AMS02 TIMCAB Project Status
JSC, January 2007Prepared by H. Cuesta / G. Muñoz
2
January 2007 AMS02 CAB Status Report (JSC January 2007)
Table of Content
1.- Cryomagnet Current Source
CCS Electrical Tests
CCS Thermal Tests
2.- CSP System
Current Lead Detector Module
3.- Valve Electronics Status
PS module
CSP PWR DRV module
CSP TM/TC
4.- CAB Schedule
3
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System
Activities of the CCS Current Source
CCS Current Source tested in Thermal Vacuum Chamber at CRISA facilities
CCS Set-up preparation during Weeks 48 and 49 of 2006
Electrical and Thermal Tests of CCS Current Source performed before Christmas.
4
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
5
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
6
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
7
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
8
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
9
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
CCS Electrical Test Campaign (Crisa facilities)
CCS electrical design verified at different temperatures and in Vacuum.
CCS Functionality in Vacuum conditions Good Performances of Voltage, Power and Current control loops of the current source
CCS Current Source operating in Ramp-up Sequence and Steady State
Active Load used for CCS electrical Tests
CCS operating in Short-Circuit conditions simulating Persistent Switch closed
Measured values of the CCS power dissipation similar to the typical values of the calculated power budget of the CCS.
10
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
11
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
12
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
13
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
14
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
CAB POWER LOSSES (W)
0
100
200
300
400
500
600
700
-10 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
TIME (min)
PO
WE
R D
ISS
IPA
TI0
N (
W)
15
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
CCS Vacuum and Thermal Test Campaign (Crisa facilities)
CCS Thermal Design Validation as main objective
Hottest temperature Monitoring during Ramp-up sequence and Steady State
Additional Thermocouples included to monitor the hottest points of CCS
CCS Thermal Test Report, including description of the Thermal Model used and the correlation with CAB detailed Thermal Model, is under preparation. It will be distributed to TWG for review.
16
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
17
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
18
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Vacuum and Thermal Tests)
19
January 2007 AMS02 CAB Status Report (JSC January 2007)
1.- CCS System(CCS Pending Actions)
Protections at CCS board level OC Protection Circuitry of the of the SR Power Supply of the 28V Interpoint CV modules Update the UV protection values at 109V instead of 95V Current Limitation at 95A for each CCS converter board Add TVS at the input stage of the SC SW
Protection circuitry Design, Manufacturing and Tests foreseen between Jan_07 and Apr_07
Protections at the CCS output Crisa has assessed the need of adding TVS “Transient Voltage Suppressors” at CCS output To foresee Transient voltages when opening the Persistent Switch at the end of Ramp up sequence or
opening the SC SW in case of aborting the Ramp up sequence during a power loss Objective: To protect the Mosfet of the SC SW during the Ramp up sequence Electrical design is available Physical design is on going
Calibration Procedure of the CCS Current Shunt (200)
20
January 2007 AMS02 CAB Status Report (JSC January 2007)
2.- CSP system(CSP_CL_DET Board & CSP_DET_CV Board)
21
January 2007 AMS02 CAB Status Report (JSC January 2007)
2.- CSP system(CSP_CL_DET Board & CSP_DET_CV Board)
Detection Function of the CL Voltages and Temperatures
New threshold values for CL voltages and temperatures defined by SCL
WARNING LEVEL (the user has time to discharge the magnet manually) Current lead cold side: 15 mV (instead of 80mV) Current lead warm side: 75 mV (instead of 80mV) Current lead temperature: 155 K (instead of 250K)
ALARM LEVEL (triggers a quench autonomously) Current lead cold side: 45 mV (instead of 100mV) Current lead warm side: 110 mV (instead of 100mV)
22
January 2007 AMS02 CAB Status Report (JSC January 2007)
3.- Valve Electronics Status
CCSC Power Switches module Electrical definition Pressure and Vacuum sensors Valve Configuration Valve Control and Timing Valve Power & Monitoring External I/F Block Diagrams of the valve control architecture Preliminary Schematics On going Tasks (Electrical Design Revision, WCA, PSA) in Dec06 and Jan07 PCB Physical design foreseen in Jan/Feb 2007 PCB Manufacturing in Feb/March 2007 Board Population in March 2007 CCSC Power Switches board Tests in April 2007
23
January 2007 AMS02 CAB Status Report (JSC January 2007)
3.- Valve Electronics Status
CSP Power Drivers module CSP TM/TC module
Electrical definition Valve Configuration (Control, Timing, Power and Monitoring) External I/F for the valves Block Diagrams of the valve control architecture Preliminary Schematics RDS and AQS sequences updated Update of the FPGA_CSP technical Specification in Dec06/Jan07 Power control of the CD & CL TMP heaters CSP PWR DRV module Design of the FPGA_CSP foreseen for Feb/March 2007 Pending Tasks (Electrical Design Revision, WCA, PSA) in Jan 2007 PCB Physical design foreseen in Feb 2007 PCB Manufacturing in Mar 2007 Board Population in Apr 2007 CSP board Tests in May 2007
24
January 2007 AMS02 CAB Status Report (JSC January 2007)
4.- CAB Schedule
The current schedule provides the following delivery dates
CAB EM pending boards To be finished May 2007
CAB EM model: 31 July 2007
CAB EM model Integration Tests at Culham, from 17th Sep 2007 (TBC)
CAB Flight model: 20th May 2008
25
January 2007 AMS02 CAB Status Report (JSC January 2007)
4.- CAB Schedule