Good PracticesGood Practicesin ICT Procurementin ICT Procurement
under RA 9184under RA 9184
rogelio vicente juan o. morales
-
8/4/2019 Alt Methods Part 2 Distrib
2/52
-
8/4/2019 Alt Methods Part 2 Distrib
3/52
Public perception: Computerization slows down
work processes.
Govt ICT Procurements
DFA
LTO
LRA
POEA
GSIS
COMELEC
-
8/4/2019 Alt Methods Part 2 Distrib
4/52
ICT Hardware Items
Description
1. Computing DevicesDesktop PCs/Laptops/TabletsServers
2. Networking DevicesWired routers and switchesWireless routers and switches
3. Duplicating machines, Printer/Fax/Scanner
4. Telephony Equipment (IP phones, etc.)
5. Data Network (copper, fiber)
6. AVR and UPS, Genset
-
8/4/2019 Alt Methods Part 2 Distrib
5/52
ICT Software Items
Description
1. Operating Systems
2. Office Productivity (i.e., MS Office)3. Specialized Software
GIS, CAD, MultimediaEnterprise/Supply Chain/CR Mgt Sys
4. Databases5. Systems & Network Mgt
-
8/4/2019 Alt Methods Part 2 Distrib
6/52
ICT Supply Items
Description
1. Paper, Inkjet/Toner
2. DVD-R, CD-R, Floppy disks
3. Flash drives
4. Network cable, patch cable/plugs
5. Other consumables
-
8/4/2019 Alt Methods Part 2 Distrib
7/52
ICT-related ServicesDescription
1. Anti-virus subscriptionEnd-point (various)
Device specific (e.g., routers)2. Tech Support & Preventive Maint
Hardware: PCs, printers, network
3. Tech Support & Preventive MaintS/W Licenses: OS, DB, incl. patches(related to an existing product)
4. Internet Connectivity
5. Web/Server Hosting, Data Conversion
6. Training (end-user, IT staff)
7. Application Svc/Subscriptions
-
8/4/2019 Alt Methods Part 2 Distrib
8/52
4 Trends in ICT & Govt
1. ICT cost/power ratio israpidly going down.
2. Demand for qualityservices increasing butthe number of people todeliver them remainsthe same.
-
8/4/2019 Alt Methods Part 2 Distrib
9/52
4 Trends in ICT & Govt
3. ICT personnel in govt arebecoming a very scarce
resource.4. Imperative for GOs to
deliver the services yetoperate in a sustainablemanner
-
8/4/2019 Alt Methods Part 2 Distrib
10/52
ICT ProcurementGood Practices
Why not best
practices?Why good practices?
Situations change
Systems change
13
13
-
8/4/2019 Alt Methods Part 2 Distrib
11/52
ICT ProcurementGood Practices
Technical capability: dont
build it, buy it.Techs change so fast.
Instead, build Project Mgtand leadership/supervisoryskills.
11
-
8/4/2019 Alt Methods Part 2 Distrib
12/52
ICT ProcurementGood Practices
Introducing a
paradigm shift forthe ICT unit: From ICT Specialists
to ICT Project Managers
Certified:
LEAN but MEANLEAN but MEANICT unit
-
8/4/2019 Alt Methods Part 2 Distrib
13/52
Keep in mind
The more a firm strivesfor self-sufficiency, thelarger it becomes. Task of mgt increasing in
complexity and diversity.
Brings back the issue of strategicintent
-
8/4/2019 Alt Methods Part 2 Distrib
14/52
IS Devt Strategy:
"Build or Buy" Rule of
thumb: Create a minimum, acceptable set of
functions.
Shop for OTS solutions. If at least 80%match, then consider a buy.
For the unmet functions, weigh the cost ofcustomizing. If more than the OTS cost,
build.
-
8/4/2019 Alt Methods Part 2 Distrib
15/52
Test: Goods or Services?
Anti-virus software
Operating systems
PC & printer maintenance contract
ERP software
RDBMS software
-
8/4/2019 Alt Methods Part 2 Distrib
16/52
ICT ProcurementGood Practices
Make ICT proc plansharmonize with APP. Why we have ISPs
ICT is cross-cutting in all functions ofthe organization.
One or more project may share thesame ICT resource/infra
22
-
8/4/2019 Alt Methods Part 2 Distrib
17/52
ICT ProcurementGood Practices
As the ICT unit, build a rosterof reliable suppliers. Rate
them periodically Feedback to Purchasing
Not just Purchasings job, its the ICT
units too.
33
-
8/4/2019 Alt Methods Part 2 Distrib
18/52
ICT ProcurementGood Practices
Procurement of ICTs:include the ICT unit in the
process Let the ICT unit review purchases;
advise the BAC; inspect the items
(work with purchasing & propertyunits)
44
-
8/4/2019 Alt Methods Part 2 Distrib
19/52
ICT ProcurementGood Practices
Equipmentpurchases: include site prep, installation,
testing & comm,training, tech supportand maintenance.
Good project packagingand specs design
55
-
8/4/2019 Alt Methods Part 2 Distrib
20/52
ICT ProcurementGood Practices
Equipmentpurchases: include site prep, installation,
testing & comm,training, tech supportand maintenance.
Good project packagingand specs design
55
Have a holistic viewof the procurement.
-
8/4/2019 Alt Methods Part 2 Distrib
21/52
ICT ProcurementGood Practices
Feasibility studies are aseparate procurementactivity Serves to inform decision-making
Example: solution design selection This process is variable
66
-
8/4/2019 Alt Methods Part 2 Distrib
22/52
ICT ProcurementGood Practices
Repeat order: should beexception, not practiceCase: each functional unit in the
agency makes its own purchases.ICT unit should assert function
Indicates lack of planning
77
-
8/4/2019 Alt Methods Part 2 Distrib
23/52
ICT ProcurementGood Practices
Plan bulk purchases of PCs There is strength in numbers
Trust branded PCs
88
-
8/4/2019 Alt Methods Part 2 Distrib
24/52
Branded vs. Clone?
1. Product Warranty
2. Manufacturer Source
3. Service Availability
4. Product Reliability
5. Maintainability (by Tech Support) If you must buy clone make sure a
supplier can closely match the warrantyof a branded
-
8/4/2019 Alt Methods Part 2 Distrib
25/52
ICT ProcurementGood Practices
PCs procured centrally butfor distribution to different
regions.Ensure local tech support.
99
-
8/4/2019 Alt Methods Part 2 Distrib
26/52
ICT ProcurementGood Practices
AMAP, limit diversity among
printers. Replenishmentcosts will be lower.
1010
-
8/4/2019 Alt Methods Part 2 Distrib
27/52
Case of Printer Inks
Relationship between
Procurement ProcessAND Printer Ink type
Inks for small users(small quantities of different
types) could cause most ofPurchasing Depts time
-
8/4/2019 Alt Methods Part 2 Distrib
28/52
Pareto Principle
The 80/20 Principle: inbuilt imbalance betweencauses and results, inputs andoutputs, and effort and
reward.
-
8/4/2019 Alt Methods Part 2 Distrib
29/52
Pareto Examples
80% computers time spentexecuting 20% of code
80% of world wealth ownedby 20% of richest
80% of profits come from20% of products sold
-
8/4/2019 Alt Methods Part 2 Distrib
30/52
ICT ProcurementGood Practices
ICT unit should provide
guidance in PC specs. Purpose of use should dictate specs.Standard specs can be developed andupdated periodically.
1111
-
8/4/2019 Alt Methods Part 2 Distrib
31/52
ICT ProcurementGood Practices
Keep this in mind:
The higher the complexityof the procurementpackage, the higher the
risk for failure.
1212
-
8/4/2019 Alt Methods Part 2 Distrib
32/52
What to do?
Do a reality check
Stricter penalty clause
Well-defined SLAs But ensure enforcement!!!
Limit bid to a minimum number ofqualified suppliers
-
8/4/2019 Alt Methods Part 2 Distrib
33/52
ICT ProcurementGood Practices
Lastly
RA 9184 is not just BACsbusiness, its everybodysbusiness. Not just IT and purchasing, ALSO property,
finance, accounting, etc.
Procurement is a process that cuts acrossdifferent functions in the organization.
1313
-
8/4/2019 Alt Methods Part 2 Distrib
34/52
SARO-related issues
Waiting game a cause ofproject implem delays
SARO near-expiry
-
8/4/2019 Alt Methods Part 2 Distrib
35/52
-
8/4/2019 Alt Methods Part 2 Distrib
36/52
-
8/4/2019 Alt Methods Part 2 Distrib
37/52
Consider Total Cost ofOwnership
Real cost of product is not just its purchaseprice.
TCO: total acquisition cost and operating
costs. Infrastructure (floor space) Electricity (for equipment, cooling, backup
power) Downtime, outage and failure expenses Backup and recovery process, technology
training Diminished performance (i.e. users having to
wait, diminished money-making ability) Security (including breaches, loss of reputation,
recovery and prevention)
-
8/4/2019 Alt Methods Part 2 Distrib
38/52
Example 1
Procurement of outsourced networkmanagement service which includes
the delivery/installation of a networkmanagement system and server on-site.
-
8/4/2019 Alt Methods Part 2 Distrib
39/52
Example 2
Procurement of a turnkey solutionusing the services of a Systems
Integrator
-
8/4/2019 Alt Methods Part 2 Distrib
40/52
Example 3
Procurement of a web-basedapplication with servers, network
infrastructure and PC workstations.
-
8/4/2019 Alt Methods Part 2 Distrib
41/52
Tech Specs for Goods
(Servers) Consider, if possible: Intended use and application
Minimum memory Minimum disk storage
Connectivity
Backup Performance (fault tolerance,
availability, proc speed, expansioncapability
Packa in
-
8/4/2019 Alt Methods Part 2 Distrib
42/52
Tech Specs for Goods
(Software) usually provide the ff: Mode of operation/gen system archi
Functional requirements, preferably detailedenough to the point of identifying all inputsand outputs
Intended number of users
Est. number of transactions to be handled Interfacing and interoperability requirements
Compatibility, security and auditabilityrequirements
-
8/4/2019 Alt Methods Part 2 Distrib
43/52
Consulting TOR
Required expertise and minimumavailability of expertise
Expected outputs preferably withtimetable
TOR would normally contain: Background
Objectives, Scope of Services, Training (when appropriate)
Reports & Time Scheulde
Data, Local Services, Personnel, and Facilitiesto be provided by procuring entity
-
8/4/2019 Alt Methods Part 2 Distrib
44/52
SLAs forOutsourced Svcs
Availability of the service to the user
Minimum acceptable performance of
the components to the service Measurement and reporting
mechanisms that allow monitoring
of the service Cost of the service or additional
services (where applicable)
-
8/4/2019 Alt Methods Part 2 Distrib
45/52
f
-
8/4/2019 Alt Methods Part 2 Distrib
46/52
SLAs forData Conversion
Possible service levels wouldinvolve:
Accuracy Turnaround time
Security/confidentiality of information
f
-
8/4/2019 Alt Methods Part 2 Distrib
47/52
SLAs forRepair & Maint
Typical service level metrics include: Availability
Location (on-site/walk-in) Response times of tech support
Service/repair times,
Service escalation clauses which mayinclude provision of service units and/orreplacements
-
8/4/2019 Alt Methods Part 2 Distrib
48/52
GPRA Principles
Technology neutralitycompetitiveness by extending equal
opportunity to enable privatecontracting parties who are eligible andqualified to participate in publicbidding.
Procurement based on objectivestandards
-
8/4/2019 Alt Methods Part 2 Distrib
49/52
GPRA Principles
Brand names Sec 3: the procurement process shall
be made simple and made adaptable toadvances in modern technology inorder to ensure an effective andefficient method.
4 justifications by way of strictexception.
-
8/4/2019 Alt Methods Part 2 Distrib
50/52
Strict Exemptions
May specify brand, product, orstandard names provided that it
allows for functional equivalentsthru addition of the words: or substantially equivalent
Wherein it means operationally andfunctionally interchangeable.
-
8/4/2019 Alt Methods Part 2 Distrib
51/52
Successful ICT Proc
Well-written TOR is aSMART TORScope and Deliverables
Timetables
CostQuality
-