    Chapter 2.0 - Project Description

    This chapter provides the background information on the project set up, details of

    manufacturing processes, layout of the plant and sources of pollution along with waste

    generation and their treatment and disposal.

    Chapter 3.0 - Description of the Environment

    This chapter presents the methodology and findings of field studies undertaken to

    establish the baseline conditions for the various environmental attributes.

    Chapter 4.0 - Anticipated Environmental Impacts and Mitigation Measures

    This chapter details the prediction of impacts using available computer models,

    assessment of impact of the proposed project activities and identification of areas of

    concern, It also describes the overall positive and negative impact of proposed project

    activities during construction and operation phases, which need to be mitigated.

    Chapter 5.0 - Analysis of Alternatives (Technology & Site)

    This chapter presents the alternatives w.r.t technology to be adopted for the proposed

    steel manufacturing industries.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 15 ~ PECS, Nagpur

    Chapter 6.0 Environmental Monitoring Programme

    This chapter presents the environmental monitoring program w.r.t the general and

    pollutants criteria for various environmental components as per the guidelines of CPCB

    during and after the establishment of the proposed steel manufacturing plant

    Chapter 7.0 - Additional Studies

    This chapter presents the identification of hazards due to various units and explosive

    materials etc. Based on the damage distances an onsite disaster management plan has also

    been delineated. Disaster management plan, Ecological Biodiversity of the study area ,

    social impact assessment (Public hearing details) and corporate social responsibility of

    project proponent is also covered.

    Chapter 8.0 Project Benefits

    This chapter outlines the benefits resulting from the proposed steel manufacturing plant.

    Chapter 9.0 Environmental Management Plan

    This chapter outlines the institutional arrangements and budgetary provision for

    implementation of the proposed environmental monitoring plan to check the efficacy of

    the environmental mitigation measures proposed.

    Chapter 10.0 - Summary and conclusion

    This chapter presents the gist of the EIA report highlighting the main features in each

    chapter pertaining to the environmental studies carried out and sums up the conclusion in

    the end.

    Chapter 11.0 - Disclosure of Consultants Engaged

    This chapter outlines the brief background of the consultants engaged w.r.t their technical

    expertise and nature of services undertaken.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 16 ~ PECS, Nagpur

    1.7 SITE PHOTOGRAPHS

    Existing Plant Photographs

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 17 ~ PECS, Nagpur

    Air Pollution Control Equipments

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 18 ~ PECS, Nagpur

    Existing Green Belt

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    INTRODUCTION

    ~ 19 ~ PECS, Nagpur

    Photographs of Fly Ash Bricks Manufacturing

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 20 ~ PECS, Nagpur

    CHAPTER 2

    PROJECT DESCRIPTION

    2.1 PLANT LAYOUT

    M/s Topworth Urja and Metals Ltd. (TUML), located on Umred road, Village Heti,

    Tehsil Umred, Distt. Nagpur. The proposed project site is about 35 km south east of

    Nagpur city and about 12 km North East of Umred Tahsil. TUML is sourcing iron

    ore/Iron Ore pellets for their existing units from Bellary / Orrisa region. The Iron ore /

    Iron ore pellets are received at Butibori Railway station, which is 35 Kms away from

    the plant site &32Km from Nagpur railway station. The same is brought by road also.

    The proposed project coordinates is Latitude: 2055'39.10"N Longitude: 7914'47.96"E

    and Ash Pond/dump coordinates is Latitude: 2055'30.24"N Longitude:

    7914'46.05"E.The proposed expansion project layout is presented as Figure 2.1.

    M/s. Topworth Urja and Metals Limited (TUML) have proposed to set up a Expansion

    unit of Sponge iron from 60,000 TPA to 2,91,000 TPA by installing 2 x 350 TPD

    rotary kiln, MS billets from 240 TPD to 480 TPD & TMT Bar From 66,000 TPA To

    1,50,000 TPA. In addition to this, it is also proposed to install 2 X 16.5 MVA

    Submerged Arc Furnaces and 300 TPD Sinter Plant to produce 50000 TPA Ferro

    Alloys, 400000 TPA Arc Furnace based Alloy Steel Melt Shop, 300000 TPA Alloy

    Steel Bar Mill, 150000 TPA Light & Medium Section Mill for Rolling of Steel section

    and 250000 TPA Heavy Section Mill for Rolling of Steel Heavy Sections at Village

    Heti, Tehsil Umred, District Nagpur, Maharashtra. Sponge Iron basedMini Steel Plant

    also having M.S Billets plant and Rolling Mill are present in the existing premises of

    TopworthUrja& Metals Limited and Captive Power Plant (30 MW) is in operation. The

    terrain of the land is almost flat and low lying.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 21 ~ PECS, Nagpur

    ROLLING MILL EXPANSION

    PROPOSED2X350 TPD SPONGE

    IRON D IVISION

    86

    68

    67

    70

    69

    71

    66

    88

    95

    72

    82

    63

    62

    57

    6174

    75

    76

    59

    60

    73\3

    PLANT LAYOUT-PLAN

    85

    86

    96

    38

    37

    1918

    17

    78

    20

    15

    1614

    13

    12

    79

    80

    81

    77

    PROPOSEDSECTION MILL

    PROPOSED

    ALLOY STEEL BILLET PLANT

    P ROP OSED

    A LLOY S TEE L BA R MILL

    PROPOSED

    FERRO

    ALLOY PLANT

    Figure 2.1: Plant Layout

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 22 ~ PECS, Nagpur

    2.1.1 PROJECT COST

    The total cost of the project is Rs.1637.55 Crore, which includes all proposed expansion

    and new installation. The Breakup of the proposed investment is given in Table 2.1

    Table 2.1 Breakup of Proposed Investment

    Sr.

    No.

    Plant Description Estimated

    Cost in (Cr.)

    1. Expansion of Sponge Iron Plant by installing 2 nos of 350 TPD

    Rotary Kilns.

    150.00

    2. Expansion of M.S. Billet Plant from 240 TPD to 480 TPD with

    Ladle Refining Furnace

    51.36

    3. Expansion of TMT Steel Bar Rolling Mill from 66000 TPA to 1.5

    Lac TPA

    132.95

    4. 2 X 16.5 MVA Submerged Arc Furnace Based 50000 TPA Ferro

    Alloys Plant with a Sinter Plant

    315.24

    5. Electric Arc Furnace Based 4 Lac TPA Alloy Steel Billet Plant 248.55

    6. 3 Lac TPA Alloy Steel Bar/Wire Rod/TMT Bar Rolling Mill 251.35

    7. 1.5 Lac TPA Light & Medium Section Mill for Rolling of Steel

    sections like Angles, Channels, round and other sections and

    Beams.

    162.25

    8. 2.5 Lac TPA Heavy Section Mill for Rolling of Structural Steel

    Heavy sections like Angles, Channels And Beams.

    325.85

    Total Estimated Cost in Rs. 1637.55

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 23 ~ PECS, Nagpur

    2.1.2. Production Scenario

    The production scenario of the existing and proposed plant is given in Table 2.2.

    Table 2.2 Existing and Proposed Production Capacities

    Sr.

    No

    Name of Units Existing

    Capacity

    Proposed

    Expansion

    Total after

    Expansion

    1 Sponge Iron 60000TPA 231000TPA 291000TPA

    2 Steel Billets 240 TPD 240 TPD 480 TPD

    3 TMT Bar 66,000TPA 84,000 TPA 1,50,000 TPA

    4 Captive Power plant 100MW -- 100MW

    5 Ferro Alloys Plant, -- 50000 TPA 50000 TPA

    6 Alloy Steel Melt shop -- 400000 TPA 400000 TPA

    7 Alloy Steel Bar/Wire Rod/TMT Bar

    Mill (Stainless Steel, Alloy Steel,

    Carbon Steel & Wire Rods)

    -- 300000 TPA 300000 TPA

    8 Section Mill For Rolling of Steel

    Sections

    -- 150000 TPA 150000 TPA

    9. Heavy Section Mill For Rolling of

    Structural Steel Heavy Sections

    - 250000 TPA 250000 TPA

    The utility requirement for the proposed expansion project is given in Table 2.3.

    Table 2.3Utility Requirement

    Sr.

    No.

    Utility

    Requirement

    Existing

    Requirement

    Utility Requirement After

    Amendment Request

    For Proposed

    Expansion

    Total Requirement

    1. Power 21.75 MW/Hr 70.75 MW/Hr 92.5 MW/Hr

    2. Compressed Air 7648 m3/hr 5981 m

    3/hr 13629 m

    3/hr

    3. Water 606 m3/day 2403 m

    3/day 3009 m

    3/day

    4. Manpower 395 nos. 670 nos. 1065 nos.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 24 ~ PECS, Nagpur

    2.1.3 Raw Material Requirement

    The main raw material for the industry is Quartz and other raw materials are Iron Ore,

    Electrode paste, Manganese Ore, Dolomite are procured from nearby mines in

    Maharashtra and Chhattisgarh for the proposed project.

    Source of Coal

    By E-Auction from various WCL Coal mines. In addition to this TUML is a successful

    bidder for Marki Mangli I Coal block in District Yavatmal which is at 150 km

    distance. Copy of vesting order is enclosed as Annexure X.

    The raw material requirement for the proposed expansion and new unit is given in

    Table 2.4.

    Table 2.4 Raw Materials Requirements & Sources

    Sr.

    No

    Raw Material

    Requirement

    Existing

    Requirement

    Raw Material Requirement After Amendment

    Request

    For Proposed Expansion Total Requirement

    1. Manganese Ore ------------- 7050 MT/M 7050 MT/M

    2. Ferro Alloy 100 MT/M 600 MT/M 700 MT/M

    3. Pig Iron ----------- 3500 MT/M 3500 MT/M

    4. Billets 5850 MT/M 70275 MT/M 76125 MT/M

    5. M. S. Scrap 1140 MT/M 6405 MT/M 7545 MT/M

    6. Sponge Iron 7200 MT/M 36615 MT/M 43815 MT/M

    7. Coal (DRI+ Power

    plant+ Rolling mill)

    69300 MT/M 28875 MT/M 98175 MT/M

    8 Iron Ore/Pellets 7500 MT/M 28875 MT/M 36375 MT/M

    9. Dolomite 750 MT/M 2888 MT/M 3638 MT/M

    2.1.4 Water Requirement

    Total water requirement for the present and expansion project is 3009 m3/day. The

    source of water is met from 3 km away Paradgaon dam. The Water requirement is

    primarily for industrial use (for cooling only), make-up, dust suppression system, green

    belt, domestic and other miscellaneous use.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 25 ~ PECS, Nagpur

    The Company has got a water allotment of 0.2 Million Cubic Metres per annum with a

    provision of withdrawing additional water upto 10% extra over and above agreed quota

    of 0.2 Million Cubic Metres/Annum at same rate. Water allotment letter is enclosed as

    Annexure-IV. To meet this additional water requirement, the Company has also

    applied for 0.5 Million Cubic Metres/Annum as additional sanction for mitigating the

    future water requirements which will be as below.The water balance is given below in

    Table 2.4 and water balance diagram of existing and expansion project is given as

    Figure 2.2and Figure 2.3 respectively.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of Ferro alloys unit, Alloy steel billet plant, Rolling

    mill and Structure mill

    PROJECT DESCRIPTION

    ~ 26 ~ PECS, Nagpur

    TABLE 2.5 WATER BALANCE

    Make up Water Requirement For TopworthUrja& Metals Limited (For Existing & Proposed Expansion)

    Sr.

    No

    Name of Units Existing Water

    Requirement per Year

    Proposed Water

    Requirement per Year

    Total Water Requirement

    after Expansion

    1. Sponge Iron Plant 6000 Cu. Mtr. 23100 Cu. Mtr. 29100 Cu.Mtr.

    2. TMT Bar 23100 Cu. Mtr. 29400 Cu. Mtr. 52500 Cu.Mtr.

    3. Steel Billets 14400 Cu. Mtr. 14400 Cu. Mtr. 28800 Cu.Mtr.

    4. 30 MW Captive Power Plant in

    operation

    42768 Cu. Mtr. - 42768 Cu.Mtr.

    5. 2 x 35 MW Captive Power Plant

    is in construction

    99792 Cu. Mtr. - 99792 Cu.Mtr.

    6. Ferro Alloys Plant - 205920Cu.Mtr 205920Cu.Mtr

    7. Alloy Steel melt shop - 240000 Cu. Mtr. 240000 Cu. Mtr.

    8. Alloy Steel Bar Mill - 105000 Cu.Mtr. 105000 Cu.Mtr.

    9. Light & Medium Section Mill For

    Rolling of Steel Sections of Alloy

    Steel & Carbon Steel

    - 52500 Cu.Mtr. 52500 Cu.Mtr.

    10. Heavy Section Mill For Rolling

    of Steel Heavy Sections

    - 87500 Cu.Mtr. 87500 Cu.Mtr.

    11. Drinking & Sanitation 13780 Cu. Mtr. 35245 Cu.Mtr. 49025 Cu.Mtr.

    12. Total in Cu. Mtr/year 199840 Cu. Mtr 793065Cu.Mtr 992905Cu.Mtr.

    13. Total Cu.M/day 606 Cu.M/day 2403 Cu.M/day 3009 Cu.M/day

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of Ferro alloys unit, Alloy steel billet plant, Rolling

    mill and Structure mill

    PROJECT DESCRIPTION

    ~ 27 ~ PECS, Nagpur

    Figure 2.2

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of Ferro alloys unit, Alloy steel billet plant, Rolling

    mill and Structure mill

    PROJECT DESCRIPTION

    ~ 28 ~ PECS, Nagpur

    Figure 2.3

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 29 ~ PECS, Nagpur

    2.1.4.1 WATER TREATMENT PLANT

    The raw water is being treated in a DM plant to maintain quality required for the high

    pressure boiler. The effluent from the DM plant is being treated in a neutralization pit

    before letting into the guard pond.

    The blowdown water from the auxiliary cooling tower and the boiler is taken to the

    Neutralization pit and from there to the Guard pond after neutralization. After cooling,

    water is pumped for green belt development and ash conditioning/wetting to prevent

    fugitive dust emission.

    Plant have the two stream of 15m3/hr DM plant followed by single ultra filtration

    system

    The proposed scheme of water treatment plant is furnished below.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 30 ~ PECS, Nagpur

    2.1.5 Power Requirement

    The existing power requirement is 21.75 MW and after expansion it will required 70.75

    MW. The existing and expansion project will require a total of 92.5 MW power. The

    power requirement is/will be met from 100 MW existingPower Plant (30 MW in

    operation and 2 x 35 MW under installation for which Consent to Establish and

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 31 ~ PECS, Nagpur

    Environmental clearance is already obtained from MPCB/MoEF, Mumbai. The Power

    consumption (Electrical Energy) for existing &proposed plants is given in Table 2.6

    Table 2.6:Power Consumption

    Sr.

    No.

    Energy required for Existing Power

    Consumption

    Proposed Power

    Consumption

    Total Power

    Consumption in

    MW

    1 Induction furnace 8.5 MW 8.5 MW 17 MW

    2 Rotary kiln 1 MW 2.5 MW 3.5 MW

    3 Rolling mills 2 MW 8.5 MW 10.5 MW

    4 Submerged arc furnace - 23.5 MW 23.5 MW

    5 Arc Furnace Steel melting

    shop

    - 25 MW 25 MW

    6 Power Plant Home Load for

    auxiliary consumption

    08 MW - 08 MW

    6 Pollution control equipment 1.5 MW 2 MW 3.5 MW

    7 Plant lighting 0.75 MW 0.75 MW 1.5 MW

    Total 21.75 MW 70.75 MW 92.5 MW

    2.1.6 Land Requirement

    M/s TopworthUrja and Metals Ltd (TUML), has identified 160 acres (64.7996 ha) of

    land at village Heti, Tehsil Umred, District Nagpur. The proposed project site is about

    35 km south east of Nagpur city. The plant layout has been developed considering the

    wind direction, environmental constraints, and power evacuation corridor. The plot for

    the Project isdeveloped taking into consideration various aspects like available land &

    its shape, ground features & terrain, corridor for outgoing transmission lines, approach

    road, prevailing wind direction and the water availability. The breakup of land use as

    per the plant requirement are given in Table 2.6

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 32 ~ PECS, Nagpur

    Table 2.7: Break-up of Land Use (Existing and Proposed)

    Sr No Description Area (Acres)

    1 Plant machinery 45

    2 Building construction 12

    3 Green Belt (Plantation) 50

    4 Open Space 53

    Total 160

    Out of 160 Acres of land, 50 Acres of land is for existing plant including all the units

    and 110 Acres of land is for the proposed expansion project.

    2.1.7 Employment potential

    The existing project has employment for 395 people. The proposed expansion project

    generates employment for 670 people. The total number of employment in existing and

    expansion project will be 1065 people. Local people will be employed based on their

    qualification and skill.

    2.1.8 Transport :

    SH 9 is 0.5 km; east from the project site and NH 7 at the distance of 24 kmsand a

    major district road passes by along theproject site and Butibori railway station is just

    35 Kms from the project site.

    2.2 PROCESS DETAILS

    The major facilities envisaged for this plant are as follows:

    2X16.5 MVA Submerged Arc Furness based 50000 TPA Ferro Alloys Plant

    with required Sinter Plant

    Enhancement of capacity of existing TMT Bar Mill from 66000 TPA to 1.5 Lac

    TPA.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 33 ~ PECS, Nagpur

    Enhancement of capacity of existing Billet Plant from 240 TPD to 480 TPD

    Steel Billet plant by installing additional 2X12 Ton Induction Furnace and also

    Installation of Ladle Refining Furnace for production of better quality of steel.

    Enhancement of capacity of Sponge iron from 60,000 TPA to 2,91,000 TPA by

    installing 2 nos of 350 TPD rotary kilns

    400,000 TPA Steel Melt Shop for production of Alloy steel Billets

    300,000 TPA Alloys Steel Bar Mill.

    1.5 Lac TPA Light & Medium Section Mill for Rolling of Steel sections.

    2.5 Lac TPA Heavy Section Mill for Rolling of Structural Steel Heavy Sections.

    2.2.1 FERRO ALLOYS PLANT FOR 50000 TPA CAPACITY

    Technological considerations and selection of facilities

    300 TPD Sintering machine

    The main areas in the Mini Sintering Plant are:

    Charge preparation

    Mixing and nodulizing drum

    Sinter machine

    Sinter cooling system

    Sinter plant automation

    Environmental pollution control equipment

    FERRO ALLOY SMELTING SHOP (SUBMERGED ARC FURNACE)

    Based on the production capacities of various furnaces, 16.5 MVA furnace for each FeMn OR

    SiMn and FeSi OR SiMn has been considered for the target production. For production of

    FeMn and SiMn, both furnaces can be used to make the same and will be determined by the

    market conditions. The major components of the submerged arc furnace are as follows:

    Set of single phase transformers

    Electrode columns

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 34 ~ PECS, Nagpur

    Secondary conductor systems

    Furnace covers

    Furnace smoke hoods

    Forged pressure rings

    Forged contact clamps

    Furnace linings

    Stoking equipment

    Tapping equipment

    Furnace control systems

    Bag filters

    Furnace charging systems

    PRODUCT CASTING MACHINE

    One number Pig Casting machine of 150 TPD capacity is considered for casting of Ferro

    manganese and Ferro silicon produced from submerged arc furnaces.

    SMELTING SHOP COMPLEX

    The smelting shop complex would comprise of furnace building, day bin building, gas cleaning

    plant buildings, laboratory, cooling water pump house, compressed air station etc.

    The furnace building would be laid out in 4 longitudinal parallel bays. The day bin buildings

    would be located close to the furnace building and parallel to it towards the raw materials

    storage yard so that individual skips could be installed to deliver the charge-mix to the top of

    the furnace. The gas cleaning plant buildings would also be Located close to the furnace

    building and parallel to it towards the raw materials storage yard and by the side of the day bin

    buildings so as to reduce the lengths of gas ducts and to avoid any possible contamination of

    the finished products with the separated dusts.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 35 ~ PECS, Nagpur

    REPAIR AND MAINTENANCE SHOPS

    In order to meet the repair and maintenance needs of the various plant units, the following

    facilities would he provided.

    Repair shop

    Servicing garage

    Mechanical Repair Section

    Repair Shop

    The repair shop building would occupy on area of 40m x 12m, with road approaches to bring

    in and take out the materials and equipment. It will have separate sections for mechanical

    repair and electrical repair.

    Servicing Garage

    The servicing garage for transport equipment would be located in a separate building having a

    covered area of 18m x 12m, with adequate road approaches.

    Laboratory

    To ensure technological control at all stages of processing and to maintain the desired quality

    of end product, adequate laboratory facilities are required. The major facilities for the

    laboratory would include jaw crusher, roll crusher, vibrating grinder, sieve shaker, weighing

    scale, infra-red moisture tester, single pan analytical balance, hooting pads, Gas analyser,

    carbon and sulphur determination apparatus, photoelectric colorimeter, conventional wet

    chemical analysis, X-ray fluorescence spectrometer, induction melting furnace, briquetting

    press and swing mill.

    Administrative Building

    Proposed Administrative/ Canteen Building shall be a modern two storey RCC framed

    structure of size 36m x15m with total built up area of 900 sqm. Ground floor hall

    accommodate Entry Lobby, Security In-charge Room, First-aid Room, Store-Room, Workers

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 36 ~ PECS, Nagpur

    Change Room and Toilets, canteen and kitchen. Office-Incharge Room, Office areas,

    Conference Room, Pantry and Toilets are being located in the first floor.

    RAW MATERIAL AND SERVICES

    The minerals required for the proposed Ferro-alloys plant are manganese ore, quartzite and

    dolomite. Other raw materials include coke, mill scale and iron/mild steel turnings and borings.

    The process flow diagram of Ferro Alloys Plant in given in Figure 2.4

    Figure 2.4

    Process Flow Diagram For Ferro Alloy Plant

    2.2.2 4 LAC TPA ELECTRIC ARC FURNACE BASED ALLOY STEEL BILLET PLANT

    (Steelmaking by Electric Arc Furnace)

    In Electric Arc Furnace recycled steel scrap and DRI is melted and converted into high quality

    steel by using high power electric Arcs. Modern EAF is a tool to convert solid raw materials in

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 37 ~ PECS, Nagpur

    to liquid crude steel as fast as possible and then refine further in secondary steel making

    processes.

    The furnace consists of a circular bath with a moveable roof, through which three graphite

    electrodes can be raised or lowered.

    At the start of the process, the electrodes are withdrawn and the roof swung clear. The steel

    scrap is then charges into the furnace from a large steel basket lowered from an overhead

    crane.

    When charging is complete, the roof is swung back into position and the electrodes and

    lowered into the furnace. A powerful electric current is passed through the charge, an arc is

    created and the heat generated melts the scrap. Lime and fluorspar are added as fluxes, and

    usually carbon and oxygen are blown into the melt. As a result, impurities in the metal

    combine to from a liquid slag.

    Samples of the steel are taken and analyzed to check composition and, when the correct

    composition and temperature have been achieved, the furnace is tapped rapidly into a ladle.

    Final adjustments to customer specification can be made by adding alloys during tapping or

    later in a secondary Steelmaking unit.

    Refining the Liquid Steel Ladle Refining Furnace (LRF)

    The Liquid Steel from the EAF is tapped into a pre heated ladle. The ladle is taken to Ladle

    Refining Furnace for carrying out refining operations. The ladle is fitted with porous plug and

    an inert gas is purged through the steel bath during entire refining operation. The steel is

    deoxidized and de-sulphurised by treating under basic reducing slag which is rendered fluid by

    arc heating and also by adding fluorspar to it. For making/ reducing &desulphurising slag,

    burnt lime, fluorspar, ferro-silicon and powdered coke are normally added. The reducing slag

    reduces the oxides in the bath and assists in the removal of sulphur as calcium sulphide. The

    desulphurization is also promoted in presence of sufficient quantity of manganese in the bath,

    high basicity of slag and high bath temperature. By blowing with the inert gas, the metal in the

    ladle is stirred and as a result of purging its temperature and composition are equalized and

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 38 ~ PECS, Nagpur

    non- metallic inclusions would float up to the surface. Necessary ferro-alloys are added to the

    liquid steel through a port on the ladle cover after the bath has been fully deoxidized. A

    sample is, thereafter, drawn out and sent to the laboratory for final analysis. Further arc power

    may be applied to increase the temperature to the desired level, if necessary. As soon as the

    final analysis conforms to the desired composition and proper temperature has been attained,

    the ready metal is transferred to vacuum degasser.

    Vacuum Degassing

    A ladle of liquid is transferred by overhead crane from the LRF unit to the vacuum degasser.

    The ladle is placed in a cylindrical tank and is supported inside the tank. The tank is

    constructed with the steel plate and is lined with refractory.

    When the ladle has been located in the tank and inert gas supply is connected to one or more

    porous plugs located in the refractory lining in the bottom of the ladle. Inert gas is blown

    through the plug at control rate to stir the liquid metal in the ladle and expose the surface of the

    liquid steel by pushing aside the slag layer on the surface.

    The tank equipped with a flange around the upper periphery of the tank side wall is then sealed

    by a cover which is located in self propelled car. The car drives over the tank and then covered

    is lowered until the flange around the lower edge of the cover is connected with the tank

    flange.

    An O ring seal between the two flanges creates a vacuum tight seal. The volume enclosed by

    the tank and the cover is then evacuated by a set of vacuum pumps connected to the tank. As

    the pressure in the tank falls, the flow of inert gas through porous plug in the bottom of the

    ladle can be adjusted to create the required degree of turbulence in the ladle. The dissolved

    gases like hydrogen, oxygen etc are removed by effusion from the surface of steel to the low

    pressure surrounding atmosphere.

    In case of un-killed steels, carbon and oxygen in metal bath react under vacuum to form carbon

    monoxide, which is then removed from steel in bubble form and is extracted from the tank by

    vacuum system. Under vacuum conditions, the steel can boil quite violently, and for this

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 39 ~ PECS, Nagpur

    reason there should be sufficient freeboard of 0.9 to 1.0m in the ladle above the normal liquid

    steel surface to accommodate the reaction.

    The vacuum cover can be equipped with a vacuum lock with arrangement for automatic

    weighing and batching of alloy additions without disturbing low pressure conditions within the

    vacuum tank during treatment.

    Alternately a simple pre filled vacuum bunker can be attached to the vacuum cover, which is

    manually pre filled with alloys.

    AOD CONVERTER

    Converter process of Argon Oxygen Decarburization (AOD) was introduced in early 1970s,

    and is now the preferred route for specialty electrical steel and stainless steels. Granulated flux

    injection into liquid steel combined with argon stirring was also introduced in 70s. This was

    soon followed by the application of cored wired feeding of alloying elements for better control

    of composition and inclusion morphology. Secondary refining equipment mainly used in final

    refining step for stainless production includes AOD furnace. Stainless steel contains a large

    amount of chromium as a basic component. Since chromium is a strong oxides forming

    element, during normal refining it is difficult to decarburize stainless steel to a sufficiently low

    carbon level while preventing loss of chromium through oxidation to slag phase. Thus low

    carbon levels are achieved by decreasing the partial pressure of carbon mono oxide in the

    refining atmosphere to ensure preferential decarburization in the presence of chromium. In

    practice this is in done in AOD furnace by dilution with argon and in VOD furnace by

    reducing the pressure.

    Description of AOD unit

    The AOD Converter Plant shall be located near the furnace. The Steel scrap/DRI is melted

    down in the Furnaces. The molten metal at temperature of 1600-1650C is transferred to the

    AOD Converter Vessel via overhead crane to refine to the desired chemical composition by

    addition of required Alloys/Fluxes and use of various gases. The gases media such as Oxygen,

    Nitrogen, Argon& Compressed Air is injected into AOD Converter through High Blowing rate

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 40 ~ PECS, Nagpur

    Tuyers for good mixing effect and excellent heat efficiency. The AOD Converter complete

    system comprises of following main equipments

    Converter Vessel complete 2 Nos.

    Top Conical Cover 2 Nos.

    Trunnion Ring with Two Forged Shafts 1 No.

    Main Pedestals base with Plummer Block fitted with G.M. Bushes 2 Sets

    Tilting Unit consisting of drive and motor 1 set

    Primary fume extraction system

    Electrical Equipments like slipring Motor, Control Panel, Starter, Resistance Box,

    Master Controller, Wiring, Cabling control desk.

    Mechanical Equipment consisting of

    Helical reduction gear Box - 01 No

    Self-Aligning spherical Roller Bearing with Housing - 01 Nos

    Open Gear Ring Pinion 01 set,

    Arrangement with full Geared Coupling, Brake Drum, and Thruster Assembly with

    brakes - 03 Nos. complete in all respects.

    Item (a) & (b) mounted on steel base frame.

    Rotary Pipe Joint: 02 Nos. (for Gas Supply)

    Electrical Push Button Panel operated, Microprocessor Based Auto Type Gas Mixing

    Station having Digital Type Flow Meter / Totaliser for Gases Complete unit.

    Motorized Sampling Trolley with Drive Mechanism -1 No.

    AOD Tuyer Pipe complete Assembly with end fittings & flexible piping -1 Lot

    Water Cooled Hood, Bend & Pipe Line -1 Unit

    Water Cooled Oxygen Top Lance Unit Complete With Drive Arrangement (Optional

    Equipment)

    Motorized moving Hood Trolley with Drive Mechanism.

    Documentation & Manual.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 41 ~ PECS, Nagpur

    UTILITIES AND THEIR CONSUMPTION

    Media Purity% Max. ----- Oxygen 99.5

    Pressure kg /cm2 -------------18

    Flow Rate (max.)Nm3/ton ---1.25(Maximum blow rate 1.6)

    throughTuyer ----------60 70 M3/ton

    Consumption for stainless steel grades

    Nitrogen 99.9 18 0.6 30 - 40

    Argon 99.9 18 0.5 2 - 12

    Compressed Air 18 0.5 30

    Consumption of utilities gases depends upon:

    - Steel grade to be produced

    - Carbon % opening in liquid metal

    - Type of Ferro- alloy used in heat making

    OXYGEN PLANT (BOO BASIS)

    Plant parameters

    S. No Item Parameter Unit Figures

    1. Capacity 200 TPD

    2. Gaseous Oxygen Purity % 99.5 Pressure kg/cm2(g) 30 Production Nm

    3/hr 5840

    3. Gaseous Nitrogen Purity % 99.9%

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 42 ~ PECS, Nagpur

    PROCESS DESCRIPTION

    Compression, pre-cooling & front end purification

    Through the air filtering device, the process air is cleared from dust and other mechanical

    Contaminations & then compressed to the required pressure (about 6.2 bar A) by multistage

    centrifugal compressor. It is then cooled down first by bringing in direct contact with normal

    temperature water and then by chilled water. Recycled water is chilled by bringing it with the

    direct contact with waste nitrogen in nitrogen wash tower, which is generated from cold box.

    Then the air enters into the absorber tower.

    The air coming from the outlet of the air water tower passes through a water, CO2 and

    hydrocarbons adsorbing system, which is composed of two absorbers, filled with alumina and

    molecular sieves. The two absorbers are working alternatively: one is in operation while the

    other is being regenerated by waste nitrogen coming from the cold box. During the heating

    regeneration phase of the adsorbents: waste nitrogen gas is heated in a reactivation heater to

    about 150 C and then sent to absorbers during normal reactivation.

    Air separation

    Air Distillation

    Most of the purified process air from the purification system is entered into the primary heat

    exchanger in the cold box and cooled by the returning gas. Then it enters into the bottom of the

    lower column at near its dew point for its first rectification. The rising gas is sufficiently

    contacted with the dropping liquid in the column. Through heat & mass transfer, the nitrogen

    concentration increases in the rising gas which transforms into pure nitrogen at the top of the

    column. The pure nitrogen is fed into the main condenser evaporator at the top of the lower

    column for condensation. At the same time the liquid oxygen in the main condenser evaporator

    is gasified.

    Some of the liquid nitrogen is used as the reflux of the lower column, the other liquid nitrogen

    is sub cooled through sub cooler. A stream of it can be drawn out as product. Another one is

    sent into upper column after throttling.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 43 ~ PECS, Nagpur

    The liquid air generated in the lower column is sub cooled by the sub cooler which then enters

    into the upper column for distillation after throttling. In the upper column, all the feed is

    distilled once more and product gaseous nitrogen, gaseous oxygen, waste nitrogen and product

    liquid oxygen are obtained.

    Generation of cold

    Most of the cold needed by the plant is generated by booster turbo expander. Some of the clean

    air from the air purification system is entered into the booster which is driven by the turbo

    expander. It is then cooled by the after cooler of the booster, fed into primary heat exchanger in

    the cold box and then into turbo expander to expand and get cold. After being cooled to a

    certain temperature, the expanded air is entered into the upper column for distillation.

    Product distribution

    Gaseous Oxygen

    The gaseous oxygen is delivered out from the cold box and pressurized by a Oxygen

    compressor then to Battery limit.

    Gaseous Nitrogen

    The gaseous nitrogen is delivered out from the cold box and pressurized by a nitrogen

    compressor, then to Battery limit.

    Waste Nitrogen

    The waste nitrogen is used for regeneration of the molecular sieve absorber and its pressure

    from the cold box is approx. 12 KPA.

    Liquid Nitrogen

    The liquid nitrogen is sent out through the cold box to liquid nitrogen tank.

    Dry air used for instruments & Defrosting

    The dry air for the plant instruments (during normal operation) and defrosting is drawn out

    from the mole sieve absorber and sent separately to instrument air pipeline or to be locally

    defrosted.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 44 ~ PECS, Nagpur

    Distributed control system

    The control system shall be designed to meet the process requirement of the oxygen plant and

    concurrently will have the features of easy operation and reliability for ensuring stable and

    long term run of the plant. The process control of the complete oxygen plant is done integrally

    by the distributed control system. The oxygen plant is centrally supervised and operated from

    the control room. Important operations and emergency shutdown shall be carried out through

    operating stations and the important parameters shall be displayed, logged and alarmed through

    DCS system. Local indication instruments and local operating devices shall be provided in

    accordance with the process of the plant. DCS system shall consist of the operating station,

    control station, printer communication line and interfaces. Field instruments and equipments

    shall be provided to match the requirements of DCS & process. A hot standby shall be

    provided for DCS system

    CONTINUOUS CASTING OF BILLETS

    Liquid metal from VD is transferred to the continuous casting machine for casting into billets.

    The main operations involved in the whole process of turning out billets are:

    i) Checking the individual major components of the casting machine and their

    synchronized operation;

    ii) Insertion of a dummy bar to close the bottom end of the mould;

    iii) Accurate centering of the tundish over the mould;

    iv) Transferring the ladle to the casting aisle and placing it on the ladle stand of the

    casting machine;

    v) Pouring of liquid steel from the ladle through a slide gate mechanism into the lined

    tundish;

    vi) Pouring of liquid steel into the water cooled mould through tundish;

    vii) Passage of liquid steel through water cooled mould tubes initiated by withdrawing

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 45 ~ PECS, Nagpur

    dummy bar;

    viii) Oscillation of the mould;

    ix) Maintaining a constant level of liquid steel in the mould and introducing lubricants

    into the mould throughout the casting process;

    x) Controlling the intensity of cooling of the emerging billets in the primary and

    secondary cooling areas; and

    xi) Straightening and cutting of billets.

    The most important component of a casting machine is the bottomless water cooled copper

    mould. The internal shape and size of the mould tube is the same as that of the cross section of

    the billet / blooms to be cast. To initiate casting, a dummy bar is inserted to the bottom end of

    each mould, while the other end of the dummy bar is held by withdrawal/ straightening rolls.

    Molten steel at the correct temperature is poured into the mould and when it reaches the

    stipulated level, the withdrawal rolls, mould reciprocation unit are operated, cooling water

    circulation through the mould and in the secondary circuit is started few minutes earlier the

    actual casting operation is started. The dummy bar is withdrawn, followed by hot solidified

    billet. The cooling water circulating around the mould has carried away enough heat from the

    liquid steel to produce a solid outer skin of sufficient strength to safely envelop the still liquid

    portion at the interior that too is solidified by a secondary cooling. The rates of solidification

    and withdrawal are obviously inter linked. Before beginning to withdraw the dummy bar it

    must be ensured that the outer casting of the billet is strong enough for the process to continue.

    An error in this regard will cause break out of the strand, which will then remain inoperative

    for the rest of that heat into casting. For obtaining satisfactory surface quality of billets and for

    satisfactory performance in general, the liquid steel temperature, casting speed, the rates of

    primary and secondary cooling must be controlled and matched. Usually this harmonization is

    developed on the basis of practice in the particular plant. If the casting speed is increased to

    raise output, the quality of the central zone of the billet may suffer because of increase in

    unsoundness, chemical heterogeneity and prone to internal cracking.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 46 ~ PECS, Nagpur

    Lubrication

    For reducing friction between the mould wall and the solidifying steel, a vegetable water free

    oil such as rapeseed oil is introduced to wet the inner wall of the mould above the metal level.

    The oil then seeps downward to lubricate the portion of the mould wall in contact with the

    solidifying steel. The cooling system of the mould prevents the oil from being burnt off.

    Mould

    The mould is made of copper of high purity and high thermal conductivity. The mould is

    tapered, hard plated with chromium on the inner surface. The mould tube is a copper tube

    fitted into a fabricated steel water jacket. The entire mould assembly together with its cooling

    jacket is oscillated by an eccentric drive.

    Secondary Cooling

    The cooling in the mould, called primary cooling, solidifies only the outer crust of the billet

    while its interior still remains liquid or semi-liquid. Hence the billet issuing from the bottom

    of the mould is immediately subjected to a secondary cooling. Water jets spray water directly

    on each of its faces all down its length. The spraying should be closely controlled so that the

    cooling rate may match the withdrawal speed, steel quality and product shape.

    Billet Cutting

    The automatic gas cutting torches are provided for cutting billets to a desired length. The

    equipment comprises a water cooled structure for trolley support. Auto cutter trolley with drive

    mechanism, a gas and pneumatic panels suitable for both the strands. The trolley moves on the

    rails above the hot strand in the direction of discharge. During cutting, torch swings like a

    pendulum across the hot strand at a predetermined cutting speed. In the forward direction

    trolley moves at casting speed swing to the clamping of the hot strand whereas retracting the

    trolley to the home position is carried out by motorized drive. As soon as predetermined

    length to be cut is sensed, the following commands are given:

    i) Positioning of the torch at the edge of the billet;

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 47 ~ PECS, Nagpur

    ii) Clamping of hot strand by the clamps through pneumatic cylinder;

    iii) Ignition of the torch by releasing oxygen and acetylene gas.

    Upon clamping, the trolley moves forward along with the hot strand at the casting speed.

    Torch drive starts thereby swinging the ignited torch across the hot strand and thereby cutting

    it. As soon as the torch cleans the width of the billet, the following function will take place:

    i) Ignition of the torch is put off;

    ii) Movement of the torch by drive is stopped and the torch retracts back to the home

    position;

    iii) First group of discharge roller table is made on, thereby separating the cut billet

    from the hot strand;

    iv) Clamps holding the hot strand are released;

    v) Trolley will retract to the home position.

    This completes one full cycle of cutting a billet. The complete operation is automatic;

    however, it can also be carried out by means of push buttons located on the control desk

    Billet Processing

    The billets from a particular cast are lifted from the cooling bank and stored separately. When

    cooled, they are inspected on each face for defects, surface defects are normally removed by a

    swing frame grinder, etc.

  • EIA study for expansion of Sponge iron plant, Induction furnaces, TMT Rolling mill & installation of

    Ferro alloys unit, Alloy steel billet plant, Rolling mill and Structure mill

    PROJECT DESCRIPTION

    ~ 48 ~ PECS, Nagpur

    2.2.3 ENHANCEMENT OF CAPACITY FROM 240 TPD TO 480 TPD BY INSTALLING 2 X

    12 TON INDUCTION FURNACE BASED STEEL BILLET PLANT AND

    INSTALLATION OF LADLE REFINING FURNACE.

    Steel Melt Shop (SMS) Division:

    1) Presently, the company is having 2 x 12 Ton capacity Induction Furnaces along with 2

    Strand, 6 x 11 meters radius Caster in the Steel Melt Shop to manufacture Steel Billets.

    Now, as per market scenario the company proposed for enhancement of capacity of

    Steel Melt Shop from 240 TPD to 480 TPD by installing the additional 2 x 12 Ton

    capacity Induction Furnace. In current design of Induction furnace the chemistry of the

    steel being manufactured and its quality is maintained by dilution method. The

    proportion of the various ingredients in the charge mix is manua