Alternatives Analysis Rpt Jan2016

download Alternatives Analysis Rpt Jan2016

of 166

Transcript of Alternatives Analysis Rpt Jan2016

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    1/166

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    2/166

     

     Alternatives Analysis Report Page iJanuary 2016

    TABLE OF CONTENTS PAGE

    PREFACE .................................................................................................................................. 1 

    INTRODUCTION AND BACKGROUND .................................................................................... 1 

     ALTERNATIVES ANALYSIS METHODOLOGY ........................................................................ 3 

    NO-BUILD ALTERNATIVE ........................................................................................................ 6 

    PURPOSE AND NEED .............................................................................................................. 6 

    SCREENING PROCESS ........................................................................................................... 8 

    PURPOSE AND NEED RATIONALE REVIEW ......................................................................... 8 

    IDENTIFICATION OF CORRIDOR ALTERNATIVES ................................................................ 9 

    LEVEL 1 SCREENING OF CORRIDOR ALTERNATIVES .......................................................12 

    TWIN CITIES SUB- AREA CORRIDOR ALTERNATIVES ...................................................................................... 13 

    Corridor Definition ................................................................................................................................ 13 

    Evaluation ............................................................................................................................................ 13 

    Summary .............................................................................................................................................. 14 MSP  AIRPORT TO COATES  ......................................................................................................................... 24 

    Corridor Definition ................................................................................................................................ 24 Evaluation ............................................................................................................................................ 24 Summary .............................................................................................................................................. 25 

    UNION DEPOT TO COATES .......................................................................................................................... 34 Corridor Definition ................................................................................................................................ 34

     

    Evaluation ............................................................................................................................................ 34 Summary .............................................................................................................................................. 37 

    COATES TO ROCHESTER –  HIGHWAY 52  ALTERNATIVES .............................................................................. 52 Corridor Definition ................................................................................................................................ 52 Evaluation ............................................................................................................................................ 52 Summary .............................................................................................................................................. 53

     

    COATES TO ROCHESTER –  HIGHWAY 56  ALTERNATIVES .............................................................................. 63 Corridor Definition ................................................................................................................................ 63 Evaluation ............................................................................................................................................ 63 Summary .............................................................................................................................................. 63 

    COATES TO RST  AIRPORT –  HIGHWAY 52  ALTERNATIVES  ........................................................................... 67 Corridor Definition ................................................................................................................................ 67

     

    Evaluation ............................................................................................................................................ 67 Summary .............................................................................................................................................. 68 

    COATES TO RST  AIRPORT –  HIGHWAY 56  ALTERNATIVES  ........................................................................... 75 Corridor Definition ................................................................................................................................ 75 Evaluation ............................................................................................................................................ 75 Summary .............................................................................................................................................. 76 

    ROCHESTER TO RST  AIRPORT  ................................................................................................................... 84 Corridor Definition ................................................................................................................................ 84 

    Evaluation ............................................................................................................................................ 84 Summary .............................................................................................................................................. 84 

    LEVEL 2 SCREENING PROCESS ...........................................................................................89 

    UNDERSTANDING THE SCREENING PROCESS  .............................................................................................. 90 DESCRIPTION OF RECOMMENDED CORRIDORS ............................................................................................ 91

     

    Corridors 1.1 to 2.4 .............................................................................................................................. 91 

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    3/166

     

     Alternatives Analysis Report Page iiJanuary 2016

    Corridors 2.3 and 2.4 ........................................................................................................................... 91 Corridors 3.1 to 5.4 .............................................................................................................................. 92 Corridors 3.3, 3.4; Corridors 4.3, 4.4; Corridors 5.3, 5.4 ..................................................................... 92 

    ENVIRONMENTAL RESOURCES MEASUREMENT ............................................................................................ 92 

    SUMMARY OF SELECTED CORRIDORS .............................................................................139 

    TECHNICAL ADVISORY COMMITTEE REVIEW AND EVOLUTION OF ALTERNATIVES ... 149 

    NEXT STEPS .........................................................................................................................150 

    SERVICE DEVELOPMENT PLAN.................................................................................................................. 150 SERVICE DEVELOPMENT PROGRAMS  ........................................................................................................ 150 

     ABBREVIATIONS

    BNSF BNSF Railway

    CEQ Council on Environmental Quality

    CP Canadian Pacific Railway

    CR County Road

    CSAH County State-Aid Highway

    DM&E Dakota, Minnesota and Eastern Railroad

    DNR Minnesota Department of Natural Resources

    DSDD Draft Scoping Decision Document

    EIS Environmental Impact Statement

    EQB Minnesota Environmental Quality Board

    FRA Federal Railroad Administration

    FSDD Final Scoping Decision Document

    HSR High-Speed Rail

    LRT Light Rail Transit

    MAC Metropolitan Airports Commission

    MEPA Minnesota Environmental Policy Act

    METRO A network of transitways operated by the Metropolitan Council

    MnDOT Minnesota Department of Transportation

    mph miles per hour

    MSP Minneapolis-St. Paul International Airport

    NEPA National Environmental Policy Act

    OCRRA Olmsted County Regional Railroad Authority

    ROCOG Rochester-Olmsted Council of Governments

    RST Rochester International Airport

    SDP Service Development Plan

    SEE Social/Economic and Environmental Impacts

    TAC Technical Advisory Committee

    TPC Train Performance Calculations

    UP Union Pacific Railroad

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    4/166

     

     Alternatives Analysis Report Page iiiJanuary 2016

    LIST OF FIGURES PAGE

    Figure 1 – Zip Rail Project Study Area ........................................................................................1

    Figure 2 – Environmental Review Process Flow ......................................................................... 3

    Figure 3 – Alternatives Analysis Process ....................................................................................5

    Figure 4 – Project Purpose and Need .........................................................................................7

    Figure 5 – Universe of Corridor Alternatives .............................................................................. 11

    Figure 6 – Corridor Alternative IA-1 ........................................................................................... 15

    Figure 7 – Corridor Alternative IU-1 ........................................................................................... 16

    Figure 8 – Corridor Alternative IU-2 ........................................................................................... 17

    Figure 9 – Corridor Alternative IU-3 ........................................................................................... 18

    Figure 10 – Comparative Evaluation Matrix IU Series ............................................................... 19

    Figure 11 – Corridor Alternative AU-1 ....................................................................................... 20

    Figure 12 – Corridor Alternative AU-2 ....................................................................................... 21

    Figure 13 – Corridor Alternative AU-3 .......................................................................................22

    Figure 14 – Comparative Evaluation Matrix AU Series .............................................................. 23

    Figure 15 – Corridor Alternative AC-1A ..................................................................................... 26

    Figure 16 – Corridor Alternative AC-1B ..................................................................................... 27

    Figure 17 – Corridor Alternative AC-2A ..................................................................................... 28

    Figure 18 – Corridor Alternative AC-2B ..................................................................................... 29

    Figure 19 – Corridor Alternative AC-3A ..................................................................................... 30

    Figure 20 – Corridor Alternative AC-3B ..................................................................................... 31

    Figure 21 – Comparative Evaluation Matrix AC Series .............................................................. 32

    Figure 22 – Corridor Alternative AC-4 ....................................................................................... 33

    Figure 23 – Corridor Alternative UC-1A ..................................................................................... 39

    Figure 24 – Corridor Alternative UC-1B ..................................................................................... 40

    Figure 25 – Corridor Alternative UC-1C .................................................................................... 41

    Figure 26 – Comparative Evaluation Matrix UC-1 Series .......................................................... 42

    Figure 27 – Corridor Alternative UC-2A ..................................................................................... 43

    Figure 28 – Corridor Alternative UC-2B ..................................................................................... 44

    Figure 29 – Comparative Evaluation Matrix UC-2 Series .......................................................... 45

    Figure 30 – Corridor Alternative UC-3A ..................................................................................... 46

    Figure 31 – Corridor Alternative UC-3B ..................................................................................... 47

    Figure 32 – Comparative Evaluation Matrix UC-3 Series .......................................................... 48

    Figure 33 – Corridor Alternative UC-4A ..................................................................................... 49

    Figure 34 – Corridor Alternative UC-4B ..................................................................................... 50

    Figure 35 – Comparative Evaluation Matrix UC-4 Series .......................................................... 51

    Figure 36 – Corridor Alternative CD52-1A ................................................................................. 54

    Figure 37 – Corridor Alternative CD52-1B ................................................................................. 55

    Figure 38 – Corridor Alternative CD52-2A ................................................................................. 56

    Figure 39 – Corridor Alternative CD52-2B ................................................................................. 57

    Figure 40 – Corridor Alternative CD52-3 ................................................................................... 58

    Figure 41 – Comparative Evaluation Matrix CD52 Series 1 ....................................................... 59

    Figure 42 – Corridor Alternative CD52-4 ................................................................................... 60

    Figure 43 – Corridor Alternative CD52-5 ................................................................................... 61

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    5/166

     

     Alternatives Analysis Report Page ivJanuary 2016

    LIST OF FIGURES, continued PAGE

    Figure 44 – Comparative Evaluation Matrix CD52 Series 2 ....................................................... 62

    Figure 45 – Corridor Alternative CD56-1A ................................................................................. 64

    Figure 46 – Corridor Alternative CD56-1B ................................................................................. 65

    Figure 47 – Comparative Evaluation Matrix CD56 Series .......................................................... 66

    Figure 48 – Corridor Alternative CA52-1 ................................................................................... 69

    Figure 49 – Corridor Alternative CA52-2 ................................................................................... 70

    Figure 50 – Corridor Alternative CA52-3 ................................................................................... 71

    Figure 51 – Corridor Alternative CA52-4 ................................................................................... 72

    Figure 52 – Corridor Alternative CA52-5 ................................................................................... 73

    Figure 53 – Comparative Evaluation Matrix CA52 Series .......................................................... 74

    Figure 54 – Corridor Alternative CA56-1A ................................................................................. 77

    Figure 55 – Corridor Alternative CA56-1B ................................................................................. 78

    Figure 56 – Corridor Alternative CA56-2A ................................................................................. 79

    Figure 57 – Corridor Alternative CA56-2B ................................................................................. 80

    Figure 58 – Corridor Alternative CA56-3A ................................................................................. 81

    Figure 59 – Corridor Alternative CA56-3B ................................................................................. 82

    Figure 60 – Comparative Evaluation Matrix CA56 Series .......................................................... 83

    Figure 61 – Corridor Alternative DA-1 ....................................................................................... 85

    Figure 62 – Corridor Alternative DA-2 ....................................................................................... 86

    Figure 63 – Corridor Alternative DA-3 ....................................................................................... 87

    Figure 64 – Comparative Evaluation Matrix DA Series .............................................................. 88

    Figure 65 – Corridor 1.1 ............................................................................................................ 94

    Figure 66 – Corridor 1.2 ............................................................................................................ 96

    Figure 67 – Corridor 1.3 ............................................................................................................ 98

    Figure 68 – Corridor 1.4 .......................................................................................................... 100

    Figure 69 – Corridor 2.1 .......................................................................................................... 102

    Figure 70 – Corridor 2.2 .......................................................................................................... 104

    Figure 71 – Corridor 2.3 .......................................................................................................... 106

    Figure 72 – Corridor 2.4 .......................................................................................................... 108

    Figure 73 – Corridor 3.1 .......................................................................................................... 110

    Figure 74 – Corridor 3.2 .......................................................................................................... 112

    Figure 75 – Corridor 3.3 .......................................................................................................... 114

    Figure 76 – Corridor 3.4 .......................................................................................................... 116

    Figure 77 – Corridor 4.1 .......................................................................................................... 118

    Figure 78 – Corridor 4.2 .......................................................................................................... 120

    Figure 79 – Corridor 4.3 .......................................................................................................... 122

    Figure 80 – Corridor 4.4 .......................................................................................................... 124

    Figure 81 – Corridor 5.1 .......................................................................................................... 126

    Figure 82 – Corridor 5.2 .......................................................................................................... 128

    Figure 83 – Corridor 5.3 .......................................................................................................... 130

    Figure 84 – Corridor 5.4 .......................................................................................................... 132

    Figure 85 – Description of Corridors Advanced to the Tier 1 EIS ............................................ 139

    Figure 86 – Location of Corridors Advanced to the Tier 1 EIS ................................................. 140

    Figure 87 – Corridor 1 – MSP to Rochester: Tier 1 EIS ........................................................... 141

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    6/166

     

     Alternatives Analysis Report Page vJanuary 2016

    LIST OF FIGURES, continued PAGE

    Figure 88 – Corridor 2 – MSP to Rochester: Tier 1 EIS ........................................................... 142

    Figure 89 – Corridor 3 – Union Depot/MSP to Rochester: Tier 1 EIS ...................................... 143

    Figure 90 – Corridor 4 – Union Depot/MSP to Rochester: Tier 1 EIS ...................................... 144

    Figure 91 – Corridor 5 – Union Depot to Rochester: Tier 1 EIS ............................................... 145

    Figure 92 – Corridor 6 – Union Depot to Rochester: Tier 1 EIS ............................................... 146

    Figure 93 – Corridor 7 – Union Depot to Rochester: Tier 1 EIS ............................................... 147

    Figure 94 – Corridor 8 – Union Depot to Rochester: Tier 1 EIS ............................................... 148

    LIST OF TABLES PAGE

    Table 1 – Prior Studies ................................................................................................................2

    Table 2 – Corridor vs. Alignment Definition .................................................................................4

    Table 3 – Level 1 Screening Criteria ......................................................................................... 12

    Table 4 – Corridors Evaluated in Level 2 Screening .................................................................. 91

    Table 5 – Level 2 Screening Criteria ......................................................................................... 93

    Table 6 – Comparative Evaluation Matrix – Level 2 Screening: Series 1 ................................. 134

    Table 7 – Comparative Evaluation Matrix – Level 2 Screening: Series 2 ................................. 135

    Table 8 – Comparative Evaluation Matrix – Level 2 Screening: Series 3 ................................. 136

    Table 9 – Comparative Evaluation Matrix – Level 2 Screening: Series 4 ................................. 137

    Table 10 – Comparative Evaluation Matrix – Level 2 Screening: Series 5 ............................... 138

     APPENDIX

     Appendix A

    •  Level 1 Screening Matrix – North Study Area

    •  Level 1 Screening Matrix – South Study Area

    •  Level 2 Screening Matrix

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    7/166

     

     Alternatives Analysis Report Page 1January 2016

    Preface

    The information and data contained in this Alternatives Analysis Report is to be used for

    comparative purposes only - to compare various corridor components against alternative

    corridor components in allowing for a reduction in the number of potential corridors to be

    analyzed in the Tier 1 EIS.

    The eight corridors advanced to the Tier 1 EIS were determined through a qualitative analysis

    and are estimated to result in fewer impacts to the built and natural environments than those

    corridors eliminated from further study. No field measurements were taken and estimates shown

    should be used only to compare various corridor components and should not be taken out of

    context or interpreted as actual field-verified data.

    In addition to analyzing the potential corridor alternatives, the Tier 1 EIS will evaluate the No-

    Build alternative as directed by the Council on Environmental Quality (40 CFR1502.14).

    Introduction and BackgroundThe Minnesota Department of Transportation (MnDOT) and the Olmsted County Regional

    Railroad Authority (OCRRA), in collaboration with the Federal Railroad Administration (FRA)

    have initiated development of the Rochester-Twin Cities Passenger Rail Corridor Investment

    Plan and Tier 1 Environmental Impact Statement (Tier 1 EIS) to evaluate the system level

    environmental impact of alternative passenger rail corridors between the Minneapolis-St. Paul

    Metropolitan Area and the Rochester MN Metropolitan Area. The proposed high speed intercity

    passenger rail service between the Twin Cities and Rochester has been branded as the Zip Rail

    Project.

    The study area is located in the counties ofDakota, Dodge, Goodhue, Hennepin,

    Olmsted, Ramsey and Rice (see Figure 1).

    This Alternatives Analysis Report

    documents the process used to develop

    and evaluate the reasonable and feasible

    passenger rail corridor alternatives

    between Rochester and the Twin Cities as

    part of the Zip Rail Project. The purpose of

    this analysis was to identify a reasonable

    number of alternatives to carry into the Tier1 Environmental Impact Statement (EIS)

    study with the intention of identifying either

    the No-Build alternative or a preferred

    passenger rail corridor alternative for

    implementation. The Tier 1 EIS will

    analyze overall corridor or System Level 

    environmental impacts. Subsequent Tier 2

    Figure 1Zip Rail Project Study Area

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    8/166

     

     Alternatives Analysis Report Page 2January 2016

    EIS environmental documents will analyze site specific or Project Level impacts.

    The conclusions presented in this report are also discussed in the Rochester-Twin Cities

    Passenger Rail Corridor Investment Plan and Tier 1 EIS Final Scoping Decision Document

    (January 2015).

    The concept of a high speed rail connection between Rochester and the Twin Cities has been

    the subject of many studies beginning in 1991 (Table 1) culminating in the inclusion of the

    Rochester to Twin Cities Corridor in the 2010 Minnesota Statewide Freight and Passenger Rail

    Plan as a ‘Phase 1 Project.’ The 2015 State Rail Plan recommends a program of priority

    improvements through 2030 that identifies the Rochester to Twin Cities Corridor as a ‘Phase 1

    Project in Advanced Planning.’ As a high speed rail project, passenger trains could travel at

    speeds of up to 186 mph with a projected end to end travel time of approximately 45-50

    minutes. 

    Table 1Prior Studies

    Study Year Findings

    Tri-State High Speed Rail Study 1991Evaluated the potential for high speed rail between the Twin Cities

    and Chicago, through Rochester and Wisconsin.

    Tri-State II High Speed Rail

    Feasibility Study2000

     Alternatives between the Twin Cities, Rochester and Winona had the

    best benefit/cost ratio of those studied and should be implemented

    following the incremental upgrading of the existing Amtrak route.

    Rochester Rail Link Feasibility

    Study2003

     A high speed rail link would provide an effective transportation

    connection between Rochester and the Twin Cities to help link these

    cities to the rest of the Midwest.

    Tri-State III High-Speed Rail

    Study: Minnesota Segment

     Assessment

    2009Supported Twin Cities to Rochester on a new alignment as part of a

    larger corridor studied.

    Minnesota Comprehensive

    Statewide Freight and

    Passenger Rail Plan

    2010

    The Rochester-Twin Cities Rail Corridor was identified in the plan as

    a Priority 1 corridor in the recommended Minnesota and Regional

    passenger rail system.

    Preliminary Economic Benefit

     Analysis of the Proposed

    Rochester–Twin Cities High–

    Speed Passenger Rail Program

    2012

    The report presented an estimate of potential economic benefits from

    the implementation of Zip Rail. The analysis suggested that the

    economic benefits of Zip Rail could easily exceed both the initial

    capital cost and the long-term operating cost of the proposed project

    and indicated that these benefits and the creation of jobs would occur

    with Zip Rail operating as a stand-alone line with the resultingeconomic benefits realized by the entire state of Minnesota.

    2015 State Rail Plan 2015

    Reiterates the state’s commitment to the Twin Cities to Rochester

    Corridor as a Phase 1 Corridor in Advanced Planning in the

    recommended Minnesota and Regional passenger rail system.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    9/166

     

     Alternatives Analysis Report Page 3January 2016

    The Rochester-Twin Cities Passenger Rail Corridor Investment Plan and Tier 1 Environmental

    Impact Statement is being prepared in compliance with both the National Environmental Policy

     Act of 1969 (NEPA) and the state

    environmental review process governed by the

    Minnesota Environmental Policy Act (MEPA)

    (Figure 2). The project team, comprised ofrepresentatives from the MnDOT Passenger

    Rail Office and OCRRA, initiated an

    alternatives analysis to evaluate the range of

    passenger rail corridors and termini options

    that exist between Rochester and the Twin

    Cities and to identify the corridors that will be

    evaluated in the Tier 1 EIS.

    The Tier 1 EIS will analyze environmental

    impacts for reasonable corridor-level

    passenger rail route alternatives between

    Rochester and the Twin Cities. The EIS will

    incorporate information from the Service Development Plan (SDP), which will provide detail on

    operation, ridership, equipment and financial performance, to better determine potential

    environmental impacts for each corridor alternative. 

     Alternatives Analysis Methodology

    The goal of the alternatives analysis process was to identify corridors and terminus locations

    with the shortest travel times and the least disruption to the natural, built, and cultural

    environments. These alternatives were described in the scoping process and identified in the

    Final Scoping Decision Document for advancing for further study in the Tier 1 EIS. Theevaluation methodology and criteria used in the two-step screening process were developed to

    be compatible with typical FRA evaluation methodologies and were based on the project’s

    stated purpose and need. The process for a FRA Tier 1 EIS includes assessing beneficial and

    adverse environmental effects associated with a reasonable range of corridor alternatives. The

    evaluation criteria were designed to compare corridor alternatives using a common measure

    and to advance the most feasible corridor alternatives for further study at the next level,

    consistent with the objectives of the FRA Tier 1 EIS process.

     At the alternatives development phase a “high level” of analysis was completed, meaning that

    data for evaluation among corridor alternatives was collected at a general level for comparative

    purposes. At this level, the analysis was used to assess a large number of corridor alternativeswhile keeping the level of analysis manageable and allowing for the identification of any fatally

    flawed options. Figure 3 illustrates the alternatives analysis process.

    For the purposes of the two-step screening process and for the environmental analysis the

    following definitions and parameters were established (Table 2):

    Corridor  – For this study, a corridor represents a 1-mile wide geographic footprint within

    which a final alignment would be located. The 1-mile wide designation allows the

    Figure 2Environmental Review Process Flow

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    10/166

     

     Alternatives Analysis Report Page 4January 2016

    opportunity to adjust the alignment to minimize impacts on land uses and environmental

    resources.

     Alignment  – The alignment is the actual linear location of a transportation facility such

    as a road surface or railroad track. Actual alignments will be determined in the Tier 2

    environmental documents.

    Right-of-way  – Right-of-way is the land within which the alignment is placed, which for

    high speed rail is approximately 200 feet wide.

    Table 2

    Corridor vs. Alignment Definit ion

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    11/166

     

     Alternatives Analysis Report Page 5January 2016

    Figure 3 Alternatives Analysis Process

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    12/166

     

     Alternatives Analysis Report Page 6January 2016

    No-Build Alternative

    In addition to analyzing the potential corridor alternatives the project team evaluated, and will

    continue to evaluate, the No-Build alternative as directed by the Council on Environmental

    Quality (40 CFR1502.14). The No-Build alternative reflects existing conditions, and includes all

    currently programmed improvements in the project area over the next 20 years includinghighway, transit or other investments. The No-Build alternative does not include passenger rail

    since passenger rail service does not currently exist within the study area.

    The No-Build alternative will be further defined in the Tier 1 EIS based on committed projects

    identified in the most recent Minnesota State Transportation Improvement Program (STIP). The

    STIP identifies the schedule and funding of transportation projects. It includes all state and local

    transportation projects with federal highway and/or federal transit funding along with 100

    percent state funded transportation projects. Greater Minnesota metropolitan planning

    organization programs are included in the listing, which will include projects identified by the

    Rochester-Olmsted Council of Governments. Local projects that are programmed will be

    included in the listing.

    The No-Build alternative serves as the base of comparison for the potential corridor alternatives.

    It will be analyzed to the same level as corridor alternatives in the Tier 1 EIS. The No-Build

    alternative will be assessed for its ability to meet the project purpose and need and evaluated

    for potential impacts. If implementing the No-Build alternative would result in predictable actions

    by others, the effect of those actions would be considered part of the effects of the No-Build

    alternative.

    Purpose and Need

    In the NEPA process the Purpose and Need document is the foundation upon which thealternatives analysis is conducted. The Purpose and Need Statement for this plan was

    approved by the FRA and distributed for public comment in June 2013. It was adopted and

    published in August 2013 (see: www.goziprail.com).

    The purpose of the project is to provide a reliable and safe passenger rail transportation

    alternative that will meet forecasted population and economic growth mobility demands in the

    Southeast Minnesota corridor between Rochester and the Twin Cities area. The system is to

    connect Rochester and the Twin Cities providing convenient and cost effective transportation.

    The project is being developed according to the Purpose and Need outlined in Figure 4.

    http://www.goziprail.com/http://www.goziprail.com/http://www.goziprail.com/http://www.goziprail.com/

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    13/166

     

     Alternatives Analysis Report Page 7January 2016

    Figure 4Project Purpose and Need

    The development of world-class and internationally recognized medical facilities in Rochester,

    along with its agribusiness and high-tech industrial base, make the city a significant economic

    engine in the north central United States. The Twin Cities is also a base of high-tech industry

    and the main transportation hub in the north central states. These factors mark the significance

    of the economic connection between Rochester and the Twin Cities. Transportation connecting

    these cities is primarily based on the private automobile with limited commercial transportation

    options. In Rochester, Mayo Clinic draws patients and their companions from around the nation

    and the world, and constitutes a primary need for transportation options not based on the

    private automobile.

    The project needs to meet existing and future transportation connectivity demands of the

    corridor between Rochester and the Twin Cities in a manner that is competitive with other

    modes of transportation. As the population, employment, and visitors grow along the corridor,

    especially in Rochester and the Twin Cities, the number of people travelling between these

    locations will increase, creating increased demand on the existing transportation network. The

    corridor lacks an existing rail modal option and is anticipated to experience capacity needs that

    will result from current and future economic growth.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    14/166

     

     Alternatives Analysis Report Page 8January 2016

    Screening Process

    The Zip Rail project team used a two-step screening process to formulate, evaluate, and refine

    the reasonable and feasible corridor alternatives between Rochester and the Twin Cities. The

    screening of alternatives was an iterative process. Following initial screening by the project

    team, the alternatives were informed by input from an agency meeting, Technical AdvisoryCommittee input and from an initial round of public meetings held in 2013. Each step in the

    process was increasingly more comprehensive than the previous step, refining the evaluation

    criteria to assess each remaining corridor alternative at a higher level of detail.

    Through the process of identifying, analyzing, and screening a range of potential passenger rail

    corridors, and based on the public and agency input gathered during the scoping process, the

    project team reduced the number of potential corridor alternatives from over 1,200 end-point to

    end-point combinations to eight end-point to end-point mile-wide corridor alternatives. The

    corridor alternatives resulting from the Alternatives Analysis process were introduced in the

    Draft Scoping Decision Document (DSDD), which was distributed to federal, state, and local

    agencies and the public on July 7, 2014 and was the subject of a series of three ScopingMeetings held July 29, 30, and 31, 2014 in Rochester, Inver Grove Heights, and Kenyon. A

    Final Scoping Decision Document (FSDD) was published in the January 19, 2015

    Environmental Quality Board (EQB) Monitor and distributed to the EQB distribution list and other

    interested parties.

    The FSDD documented the No-Build Alternative and eight end-point to end-point mile-wide

    study corridors that will be evaluated in the Tier 1 EIS as described in the summary of this

    report.

    Purpose and Need Rationale Review

    Prior to initiating the Level 1 screening, a purpose and need rationale review was applied to the

    universe of corridor alternatives. This review focused on the terminal station options as they

    serve as the end points of the corridor alternatives. Non-technical factors were considered in

    reviewing terminal options or combinations of terminal options. Two primary factors were

    considered in the purpose and need rationale review:

    •  Purpose and Need – any terminal station or combination of terminal stations that did not

    meet the objectives in the purpose and need statement should be removed from further

    consideration;

      Logical Termini/Duplicative Service – any terminal station or combination of terminalstations that did not provide logical termini or would introduce duplicative service should

    be removed from further consideration.

     As a result of the purpose and need rationale review, it was determined that MSP and/or Union

    Depot provided the most logical termini in the Twin Cities. A direct connection, without

    intermediate stops, to Target Field Station was not deemed appropriate as a primary terminal

    for this project. A high speed rail connection to Target Field Station in downtown Minneapolis

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    15/166

     

     Alternatives Analysis Report Page 9January 2016

    would very likely require a separate track to be built through a densely developed and highly

    traveled urban travel corridor. The probability of a high level of impacts to both natural and built

    environments could be rationally assumed. Existing passenger transit service is available to

    Target Field Station from both MSP and Union Depot on the Blue Line and the Green Line of

    the Metro Transit system, respectively.

    Identification of Corridor Alternatives

     As noted above, the evaluation of alternative routes is based upon the recognition that at this

    level of analysis it is not possible or appropriate to identify specific alignments. What are

    referred to herein as ‘corridor alternatives’ are generally described as a ‘path along the ground’

    (approximately one mile wide) within which it would be possible to engineer a specific alignment

    and to define its corresponding right-of-way. The determination of a final alignment within the

    corridor, including the potential use of elevated track, would be evaluated during the Tier 2 EIS

    process.

    Five potential termini alternatives were initially identified. Two potential termini were identified inRochester and three potential termini were identified in the Twin Cities. They included:

    •  Rochester

    •  Rochester International Airport (RST)

    •  Target Field Station, Minneapolis

    •  Minneapolis-St. Paul International Airport (MSP)

    •  Union Depot, St. Paul

     As part of the evaluation process, an intermediate station in Dakota County was introduced for

    consideration.

    The initial step in the identification of corridor alternatives was the compilation of the ‘universe of

    route alternatives’ as shown in Figure 5 that includes a large number of potential route

    segments each of which have the potential for supporting a high speed rail alignment that would

    connect the termini identified above. These route segments were initially developed based on

    previous studies, meetings with project stakeholders and from field observations. A complete

    route between the Twin Cities and Rochester would consist of a series of route segments that

    would be chained together in a continuous sequence.

     An examination of the universe of route segments reveals that the number of unique routes

    connecting the two termini is very high. To facilitate the screening process, individual route

    segments were combined into a smaller number of corridor alternatives. The corridor

    alternatives recommended for study were refined to reflect local planning efforts regarding both

    transportation and land use.

    The study area was divided into two sub-areas:

    •  Twin Cities Subarea – this subarea encompassed the portion of the project area north of

    Coates.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    16/166

     

     Alternatives Analysis Report Page 10January 2016

    •  Greater Minnesota Subarea – this subarea encompassed the portion of the project area

    south of Coates.

    Within each sub-area the corridor alternatives were grouped according to common

    characteristics, including shared endpoints. As part of level 1 screening, individual corridor

    alternatives were compared against other corridor alternatives within that group. The result is a

    step-wise process that begins by selecting the most promising corridor alternative amongst

    those with similar features.

     A nomenclature for identifying corridor segments was established. Each segment was identified

    with a geographic description and assigned a multi-letter code. The multi- letter code

    represented the termini at each end of the corridor alternative. This nomenclature is detailed

    below:

    •  IA – Target Field Station to MSP Airport

    •  IU—Target Field Station to Union Depot

    •  AU – MSP to Union Depot

    •  UC – Union Depot to Coates, MN

    •  AC – MSP to Coates, MN

    •  CD – Coates, MN to Rochester

    •  CA – Coates, MN to RST Airport

    •  DA – Rochester to RST Airport

    Target Field Station is noted as “I” due to the fact that the naming convention was established at

    the beginning of the project when Target Field Station was known as “The Interchange.”

    In addition to these groupings, the CA and CD alternatives were further broken down as follows:

    •  52 – An eastern route between Coates and Rochester or RST that closely parallels the

    existing US 52 corridor.

    •  56 – A western route between Coates and Rochester or RST that parallels a former

    railroad corridor and the MN 56 corridor to the Dodge Center/Kasson, MN area and then

    generally parallels US 14 east into the Rochester area.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    17/166

     

     Alternatives Analysis Report Page 11January 2016

    Figure 5Universe of Corridor Alternatives

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    18/166

     

     Alternatives Analysis Report Page 12January 2016

    Level 1 Screening of Corridor Alternatives

    Forty-six corridor alternatives were advanced to Level 1 screening. The criteria that were

    applied in the Level 1 assessment are described in Table 3.

    Table 3Level 1 Screening Criteria 

    Each of the criteria above were analyzed and assigned a three-tiered, color coded ranking

    system. Red indicates the highest potential for impacts, yellow for a moderate level and green

    for the least potential for major impacts compared to others within the same grouping. The

    color coded ranking is shown for each corridor on the following individual corridor map tables;

    data source information and complete data tables are located in Appendix A.

    The following detailed evaluation is organized around the following categories:

    •  MSP to Coates

    •  Union Depot to Coates

    •  Coates to Rochester

    •  Coates to RST

    The discussion identifies the corridor alternatives that have been defined and provides a

    rationale for excluding particular corridor alternatives for further consideration. Those corridor

    alternatives that are not screened out at this stage will be reviewed a second time in the Level 2

    screening step. In the following text, corridor alternatives that are listed in bold text in the

    corridor definition section are those that were carried forward to level 2 screening.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    19/166

     

     Alternatives Analysis Report Page 13January 2016

    Twin Cities Sub-area Corridor Alternatives

    The first group of segments consists of corridor alternatives that would provide connections to

    potential project termini within the Twin Cities subarea, including Target Field Station, Union

    Depot and MSP Airport.

    Corridor DefinitionThe corridors are defined as follows:

    •  IA-1 – Target Field Station to MSP via the existing Metro Blue Line LRT Corridor

    •  IU-1 – Target Field Station to Union Depot via Mississippi River crossing at Nicollet

    Island and BNSF Midway Subdivision railroad line.

    •  IU-2 – Target Field Station to Union Depot via Mississippi crossing at Nicollet

    Island and existing BNSF and CP railroad l ines (current Amtrak route)

    •  IU-3 – Target Field Station to Union Depot via the Metro Blue Line LRT right-of-

    way, crossing the Mississippi River via the Soo Line Bridge and existing CP

    Railroad line•  AU-1 – MSP to Union Depot via a new Mississippi River crossing northeast of MSP, the

    existing CP (Ford Spur) rail line, and a route in the vicinity of Seventh Street West

    •   AU-2 – MSP to Union Depot via a new Mississippi River crossing, UP Mankato Sub

    rail line and Mississippi River cross ing on an existing railroad bridge

    •  AU-3 – MSP to Union Depot via the existing Metro Blue Line LRT right-of-way crossing

    Mississippi River on the former Soo Line bridge and CP railroad line

    Evaluation

    These corridor alternatives were identified in the initial universe of alternatives because Target

    Field Station was initially considered as an alternative terminal in the Twin Cities area.

    However, all of these corridor segments were removed from further consideration as part of thisstudy for the following reasons:

    •  A review of the purpose and need for the project determined that MSP and/or Union

    Depot provided the most logical termini in the Twin Cities.

    •  Potential corridor alternatives between MSP Airport and Target Field Station would

    require a separate track to be built in a densely developed and highly traveled urban

    corridor that is already served by light rail transit. The probability of a high level of

    impacts to both the natural and built environments could be rationally assumed.

      Potential corridor alternatives between MSP Airport and Union Depot involve eitherhighly developed dense urban corridors or require crossing the Mississippi River at a

    new crossing in a highly sensitive area from both a cultural and environmental

    perspective.

    •  Potential corridor alternatives between Union Depot and Target Field Station primarily

    involve existing rail corridors that will be evaluated in the Twin Cities to Milwaukee High

    Speed Rail Tier 1 EIS.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    20/166

     

     Alternatives Analysis Report Page 14January 2016

     A direct connection from the south, without intermediate stops, to Target Field Station was not

    deemed appropriate as a primary terminal for this project. Further consideration of Target Field

    Station as a primary terminal was eliminated from this study and deferred to the Twin Cities to

    Milwaukee study for conclusion about future passenger rail linkages.

    SummaryIn summary, none of the alternatives are retained for further consideration in the Zip Rail Tier 1EIS. The following corridors were identified for consideration in future, separate studies.

    •  IA-1: Target Field Station to MSP via the existing Metro Blue Line LRT Corridor

    •  IU-2: Target Field Station to Union Depot via Mississippi crossing at Nicollet Island and

    existing BNSF and CP railroad lines (current Amtrak route)

    •  IU-3: Target Field Station to Union Depot via the Metro Blue Line LRT right-of-way,

    crossing the Mississippi River via the Soo Line Bridge and existing CP Railroad line

    •  AU-2: MSP to Union Depot via a new Mississippi River crossing, UP Mankato Sub rail

    line and Mississippi River crossing on an existing railroad bridge

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    21/166

     

     Alternatives Analysis Report Page 15January 2016

    Figure 6Corridor Alternative IA-1 (Retained for separate study)Evaluation Matrix and Location

    Corridor IA-1: Target Field Station to MSP via the existing Metro Blue Line LRT corridor.

    Corridor

    Segment1A-1

    Length (miles) 11.0

    Preliminary

    travel time

    (minutes)

    28

    Redundancy Metro Blue Line

    Impacts to Built

    Environment

    Limited space

    available for

    additional rail

    service within

    corridor

    Impacts to

    Natural

    Environment

    Potential for

    impacts near

    Minnehaha Park,

    Highway 55/62 and

    Fort Snelling

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    22/166

     

     Alternatives Analysis Report Page 16January 2016

    Figure 7Corridor Alternative IU-1 (Eliminate from further study)Evaluation Matrix and Location

    Corridor IU-1: Target Field Station to Union Depot via Mississippi River crossing at Nicollet

    Island and BNSF Midway Subdivision railroad line. 

    Corridor

    SegmentIU-1

    Length (miles) 11.3

    Preliminary

    travel time

    (minutes)

    26

    RedundancyExisting HSR Studyand Metro Green

    Line LRT

    Impacts to Built

    Environment

    Heaviest freight

    traffic on existing

    corridor compared

    to other IU

    corridors

    Impacts to

    Natural

    Environment

    Expanded

    Mississippi River

    crossing in

    Minneapolis

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    23/166

     

     Alternatives Analysis Report Page 17January 2016

    Figure 8Corridor Alternative IU-2 (Retained for separate study)Evaluation Matrix and Location

    Corridor IU-2: Target Field Station to Union Depot via Mississippi River crossing at Nicollet

    Island and existing BNSF and CP railroad lines (current Amtrak route). 

    Corridor

    SegmentIU-2

    Length (miles) 12.4

    Preliminary

    travel time

    (minutes)26

    RedundancyExisting HSR Studyand Metro Green

    Line LRT

    Impacts to Built

    Environment

    High volume of

    freight traffic on

    existing corridor, but

    less than the IU-1

    corridor

    Impacts to

    Natural

    Environment

    Expanded Mississippi

    River crossing in

    Minneapolis

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    24/166

     

     Alternatives Analysis Report Page 18January 2016

    Figure 9Corridor Alternative IU-3 (Retained for separate study)Evaluation Matrix and Location

    Corridor IU-3: Target Field Station to Union Depot via the Metro Blue LRT Line right-of-way,

    crossing the Mississippi River via the former Soo Line Bridge and existing CP railroad line.

    Corridor

    SegmentIU-3

    Length (miles) 11.0

    Preliminary

    travel time

    (minutes)

    30

    RedundancyExisting HSR Studyand Metro Green

    Line LRT

    Impacts to Built

    Environment

    High volume of

    freight traffic on

    existing corridor,

    but less than the

    IU-1 corridor

    Impacts to

    NaturalEnvironment

    Expanded

    Mississippi River

    crossing in

    Minneapolis on theformer Soo Line

    bridge

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    25/166

     

     Alternatives Analysis Report Page 19January 2016

    Figure 10Comparative Evaluation Matrix IU Series

    Corridor Alternatives IU-1, IU-2, IU-3

    Recommendation  Eliminate from furtherstudy

    Retained for separatestudy

    Retained for separatestudy

    Corridor Segment IU-1 IU-2 IU-3

    Length (miles) 11.3 12.4 11.0

    Preliminary travel

    time (minutes)26 26 30

    Redundancy

    Existing HSR Study

    and Metro Green Line

    LRT 

    Existing HSR Study

    and Metro Green

    Line LRT

    Existing HSR Study andMetro Green Line LRT

    Impacts to Built

    Environment

    Heaviest freight traffic

    on existing corridor

    compared to other IU

    corridors

    High volume of

    freight traffic on

    existing corridor,

    but less than the

    IU-1 corridor

    High volume of freight

    traffic on existing

    corridor, but less than

    the IU-1 corridor

    Impacts to

    Natural

    Environment

    Expanded Mississippi

    River crossing in

    Minneapolis

    Expanded

    Mississippi River

    crossing in

    Minneapolis

    Expanded Mississippi

    River crossing in

    Minneapolis on the

    former Soo Line bridge

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    26/166

     

     Alternatives Analysis Report Page 20January 2016

    Figure 11

    Corridor Alternative AU-1 (Eliminate from further s tudy)Evaluation Matrix and Location

    Corridor AU-1: MSP to Union Depot via a new Mississippi River crossing northeast of MSP, the

    existing CP (Ford Spur) rail line, and a route in the vicinity of Seventh Street West.

    Corridor

    SegmentAU-1

    Length (miles) 8.1

    Preliminary

    travel time

    (minutes)

    10-12

    Redundancy No redundantpassenger rail service

    Impacts to Built

    Environment

    Potential impacts to

    residential

    neighborhoods in St.

    Paul

    Impacts to

    NaturalEnvironment

    Major impacts

    associated with new

    Mississippi River

    crossing; Potential

    impacts to parks,federal and historic

    properties and Hwy

    55/62 vicinity

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    27/166

     

     Alternatives Analysis Report Page 21January 2016

    Figure 12Corridor Alternative AU-2 (Retained for separate study)Evaluation Matrix and Location

    Corridor AU-2: MSP to Union Depot via new Minnesota River crossing, UP Mankato Sub rail

    line and Mississippi River crossing on existing railroad bridge.

    Corridor

    SegmentAU-2

    Length (miles) 9.6

    Preliminary

    travel time

    (minutes)

    12-14

    RedundancyNo redundantpassenger rail

    service

    Impacts to Built

    Environment

    Moderate to high

    volume of freight

    traffic on existing

    corridor.

    Impacts to

    NaturalEnvironment

    Potential to use

    existing rail

    connection over

    Mississippi River,

    but major impactscould be

    associated with

    new Minnesota

    River crossing

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    28/166

     

     Alternatives Analysis Report Page 22January 2016

    Figure 13Corridor Alternative AU-3 (Eliminate from further s tudy)Evaluation Matrix and Location

    Corridor AU-3: MSP to Union Depot via the existing Metro Blue Line LRT corridor, crossing

    Mississippi River on the former Soo Line bridge and CP railroad line.

    Corridor

    SegmentAU-3

    Length (miles) 13.0

    Preliminary

    travel time

    (minutes)

    20

    Redundancy

    No redundant

    passenger rail

    service between

    these destinations

    Impacts to Built

    Environment

    Limited space

    available for

    additional rail

    service within

    corridor closer to

    MSP

    Impacts to

    Natural

    Environment

    Potential for

    impacts near

    Minnehaha Park,

    Highway 55/62 and

    Fort Snelling

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    29/166

     

     Alternatives Analysis Report Page 23January 2016

    Figure 14Comparative Evaluation Matrix AU Series

    Corridor Al ternatives AU-1, AU-2, AU-3 

    Recommendation Eliminate from

    further study

    Retained for separate

    study

    Eliminate from

    further study

    Corridor Segment AU-1 AU-2 AU-3

    Length (miles) 8.1 9.6 13.0

    Preliminary travel

    time (minutes)10-12 12-14 20

    RedundancyNo redundantpassenger rail

    service

    No redundantpassenger rail

    service

    No redundantpassenger rail

    service

    Impacts to Built

    Environment

    Potential impacts

    to residential

    neighborhoods in

    St. Paul

    Moderate to high

    volume of freight

    traffic on existing

    corridor

    Limited space

    available for

    additional rail

    service within

    corridor closer to

    MSP

    Impacts to Natural

    Environment

    Major impacts

    associated with

    new Mississippi

    River crossing;

    Potential impacts

    to parks, federal

    and historic

    properties andHwy 55/62 vicinity

    Potential to use

    existing rail

    connection over

    Mississippi River,

    but major impacts

    could be

    associated with

    new MinnesotaRiver crossing

    Potential for

    impacts near

    Minnehaha Park,

    Highway 55/62 and

    Fort Snelling

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    30/166

     

     Alternatives Analysis Report Page 24January 2016

    MSP Airport to Coates

    This group of segments consists of corridor alternatives that would provide connections

    between the Minneapolis-St. Paul International Airport and Coates, MN.

    Corridor Definition

    The corridors are defined as follows:

    •  AC-1A – MSP to Coates via a new crossing of the Minnesota River adjacent to I-494 for

    a portion of its length, then veering northeast to match an abandoned rail segment east

    of the river; then along MN 55 and US 52 corridors.

    •   AC-1B – MSP to Coates via new Minnesota River crossing adjacent to the exist ing

    I-494 bridge for its full length, and then along MN 55 and US 52 corridors.

    •  AC-2A – MSP to Coates via a new crossing of the Minnesota River adjacent to I-494 for

    a portion of its length, then veering northeast to match an abandoned rail segment east

    of the river. Then along Dakota County Road 71 corridor (Rich Valley Blvd.), and US 52

    corridor.•   AC-2B – MSP to Coates via new Minnesota River crossing adjacent to the exist ing

    I-494 bridge for its full length, Dakota County Road 71 corridor (Rich Valley Blvd.)

    and US 52 corridor.

    •  AC-3A – MSP to Coates via a new crossing of the Minnesota River adjacent to I-494 for

    a portion of its length, then veering northeast to match an abandoned rail segment east

    of the river. Then along existing CP and UP rail corridors, to US 52 corridor.

    •  AC-3B – MSP to Coates via new crossing of the Minnesota River adjacent to the existing

    I-494 bridge for its full length and existing CP and UP rail corridors to US 52 corridor.

    •  AC-4 – MSP to Coates via Minnesota 77/Cedar Avenue and Dakota County Road 46

    (160th Street) to US 52 corridor.

    Evaluation

    The alternatives identified above utilize one of two locations for crossing the Minnesota River.

    Corridor Alternatives AC-1A/B, AC-2A/B and AC-3A/B assume a crossing of the Minnesota

    River valley parallel to the existing I-494 highway bridge, which crosses the river on an east-

    west alignment. Corridor Alternative AC-4 assumes a crossing of the Minnesota River adjacent

    to the Cedar Avenue Bridge.

    I-494 Crossing

    For corridor alternatives AC-1, 2 and 3, the proposed alignment crosses the Minnesota River

    adjacent to and on the north side of the I-494 Bridge. The exact design and impact of the bridge

    would need to be determined in preliminary design but of all the possible crossing points in thisvicinity, remaining adjacent to the existing bridge would minimize environmental impacts on a

    very sensitive area that includes the Minnesota Valley National Wildlife Refuge and other state

    and federally protected areas when compared to crossing the river at a location that does not

    already have a bridge.

    The ‘B’ sub-alternatives remain adjacent to the bridge and continue to parallel I-494 after

    crossing the river. However, the ‘A’ alternatives swing northward after crossing the river and

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    31/166

     

     Alternatives Analysis Report Page 25January 2016

    connect to an abandoned railroad right-of-way. While the ‘A’ alternatives have less interaction

    with I-494, the impact on sensitive areas along the Minnesota River is far greater.

    Therefore, AC-1A, AC-2A and AC-3A are eliminated from further consideration.

    Corridors AC-1B, AC-2B and AC-3B follow I-494 after crossing the Minnesota River to the

    vicinity of the I-494/I-35E interchange. Corridor AC-1B shifts to State Highway 55, following that

    roadway to US Highway 52 and then to Coates. Corridor AC-2B shifts to State Highway 55 and

    follows that roadway to County Road 71 (Rich Valley Blvd.) whereupon the corridor follows

    County Road 71 to the Union Pacific Railroad, follows the roadway to US Highway 52 and then

    to Coates. Corridor AC-3B shifts to a railroad alignment that parallels State Highway 149 and

    State Highway 3 to Rosemount where it turns east to intersect with US Highway 52 at Coates.

    In comparing the three corridors between the I-494/I35E interchange and Coates, AC-3B is the

    longest in distance and the least direct. AC-3B also has significant impacts on the built

    environment, particularly in Rosemount.

    Therefore AC-3B is eliminated from further consideration. 

    Cedar Avenue Crossing

    Corridor AC-4 crosses the Minnesota River adjacent to State Highway 77 (Cedar Avenue),

    following that roadway to Dakota County Road 46 (160th Street), then to US Highway 52 and

    Coates. This corridor is longest in distance and least direct of all AC corridor alternatives with

    significantly greater travel time. In addition, the Highway 77 corridor is highly developed and

    construction of a new rail alignment would have significant impact on residential and commercial

    structures. (Redundancy with the METRO Red Line is irrelevant because the high speed rail

    line would have no stops along the Red Line and therefore would not be in competition with it.)

    Therefore AC-4 is eliminated from further consideration.

    Summary

    In summary, the following alternatives are retained for further consideration:

    •  AC-1B: MSP to Coates via new Minnesota River crossing adjacent to the existing I-494

    bridge for its full length, and then along MN 55 and US 52 corridors.

    •  AC-2B: MSP to Coates via new Minnesota River crossing adjacent to the existing I-494

    bridge for its full length, Dakota County Road 71 corridor (Rich Valley Blvd.) and US 52

    corridor.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    32/166

     

     Alternatives Analysis Report Page 26January 2016

    Figure 15Corridor Alternative AC-1A (Eliminate from further study)Evaluation Matrix and Location

    Corridor AC-1A: MSP to Coates via a new crossing of the Minnesota River adjacent to I-494 for

    a portion of its length, then veering northeast to match an abandoned rail segment east of the

    river; then along MN 55 and US 52 corridors.

    Corridor

    SegmentAC-1A

    Length (miles) 18.5

    Preliminary

    travel time

    (minutes)

    20-22

    Redundancy

    No redundant

    passenger rail

    service in this

    segment

    Impacts to Built

    Environment

    Potential for

    impacts to adjacent

    residential and

    commercial

    developments along

    MN 55 and US 52

    Impacts to

    Natural

    Environment

    Major impactsassociated with new

    Minnesota River

    crossing and at Fort

    Snelling State Park

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    33/166

     

     Alternatives Analysis Report Page 27January 2016

    Figure 16Corridor Alternative AC-1B (Advance to Level 2 Screening)Evaluation Matrix and Location

    Corridor AC-1B: MSP to Coates via new Minnesota River crossing adjacent to the existing I-494

    bridge for its full length, and then along MN 55 and US 52 corridors.

    Corridor

    SegmentAC-1B

    Length (miles) 18.5

    Preliminary

    travel time

    (minutes)

    20-22

    Redundancy

    No redundantpassenger rail

    service in this

    segment

    Impacts to Built

    Environment

    Potential for

    impacts to adjacent

    residential and

    commercial

    developments along

    MN 55 and US 52

    Impacts toNatural

    Environment

    Impacts associated

    with newMinnesota River

    crossing are less

    than other AC

    corridors

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    34/166

     

     Alternatives Analysis Report Page 28January 2016

    Figure 17Corridor Alternative AC-2A (Eliminate from further study)Evaluation Matrix and Location

    Corridor AC-2A: MSP to Coates via a new crossing of the Minnesota River adjacent to I-494 for

    a portion of its length, then veering northeast to match an abandoned rail segment east of the

    river. Then along Dakota County Road 71 corridor (Rich Valley Blvd.), and US 52 corridor.

    Corridor

    SegmentAC-2A

    Length (miles) 17.6

    Preliminary

    travel time

    (minutes)

    20-21

    Redundancy

    No redundant

    passenger rail service

    in this segment

    Impacts to Built

    Environment

    Potential for impacts

    to fewer adjacent

    residential and

    commercial

    developments along

    Rich Valley Blvd

    corridor when

    compared to AC-1

    corridors

    Impacts to

    Natural

    Environment

    Major impacts

    associated with new

    Minnesota River

    crossing and at Fort

    Snelling State Park

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    35/166

     

     Alternatives Analysis Report Page 29January 2016

    Figure 18Corridor Alternative AC-2B (Advance to Level 2 Screening)Evaluation Matrix and Location

    Corridor AC-2B: MSP to Coates via new Minnesota River crossing adjacent to the existing I-

    494 bridge for its full length, Dakota County Road 71 corridor (Rich Valley Blvd.) and US 52

    corridor.

    Corridor

    SegmentAC-2B

    Length (miles) 17.4

    Preliminary

    travel time

    (minutes)

    20-21

    Redundancy

    No redundant

    passenger rail

    service in this

    segment

    Impacts to Built

    Environment

    Potential for fewer

    existing property

    impacts along Rich

    Valley Blvd corridor

    when compared to

    AC-1 corridors

    Impacts to

    Natural

    Environment

    Impacts associated

    with new

    Minnesota River

    crossing are less

    than other AC

    corridors

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    36/166

     

     Alternatives Analysis Report Page 30January 2016

    Figure 19Corridor Alternative AC-3A (Eliminate from further study)Evaluation Matrix and Location

    Corridor AC-3A: MSP to Coates via a new crossing of the Minnesota River adjacent to I-494 for

    a portion of its length, then veering northeast to match an abandoned rail segment east of the

    river. Then along existing CP and UP rail corridors to US 52 corridor.

    Corridor

    SegmentAC-3A

    Length (miles) 21.2

    Preliminary

    travel time

    (minutes)

    22-26

    Redundancy

    No redundant

    passenger rail

    service in this

    segment

    Impacts to Built

    Environment

    Potential for

    conflicts with

    existing freight rail

    operations near

    Rosemount

    Impacts to

    Natural

    Environment

    Major impacts

    associated with new

    Minnesota River

    crossing and at Fort

    Snelling State Park

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    37/166

     

     Alternatives Analysis Report Page 31January 2016

    Figure 20Corridor Alternative AC-3B (Eliminate from further study)Evaluation Matrix and Location

    Corridor AC-3B: MSP to Coates via new crossing of the Minnesota River adjacent to the

    existing I-494 bridge for its full length and existing CP and UP rail corridors to US 52 corridor.

    Corridor

    SegmentAC-3B

    Length (miles) 20.9

    Preliminary

    travel time

    (minutes)

    21-25

    Redundancy

    No redundant

    passenger rail servicein this segment

    Impacts to Built

    Environment

    Potential for conflicts

    with existing freight

    rail operations near

    Rosemount

    Impacts to

    Natural

    Environment

    Impacts associated

    with new Minnesota

    River crossing are

    less than other AC

    corridors

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    38/166

     

     Alternatives Analysis Report Page 32January 2016

    Figure 21Comparative Evaluation Matrix AC Series

    Corridor Alternatives AC-1A, AC-1B, AC-2A, AC-2B, AC-3A, AC-3B

    Recommendation Eliminate from

    further study

    Advance to Level

    2 Screening

    Eliminate from

    further study

    Advance to Level

    2 Screening

    Eliminate from

    further study

    Eliminate from

    further study

    Corridor

    SegmentAC-1A AC-1B AC-2A AC-2B AC-3A AC-3B

    Length (miles) 18.5 18.5 17.6 17.4 21.2 20.9

    Preliminary

    travel time

    (minutes)

    20-22 20-22 20-21 20-21 22-26 21-25

    Redundancy

    No

    redundant

    passenger

    rail service in

    this segment

    No

    redundant

    passenger

    rail service in

    this segment

    No

    redundant

    passenger

    rail service in

    this segment

    No

    redundant

    passenger

    rail service in

    this segment

    No

    redundant

    passenger

    rail servicein this

    segment

    No

    redundant

    passenger

    rail servicein this

    segment

    Impacts to

    Built

    Environment

    Potential for

    impacts to

    adjacent

    residential and

    commercial

    development

    along MN 55

    and US 52

    Potential for

    impacts to

    adjacent

    residential

    and

    commercial

    development

    along MN 55

    and US 52

    Potential for

    impacts to

    fewer

    adjacent

    residential

    and

    commercial

    developments

    along Rich

    Valley Blvd

    corridor when

    compared to

    AC-1 corridors

    Potential for

    fewer existing

    property

    impacts along

    Rich Valley

    Blvd corridor

    when

    compared to

    AC-1 corridors

    Potential for

    conflicts with

    existing

    freight rail

    operations

    near

    Rosemount

    Potential for

    conflicts with

    existing

    freight rail

    operations

    near

    Rosemount

    Impacts to

    Natural

    Environment

    Major

    impacts

    associated

    with new

    Minnesota

    River

    crossing and

    at Fort

    Snelling

    State Park

    Impacts

    associated

    with new

    Minnesota

    River

    crossing are

    less than

    other AC

    corridors

    Major

    impacts

    associated

    with new

    Minnesota

    River

    crossing and

    at Fort

    Snelling

    State Park

    Impacts

    associated

    with new

    Minnesota

    River

    crossing are

    less than

    other AC

    corridors

    Major

    impacts

    associated

    with new

    Minnesota

    River

    crossing

    and at Fort

    Snelling

    State Park

    Impacts

    associated

    with new

    Minnesota

    River

    crossing are

    less than

    other AC

    corridors

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    39/166

     

     Alternatives Analysis Report Page 33January 2016

    Figure 22Corridor Alternative AC-4 (Eliminate from further study)Evaluation Matrix and Location

    Corridor AC-4: MSP to Coates via Minnesota 77/Cedar Avenue and Dakota County Road 46

    (160th Street) to US 52 corridor.

    Corridor

    SegmentAC-4

    Length (miles) 22.7

    Preliminary

    travel time

    (minutes)

    34

    Redundancy

    Metro Red Line BRT

    serves a portion of

    this segment

    Impacts to Built

    Environment

    Potential for major

    impacts to existing

    commercial

    developments along

    Cedar Avenue

    Impacts to

    NaturalEnvironment

    Expanded Minnesota

    River crossing

    adjacent to MN 77

    south of MSP

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    40/166

     

     Alternatives Analysis Report Page 34January 2016

    Union Depot to Coates

    This group of segments consists of corridor alternatives that would provide connections

    between Union Depot and Coates, MN. 

    Corridor DefinitionThe corridors are defined as follows:

    •  UC-1A – Union Depot to Coates via existing BNSF and CP rail lines, with Mississippi

    River crossing near the former Rock Island swing bridge in St. Paul Park/Inver Grove

    Heights onto the UP line west of the Mississippi River

    •  UC-1B – Union Depot to Coates via exist ing BNSF and CP rail l ines, with

    Mississippi River crossing to the UP line near I-494/Newport

    •  UC-1C – Union Depot to Coates via existing BNSF and CP rail lines, with Mississippi

    River crossing to the UP lines south of I-494 in St. Paul Park

    •  UC-2A – Union Depot to Coates via existing UP rail line, with an existing Mississippi

    River railroad crossing near Pig’s Eye Lake•  UC-2B – Union Depot to Coates via existing UP rail line, with a Mississippi River

    cross ing adjacent to the existing Robert Street railroad bridge

    •  UC-3A – Union Depot to Coates via existing BNSF and CP rail lines, with a new or

    rehabilitated Mississippi River crossing in Hastings and through an abandoned rail

    corridor, including a new crossing of the Vermillion River

    •  UC-3B – Union Depot to Cannon Falls via existing BNSF and CP rail lines, with a

    crossing of the Vermillion River and the US 61 corridor to Cannon Falls.

    •  UC-4A – Union Depot to Coates via the Union Pacific (Mankato Subdivision) line, with

    Mississippi River crossing on existing railroad swing bridge, with an intermediate stop in

    the vicinity of MSP, then south to Coates on a corridor adjacent to MN 55 and US 52

    •  UC-4B – Union Depot to Coates via the Union Pacific (Mankato Subdivision) line,with Mississippi River crossing on existing railroad swing bridge, with an

    intermediate stop in the vicinity of MSP, then south to Coates near the Dakota

    County 71 (Rich Valley Blvd) cor ridor to US 52 corridor

    EvaluationThe above described alternatives depart the Union Depot over different existing rail lines

    including:

    1. BNSF and CP to the southeast,

    2. Union Pacific to the southeast,

    3. Union Pacific to the southwest or4. Union Pacific to the south.

    The alternatives also vary according to where the Mississippi River is crossed including one of

    the following:

    1. The former Rock Island swing bridge area in St. Paul Park/Inver Grove Heights

    2. Near the I-494 highway bridge in Newport

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    41/166

     

     Alternatives Analysis Report Page 35January 2016

    3. South of I-494 in St. Paul Park

    4. Existing Union Pacific railroad crossing near Pig’s Eye Lake

    5. Existing Union Pacific Robert Street railroad bridge

    6. New or rehabilitated Mississippi River crossing in Hastings

    7. The existing Union Pacific railroad swing bridge west of downtown St Paul

    The location of the Mississippi River crossing determines the route south or west of the River to

    Coates.

    BNSF/CP to the Southeast – UC-1 Alternatives

    The UC-1 alternatives extend from Union Depot southeast over BNSF and CP tracks along the

    east side of the Mississippi River then cross to the west side of the Mississippi River and

    continue south on the UP line to the US 52 corridor to Coates. A new crossing of the

    Mississippi River would be required. The three UC-1 alternatives differ in the location of the

    new crossing.

    North of a future river crossing, these alternatives utilize active freight lines, which raise issues

    of capacity and coordination with freight traffic. On the other hand, this corridor would share thesame track with existing Amtrak Empire Builder service, potential Red Rock commuter rail

    service and future high speed passenger rail service between the Twin Cities and Chicago.

    Several projects, documented in the East Metro Rail Capacity Study, the Twin Cities to

    Milwaukee HSR study and the Red Rock Corridor Study identify new construction through

    Dayton’s Bluff/Hoffman yards.

    South of a future river crossing, the corridor follows the existing Union Pacific right-of-way south

    to the US 52 corridor to Coates.

    The principal differentiation between the three alternatives is the location of a potential

    Mississippi River crossing:

    •  UC-1A – The former Rock Island swing bridge area in St. Paul Park/Inver Grove Heights

    •  UC-1B – Near the I-494 highway bridge in Newport

    •  UC-1C – South of I-494 in St. Paul Park

     All three potential crossings are problematic from an environmental perspective because each

    represents a new crossing of the Mississippi River. A new bridge would also need to

    accommodate river navigation, suggesting either a swing or lift bridge due to the difficulty of

    attaining the requiring height clearance for a railroad bridge. Although the Rock Island Swing

    Bridge was formerly used as a railroad bridge, only part of the bridge remains and is now used

    as a park, raising 4F concerns. In addition, the Rock Island Bridge formerly entered theproperty of the St. Paul Park refinery; there would be security concerns raised if efforts were

    made to construct a new bridge into that area. A bridge crossing near St. Paul Park would

    require a longer bridge and a longer stretch of greenfield alignment on the east side of the river

    than a new bridge near the I-494 highway crossing. The latter also has the advantage of being

    near an existing river crossing, which would presumably reduce the visual impact. Of the three

    river crossing alternatives, the location near I-494 is most favorable.

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    42/166

     

     Alternatives Analysis Report Page 36January 2016

    Therefore, UC-1A and UC-1C are eliminated from further consideration.

    Union Pacific to the South or Southeast – UC-2 Alternatives

    The UC-2 alternatives extend from Union Depot over Union Pacific tracks, cross the Mississippi

    River and continue south on the UP line to the US 52 corridor to Coates. In both cases, an

    existing crossing of the Mississippi River would be utilized. The two UC-2 alternatives differ in

    the location of the existing crossing.

    North of a future river crossing, these alternatives utilize active freight lines, which raise issues

    of capacity and coordination with freight traffic. However, in contrast to the UC-1 alternatives,

    the distance travelled along the existing passenger corridor is much shorter. South of a future

    river crossing, the corridor follows the existing Union Pacific right-of-way south to where the

    Union Pacific swings to the west towards Rosemount. South of this point, the corridor follows a

    path west of the Flint Hills Refinery then southeast to the US 52 corridor to Coates.

    The principal differentiation between the two alternatives is the location of the existing

    Mississippi River crossing:

    •  UC-2A – The existing UP bridge near Pig’s Eye Lake

    •  UC-2B – The existing UP bridge near Robert Street

    In both cases, the Union Pacific railroad line is used directly out of the Union Depot. And in both

    cases, the proposed passenger service crosses the Mississippi River at the location of an

    existing Union Pacific bridge. The difference between the two alternatives is how to get to those

    bridges. The path to the southeast is complicated by the necessity of crossing BNSF and CP

    railroad tracks to get first to the Union Pacific St. Paul Hoffman yard and then by the necessity

    of going through the yard and around the Metropolitan Council’s wastewater treatment facility.

    Crossing the Mississippi River directly from Union Depot near the Robert Street Bridge requires

    crossing the CP mainline tracks but at this location there is a very low volume and trains do nothave to leave the Union Pacific tracks. The UC-2B alternative would provide access into Union

    Depot without the freight congestion associated with the UC-2A alternative through the Dayton’s

    Bluff/Hoffman Yards area.

    Therefore, UC-2A is eliminated from further consideration. 

    BNSF/CP to the southeast – Mississippi River Crossing at Hastings – UC-3 alternatives

    The UC-3 alternatives extend from Union Depot southeast over BNSF and CP tracks along the

    east side of the Mississippi River to Hastings, MN, cross the Mississippi River and proceed to

    either Coates or Cannon Falls. A new or rehabilitated crossing of the Mississippi River and a

    new crossing of the Vermillion River would be required. The two UC-3 alternatives differ in thepath taken south of Hastings.

    North of a future river crossing, these alternatives utilize active freight lines, which raise issues

    of capacity and coordination with freight traffic. On the other hand, this corridor would share the

    same track with existing Amtrak Empire Builder service, potential Red Rock commuter rail

    service and future high speed passenger rail service between the Twin Cities and Chicago.

    Several projects, documented in the East Metro Rail Capacity Study, the Twin Cities to

  • 8/20/2019 Alternatives Analysis Rpt Jan2016

    43/166

     

     Alternatives Analysis Report Page 37January 2016

    Milwaukee HSR study and the Red Rock Corridor Study identify new construction through

    Dayton’s Bluff/Hoffman yards.

    In contrast to the UC-1 alternatives, the UC-3 alternatives parallel the BNSF/CP tracks for a

    longer distance. But the East Metro Rail Capacity Study recognized the need for capacity

    improvements at least as far as Hastings to accommodate passenger rail service. These

    alternatives would utilize infrastructure that would already be carrying high speed passenger

    trains.

    The principal differentiation between the two alternatives is the path followed south of Hastings:

    •  UC-3A – This corridor follows an abandoned railroad alignment through the Vermillion

    River Valley between Hastings and Coates

    •  UC-3B – This corridor crosses the Vermillion River and follows the US Highway 61

    corridor to Cannon Falls.

    South of Hastings, both of these alternatives are problematic. Neither follows an existing